Attach 1 - NFARS_Repair Airfield Pavement_Specs 08112021_Rev.11JAN23.pdf

PDF 2 MB Posted

Attached to
Repair Airfield Pavement Spalling Federal contract opportunity
Solicitation number
FA667025B0002
Issued by
Department of the Air Force Reserve Command

About this file

This document is a comprehensive set of technical specifications for a repair project at the Niagara Falls Air Reserve Station (NFARS). The project involves full depth replacement, partial depth repair, and joint seal repair of apron and taxiway pavements, with work to be performed in three carefully coordinated phases. Major construction activities include saw cutting and removing isolated concrete slab sections, constructing new reinforced concrete slabs, replacing pavement markings, and installing temporary erosion and sediment controls.

The project is set aside 100% for Service-Disabled Veteran-Owned Small Businesses, with an estimated construction value between $1,000,000 and $5,000,000. The contract (Solicitation Number: FA667025B0002) will be a single Firm Fixed-Price construction contract with a 360-calendar day performance period. Contractors must be registered in the System for Award Management (SAM) and Wide Area Workflow (WAWF), and the complete solicitation is available electronically on beta.sam.gov. The project is being executed by the Department of the Air Force Reserve Command at the 914th Air Refueling Wing, located in Niagara County, New York.

View the file

Other files for this federal contract opportunity

Other files attached to Repair Airfield Pavement Spalling, newest first.
File Type Posted
Spalling - Bid Opening Sign In Sheet 26 Aug 2025.pdf PDF
Spalling - ABSTRACT OF OFFERS - 26 Aug 2025.pdf PDF
Amendment 3 - Repair Airfield Pavement Spalling RVKQ 20-0770 19 Aug 2025.pdf PDF
Attach 1 - NFARS_Repair Airfield Pavement_Specs rev 19 August 2025.pdf PDF
Attach 2 - NFARS_Repair Airfield Pavement_Plans_rev19Aug2025.pdf PDF
Attach 3 - DBA NY20250011 H and H 8 Aug 2025.pdf PDF
Attach 7 - Addendum 2 - Repair Airfield Pavement Spalling RVKQ 20-0770 dtd 14 Aug 2025.pdf PDF
Repair Airfield Spalling Solicitation - Q_and_A_Set2_19Aug2025.pdf PDF
Repair Airfield Spalling Amendment 2 - FA667025B0002.pdf PDF
Repair Airfield Pavement Spalling - Question and Answers - 23 July 2025.pdf PDF
Repair Airfield Spalling Amendment 1 - FA667025B0002.pdf PDF
AF IMT 3000 - Material Approval Submittal.pdf PDF
Attach 3 - DBA NY20250011 H and H 25 July 2025.pdf PDF
Spalling Project - Site Vist - Attendance Sheet 16 July 2025.pdf PDF
Addendum 1 - Repair Airfield Pavement Spalling RVKQ 20-0770 24 July 2025.pdf PDF
Attach 3 - DBA NY20250011 H and H 20 June 2025.pdf PDF
Attach 5 - Entry Access Request for Base Access - 1 pg.pdf PDF
Attach 2 - NFARS_Repair Airfield Pavement_Plans 22x34_100percent Design_08112021.pdf PDF
Repair Airfield Spalling Solicitation - FA667025B0002.pdf PDF
Attach 4 - Insurance Certification.pdf PDF
Show all 20

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CUI

Project Specifications for 100% Design Submittal

Repair Airfield Pavement Spalling Contract: FA6643-18-D-0008 Project #: RVKQ 20-0770 Program Funding: FYXX Niagara Falls ARS, NY

Design Firm:

Farnsworth Group, Inc.

2709 McGraw Drive Bloomington, IL 61704

Book I 11 August 2021

TABLE OF CONTENTS

Section Number Title Pages

BASE SPECIFIC - GENERAL REQUIREMENTS

01 11 00 Summary of Work 3-11 01 57 20.00 10 Environmental Management and Protection 12-27

Off-Station Contractors and Suppliers 28-31 Waste / Recycled Materials Log for Contractors 32 Storm Water Pollution / Erosion & Sediment Control Plan 33-38

DIVISION 1- GENERAL REQUIREMENTS

00 22 13.00 20 Supplementary Instruction to Offerors 39 01 30 00 Administrative Requirements 40-43 01 33 00 Submittal Procedures 44-50 01 42 00 Sources for Reference Publications 51-53 01 78 00 Closeout Submittals 54-61

DIVISION 2- EXISTING CONDITIONS

02 41 00 Demolition 62-65

DIVISION 32 – EXTERIOR IMPROVEMENTS

32 01 11.51 Rubber and Paint Removal from Airfield Pavements 66-73 32 01 19.61 Sealing of Joints in Rigid Pavement 74-84 32 01 29.61 Partial Depth Patching of Rigid Paving * 85-101 32 13 14.13 Concrete Paving for Airfields and

Other Heavy-Duty Pavements 102-152 32 17 23 Pavement Markings 153-163

* Includes an attachment.

STORM WATER POLLUTION PREVENTION PLAN

Contractor SWPPP / E&S Plan 164-166

REPAIR APRON

NIAGARA FALLS ARS, NY

RVKQ 20-0770

SECTION 01 11 00 Page 2

SECTION 01 11 00

SUMMARY OF WORK

PART 1 GENERAL

1.1 General

1.1.1 Project Background

The project is located at the Niagara Falls Air Reserve Station (NFARS), Niagara Falls, NY. The Contractor shall conduct all work so as to cause the least interference with normal activities at the NFARS, related facilities and surrounding areas.

