Att E JME Schedule.pdf
PDF 3 MB Posted
- Solicitation number
- S-P03062-00016905
- Issued by
- Clackamas County, Oregon
About this file
This document is a detailed project schedule (JMES - Master - GMP Schedule Revision 6.1) for the John McLoughlin Elementary School Addition & Renovation project being undertaken by Oregon City School District No. 62. The schedule establishes a comprehensive timeline spanning from August 18, 2025, through October 29, 2027, encompassing the entire project lifecycle from preconstruction through final completion. The project is organized into three primary phases: the preconstruction phase (August 2025 - May 2026), the construction phase (June 2026 - September 2027), and includes school move schedules coordinated with instructional calendars to minimize disruption. Key milestones include design development completion by January 2026, construction document finalization by May 2026, modular classroom procurement and installation throughout summer 2026, phased interior buildout of classrooms, restrooms, cafeteria, kitchen, gymnasium, music room, and library spaces, and final school move-in operations scheduled for August 2027. The schedule incorporates city and OAC (Oregon City/Owner's Agent) acceptance requirements for each space prior to occupancy, with multiple inspection and commissioning activities required throughout construction.
The schedule details extensive material procurement timelines with submission, architect review, and approval processes for mechanical systems (AHUs, rooftop units), electrical components (lighting, panels, fire alarm connections), plumbing and fire suppression systems, structural elements, roofing, doors and hardware, glazing, casework, and photovoltaic systems. Site work includes demolition, abatement of hazardous materials in phases, structural modifications, installation of modular classroom units to serve as temporary surge space, utility connections (sewer, water, storm drainage), and final hardscaping and landscaping restoration. The project establishes specific completion targets for each construction phase, with Phase 1 (East Side Classrooms) moving into permanent spaces by January 2027, Phase 2 (North/South Classrooms and Music) becoming operational by June 2027, and Phase 3 (Kindergarten and remaining spaces) completing by August 2027. MEP commissioning and start-up activities are scheduled coincident with each phase's completion, and final site demobilization, parking lot restoration, and playground installation are planned for late summer 2027.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ID Description Original
Duration Start Finish
Project Summeries 573 08/18/25A 10/29/27A
School Calender 524 09/02/25A 09/07/27
10 School Calender - 2025/2026/2027 524 09/02/25A 09/07/27
20 School Closed 1 10/10/25A 10/10/25A
30 Staff Working - No Students 1 10/20/25A 10/20/25A
40 Staff Working - No Students 1 11/10/25A 11/10/25A
50 Thanksgiving Break 2026 3 11/26/25A 11/28/25A
60 Winter Break 2025 9 12/22/25A 01/05/26A
70 Staff Working - No Students 1 01/05/26A 01/05/26A
80 MLK Holiday 1 01/19/26A 01/19/26A
90 Staff Working - No Students 2 01/29/26A 01/30/26A
100 School Closed 1 02/13/26A 02/13/26A
110 Presidents Holiday 1 02/16/26A 02/16/26A
120 Staff Working - No Students 1 03/06/26A 03/06/26A
130 Spring Break 2026 5 03/23/26A 03/27/26A
140 Staff Working - No Students 1 04/10/26A 04/10/26A
150 Staff Working - No Students 1 05/01/26A 05/01/26A
160 Memorial Holiday 1 05/25/26A 05/25/26A
170 Last Day Of School 2026 1 06/12/26 06/12/26
180 Summer Break 2026 57 06/15/26 09/01/26
190 First Day of School 2026 1 09/02/26 09/02/26
200 Thanksgiving Break 2026 2 11/26/26A 11/27/26A
