DEPARTMENT OF THE ARMY
US ARMY INSTALLATION MANAGEMENT COMMAND
HEADQUARTERS, UNITED STATES ARMY GARRISON, AREA NORTH
UNIT #15543
APO AP 96224-5543
AMIM-YNP-G 5 December 2022
SPECIFICATIONS
FOR
PROJECT NO.: TBD
Repair Operation Building
TBD, Korea
TABLE OF CONTENTS
1. Technical Provisions - I: Statement of Work
2. Technical Provisions - II: Technical Detail Specifications
3. Technical Provisions - III: Special Conditions
4. Appendix "A": List of Applicable Contract Drawings
TECHNICAL PROVISIONS - I
STATEMENT OF WORK
PROJECT NO TITLE LOCATION
XXXXX Repair Operation Building TBD
1. DESCRIPTION: The work to be performed to repair building is described below and executed by one or more of the groups.
1.1. Work by Contractor: The contractor shall provide all labor, tools, equipment, supplies and any other resources necessary to accomplish the scope of work contained herein as indicated in the drawings and in accordance with the specifications
1.2. Work by In-House Labor: Not applicable to this project.
1.3. Work by Troop Labor: Not applicable to this project.
2. PRINCIPAL FEATURES: This project includes the following principal features:
2.1. Schedule #I, Repair (K): All work shall be in accordance with the attached drawings and specifications.
2.1.1. Civil Work
2.1.1.1. Replace exist turf area w/asphalt paving.
2.1.1.2. Mill/overlay with 50MM thick AC surface course.
2.1.1.3. Replace 0.4M W steel grating cover ditch.
2.1.1.4. Replace exist three (3) surface inlet with new.
2.1.1.5. Replace exist 1.3M X 1.3M two (2) sewer manhole and 150MM PVC sewer line.
2.1.1.6. Replace 50MM DIA PVC water line with gate valve.
2.1.1.7. Restore carpet sodding with topsoil.
2.1.1.8. Paint hydrant and replace guard post.
2.2. Schedule #II, New Construction (L): All work shall be in accordance with the attached drawings and specifications.
2.2.1. Civil Work
2.2.1.1. Construct mud area and stoop with step and ramp.
TP I-1
2.2.1.2. Connect 100MM PVC pipe from mud area to ditch.
2.2.1.3. Construct concrete encasement.
2.2.2. Architectural Work
1. FLOOR WORK
2.2.2.1.1. Replace deteriorated existing floor tile with new PVCT including VCB as shown on floor plan & interior finish schedule. The existing concrete flooring shall be smooth, true, level plane with all defects such as rough or scaling concrete, low spots, high spots, paining, and uneven surface shall have been corrected for new flooring. Provide leveling concrete for existing concrete slab if needed.
2.2.2.1.2. Replace deteriorated existing FCT with new including cement bond coat, waterproof membrane, mortar bed as shown on floor plans, section and details drawings.
2.2.2.1.3. Apply epoxy coating with non-slip grits on existing floors as shown on floor plan and interior finish schedule.
2.2.2.1.4. Install quarry tile including quarry tile base with new as shown on floor plans and interior finish schedule
2. INTERIOR & EXTERIOR WALL WORK
2.2.2.2.1 Replace deteriorated existing all GWB wall board with new GWB wall (GWB, Normal, Water Resistant or ‘X’ Type) including metal studs and insulation as shown on floor plans, sections and detail drawings.
2.2.2.2.2. Paint all existing interior walls including as shown on floor plan, detail drawings interior finish schedule
2.2.2.2.3. Replace exist exterior walls with new EIFS as shown on floor plan, elevations, sections and detail drawings
2.2.2.2.4. Apply skim coat plaster on concrete walls as shown on floor plan, sections and finish schedule.
2.2.2.2.5. Replace deteriorated existing GCWT with new including cement bond coats waterproof membrane, plastering w/metal lath and waterproof GWB as shown on floor plans and sections.
3. Interior & Exterior Ceiling/Roof Work
2.2.2.3.1. Replace deteriorated existing ceiling with new acoustical ceiling tiles including metal suspension systems as shown on floor plans and interior finish schedule.
2.2.2.3.2. Replace deteriorated existing ceiling with new gypsum wall board (GWB, Normal, water resistant or ‘X’ type) ceiling including ceiling suspension system as shown on floor plans and finish schedule.