1.1.2 Project Description

This general description is given to indicate the scope of this project only. It does not limit the work required under the project drawings and specifications. The work of the Repair Airfield Pavement Spalling Project (RVQK 20-0770) consists of furnishing all labor, equipment, materials and all miscellaneous services necessary to accomplish the following work described below and as indicated on the contract drawings / specifications. The project involves full depth replacement of apron and taxiway pavements, partial depth repair of apron and taxiway pavements, and joint seal repair of apron and taxiway pavements. More detailed descriptions of work components are given in Section 1.2 of this document.

1.1.3 Site Visit

This contract will require a site visit. The Contractor is solely responsible to attend the scheduled site visit and take measurements of existing conditions. Plans for the project are included as part of the bid package. Additional plans may be reviewed at the Office of the Base Civil Engineer located at Building 403.

1.1.4 Clean Work Site

The Contractor is solely responsible to clean the work sites regularly during and at the end of each workday of each phase as the work progresses, to prevent the accumulation of FOD (foreign object debris). The Contractor will only be permitted to work on one phase at a time for the project. All debris shall be placed in a demolition container/dumpster to prevent accumulation of debris at the demolition site and surrounding area.

1.1.5 Construction Phasing

The project will be done in four phases; this will include an initial concrete mix design phase (Phase 1), followed by three construction phases (Phases 2-4). Concrete mix design submittals are required and must be approved by the Contracting Officer (CO) before starting construction. Construction may not begin until Calendar Year (CY) 2024. Contractor may perform survey work or trailer installation prior to CY 2024, with written permission from the CO. The construction work shall be carefully coordinated and scheduled with the CO and user groups to allow continued occupancy and operations at the NFARS. The Contractor shall only be permitted to work on a single phase of the project at a time.

1.1.6 Sequence of Work

A. The Contractor shall coordinate all parts of the work with the Contracting Officer. The Contractor shall submit the Contractor’s Project Management Professional (PMP) Badge Request Letter and Badges within ten (10) calendar days after the Notice to Proceed (NTP) for approval.

SECTION 01 11 00 Page 3

B. The Contractor shall not begin any construction or perform any other physical work at the construction site until the particular submittals identified in Spec Section 01 33 00 are received and found acceptable by the Contracting Officer.

1.1.7 Site Availability

A. The project areas for each phase will be available for contract work Monday through Friday between the hours of 7:15 AM (0715) and 4:00 PM (1600). If the Contractor desires or needs to perform work during hours or days other than that stated, a written request, which is to include the number of work hours, starting times, dates of the proposed work and a statement that this after hour work is to be performed at no additional cost to the government, shall be submitted to the Contracting Officer seven (7) days in advance. The Contracting Officer will review each such request and respond with written approval, approval with qualifications or restrictions if and as necessary or disapproval. Approval of extended work hour requests are not guaranteed and are at the sole discretion of the Contracting Officer and or the 914 Base Civil Engineer.

B. No work is to be performed on Federal Holidays.

C. Major portions of the work in each phase occurs within the controlled area of the base within the flightline fence on or adjacent to the apron area and on Taxiway A. Contractor personnel will be required to receive a briefing on operating a motor vehicle on the airfield. At the conclusion of this training, competent personnel will be issued a pass which will allow them to drive to and from the project phase work areas without an escort. Violations of the driving procedures can result in suspension of driving privileges or even removal from the project based on the severity of the infraction. To access the work sites within the controlled area, the Contractor shall notify Airfield Management when enroute to work area and when completed for the day by checking in and out, in person, at Building 700, room 120. The Contractor shall also notify Security Forces Squadron at 716-236-2280. At the commencement of each construction phase, the government will establish a free zone to accommodate the work area and access thereto which will alleviate any escorting requirements.

D. With work areas being adjacent to the flightline, the work sites can be periodically considered as a very high noise area. Workers shall be equipped with the necessary personal protective equipment.

E. The work areas can be subjected to high winds. The Contractor shall employ methods to prevent the blowing of dust, debris or any other materials at all times. To reiterate, being adjacent to the flightline and airfield, blowing debris in the vicinity of parked or operating aircraft will not be tolerated at any time.

1.1.8 Work Exclusion Period

None

1.1.9 Work Requirements

The Contractor shall provide non-combustible or self-extinguishing material drop cloths to cover material storage during construction. Contractor shall take necessary care to ensure inclement weather does not damage government property and schedule work so as to minimize its impact on progress of the work. At the end of each workday the Contractor shall protect all entrances and access lanes to the project phases and work areas. No work will be permitted unless barriers and guarding devices are used that meet applicable safety standards and have been approved by the Contracting Officer.

SECTION 01 11 00 Page 4

1.1.10 Contractors Work Plan / Progress Schedule

A. In addition to the submission of AF Forms 3064 and 3065 as required, the Contractor shall, within ten (10) calendar days after receipt of Notice to Proceed and prior to the commencement of on-site work, prepare and submit to the Contracting Officer three copies of the Contractor's Work Plan for review and acceptance. The Plan shall be a practicable schedule visually showing the order in which the Contractor proposes to perform the work, and the dates on which the Contractor contemplates starting and completing the salient elements of the work and critical sub-tasks of each element. The schedule shall be in the form of a progressive bar chart indicating a logical sequence of work and will indicate the percentage of work scheduled for completion by any given weekend date during the contract period. The Contractor shall revise the Plan as necessary to gain acceptance by the Contracting Officer.

B. The Contractor shall update the original schedule by entering the actual start and completion dates of each work element and associated sub-tasks on the chart and deliver three copies of the annotated schedule with each request for progress payment to the Contracting Officer or as otherwise requested by the Contracting Officer.