210 Winter Break 2027 10 12/21/26 01/01/27
220 Spring Break 2027 5 03/22/27 03/26/27
230 Last Day of School 2027 1 06/11/27 06/11/27
240 Summer Break 2027 59 06/14/27 09/02/27
250 First Day of School 2027 1 09/02/27A 09/02/27A
Preconstruction Phase 202 08/18/25A 05/29/26
260 Precon Activities 202 08/18/25A 05/29/26
Construction Phase 320 06/15/26 09/03/27
270 Construction Activities 320 06/15/26 09/03/27
School Move Schedule 317 06/12/26 08/30/27
2026 2027 2028
P ro je ct
F in is h
D a ta
D a te
School Calender - 2025/2026/2027
School Closed
Staff Working - No Students
Staff Working - No Students
Thanksgiving Break 2026
Winter Break 2025
Staff Working - No Students
MLK Holiday
Staff Working - No Students
School Closed
Presidents Holiday
Staff Working - No Students
Spring Break 2026
Staff Working - No Students
Staff Working - No Students
Memorial Holiday
Last Day Of School 2026
Summer Break 2026
First Day of School 2026
Thanksgiving Break 2026
Winter Break 2027
Spring Break 2027
Last Day of School 2027
Summer Break 2027
First Day of School 2027
Precon Activities
Construction Activities
Start Date: 08/18/25
Finish Date: 09/07/27
Data Date: 04/24/26
Run Date: 04/29/26
JMES - Master - GMP Schedule (REV-6.1) 4.27.26.ppx
JOHN McLOUGHLIN ELEMENTARY SCHOOL
ADDITION & RENOVATION
OREGON CITY SCHOOL DISTRICT 62
Page 1A
Duration Start Finish
Phase 1 - School Surge Space Move Schedule 56 06/12/26 08/28/26
East Side Classrooms / Restrooms / ERC / Library 56 06/12/26 08/28/26
280 All Spaces Move Out for Construction 1 06/12/26 06/12/26
290 (8) Classrooms Move Into Modulars 5 08/24/26 08/28/26
300 Library Move Into Modular 5 08/24/26 08/28/26
310 Gang Restrooms Utilize Portable Restroom Trailers 5 08/24/26 08/28/26
Music / Cafeteria / Kitchen / OT/PT / Storage / Existing MDF 1 06/12/26 06/12/26
320 Move Into GYM for Summer Storage 1 06/12/26 06/12/26
330 Storage / OT/PT - Move Out for Construction 1 06/12/26 06/12/26
335 Music Move Into Existing Modular 1 06/12/26 06/12/26
Hard Hat Hallway 1 06/12/26 06/12/26
340 Clear / Protect Hallway of All Wall Art 1 06/12/26 06/12/26
Phase 1 - School Move In Schedule 100 08/24/26 01/08/27
East Side Classrooms 10 12/28/26 01/08/27
350 Move Into (8) Classrooms 10 12/28/26 01/08/27
360 Move Into SPED / ERC 10 12/28/26 01/08/27
370 Open Gang Restrooms 1 12/28/26 12/28/26
Cafeteria / Music / New Corridor / Gym 5 08/24/26 08/28/26
380 Move Into Cafeteria / Open New Corridor 5 08/24/26 08/28/26
Phase 2 - School Surge Space Move Schedule 10 12/28/26 01/08/27
North / South Classrooms / Music 10 12/28/26 01/08/27
400 (10) Classrooms Move Into Modulars 10 12/28/26 01/08/27
410 (2) Classrooms Move Into Library Shelled Space 10 12/28/26 01/08/27
420 Music Moves Back Into New Space 10 12/28/26 01/08/27
Phase 3 - School Surge Space Move Schedule 1 06/14/27 06/14/27
Kindergarten Classrooms / Kitchen / Cafeteria / Remaining Spaces 1 06/14/27 06/14/27
430 Move Out for Construction (Store in Gym?) 1 06/14/27 06/14/27
Phase 3 - School Move In Schedule 10 08/16/27 08/27/27
All Classrooms / Spaces Move Into Final Locations 10 08/16/27 08/27/27
2026 2027 2028
P ro je ct
F in is h
D a ta
D a te
All Spaces Move Out for Construction
(8) Classrooms Move Into Modulars
Library Move Into Modular
Gang Restrooms Utilize Portable Restroom Trailers
Move Into GYM for Summer Storage
Storage / OT/PT - Move Out for Construction
Music Move Into Existing Modular
Clear / Protect Hallway of All Wall Art
Move Into (8) Classrooms
Move Into SPED / ERC
Open Gang Restrooms
Move Into Cafeteria / Open New Corridor
(10) Classrooms Move Into Modulars
(2) Classrooms Move Into Library Shelled Space
Music Moves Back Into New Space
Move Out for Construction (Store in Gym?)