TP I-2
2.2.2.3.3. Paint on all interior ceiling surfaces as shown on interior finish schedule and section.
2.2.2.3.4. Replace deteriorated existing roof with new standing seam metal roof as shown on floor plan, roof plan, elevations and details.
2.2.2.3.5. Apply skim coat plaster on concrete ceilings as shown on floor plan, sections and finish schedule.
2.2.2.3.6. Replace deteriorated existing metal canopy with new as shown on floor plan elevations and detail drawings
2.2.2.3.7. Install rain gutters, downspouts and concrete splash blocks with new as shown on floor plans, elevations, sections and detail drawings
4. Miscellaneous work
2.2.2.4.1. Replace deteriorated existing doors and door frames with new including new hardware sets as shown on new floor plan and door schedule.
2.2.2.4.2. Replace deteriorated existing windows including insect screen with new aluminum thermal breaker type windows including glass as shown on floor plans, elevations, and window schedule.
2.2.2.4.3. Replace deteriorated existing window horizontal mini blinds with new, fireproof type.
2.2.2.4.4. Replace deteriorated existing wooden head, jam & sill for all windows with new as shown on door/window schedule. (Natural color, oak)
2.2.2.4.5. Replace deteriorated existing aluminum louver with new as shown on floor plans and louver schedule.
2.2.2.4.6. Replace deteriorated existing fire extinguishers cabinets(FEC) with new as shown on floor plans and detail drawing.
2.2.2.4.7. Replace deteriorated existing all toilet accessories with new as shown on floor plans and detail drawings.
2.2.2.4.8. Replace interior & exterior signages with new as shown on floor plan, elevations and signage schedule.
2.2.2.4.9. Replace deteriorated existing metal shelf with mop rack with new in janitor room.
2.2.2.4.10. Replace deteriorated existing bulletin board with new as shown on floor plan, detail drawing and signage schedule.
2.2.2.4.11. Install trenches with new at mud area, mud room, eye washerroom and lab as shown on floor plan and detail drawing
2.2.2.4.12. Install projection screen and projector mount with new as shown on floor plans detail drawings and interior finish schedule.
2.2.2.4.13. Replace deteriorated existing universal tv wall mount with new as shown on floor plans, detail drawings and interior finish schedule.
2.2.2.4.14. Install SST handrail, guard rail, and SST boot scraper as shown on floor plan and detail drawing.
2.2.2.4.15. Replace deteriorated existing lockers with new(2tier) including lockset as shown on floor plan, elevation and material finish schedule.
TP I-3
2.2.2.4.16. replace deteriorated access doors with new on wall & ceiling as required.
2.2.2.4.17. Install wooden shower benches, shower curbs and shower curtains with new as shown on floor plan, interior elevation and detail drawing.
2.2.2.4.18. replace deteriorated existing lavatory cabinets and kitchen cabinet with new including base cabinets and upper cabinets as shown on floor plan, interior elevation and detail drawing.
2.2.3. Structural Work
2.2.3.1. Construct 150 THK concrete slab.
2.2.3.2. Construct wall with 200THK concrete wall & foundation.
2.2.3.3. Construct roof with steel column and beam.
2.2.3.4. Submit structural design analysis and shop drawing for approval.
2.2.4. Mechanical Work
2.2.4.1. Repair the heating and cooling system by installing new VRF duct-free heat pump outdoor units & indoor units, split air conditioning indoor & outdoor unit, electric unit heaters, electric wall heaters, electric ceiling heaters, pipes, valves, controller, insulations, controls, access doors, equipment support (conc. pad) and all associated accessories for heating and cooling system as shown on drawings. Remote controller indicators and labels shall be in English.
2.2.4.2. Repair the ventilation system by installing new exhaust fans, energy recovery ventilator outside air supply unit, controller, CO2 sensor, HVAC emergency shutdown switch, dampers, controls, diffusers, grilles, louvers, ducts, insulations, access doors, equipment support and all associated accessories for ventilation system as shown on drawings.
2.2.4.3. Perform DALT (Duct Air Leakage Test) and T.A.B. (Testing, Adjusting, and Balancing) after construction to verify that the H.V.A.C. system works properly.