1.1.11 Removal and Replacement Responsibility

Replace or repair all existing finished surfaces to its original condition, utilities, equipment, products, vegetation, and structures or parts thereof that have been damaged, or have to be removed, or cut into by the Contractor in order to perform work specified in this project.

1.1.12 Superintendence by the Contractor

A. At all times during the performance of the contract and until the work is completed and accepted, the Contractor shall directly superintend the work or assign and have on the worksite a competent Superintendent who is satisfactory to the Contracting Officer and has the authority to act for the Contractor.

B. The Superintendent is to oversee and coordinate all project related work and is required to be on site at any and all times physical work is being performed. The Superintendent shall be able to read, write, fluently speak and understand the English language.

C. Failure to comply with this requirement may be deemed as cause for a non-compensatory stoppage and suspension of work until the deficiency is remedied.

1.1.13 Quality Assurance

A. All items of work not addressed in these Technical Provisions shall be completed in strict accordance with the manufacturer's specifications.

B. The contents of the Technical Provisions shall govern in all situations, except where they conflict with the manufacturer's warranty requirements. All procedures necessary to obtain the specified manufacturer’s warranty shall be followed.

C. The Government is not obligated to inspect the Contractor's work or protect the Contractor from the consequences of such work. The Government inspection is a general examination of the Contractor's conduct and workmanship and is solely for the purpose of the Government.

D. Government agents, including inspectors, engineers, and quality assurance evaluators are not authorized to change the Contract without the written approval of the Contracting Officer. This lack of authority extends to all situations in which the actions of these agents could be considered as constituting a change to the Contract.

SECTION 01 11 00 Page 5

E. The quality of workmanship is subject to audit by the Government or Government designated inspectors at any time during the Contract. The Contractor shall cooperate fully and provide all information necessary for this audit.

F. The Contracting Officer shall be notified prior to all tests. All tests shall be conducted in a timely manner so as not to impede the progress of the work. The Contractor shall conduct all tests as required by the Contract documents and the Contracting Officer.

G. The Contractor shall institute immediate action to correct all variances from the Contract and employ all procedures necessary to ensure future work conforms to the requirements of the Contract.

H. Submit all requests for changes in writing to the Contracting Officer. Do not proceed with changes without possession of written authorization by the Contracting Officer.

I. All materials shall be transported, delivered, handled and stored in a manner recommended by the manufacturer so as to prevent their damage or contamination. All materials shall be delivered in their original unopened containers with their descriptive labels clearly visible and legible. All materials susceptible to aging or curing shall be stored with the descriptive labels, including manufacturing date and shelf life, clearly visible and legible. The Contractor shall reject all materials, which have exceeded their shelf life.

1.1.14 Quality Control

A. The Contractor shall appoint or hire one person to act as Contractor Quality Control System

Manager whose sole responsibility shall be to ensure that all work proceeds according to the Contract.

B. This individual shall complete Quality Control report on a daily basis and submit to the

Contracting Officer prior to the commencement of work on the next day, or as instructed by the Contracting Officer.

1.1.15 Demolition Work Plan/Recycling Plan

A. Contractor shall provide a work/demolition plan prior to starting any work. Work shall not proceed until the Contractor's work/demolition plan has been reviewed and approved by the Base Contracting Officer and/or his representatives. The work/demolition plan shall include the following:

B. The demolition plan shall be the following (where applicable): proposed method of demolition, recycling plan, engineering controls to reduce the amount of dust released to the air, disposal location, utilities capping plan, etc. The recycling plan shall also include documentation from each recycling center that the demolition Contractor will use for recycling. The recycling plan shall indicate which materials will be recycled at each center.

C. The recycling plan shall also include written certification (state, local, etc.) showing that the recycling center is approved to accept and has the capacity for each material listed to be recycled at their facility. The recycling plan shall indicate how the recycling facility/demolition Contractor will supply the net weights on each, material recycled. The documentation for each recycling center shall be on recycling center letterhead with original signature by the qualified recycling center representatives.

1.1.16 Description of Work

A. The work to be performed under this contract consists of pavement repairs to the existing apron area and Taxiway systems at the NFARS. The work will be done in three phases.

SECTION 01 11 00 Page 6

B. After construction, but before the contract is considered final, the Contractor shall supply an itemized list of materials recycled, including quantities, to the Base Contracting Officer (who in turn shall forward list to CEV).

1.2 WORK COVERED BY CONTRACT DOCUMENTS

1.2.1 Project Description

Major work components for general construction work consist of the following as shown on the Construction Plans:

• Saw cut, excavate and remove isolated full depth concrete slabs. Construct new full depth reinforced, isolated slabs.

• Saw cut, excavate and remove isolated partial depth concrete slab sections. Construct new partial depth reinforced, isolated slab sections.

• Joint removal and replacement

• Replace pavement markings where removed for pavement patching or where damaged during construction.

• Install and maintain temporary erosion and sediment controls as per the SWPPP

• Provide temporary toilet facilities at locations determined by Contracting Officer

1.2.2 Location

The project site is located on portions of the existing apron area and taxiway systems at the NFARS.

Project is to be considered to be constructed in three (3) Phases, refer to drawings for Phasing locations.

1.3 PROJECT ENVIRONMENTAL GOALS

Contractor shall distribute copies of the Environmental Goals to each subcontractor and the Contracting Officer. The overall goal for design, construction, and operation is to produce a building that meets the functional program needs and incorporate the principles of sustainability.

Specifically:

a. Preserve and restore the site ecosystem and biodiversity; avoid site degradation and erosion.

Minimize offsite environmental impact.

b. Use the minimum amount of energy, water, and materials feasible to meet the design intent.