Start Date: 08/18/25
Finish Date: 09/07/27
Data Date: 04/24/26
Run Date: 04/29/26
JMES - Master - GMP Schedule (REV-6.1) 4.27.26.ppx
JOHN McLOUGHLIN ELEMENTARY SCHOOL
ADDITION & RENOVATION
Page 2A
Duration Start Finish
440 Move-In 10 08/16/27 08/27/27
Phase 3.1 School Move In Schedule 1 08/30/27 08/30/27
Kitchen 1 08/30/27 08/30/27
450 Move - In 1 08/30/27 08/30/27
City / Fire Marshal / OAC Sign-Off / Building Completion 374 05/26/26 10/29/27A
1010 Mobilize Lewis Office Trailer / Temp Power / Small Section of Fencing 1 05/26/26 05/26/26
1020 Abatement Phase - 1 (Weekend Work) 6 06/12/26 06/19/26
1030 Abatement Phase 1 Clearance 1 06/19/26 06/19/26
1040 City / OAC Acceptance of Modular Spaces (Move-In Ready) 1 08/03/26 08/03/26
1045 Modulars Fire Alarm - Fully Functional (City / Fire Marshal Acceptance) 1 08/03/26 08/03/26
1050 City / OAC Acceptance of Phase 1 Summer Spaces (Move-In Ready) 5 08/24/26 08/28/26
1060 City / OAC Acceptance of Phase 1 Spaces (Move-In Ready) 5 12/07/26 12/11/26
1065 Fire Alarm - Sprinkler System Fully Functional - Phase 1 Spaces (City / Fire Marshal Acceptance) 1 12/07/26 12/07/26
1070 City / OAC Acceptance of Music Room (Move-In Ready) 4 12/07/26 12/10/26
1075 Fire Alarm - Sprinkler System Fully Functional (City / Fire Marshal Acceptance) 1 12/07/26 12/07/26
1080 City / OAC Acceptance of Phase 2 Spaces (Move-In Ready) 5 06/15/27 06/21/27
1085 Fire Alarm - Sprinkler System Fully Functional - Phase 2 Spaces (City / Fire Marshal Acceptance) 1 06/15/27 06/15/27
1096 Substantial Completion Phase 1 and Phase 2 1 08/02/27 08/02/27
1090 City / OAC Acceptance of Phase 3 Spaces (Move-In Ready) 4 08/16/27 08/19/27
1092 Fire Alarm - Sprinkler System Fully Functional - Phase 3 Spaces (City / Fire Marshal Acceptance) 1 08/16/27 08/16/27
1103 Substaintial Completion Phase 3 1 08/20/27 08/20/27
1101 Final Completion 1 10/29/27A 10/29/27A
Preconstruction 257 07/25/25A 07/22/26
Proposal / Contract 164 09/22/25A 05/11/26
460 MEP - RFP Process / Award 15 09/22/25A 10/10/25A
470 Board Approved GMP 1 05/11/26 05/11/26
Design 207 07/25/25A 05/12/26
Schematic Design 1 07/25/25A 07/25/25A
480 SD Drawings - Issued 1 07/25/25A 07/25/25A
Design Development 122 07/25/25A 01/14/26A
490 DD Drawings (16 Weeks) 66 07/25/25A 11/14/25A
2026 2027 2028
P ro je ct
F in is h
D a ta
D a te
Move-In
Move - In
Mobilize Lewis Office Trailer / Temp Power / Small Section of Fencing
Abatement Phase - 1 (Weekend Work)
Abatement Phase 1 Clearance
City / OAC Acceptance of Modular Spaces (Move-In Ready)
Modulars Fire Alarm - Fully Functional (City / Fire Marshal Acceptance)
City / OAC Acceptance of Phase 1 Summer Spaces (Move-In Ready)
City / OAC Acceptance of Phase 1 Spaces (Move-In Ready)
Fire Alarm - Sprinkler System Fully Functional - Phase 1 Space
City / OAC Acceptance of Music Room (Move-In Ready)
Fire Alarm - Sprinkler System Fully Functional (City / Fire Mars
City / OAC Acceptance of Phase 2 Spaces (Move