2.2.4.4. Repair the plumbing system by installing new domestic cold and hot water piping system, sewer and vent piping system including plumbing fixtures, electric domestic hot water heater, domestic hot water recirculation pump, electric water cooler, trap primer, water hammer arresters, valves, control, access doors and all associated accessories as shown on drawings
2.2.5. Electrical Work
2.2.5.1. Install new interior/ exterior lighting fixtures, exit lights, toggle switches, 3 way switches, dimming switch, lighting contactors, photocell, wires and conduit.
2.2.5.2. Install new watthour meter, panelboards, receptacles, w/cover plates associated wiring & conduit.
2.2.5.3. Install new safety switches, motor controllers, junction boxes, control/power wires and conduit for mechanical systems.
TP I-4
2.2.5.4. Install new addressable fire alarm control and mass notification system panel, manual pull station, smoke & heat detectors, addressable module, antenna, visual signal strobes (15 or 75 candela), microphone, speaker (wattage as Req'd) device, fire alarm building transmitter and associated wiring and conduit.
2.2.5.5. Install new telecommunication system including telephone terminal board, telephone/data outlets w/cover plates, terminal blocks, equipment rack and associated wire & conduit.
2.2.5.6. Install CATV distribution cabinet, pull boxes, CATV outlets & associated wiring and conduit.
2.2.5.7. Install new exterior underground telecommunication line and accessories including telecommunication manhole.
2.2.5.8. Install new exterior underground power distribution line.
TP I-5
TECHNICAL PROVISIONS - II
TECHNICAL DETAIL SPECIFICATIONS
PROJECT NO TITLE LOCATION
XXXXX Repair Operation Building TBD
GENERAL: The specification sections listed below are applicable to this project. The specifications are from the “Standard Technical Specifications for O&MA Projects, Korea, Revision 1” (2014 OMA SPECS, REVISION 1), dated 20151030, located on the http://www.usfk.mil/Portals/105/Documents/Contracting/NewContract/2014-OMA-SPECS_REVISION-1.pdf. The electronic version of the specifications is Acrobat® PDF format and can be read with the Acrobat Reader® software.
The Standard Technical Detail Specifications:
The work shall conform to the most current version of the listed standards/specifications below.
DIVISION 01 – GENERAL REQUIREMENTS
| 01 30 00 | ADMINISTRATIVE REQUIREMENTS | |
| 01 32 01.00 10 | PROJECT SCHEDULE | |
| 01 33 00 | SUBMITTAL PROCEDURES | |
| 01 33 29 | LEED(TM) DOCUMENTATION | |
| 01 35 26 | GOVERNMENTAL SAFETY REQUIREMENTS | |
| 01 35 29.13 | HEALTH, SAFETY, AND EMERGENCY RESPONSE PROCEDURES |
FOR CONTAMINATED SITES
| 01 42 00 | SOURCES FOR REFERENCE PUBLICATIONS | |
| 01 45 00.00 10 | QUALITY CONTROL | |
| 01 50 00 | TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS | |
| 01 58 00 | PROJECT IDENTIFICATION | |
| 01 74 19 | CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT | |
| 01 78 00 | CLOSEOUT SUBMITTALS | |
| 01 78 23 | OPERATION AND MAINTENANCE DATA |
DIVISION 02 - EXISTING CONDITIONS
| 02 41 00 | DEMOLITION AND DECONSTRUCTION |
| 02 61 13 | EXCAVATION AND HANDLING OF CONTAMINATED |
MATERIAL
02 65 00 UNDERGROUND STORAGE TANK REMOVAL
| TP II-1 | ||
| 02 81 00 | TRANSPORTATION AND DISPOSAL OF HAZARDOUS |
MATERIALS
| 02 82 14.00 10 | ASBESTOS HAZARD CONTROL ACTIVITIES |
| 02 83 19.00 10 | LEAD BASED PAINT HAZARD ABATEMENT, TARGET |
HOUSING & CHILD OCCUPIED FACILITIES
DIVISION 03 – CONCRETE
| 03 11 13.00 10 | STRUCTURAL CAST-IN-PLACE CONCRETE FORMING | |
| 03 15 00.00 10 | CONCRETE ACCESSORIES | |