Select energy and water efficient equipment and strategies.

c. Use environmentally preferable products and decrease toxicity level of materials used.

d. Use renewable energy and material resources.

e. Optimize operational performance (through commissioning efforts) in order to ensure energy efficient equipment operates as intended. Consider the durability, maintainability, and flexibility of building systems.

f. Manage construction site and storage of materials to ensure no negative impact on the indoor environmental quality of the building.

g. Reduce construction waste through reuse, recycling, and supplier take-back.

SECTION 01 11 00 Page 7

1.4 EXISTING WORK

In addition to "FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements":

a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.

b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work shall be in a condition equal to or better than that which existed before new work started.

1.5 DIG PERMIT AND UNDERGROUND UTILITIES MARKING

The Contractor shall submit Form AF 103 (a.k.a. Dig Permit) through Base Civil Engineering at least Twenty-One (21) calendar days in advance of any digging or ground-breaking activities, which activities may commence only after the Contractor receives Base final approval of Form AF 103.

The Contractor shall be responsible for locating, marking, and verifying all utilities in the vicinity of the work area(s) using ground penetrating radar. Said locating, marking, and verifying of all utilities must be completed prior to base granting final approval of Form AF 103. The contractor shall complete utility locations in general conformance with Dig Safe requirements and the Base will verify adequate field surface markings before approving the Dig Permit. The Contractor shall be responsible to coordinate with base agencies, and to ensure markings are placed over existing base infrastructure and/or utilities prior to any digging, drilling, boring, or directional drilling. The Contractor shall take precautions to protect existing infrastructure, and shall be responsible for costs associated with repair of any damages caused during digging, drilling, boring, and installation activities. The Contractor is responsible for maintaining all markings prior to and during the course of construction.

Mark the surface of the ground or paved surface where existing underground utilities are discovered.

Verify the elevations of existing piping, utilities, and any type of underground or encased obstruction not indicated to be specified or removed but indicated or discovered during scanning in locations to be traversed by piping, ducts, and other work to be conducted or installed. Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made.

1.6 CONTRACT DOCUMENTS

Dimensions on drawings shall be checked, for accuracy, by the Contractor. The Contractor shall verify exact dimensions for proper fit. Drawings shall not be construed as being detailed working drawings.

The following drawings accompany these specifications and are a part thereof:

1 Title Sheet, Location Map 2 Site Plan 3-4 Phasing Plan and Details 5 General Notes 6 Typical Sections 7-8 Schedules for Improvements 9-20 Existing Condition and Proposed Improvements Base Sheets 21 Pavement Marking Plans & Details 22 Erosion and Sediment Control Plan 23-26 Special Details & Standards

SECTION 01 11 00 Page 8

One (1) set of contract drawings and specifications will be furnished to the Contractor in electronic or paper media without charge. Reference publications will not be furnished.

The Contractor shall immediately check furnished drawings and Specifications and notify the Government of any discrepancies.

1.7 Notice to Commence Work

The Contractor shall give the Contracting Officer or his representative a 48 hour notice of the Contractor’s intent to commence work.

1.7.1 Daily Sign-In Sheet

Prior to starting the work each day, the Contractor and/or subcontractor must fill out the Sign-In sheet located at the 914th AW, Base Civil Engineering Office Building 403.

1.8 ON-SITE PERMITS

1.8.1 Utility Outages and Connections

Work shall be scheduled to hold outages to a minimum. The Contracting Officer may permit outages at his discretion. The Contractor shall coordinate planned outages with the Contracting Officer at least seven (7) working days in advance of the outage if the implementation necessitates disruption of services (e.g. communications, electrical, or other utilities). Each request shall state the system involved, area involved, approximate duration of outage, and the nature of the work involved. The Contractor is responsible for preventing any unscheduled (i.e. cutting or disabling any in-service cables or equipment), Contractor-caused interruptions of communications capabilities. The Contractor and/or subcontractor shall coordinate any power shut downs with the Government. Any additional costs related to overtime, premium pay or impacts shall be paid by the Contractor at no increase to the contract.

1.8.2 Borrow, Digging, Welding, and Burning Permits

ACTIVITY SUBMISSION DATE SUBMISSION FORM

Borrow 21 days prior to work from Base Environmental Dept. AF 103, Full source Bldg. 403 documentation.

Digging 21 days prior to work from Base Civil Engineer

Bldg. 403

Welding Each day prior to work from Base Fire Station Bldg. 821

Burning Each day prior to work from Base Fire Chief

Bldg. 821

Permits shall be posted at a conspicuous location in the construction area. Permits are the property of the Government and shall be returned to the Contracting Officer upon completion of permitted work.

The Contractor is responsible for hand excavation within 3’-0” from either side of all known utilities that have been either staked or marked during utility locating activities, or as noted on scaled drawings.

Burning of trash is not permitted.

SECTION 01 11 00 Page 9

Use of explosives shall not be permitted.

Portions of the project work areas are located in or near AFFF (aqueous film forming foam) contaminated sites. Contactor shall be aware of AFFF sites and if contaminated soils are encountered the Contractor shall contact the 914 MSG/LGC immediately.

Excavated soils from identified AFFF sites shall be backfilled from where it originated. Clean backfill shall be used as needed to fill excavations. If excess soil or contaminated soil is generated by the project it must be segregated, placed on plastic sheeting, covered, tested, characterized and properly disposed of at the Contractors expense.

If dewatering is required at AFFF excavation areas it must be pumped and containerized for proper disposal.

Industry standard safety measures and equipment decontamination shall be followed for work on IRP sites. The 914th MSG/CEV will provide guidance on collection, storage, characterization and disposal requirements. Contractor shall document contaminated waste generation locations, dates and approximate amounts.