Fire Alarm - Sprinkler System Fully Functional - P
Substantial Completion Phase 1 and Phase 2
City / OAC Acceptance of Phase 3 Spaces (M
Fire Alarm - Sprinkler System Fully Functiona
Substaintial Completion Phase 3
Final Completion
MEP - RFP Process / Award
Board Approved GMP
SD Drawings - Issued
DD Drawings (16 Weeks)
Start Date: 08/18/25
Finish Date: 09/07/27
Data Date: 04/24/26
Run Date: 04/29/26
JMES - Master - GMP Schedule (REV-6.1) 4.27.26.ppx
JOHN McLOUGHLIN ELEMENTARY SCHOOL
ADDITION & RENOVATION
Page 3A
Duration Start Finish
500 DD District Direction 5 10/13/25A 10/17/25A
510 DD Drawings - Issued 5 11/10/25A 11/14/25A
520 DD Structural Revisions 6 11/17/25A 11/24/25A
530 DD Drawing District Review (2 Weeks) 10 11/25/25A 12/08/25A
540 DD Cost Estimate 20 11/25/25A 12/30/25A
550 DD Review / VE (2 Weeks) 10 12/31/25A 01/14/26A
Construction Documents 120 11/25/25A 05/12/26
560 CD Drawings 120 11/25/25A 02/27/26A
570 100% CD Drawings - Issued 1 02/27/26A 02/27/26A
580 Bid Set CD Drawings - Issued 1 03/06/26A 03/06/26A
EWA's / GMP 47 03/09/26A 05/12/26
EWA 2-Long Lead Equipment (AHUs, Modular Classrooms) 2 03/09/26A 03/10/26A
590 OCSD Board Meeting >Approval EWA 2 1 03/09/26A 03/09/26A
600 Modular Classrooms Hold 1 03/10/26A 03/10/26A
610 Long Lead Mechanical - AHU's 1 03/10/26A 03/10/26A
620 Lewis MOB 1 03/10/26A 03/10/26A
EWA 3-Long Lead & Critical Procurement/Fire Protect/Sewer/Water Conn 2 04/27/26 04/28/26
630 OCSD Board Meeting >Approval EWA 3 1 04/27/26 04/27/26
631 Modular Classrooms Award 1 04/28/26 04/28/26
632 Demo & Abatement 1 04/28/26 04/28/26
640 Lighting - Prairie 1 04/28/26 04/28/26
650 Electrical Panels - Prairie 1 04/28/26 04/28/26
651 FACP (Tie into Classroom Trailers) - Prairie 1 04/28/26 04/28/26
660 DFH Award -TBD 1 04/28/26 04/28/26
670 Roofing Award - TBD 1 04/28/26 04/28/26
680 Skylight Award - TBD 1 04/28/26 04/28/26
690 Fire Protection Award - TBD 1 04/28/26 04/28/26
700 Sewer / Water Connections: Civil Award - TBD 1 04/28/26 04/28/26
710 Structural Award - TBD 1 04/28/26 04/28/26
GMP - Structural, Remaining Scopes / Finishes 2 05/11/26 05/12/26
709 OCSD Board Meeting >Approval GMP 1 05/11/26 05/11/26
720 Remaining Scopes / Finishes Award - TBD 1 05/12/26 05/12/26
2026 2027 2028
P ro je ct
F in is h
D a ta
D a te
DD District Direction
DD Drawings - Issued
DD Structural Revisions
DD Drawing District Review (2 Weeks)
DD Cost Estimate
DD Review / VE (2 Weeks)
CD Drawings
100% CD Drawings - Issued
Bid Set CD Drawings - Issued
OCSD Board Meeting >Approval EWA 2
Modular Classrooms Hold
Long Lead Mechanical - AHU's
Lewis MOB
OCSD Board Meeting >Approval EWA 3
Modular Classrooms Award
Demo & Abatement
Lighting - Prairie
Electrical Panels - Prairie
FACP (Tie into Classroom Trailers) - Prairie
DFH Award -TBD
Roofing Award - TBD
Skylight Award - TBD
Fire Protection Award - TBD
Sewer / Water Connections: Civil Award - TBD
Structural Award - TBD
OCSD Board Meeting >Approval GMP
Remaining Scopes / Finishes Award - TBD