| 03 20 00.00 10 | CONCRETE REINFORCING | |
| 03 30 00 | CAST-IN-PLACE CONCRETE |
DIVISION 04 – MASONRY
04 20 00 MASONRY
DIVISION 05 - METALS
| 05 50 13 | MISCELLANEOUS METAL FABRICATIONS |
| 05 52 00 | METAL RAILINGS |
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
| 06 10 00 | ROUGH CARPENTRY |
| 06 20 00 | FINISH CARPENTRY |
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
| 07 21 16 | MINERAL FIBER BLANKET INSULATION | |
| 07 24 00 | EXTERIOR INSULATION AND FINISH SYSTEMS | |
| 07 41 13 | METAL ROOF PANELS | |
| 07 60 00 | FLASHING AND SHEET METAL | |
| 07 61 14.00 20 | STEEL STANDING SEAM ROOFING | |
| 07 84 00 | FIRESTOPPING | |
| 07 92 00 | JOINT SEALANTS |
DIVISION 08 – OPENINGS
| 08 11 13 | STEEL DOORS AND FRAMES | |
| 08 11 16 | ALUMINUM DOORS AND FRAMES | |
| 08 14 00 | WOOD DOORS |
TP II-2
| 08 51 13 | ALUMINUM WINDOWS | |
| 08 71 00 | DOOR HARDWARE | |
| 08 81 00 | GLAZING | |
| 08 87 16 | FRAGMENT RETENTION FILM FOR GLASS |
DIVISION 09 – FINISHES
| 09 22 36 | LATH | |
| 09 29 00 | GYPSUM BOARD | |
| 09 30 00 | CERAMIC TILE, QUARRY TILE, AND PAVER TILE | |
| 09 51 00 | ACOUSTIC CEILINGS | |
| 09 65 00 | RESILIENT FLOORING | |
| 09 90 00 | PAINTS AND COATINGS |
DIVISION 10 – SPECIALTIES
| 10 14 01 | EXTERIOR SIGNAGE | |
| 10 14 02 | INTERIOR SIGNAGE | |
| 10 21 13 | TOILET COMPARTMENTS | |
| 10 28 13 | TOILET ACCESSORIES |
DIVISION 12 – FURNISHINGS
| 12 21 00 | WINDOW BLINDS |
| 12 32 00 | MANUFACTURED WOOD CASEWORK |
DIVISION 22 – PLUMBING
22 00 00 PLUMBING, GENERAL PURPOSE
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING
| 23 00 00 | AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST SYSTEMS | |
| 23 05 93 | TESTING, ADJUSTING, AND BALANCING FOR HVAC | |
| 23 07 00 | THERMAL INSULATION FOR MECHANICAL SYSTEMS | |
| 23 09 53.00 20 | SPACE TEMPERATURE CONTROL SYSTEMS | |
| 23 82 02.00 10 | UNITARY HEATING AND COOLING EQUIPMENT |
DIVISION 26 – ELECTRICAL
26 00 00.00 20 BASIC ELECTRICAL MATERIALS AND METHODS
TP II-3
| 26 08 00 | APPARATUS INSPECTION AND TESTING | |
| 26 20 00 | INTERIOR DISTRIBUTION SYSTEM | |
| 26 41 00 | LIGHTING PROTECTION SYSTEM | |
| 26 51 00 | INTERIOR LIGHTING | |
| 26 56 00 | EXTERIOR LIGHTING |
DIVISION 27 – COMMUNICATIONS
27 10 00 BUILDING TELECOMMUNICATIONS CABLING SYSTEM
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY
| 28 31 33.00 10 | FIRE ALARM REPORTING SYSTEM, RADIO TYPE | |
| 28 31 64.00 10 | FIRE DETECTION AND ALARM SYSTEM, ADDRESSABLE | |
| 28 31 76 | INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEM |
DIVISION 31 – EARTHWORK
31 00 00 EARTHWORK
DIVISION 32 - EXTERIOR IMPROVEMENTS
| 32 01 16.17 | COLD MILLING OF BITUMINOUS PAVEMENTS |
| 32 05 33 | LANDSCPAE ESTABLISHMENT |
| 32 11 16.16 | BASE COURSE FOR RIGID AND SUBBASE COURSE FOR PERVIOUS |
PAVING
| 32 11 16 | SUBBASE FOR FLEXIBLE PAVING | |
| 32 12 10 | BITMUNOUS TRACK AND PRIME COATS | |
| 32 13 17 | COMPRESSION JOINT SEAL FOR CONCRETE PAVEMENTS | |
| 32 16 13 | CONCRETE SIDEWALK AND CURBS AND GUTTERS | |
| 32 17 24.00 10 | PAVEMENT MARKINGS | |
| 32 92 23 | SODDING |
DIVISION 33 – UTILITIES
| 33 11 00 | WATER DISTRIBUTION | |
| 33 30 00 | SANITARY SEWERS | |
| 33 70 02.00 10 | ELECTRICAL DISTRIBUTION SYSTEM, UNDERGROUND | |
| 33 82 00 | TELECOMMUNICATION OUTSIDE PLANT (OSP) |
TP II-4
TECHNICAL PROVISIONS - III
SPECIAL CONDITIONS
PROJECT NO TITLE LOCATION
XXXXX Repair Operation Building TBD
1. Material Approval Submittal:
1.1. The contractor shall submit a shop drawing submittal schedule and the material approval request with all supporting documents to the COR within 7 days after receipt of NTP.