1.9 REMOVAL OF WASTE MATERIAL

During the progress and at the completion of work, all refuse and waste material shall be removed from Government property and disposed according to Federal, State, and Local environmental regulations. If waste material is not removed daily, the Contractor shall provide a covered waste container at his expense.

1.10 UTILITIES

Electricity and water shall be provided by the Government. Any extension of, or corrections to, the existing lines and their removal will be at the expense of the Contractor. All connections to existing utilities, if necessary, shall be coordinated with the Government. The Contractor is responsible for supplying his own restroom facilities.

1.11 RADIOACTIVE TESING EQUIPMENT

Before bringing radioactive testing equipment on base, the Contractor shall (a) provide the base Bioenvironmental Office with a copy of the company’s NY State license to perform radiographic work, and copies of their current Radiation Safety Training Certificate, and (b) obtain approval from the base Bioenvironmental Office to bring the equipment on base.

PART 2 ENVIRONMENTAL PROTECTION REQUIREMENTS

2.1

Refer to specifications Sections 01 57 20.00 10 ENVIRONMENTAL MANAGEMENT & PROTECTION for project requirements. Any questions concerning environmental conditions or problems shall be referred to 914th AW/CEV at 236-3126.

PART 3 SPECIAL CONDITIONS

3.1

The contractor shall supply the Base Contracting Officer with a list of quantities of materials used and removed prior to final acceptance of the project completion. The Contractor shall use the areas

SECTION 01 11 00 Page 10 designated by the Contracting Officer for storage of materials and vehicles. The Contractor shall submit to the Contracting Officer, for approval, a sequence and schedule of work.

3.2 CONTRACTOR REPORTS

3.2.1 Weekly Status Reports

The Contractor shall prepare a Weekly Status Report and distribute to the IPT members, 914 Contracting Officer, and Base Civil Engineering POC. The purpose of the report is to inform IPT members and other recipients of project progress, problems being encountered, and other topics necessary or beneficial to ensure success and timely completion of the contract requirements. The status Report and meeting agenda may be combined as long as the resulting report contains all the required elements and contains sufficient detail to serve as project record.

3.2.2 Daily Construction Report

In addition to the Weekly Status Reports, the Contractor shall prepare and distribute a daily construction report to the 914 Contracting Officer, and Base Civil Engineering POC by 10:30 AM (1030) of the next business day. The report will include 4 photos, and describe construction activities, major issues, equipment on site, connections with any buildings, and utility outages.

-- End of Section--

SECTION 01 57 20.00 10 Page 1

SECTION 01 57 20.00 10

ENVIRONMENTAL MANAGEMENT AND PROTECTION

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only.

U.S. AIR FORCE (USAF) / DEPARTMENT OF DEFENSE (DOD)

AFMAN 32-1053 Pest Management Program, 6 Aug 19

AFMAN 32-1067 Water and Fuel Systems, 4 Aug 20

AFMAN 32-7002 Environmental Compliance and Pollution Prevention, 4 Feb

DOD Energy Independence and Security Act (EISA) Section 438, Storm Water Requirements

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

29 CFR 1910.120 Hazardous Waste Operations and Emergency Response

33 CFR 328 Definitions of Waters of the United States

40 CFR 68 Chemical Accident Prevention Provisions

40 CFR 152 - 186 Pesticide Programs

40 CFR 261 Identification and Listing of Hazardous Waste

40 CFR 262 Standards Applicable to Generators of Hazardous Waste

40 CFR 273 Standards for Universal Waste Management

40 CFR 279 Standards for the Management of Used Oil

40 CFR 300 National Oil and Hazardous Substances Pollution Contingency Plan

40 CFR 302 Designation, Reportable Quantities, and Notification

40 CFR 355 Emergency Planning and Notification

49 CFR 171 - 178 Hazardous Materials Regulations

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (1996) U.S. Army Corps on Engineers Safety and Health

Requirements Manual, 30 Nov 14

SECTION 01 57 20.00 10 Page 2

WETLAND MANUAL Corps of Engineers Wetlands Delineation Manual Technical Report Y-87-1

WETLANS MANUAL ERDC/EL TR-12-1, Regional Supplement to the Corps of REGIONAL SUPPLEMENT Engineers Wetland Delineation Manual: Northcentral and

Northeast Region (Version 2.0), January 2012

1.2 DEFINITIONS

1.2.1 Environmental Pollution and Damage

Environmental pollution and damage is the presence of chemical, physical, or biological elements or agents which adversely affect human health or welfare; unfavorably alter ecological balances of importance to human life; affect other species of importance to humankind; or degrade the environment aesthetically, culturally and/or historically.

1.2.2 Environmental Protection

Environmental protection is the prevention/control of pollution and habitat disruption that may occur to the environment during construction. The control of environmental pollution and damage requires consideration of land, water, and air; biological and cultural resources; and includes management of visual aesthetics; noise; solid, chemical, gaseous, and liquid waste; radiant energy and radioactive material as well as other pollutants.

1.2.3 Solid Waste

Includes but is not limited to garbage, refuse, debris, sludge, or other discharged material, including solid, liquid, semisolid, or contained gaseous materials resulting from domestic, industrial, commercial, mining, or agricultural operations. Types of solid waste typically generated at construction sites may include:

a. Green waste: The vegetative matter from landscaping, land clearing and grubbing, including, but not limited to, grass, bushes, scrubs, small trees and saplings, tree stumps and plant roots. Marketable trees, grasses and plants that are indicated to remain, be re-located, or be re-used are not included.

b. Surplus soil: Existing soil that is in excess of what is required for this work, including aggregates intended, but not used, for on-site mixing of concrete, mortars and paving.