Start Date: 08/18/25
Finish Date: 09/07/27
Data Date: 04/24/26
Run Date: 04/29/26
JMES - Master - GMP Schedule (REV-6.1) 4.27.26.ppx
JOHN McLOUGHLIN ELEMENTARY SCHOOL
ADDITION & RENOVATION
Page 4A
Duration Start Finish
Land Use Drawings 81 08/18/25A 12/30/25A
Permitting 103 12/31/25A 05/25/26A
750 Submit / Procure - Erosion Prevention and Sediment Control (EPSC) Permit 72 12/31/25A 04/10/26A
760 Submit / Procure - City Approved Land Use / Modular Permit 89 12/31/25A 05/05/26
770 Submit - Demo / Site Permit 5 03/06/26A 03/12/26A
780 Submit - Final Building Permit Package 5 03/06/26A 03/12/26A
800 Final Building Permit - City Review / Approval 38 03/13/26A 05/05/26
810 City Approved Demo / Building Permits 1 05/06/26 05/06/26
820 City Approved SUPA Permit 1 05/25/26A 05/25/26A
Submittals / Procurement 98 03/09/26A 07/22/26
830 Approve Hold on Classroom Modular Order 1 03/10/26A 03/10/26A
840 Procure Classroom Modulars 90 03/10/26A 07/10/26
Material Procurement Onsite Target 98 03/09/26A 07/22/26
23 74 00 AHU- GYM, AHU-CAF, AHU-LIB 72 03/10/26A 06/17/26
850 SUB - Prepare & Submit AHU's Section 23 74 00 30 03/10/26A 03/26/26A
867 A/E - Review AHU's Section 23 74 -00 Submittal 5 03/27/26A 04/07/26A
868 A/E - Approval AHU's Section 23 74 00 1 04/07/26A 04/07/26A
869 SUB- Release AHU's Section 23 74 00 for Fabrications and Procurement (Breakout Roof Curbs if AHU's are longer Leadtime)50 04/08/26A 06/16/26
980 Section 23 74 00 AHU- GYM, AHU-CAF, AHU-LIB -Onsite 1 06/17/26 06/17/26
26 51 00 Lighting 78 03/09/26A 06/24/26
6520 SUB - Prepare & Submit Section 26 51 00 37 03/09/26A 04/28/26
6530 A/E - Review Section 26 51 00 Submittal 10 04/29/26 05/12/26
6540 A/E - Approval Section 26 51 00 1 05/12/26 05/12/26
6550 SUB- Release Section 26 51 00 Materials for Fabrications and Procurement 30 05/13/26 06/23/26
6560 Section 26 51 00 Materials Onsite 1 06/24/26 06/24/26
All Sections Starting with 22 00 00 thru 22 40 00 70 03/09/26A 06/12/26
7220 SUB - Prepare & Submit Section 22 00 00 thru 22 40 00 39 03/09/26A 04/30/26
7230 A/E - Review Section 22 00 00 thru 22 40 00 Submittal 10 05/01/26 05/14/26
7240 A/E - Approval Section 22 00 00 thru 22 40 00 1 05/14/26 05/14/26
7250 SUB- Release Section 22 00 00 thru 22 40 00 Materials for Fabrications and Procurement 20 05/15/26 06/11/26
7260 Section 22 00 00 thru 22 40 00 Materials Onsite 1 06/12/26 06/12/26
2026 2027 2028
P ro je ct
F in is h
D a ta
D a te
Submit / Procure - Erosion Prevention and Sediment Control (EPSC) Permit
Submit / Procure - City Approved Land Use / Modular Permit
Submit - Demo / Site Permit
Submit - Final Building Permit Package
Final Building Permit - City Review / Approval
City Approved Demo / Building Permits
City Approved SUPA Permit
Approve Hold on Classroom Modular Order
Procure Classroom Modulars
SUB - Prepare & Submit AHU's Section 23 74 00
A/E - Review AHU's Section 23 74 -00 Submittal
A/E - Approval AHU's Section 23 74 00