1.2. The Contractor shall process submittals in accordance with Section 013300 – SUBMITTAL PROCEDURES.
2. Extended warranty - FAR 52.246-21
2.1. Extended warranty list
2.2. Contractor shall submit to COR the Warranty Certification with 4025 for the listed items.
2.3. Contractor shall submit to COR Warranty management plan and approve it before 30 days of pre-warranty conference. (OMA Sec 01 78 00)
2.4. Contractor shall have the Pre-Warranty Conference before Contract Close Date. (OMA Sec 01 78)
2.5. Warranty Information and Data
2.5.1. Contractor shall submit Warranty tag design, COR shall review and approve it for the listed and shall install it for the listed items. (OMA Sec 01 78 00)
2.5.2. Submit the O&M Manual with Manufacture’s instruction for DPW training. (OMA Sec 01 78 00)
TP III-1
3. The contractor shall have personnel on site for the sprinkler work and the fire alarm work upon Government's direction, who are certified by the National Institute for Certification in Engineering Technologies (NICET) Level III or equivalent. Equivalent Certificates in Korea are the followings which are issued by the Human Resource Development Service of Korea. If the contractor doesn’t have personnel who are certified by NICET, the contractor shall have two personnel that one is certified for (1) and the other for (2) below.
(1) Engineer Fire Fighting Facilities - Electrical (소방설비기사 -전기)
(2) Engineer Fire Fighting Facilities - Mechanical (소방설비기사 -기계)
4. Environmental Requirements in Contract:
The Contractor shall perform work consistent with the relevant policy and objectives identified in Installation’s Environmental Management System (EMS). The Contractor shall perform work in a manner that conforms to all appropriate Environmental Management Programs and Operational Controls identified by Installation’s EMS, including pollution prevention, waste reduction, energy use, and natural resource protection. The Contractor shall provide monitoring and measurement information as necessary for the organization to address environmental performance relative to the environmental, energy, and transportation management goals. In addition, the Contractor shall advise their employees of their roles and responsibilities identified by the EMS and how these requirements affect their work performed under this contract. The Contractor is responsible for ensuring that the Contractor and any persons involved in the supervision or performance of the contract complete all required Environmental training.
In the event of any environmental nonconformance or noncompliance associated with the contracted services, the contractor shall take corrective and/or preventative actions. In the event of any noncompliance with any federal, state, or local environmental law, regulation or requirement, the Contractor shall immediately respond by taking all appropriate corrective actions and notifying the Contracting Officer’s Representative (COR) and the Environmental Office. For any nonconformance with the EMS, the Contractor shall take corrective action and initiate further preventative action, as required by the Environmental Office.
All on-site contractor personnel shall complete necessary safety and environmental training specified for the type of work conducted on-site. Upon contract award, the COR will notify the EMS Manager to arrange Environmental training for appropriate staff.
Additionally, when ordering supplies for use on Installation, all contractor personnel must favor energy-efficient, recycled or reclaimed material whenever practicable.
The responsibilities of all contractor personnel include:
(1) Comply with all applicable environmental laws, regulations and installation environmental policies.
(2) Control and prevent spills or hazardous substances releases IAW installation Spill Prevention Plan.