Contaminated soil meeting the definition of hazardous material or hazardous waste is not included. Surplus soil must be disposed of at a facility approved by 914 MSG/CEV. Please provide written documentation prior to soil removal.

c. Debris: Non-hazardous solid material generated during the construction, demolition, or renovation of a structure which exceeds 60 mm( 2.5 inch) (2.5 inch) particle size that is: a manufactured object; plant or animal matter; or natural geologic material (e.g. cobbles and boulders), broken or removed concrete, masonry, and rock asphalt paving; ceramics;

roofing paper and shingles. Inert materials may be reinforced with or contain ferrous wire, rods, accessories and weldments. A mixture of debris and other material such as soil or sludge is also subject to regulation as debris if the mixture is comprised primarily of debris by volume, based on visual inspection will be disposed of by the contractor with weights and recycling facilities documented and submitted to LGC. This includes wood, and scrap metal. Recyclable materials will be handled in a similar manner.

1.2.4 Hazardous Waste

SECTION 01 57 20.00 10 Page 3

Any discarded material, liquid, solid, or gas, which meets the definition of hazardous material or is designated hazardous waste by the Environmental Protection Agency or State Hazardous Control Authority as defined in 40 CFR 260, 40 CFR 261, 40 CFR 263, 40 CFR 264, 40 CFR 265, 40 CFR 266, 40 CFR 268, 40 CFR 270, 40 CFR 271, 40 CFR 272, 40 CFR 273, 40 CFR 279, and 40 CFR 280.

1.2.5 Contractor Generated Hazardous Waste

Contractor generated hazardous waste means materials that, if abandoned or disposed of, may meet the definition of a hazardous waste. These waste streams would typically consist of material brought on site by the Contractor to execute work, but are not fully consumed during the course of construction.

Examples include, but are not limited to, excess paint thinners (i.e. methyl ethyl ketone, toluene etc.), waste thinners, excess paints, excess solvents, waste solvents, and excess pesticides, and contaminated pesticide equipment rinse water.

1.2.6 Hazardous Materials

Hazardous materials as defined in 49 CFR 171 and listed in 49 CFR 172.

Hazardous material is any material that:

a. Is regulated as a hazardous material per 49 CFR 173, or

b. Requires a Material Safety Data Sheet (MSDS) per 29 CFR 1910.120, or

c. During end use, treatment, handling, packaging, storage, transportation, or disposal meets or has components that meet or have potential to meet the definition of a hazardous waste as defined by 40 CFR 261 Subparts A, B, C, or D.

Designation of a material by this definition, when separately regulated or controlled by other instructions or directives, does not eliminate the need for adherence to that hazard-specific guidance which takes precedence over this instruction for "control" purposes. Such material include ammunition, weapons, explosive actuated devices, propellants, pyrotechnics, chemical and biological warfare materials, medical and pharmaceutical supplies, medical waste and infectious materials, bulk fuels, radioactive materials, and other materials such as asbestos, mercury, and polychlorinated biphenyls (PCBs). Nonetheless, the exposure may occur incident to manufacture, storage, use and demilitarization of these items. All hazardous materials used in this project must be registered with the Niagara Falls HAZMART.

1.2.7 Waste Hazardous Material (WHM)

Any waste material which because of its quantity, concentration, or physical, chemical, or infectious characteristics may pose a substantial hazard to human health or the environment and which has been so designated. Used oil not containing any hazardous waste, as defined above, falls under this definition. Hazardous waste will be appropriately tested and discarded in a manner which is in compliance with other State and local, 914 MSG/CEV requirements.

1.2.8 Oily Waste

Oily wastes are those materials which are, or were, mixed with oil and have become separated from that oil. Oily wastes also includes materials which have come into contact with oil including wastewaters, centrifuge solids, filter residues or sludges, bottom sediments, tank bottoms, and sorbents.

This definition includes materials such as oily rags, “spedi-dry” sorbent clay and organic sorbent material. These materials must be handled as directed by 914 MSG/CEV.

SECTION 01 57 20.00 10 Page 4

1.2.9 Regulated Waste

Those solid wastes that have specific additional Federal, state, or local controls for handling, storage, or disposal.

1.2.10 Ozone Depleting Substances (ODS)

Ozone Depleting Substances are any Class I or Class II controlled substances as defined in Federal Regulations 40 CFR 82. All Class I and Class II Ozone Depleting Substance (ODS) must be handled in accordance with 40 CFR 82, and Section 602(a) and 602(s) of The Clean Air Act Amendments of 1990.

1.2.11 Universal Waste

The universal waste regulations streamline collection requirements for certain hazardous wastes in the following categories: batteries, pesticides, mercury-containing equipment (e.g., thermostats) and lamps (e.g., fluorescent bulbs). Please contact 914 MSG/CEV for disposition instructions.

1.2.12 Installation Pest Management Coordinator

Installation Pest Management Coordinator (IPMC) is the individual officially designated by the Installation Commander to oversee the Installation Pest Management Program and the Installation Pest Management Plan.

1.2.13 Pesticide

Pesticide is defined as any substance or mixture of substances intended for preventing, destroying, repelling, or mitigating any pest, or intended for use as a plant regulator, defoliant or desiccant.

1.2.14 Pests

The term "pests" means arthropods, birds, rodents, nematodes, fungi, bacteria, viruses, algae, snails, marine borers, snakes, weeds and other organisms (except for human or animal disease-causing organisms) that adversely affect readiness, military operations, or the well-being of personnel and animals; attack or damage real property, supplies, equipment, or vegetation; or are otherwise undesirable.