SUB- Release AHU's Section 23 74 00 for Fabrications and Procurement (B
Section 23 74 00 AHU- GYM, AHU-CAF, AHU-LIB -Onsite
SUB - Prepare & Submit Section 26 51 00
A/E - Review Section 26 51 00 Submittal
A/E - Approval Section 26 51 00
SUB- Release Section 26 51 00 Materials for Fabrications and Procuremen
Section 26 51 00 Materials Onsite
SUB - Prepare & Submit Section 22 00 00 thru 22 40 00
A/E - Review Section 22 00 00 thru 22 40 00 Submittal
A/E - Approval Section 22 00 00 thru 22 40 00
SUB- Release Section 22 00 00 thru 22 40 00 Materials for Fabrications and
Section 22 00 00 thru 22 40 00 Materials Onsite
Start Date: 08/18/25
Finish Date: 09/07/27
Data Date: 04/24/26
Run Date: 04/29/26
JMES - Master - GMP Schedule (REV-6.1) 4.27.26.ppx
JOHN McLOUGHLIN ELEMENTARY SCHOOL
ADDITION & RENOVATION
Page 5A
Duration Start Finish
All Sections Starting with 26 00 00 thru 26 28 16 70 03/09/26A 06/12/26
7270 SUB - Prepare & Submit Section 26 00 00 thru 26 28 16 39 03/09/26A 04/30/26
7280 A/E - Review Section 25 31 00 Submittal 10 05/01/26 05/14/26
7290 A/E - Approval Section 26 00 00 thru 26 28 16 1 05/14/26 05/14/26
7300 SUB- Release Section 26 00 00 thru 26 28 16 Materials for Fabrications and Procurement 20 05/15/26 06/11/26
7310 Section 26 00 00 thru 26 28 16 Materials Onsite 1 06/12/26 06/12/26
All Sections Starting with 23 00 00 thru 23 82 00 70 03/09/26A 06/12/26
7170 SUB - Prepare & Submit Section 23 00 00 thru 23 82 00 39 03/09/26A 04/30/26
7180 A/E - Review Section 23 00 00 thru 23 82 00 Submittal 10 05/01/26 05/14/26
7190 A/E - Approval Section 23 00 00 thru 23 82 00 1 05/14/26 05/14/26
7200 SUB- Release Section 23 00 00 thru 23 82 00 Materials for Fabrications and Procurement 20 05/15/26 06/11/26
7210 Section 23 00 00 thru 23 82 00 Materials Onsite 1 06/12/26 06/12/26
08 11-13 Hollow Metal Doors and Frames 51 04/29/26 07/08/26
6620 SUB - Prepare & Submit Section 08 11 13 10 04/29/26 05/12/26
6630 A/E - Review Section 08 11 13 Submittal 10 05/13/26 05/26/26
6640 A/E - Approval Section 08 11 13 1 05/26/26 05/26/26
6650 SUB- Release Section 08 11 13 Materials for Fabrications and Procurement 30 05/27/26 07/07/26
6660 Section 08 11 13 Materials Onsite 1 07/08/26 07/08/26
08 71 00.01 Door Hardware Sets 61 04/29/26 07/22/26
6720 SUB - Prepare & Submit Section 08 71 00.01 10 04/29/26 05/12/26
6730 A/E - Review Section 08 71 00.01 Submittal 10 05/13/26 05/26/26
6740 A/E - Approval Section 08 71 00.01 1 05/26/26 05/26/26
6750 SUB- Release Section 08 71 00.01 Materials for Fabrications and Procurement 40 05/27/26 07/21/26
6760 Section 08 71 00.01 Materials Onsite 1 07/22/26 07/22/26
21 00 00 / 21 13 00 Fire Suppression Sprinkler Systems 41 04/29/26 06/24/26
870 SUB - Prepare & Submit Section 21 00 00 / 21 13 00 10 04/29/26 05/12/26
7370 A/E - Review Section 21 00 00 / 21 13 00 Submittal 10 05/13/26 05/26/26
7380 A/E - Approval Section 21 00 00 / 21 13 00 1 05/26/26 05/26/26
7390 SUB- Release Section 21 00 00 / 21 13 00 for Fabrications and Procurement 20 05/27/26 06/23/26