TP III-2
| (3) | Ensure dust, debris, materials, trash, etc., do not become air borne and travel off the project site. |
| (4) | Do not remove, cut, deface, injure, or destroy land resources including trees, shrubs, vines, topsoil and land forms without approval, except in areas indicated on the drawings or specified to be cleared. |
(5) Monitor all water areas affected by construction activities to prevent pollution of surface and ground waters. Do not apply toxic or hazardous chemicals to soil or vegetation unless otherwise indicated.
(6) Open burning is prohibited on the Government premises IAW installation environmental policy.
(7) Participate in installation’s recycling program.
(8) Reducing the amount of hazardous material and/or solvent used by purchasing fewer hazardous materials and by increasing the use of products with recycled content. Spills of hazardous or toxic materials must be immediately reported to the Contracting Officer and the Environmental Office. Storage, describing, packaging, labeling, marking and placarding of hazardous waste and hazardous material IAW applicable environmental laws, regulations and local environmental policies. Transport hazardous waste off Government property and dispose of it in compliance with National, Provincial, and/or Local requirements for solid waste disposal.
(9) Reducing the amount of solid waste from construction and demolition debris, and scrap metal sent to municipal and rubble landfills by reducing, reusing, and recycling. Handling, storage, and disposal of solid waste must be conducted to prevent contamination. Transport solid waste off Government property and dispose of it in compliance with National, Provincial, and/or Local requirements for solid waste disposal.
(10) Conserving energy and water usage by turning off lights and equipment when not in use and using only the necessary amount of water needed to complete the required tasks. Continuous conservation of our natural resources is a must.
(11) When potential cultural or historic items are inadvertently found during construction activities, immediately cease activities in the vicinity of the discovery and report the findings to the Environmental Office.
(12) Participate in installation’s Integrated Pest Management (IPM) program whenever practicable.
(13) Minimize interference with disturbance to, and damage to fish, wildlife, and plants including their habitat.
5. CONTRACT REQUIREMENTS PACKAGE ANTITERRORISM/OPERATIONS SECURITY REVIEW COVER SHEET
TP III-3
After Notice to process is issued, COR shall take following action, Section IV. Standard Contract Language/Contract Clause Applicability and/or Additional SOW Language.
A. AT Level I training. This standard language is for contractor employees with an area of performance within as Army controlled installation, facility or area. All contractor employees, including subcontractor employees, requiring access to Army installations, facilities, and controlled-access areas shall complete AT Level I awareness training within 30 calendar days after the contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR or to the contracting officer, if a COR is not assigned, within 05 calendar days after completion of training by all employees and subcontractor personnel. AT Level I awareness training is available at the following website: http://jko.jten.mil
B. Access and general protection/security policy and procedures. This standard language is for contractor employees with an area of performance within Army controlled installation, facility, or area. Contractor and all associated sub-contractors employees shall provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9, Personal Identity Verification of Contractor Personnel) as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.
B-a. For contractors that do not require CAC, but require access to a DoD facility or installation. Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05/AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.
C. iWATCH Training. The contractor and all associated sub-contractors shall brief all employees on the local iWATCH program (training standards provided by the requiring activity ATO). This local developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR. This training shall be completed within 30 calendar days of contract award and within 05 calendar days of new employees commencing performance with the results reported to the COR NLT 30 calendar days after contract award.
D. For contracts that require OPSEC Training. Per AR 530-1 Operations Security, the contractor employees must complete Level I OPSEC Awareness training. New employees must be trained within 30 calendar days of their reporting for duty and annually thereafter.
TP III-4
APPENDIX "A"
LIST OF APPLICABLE CONTRACT DRAWINGS
PROJECT NO TITLE LOCATION
XXXXX Repair Operation Building TBD
GENERAL: The work shall conform to the following contract drawings and OMA standard detail drawings, 2014 (dated 30 November 2015), issued by the Department of the Army, Installation Management Agency, Korea Region Office and located on http://www.usfk.mil/Portals/105/Documents/Contracting/NewContract/STANDARD-DETAIL-DRAWINGS-FOR-OMA-PROJECTS-KOREA_20151130.pdf, all of which form a part of the specifications.