1.2.15 Surface Discharge

The term "Surface Discharge" implies that the water is discharged with possible sheeting action and subsequent soil erosion may occur. Waters that are surface discharged may terminate in drainage ditches, storm sewers, creeks, and/or "waters of the United States" and would require a permit to discharge water from the governing agency.

1.2.16 Waters of the United States

All waters which are under the jurisdiction of the Clean Water Act, as defined in 33 CFR 328.

1.2.17 Wetlands & Other Waters of the U.S.

Wetlands means those areas that are inundated or saturated by surface or ground water at a frequency and duration sufficient to support, and that under normal circumstances do support, a prevalence of vegetation typically adapted for life in saturated soil conditions. Wetlands generally include swamps, marshes, and bogs. There are Federal and State wetlands located on Niagara Falls Air Reserve Station. Construction or work in these areas including other “Waters of the U.S.” such as Cayuga Creek and its tributaries and certain drainage ditches are regulated by the NYSDEC and the

SECTION 01 57 20.00 10 Page 5

U.S. Army Corps of Engineers. The Contractor shall prepare permit applications for work in these areas in coordination with the 914 MSG/CEV.

1.3 GENERAL REQUIREMENTS

The Contractor shall minimize environmental pollution and damage that may occur as the result of construction operations. The environmental resources within the project boundaries and those affected outside the limits of permanent work shall be protected during the entire duration of this contract. The Contractor shall comply with all applicable environmental Federal, State, and local laws and regulations.

The Contractor shall be responsible for any delays resulting from failure to comply with environmental laws and regulations.

1.4 CONFORMANCE WITH ENVIRONMENTAL MANAGEMENT SYSTEM

The Contractor shall perform work under this contract consistent with the relevant policy and objectives identified in the agency, organizational, or facility environmental management system (EMS) applicable for your contract. The Contractor shall perform work in a manner that conforms to all appropriate Environmental Management Programs and Operational Controls identified by the agency, organizational, or facility EMS, and provide monitoring and measurement information as necessary for the organization to address environmental performance relative to the environmental, energy, and transportation management goals. In the event an environmental nonconformance or noncompliance associated with the contracted services is identified, the contractor shall take corrective and/or preventative actions. In the case of a noncompliance, the Contractor shall respond and take corrective action immediately. In the case of a nonconformance, the Contractor shall respond and take corrective action based on the time schedule established by the EMS Site Coordinator. In addition, the Contractor shall ensure that their employees are aware of the roles and responsibilities identified by the environmental management system and how these requirements affect their work performed under this contract.

1.5 SUBCONTRACTORS

The Contractor shall ensure compliance with this section by subcontractors.

1.6 PAYMENT

No separate payment will be made for work covered under this section. The Contractor shall be responsible for payment of fees associated with environmental permits, application, plan development, and/or notices obtained by the Contractor. All costs associated with this section shall be included in the contract price. The Contractor shall be responsible for payment of all fines/fees for violation or non-compliance with Federal, State, Regional and local laws and regulations. The Contractor shall be responsible for payment of all costs associated with the cleanup of a spill caused by the Contractor.

1.7 SUBMITTALS

Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Environmental Protection Plan; G, Stormwater Pollution Prevention Plan; G, Certificate of Applicability/Non-Applicability of EISA 2007 Section 438; G, SECTION 01 57 20.00 10 Page 6

Survey Report

Demolition Plan, [IF REQUIRED, SEE SECT 1.10 OF THIS SPEC], G

SD-09 Field Reports

Stormwater Inspection Reports, Waste/Recycled Material Log (Attachment 2)

SD-11 Closeout Submittals

Disposal Documentation for Hazardous and Regulated Waste, Waste/Recycled Material Log (Attachment 2)

1.8 ENVIRONMENTAL PROTECTION PLAN

Prior to commencing construction activities or delivery of materials to the site, the Contractor shall submit an Environmental Protection Plan for review and approval by the Contracting Officer and 914 MSG/CEV. The purpose of the Environmental Protection Plan is to present a comprehensive overview of known or potential environmental issues which the Contractor must address during construction.

Issues of concern shall be defined within the Environmental Protection Plan as outlined in this section.

The Contractor shall address each topic at a level of detail commensurate with the environmental issue and required construction task(s). Topics or issues which are not identified in this section, but which the Contractor considers necessary, shall be identified and discussed after those items formally identified in this section. Prior to submittal of the Environmental Protection Plan, the Contractor shall meet with the Contracting Officer for the purpose of discussing the implementation of the initial Environmental Protection Plan; possible subsequent additions and revisions to the plan including any reporting requirements; and methods for administration of the Contractor's Environmental Plans. The Environmental Protection Plan shall be current and maintained onsite by the Contractor.

1.8.1 Compliance

No requirement in this Section shall be construed as relieving the Contractor of any applicable Federal, State, and local environmental protection laws and regulations. During Construction, the Contractor shall be responsible for identifying, implementing, and submitting for approval any additional requirements to be included in the Environmental Protection Plan.

1.8.2 Contents

The environmental protection plan shall include, but shall not be limited to, the following:

a. Name(s) of person(s) within the Contractor's organization who is(are) responsible for ensuring adherence to the Environmental Protection Plan.

b. Name(s) and qualifications of person(s) responsible for manifesting hazardous waste to be removed from the site, if applicable.

c. Name(s) and qualifications of person(s) responsible for training the Contractor's environmental protection personnel.

d. Description of the Contractor's environmental protection personnel training program.