930 Section 21 00 00 / 21 13 00 Materials Onsite 1 06/24/26 06/24/26
07 54 00 Thermoplasteic Membrane Roofing 41 04/29/26 06/24/26
860 SUB - Prepare & Submit Section 07 54 00 10 04/29/26 05/12/26
2026 2027 2028
P ro je ct
F in is h
D a ta
D a te
SUB - Prepare & Submit Section 26 00 00 thru 26 28 16
A/E - Review Section 25 31 00 Submittal
A/E - Approval Section 26 00 00 thru 26 28 16
SUB- Release Section 26 00 00 thru 26 28 16 Materials for Fabrications and
Section 26 00 00 thru 26 28 16 Materials Onsite
SUB - Prepare & Submit Section 23 00 00 thru 23 82 00
A/E - Review Section 23 00 00 thru 23 82 00 Submittal
A/E - Approval Section 23 00 00 thru 23 82 00
SUB- Release Section 23 00 00 thru 23 82 00 Materials for Fabrications and
Section 23 00 00 thru 23 82 00 Materials Onsite
SUB - Prepare & Submit Section 08 11 13
A/E - Review Section 08 11 13 Submittal
A/E - Approval Section 08 11 13
SUB- Release Section 08 11 13 Materials for Fabrications and Procureme
Section 08 11 13 Materials Onsite
SUB - Prepare & Submit Section 08 71 00.01
A/E - Review Section 08 71 00.01 Submittal
A/E - Approval Section 08 71 00.01
SUB- Release Section 08 71 00.01 Materials for Fabrications and Procure
Section 08 71 00.01 Materials Onsite
SUB - Prepare & Submit Section 21 00 00 / 21 13 00
A/E - Review Section 21 00 00 / 21 13 00 Submittal
A/E - Approval Section 21 00 00 / 21 13 00
SUB- Release Section 21 00 00 / 21 13 00 for Fabrications and Procureme
Section 21 00 00 / 21 13 00 Materials Onsite
SUB - Prepare & Submit Section 07 54 00
Start Date: 08/18/25
Finish Date: 09/07/27
Data Date: 04/24/26
Run Date: 04/29/26
JMES - Master - GMP Schedule (REV-6.1) 4.27.26.ppx
JOHN McLOUGHLIN ELEMENTARY SCHOOL
ADDITION & RENOVATION
Page 6A
Duration Start Finish
2480 A/E - Review Section 07 54 00 Submittal 10 05/13/26 05/26/26
2560 A/E - Approval Section 07 54 00 1 05/26/26 05/26/26
4550 SUB- Release Section 07 54 00 for Fabrications and Procurement 20 05/27/26 06/23/26
920 Section 07 54 00 Materials Onsite 1 06/24/26 06/24/26
33 31 00 Sanitary Utility Sewerage Piping 41 04/29/26 06/24/26
880 SUB - Prepare & Submit Section 33 31 00 10 04/29/26 05/12/26
7400 A/E - Review Section 33 31 00 Submittal 10 05/13/26 05/26/26
7410 A/E - Approval Section 33 31 00 1 05/26/26 05/26/26
7420 SUB- Release Section 33 31 00 for Fabrications and Procurement 20 05/27/26 06/23/26
940 Section 33 31 00 Materials Onsite 1 06/24/26 06/24/26
33 41 00 Storm Utility Drainage Piping 41 04/29/26 06/24/26
7460 SUB - Prepare & Submit Section 33 41 00 10 04/29/26 05/12/26
7470 A/E - Review Section 33 41 00 Submittal 10 05/13/26 05/26/26
7480 A/E - Approval Section 33 41 00 1 05/26/26 05/26/26
7490 SUB- Release Section 33 41 00 Materials for Fabrications and Procurement 20 05/27/26 06/23/26
7500 Section 33 41 00 Materials Onsite 1 06/24/26 06/24/26
33 11 00 Water Utility Distribution Piping 41 04/29/26 06/24/26