| Ring No. |
| Sheet No. |
| Description |
| Date |
| 1 |
| T-1 |
| TITLE SHEET -1 |
| 1 DEC 22 |
| 2 |
| T-2 |
| TITLE SHEET -2 |
| 1 DEC 22 |
1 DEC 22
CIVIL
1 DEC 22
| 3 |
| C-1 |
| GENERAL NOTS |
| 1 DEC 22 |
| 4 |
| C-2 |
| REMOVAL PLAN |
| 1 DEC 22 |
| 5 |
| C-3 |
| SITE LAYOUT PLAN AND SCOPE OF WORK |
| 1 DEC 22 |
| 6 |
| C-4 |
| RAMP DETAIL |
| 1 DEC 22 |
| 7 |
| C-5 |
| MISC DEAILS -1 |
| 1 DEC 22 |
| 8 |
| C-6 |
| MISC DEAILS -2 |
| 1 DEC 22 |
| 9 |
| C-7 |
| MISC DETAILS -3 |
| 1 DEC 22 |
| 10 |
| C-8 |
| SEWER M/H |
| 1 DEC 22 |
1 DEC 22
ARCHITECTURAL
| 11 |
| A-1 |
| SCOPE OF WORK & GENERAL NOTES |
| 1 DEC 22 |
| 12 |
| A-2 |
| EXIST/REMOVAL GROUND FLOOR PLAN |
| 1 DEC 22 |
| 13 |
| A-3 |
| NEW GROUND FLOOR PLAN |
| 1 DEC 22 |
| 14 |
| A-4 |
| ROOF PLAN |
| 1 DEC 22 |
| 15 |
| A-5 |
| ELEVATIONS -1 |
| 1 DEC 22 |
| 16 |
| A-6 |
| ELEVATIONS -2 |
| 1 DEC 22 |
| 17 |
| A-7 |
| SECTIONS |
| 1 DEC 22 |
| 18 |
| A-8 |
| ENLARGED FLOOR PLAN |
| 1 DEC 22 |
A-1
| 19 |
| A-9 |
| ENLARGED FLOOR PLAN AND INTERIOR ELEVATIONS -1 |
| 1 DEC 22 |
| 20 |
| A-10 |
| ENLARGED FLOOR PLAN AND INTERIOR ELEVATIONS -2 |
| 1 DEC 22 |
| 21 |
| A-11 |
| EXTERIOR WALL SECTIONS |
| 1 DEC 22 |
| 22 |
| A-12 |
| INTERIOR WALL SECTION |
| 1 DEC 22 |
| 23 |
| A-13 |
| ROOF DETAILS |
| 1 DEC 22 |
| 24 |
| A-14 |
| CABINET DETAILS |
| 1 DEC 22 |
| 25 |
| A-15 |
| MISC DETAILS -1 |
| 1 DEC 22 |
| 26 |
| A-16 |
| MISC DETAILS -2 |
| 1 DEC 22 |
| 27 |
| A-17 |
| MISC DETAILS -3 |
| 1 DEC 22 |
| 28 |
| A-18 |
| MISC DETAILS -4 |
| 1 DEC 22 |
| 29 |
| A-19 |
| MISC DETAILS -5 |
| 1 DEC 22 |
| 30 |
| A-20 |
| INTERIOR, EXTERIOR FINISH SCHEDULE & FINISH SCHEDULE NOTES |
| 1 DEC 22 |
| 31 |
| A-21 |
| MATERIRAL & COLOR SCHEDULE |
| 1 DEC 22 |
| 32 |
| A-22 |
| DOOR/WINDOW SCHEDULE, ELEVATIONS AND DETAIL |
| 1 DEC 22 |
| 33 |
| A-23 |
| HARDWARE SCHEDULE & DOOR/WINDOW NOTE |
| 1 DEC 22 |
| 34 |
| A-24 |
| SIGNAGE PLAN, SCHEDULE & DETAILS |
| 1 DEC 22 |
STRUCTURAL
| 35 |
| S-1 |
| GENERAL NOTES, DESIGN DATA & TYPICAL DETAILS |
| 1 DEC 22 |
| 36 |
| S-2 |
| EXIST/REMOVAL GROUND FLOOR PLAN |
| 1 DEC 22 |
| 37 |
| S-3 |
| FOUNDATION/NEW GROUND FLOOR PLAN |