SECTION 01 57 20.00 10 Page 7

e. Drawings showing locations of proposed temporary excavations or embankments for haul roads, stream crossings, material storage areas, structures, sanitary facilities, and stockpiles of excess or spoil materials including methods to control runoff and to contain materials on the site.

f. Traffic control plans including measures to reduce erosion of temporary roadbeds by construction traffic, especially during wet weather. Plan shall include measures to minimize the amount of sediment transported onto paved roads by vehicles or runoff.

g. Work area plan showing the proposed activity in each portion of the area and identifying the areas of limited use or nonuse. Plan should include measures for marking the limits of use areas including methods for protection of features to be preserved within authorized work areas.

h. Drawing showing the location of borrow areas.

i. A Spill Control Plan which shall include the procedures, instructions, and reports to be used in the event of an unforeseen spill of a substance regulated by 40 CFR 68, 40 CFR 302, 40 CFR 355, and/or regulated under State or Local laws and regulations. The Spill Control Plan shall include procedures contained within the Hazardous Materials Emergency Planning and Response (HAZMAT) Plan for Niagara Falls Air Reserve Station “Quick Reference Guide, Off- Station Contractors and Suppliers” (Attachment 1). In response to a spill, the Contractor is responsible for assisting the Fire Department (914 MSG/CEF) or Environmental Office (914 MSG/CEV) in development of a spill report and any other actions needed by Niagara Falls ARS to respond to the spill/cleanup. This plan shall include as a minimum:

1. The name of the individual who will report any spills or hazardous substance releases and who will follow up with complete documentation. This individual shall immediately notify the Fire Department and the Contracting Officer. The plan shall contain a list of the required reporting channels and telephone numbers.

2. The name and qualifications of the individual who will be responsible for implementing and supervising the containment and cleanup.

3. Training requirements for Contractor's personnel and methods of accomplishing the training.

4. A list of materials and equipment to be immediately available at the job site, tailored to cleanup work of the potential hazard(s) identified.

5. The methods and procedures to be used for expeditious contaminant and cleanup.

j. A Non-hazardous Solid Waste Disposal Plan which identifies methods and locations for solid waste disposal including clearing debris. The plan shall include schedules for disposal. The Contractor shall identify any subcontractors responsible for the transportation and disposal of solid waste. Licenses or permits shall be submitted for solid waste disposal sites that are not a commercial operating facility. Evidence of the disposal facility's acceptance of the solid waste (i.e. acceptance letter prior to disposal, weight tickets, receipts, etc.) shall be attached to this plan during the construction.

The Contractor shall attach a copy of each of the Non-hazardous Solid Waste Diversion Reports to the disposal plan. The report shall be submitted to the Contracting Officer and 914 MSG/CEV on the first working day after the first quarter that non-hazardous solid waste has been disposed and/or diverted and shall be for the previous quarter (e.g. the first working day of January, April, July, and October) and at project completion. The report shall state the project name, project number, project duration, contractor name, name of contact, and phone number. Additionally, the report shall include the date the waste was disposed, waste type (i.e. scrap metal concrete, construction debris, etc.), disposal method (landfill, recycle, incineration, etc.), disposal location

SECTION 01 57 20.00 10 Page 8

(facility name, city, state), and total amount (in tons) of waste generated. See Attachment 2 for Waste/Recycled Material Log.

k. A Recycling and Solid Waste Minimization Plan which identifies the measures to divert waste disposal from landfills. The Contractor must divert solid waste and construction and demolition debris (C&D) in accordance with federal regulations, see tables below. The Contractor will generate the least amount of solid waste possible, maximize pollution prevention processes, and maximize landfill diversion through source reduction, reuse of materials, and recycling. The Contractor will not dispose of any hazardous waste, salvageable items, green waste, concrete, or asphalt in landfills. These items must be properly disposed, diverted, recycled, or reused. The plan shall detail the Contractor's actions to comply with and to participate in Federal, State, Regional, and local government sponsored recycling programs to reduce the volume of solid waste at the source.

Solid Waste

Fiscal year 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 Minimum Diversion

Rate Requirement

42% 44% 46% 48% 50% 50% 50% 50% 50% 50%

C&D Waste

Fiscal year 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 Minimum Diversion

Rate Requirement

52% 54% 56% 58% 60% 60% 60% 60% 60% 60%

l. An Air Pollution Control plan which details the measures to limit dust, debris, materials, trash, etc. from impacting air quality.

m. A Contaminant Prevention Plan that: identifies potentially hazardous substances to be used on the job site; identifies the intended actions to prevent introduction of such materials into the air, water, or ground; and details provisions for compliance with Federal, State, and local laws and regulations for storage and handling of these materials. In accordance with EM 385-1-1, a copy of the Material Safety Data Sheets (MSDS) and the maximum quantity of each hazardous material to be on site at any given time shall be included in the contaminant prevention plan. As new hazardous materials are brought on site or removed from the site, the plan shall be updated.

n. A Waste Water Management Plan that identifies the methods and procedures for management and/or discharge of waste waters which are directly derived from construction activities, such as concrete curing water, dewatering of ground water, disinfection water, hydrostatic test water, and water used in flushing of lines. Waste water must be discharged in accordance with applicable Federal, state, and local regulations. If proposed discharge methods require permits, the Contractor shall submit a copy of the permit and associated documentation to the Contracting Officer prior to discharging the waste water.

o. A Historical, Archaeological, Cultural, Biological Resources and Wetlands Plan that defines procedures for identifying and protecting historical, archaeological, cultural resources, biological resources and wetlands known to be on the project site: and/or identifies procedures to be followed if historical archaeological, cultural resources, biological resources and wetlands not previously known to be onsite or in the area are discovered during construction.