| 1 DEC 22 |
| 38 |
| S-4 |
| ROOF FRAMING PLAN |
| 1 DEC 22 |
| 39 |
| S-5 |
| CROSS SECTIONS |
| 1 DEC 22 |
| 40 |
| S-6 |
| BEAM, COLUMN, WALL & FOUNDATION SCHEDULE |
| 1 DEC 22 |
| 41 |
| S-7 |
| DETAILS |
| 1 DEC 22 |
MECHANICAL
| 42 |
| M-1 |
| LEGEND & ABBREVIATION |
| 1 DEC 22 |
| 43 |
| M-2 |
| GENERAL NOTES & SCOPE OF WORK |
| 1 DEC 22 |
| 44 |
| M-3 |
| EQUIPMENT SCHEDULE -1 |
| 1 DEC 22 |
| 45 |
| M-4 |
| EQUIPMENT SCHEDULE -2 |
| 1 DEC 22 |
| 46 |
| M-5 |
| NEW HVAC PIPING ENLARGED PLAN |
| 1 DEC 22 |
| 47 |
| M-6 |
| NEW HVAC ENLARGED PLAN |
| 1 DEC 22 |
| 48 |
| M-7 |
| NEW DOMESTIC WATER PIPING ENLARGED PARTIAL PLAN |
| 1 DEC 22 |
| 49 |
| M-8 |
| NEW SEWER & VENT PIPING ENLARGED PARTIAL PLAN |
| 1 DEC 22 |
A-2
| 50 |
| M-9 |
| MECH CONTROL DIAGRAMS |
| 1 DEC 22 |
| 51 |
| M-10 |
| MECH DETAILS -1 |
| 1 DEC 22 |
| 52 |
| M-11 |
| MECH DETAILS -2 |
| 1 DEC 22 |
| 53 |
| M-12 |
| MECH DETAILS -3 |
| 1 DEC 22 |
ELECTRICAL
| 54 |
| E-1 |
| LEGEND, GENERAL NOTES AND SCOPE OF WORKS |
| 1 DEC 22 |
| 55 |
| E-2 |
| EXIST/NEW EXTERIOR POWER LINE DISTRIBUTION PLAN |
| 1 DEC 22 |
| 56 |
| E-3 |
| EXIST/NEW EXTERIOR TELECOMMUNICATION LINE DISTRIBUTION PLAN -1 |
| 1 DEC 22 |
| 57 |
| E-4 |
| EXIST/NEW EXTERIOR TELECOMMUNICATION LINE DISTRIBUTION PLAN -2 |
| 1 DEC 22 |
| 58 |
| E-5 |
| NEW LIGHTING PLAN |
| 1 DEC 22 |
| 59 |
| E-6 |
| LIGHTING FIXTURE DETAILS |
| 1 DEC 22 |
| 60 |
| E-7 |
| LIGHT FIXTURE SCHEDULE |
| 1 DEC 22 |
| 61 |
| E-8 |
| NEW POWER PLAN |
| 1 DEC 22 |
| 62 |
| E-9 |
| NEW POWER/CONTROL PLAN FOR MECHANICAL SYSTEM |
| 1 DEC 22 |
| 63 |
| E-10 |
| EXIST/NEW POWER ONE LINE DIAGRAM |
| 1 DEC 22 |
| 64 |
| E-11 |
| NEW PANELBOARD “P1”, “P2” & “M” LOAD SCHEDULE |
| 1 DEC 22 |
| 65 |
| E-12 |
| NEW PANELBOARD “C” & “MDP” LOAD SCHEDULE |
| 1 DEC 22 |
| 66 |
| E-13 |
| NEW FIRE ALARM AND MASS NOTIFICATION SYSTEM PLAN |
| 1 DEC 22 |
| 67 |
| E-14 |
| NEW FIRE ALARM/MASS NOTIFICATION SYSTEM DIAGRAM |
| 1 DEC 22 |
| 68 |
| E-15 |
| NEW LAN/TEL PLAN |
| 1 DEC 22 |
| 69 |
| E-16 |
| NEW LAN/TEL SYSTEM DIAGRAM |
| 1 DEC 22 |
| 70 |
| E-17 |
| NEW CATV PLAN |
| 1 DEC 22 |
| 71 |
| E-18 |
| NEW CATV DIAGRAM |
| 1 DEC 22 |