890 SUB - Prepare & Submit Section 33 11 00 10 04/29/26 05/12/26
7430 A/E - Review Section 33 11 00 Submittal 10 05/13/26 05/26/26
7440 A/E - Approval Section 33 11 00 1 05/26/26 05/26/26
7450 SUB- Release Section 33 31 00 for Fabrications and Procurement 20 05/27/26 06/23/26
950 Section 33 11 00 Materials Onsite 1 06/24/26 06/24/26
08 62 23 Tubular Skylights 41 04/29/26 06/24/26
6820 SUB - Prepare & Submit Section 08 62 23 10 04/29/26 05/12/26
6830 A/E - Review Section 08 62 23 Submittal 10 05/13/26 05/26/26
6840 A/E - Approval Section 08 62 23 1 05/26/26 05/26/26
6850 SUB- Release Section 08 62 23 Materials for Fabrications and Procurement 20 05/27/26 06/23/26
6860 Section 08 62 23 Materials Onsite 1 06/24/26 06/24/26
08 14 16 Flush Wood Doors 51 04/29/26 07/08/26
6670 SUB - Prepare & Submit Section 08 14 16 10 04/29/26 05/12/26
6680 A/E - Review Section 08 14 16 Submittal 10 05/13/26 05/26/26
6690 A/E - Approval Section 08 14 16 1 05/26/26 05/26/26
2026 2027 2028
P ro je ct
F in is h
D a ta
D a te
A/E - Review Section 07 54 00 Submittal
A/E - Approval Section 07 54 00
SUB- Release Section 07 54 00 for Fabrications and Procurement
Section 07 54 00 Materials Onsite
SUB - Prepare & Submit Section 33 31 00
A/E - Review Section 33 31 00 Submittal
A/E - Approval Section 33 31 00
SUB- Release Section 33 31 00 for Fabrications and Procurement
Section 33 31 00 Materials Onsite
SUB - Prepare & Submit Section 33 41 00
A/E - Review Section 33 41 00 Submittal
A/E - Approval Section 33 41 00
SUB- Release Section 33 41 00 Materials for Fabrications and Procuremen
Section 33 41 00 Materials Onsite
SUB - Prepare & Submit Section 33 11 00
A/E - Review Section 33 11 00 Submittal
A/E - Approval Section 33 11 00
SUB- Release Section 33 31 00 for Fabrications and Procurement
Section 33 11 00 Materials Onsite
SUB - Prepare & Submit Section 08 62 23
A/E - Review Section 08 62 23 Submittal
A/E - Approval Section 08 62 23
SUB- Release Section 08 62 23 Materials for Fabrications and Procureme
Section 08 62 23 Materials Onsite
SUB - Prepare & Submit Section 08 14 16
A/E - Review Section 08 14 16 Submittal
A/E - Approval Section 08 14 16
Start Date: 08/18/25
Finish Date: 09/07/27
Data Date: 04/24/26
Run Date: 04/29/26
JMES - Master - GMP Schedule (REV-6.1) 4.27.26.ppx
JOHN McLOUGHLIN ELEMENTARY SCHOOL
ADDITION & RENOVATION
Page 7A
Duration Start Finish
6700 SUB- Release Section 08 14 16 Materials for Fabrications and Procurement 30 05/27/26 07/07/26
6710 Section 08 14 16 Materials Onsite 1 07/08/26 07/08/26
05 50 00 Metal Fabrication 41 04/29/26 06/24/26
7320 SUB - Prepare & Submit Section 05 50 00 10 04/29/26 05/12/26
7330 A/E - Review Section 05 50 00 Submittal 10 05/13/26 05/26/26
7340 A/E - Approval Section 05 50 00 1 05/26/26 05/26/26
7350 SUB- Release Section 05 50 00 Materials for Fabrications and Procurement 20 05/27/26 06/23/26
7360 Section 05 50 00 Materials Onsite 1 06/24/26 06/24/26
06 18 00 Glued-Laminated Construction 31 04/29/26 06/10/26
6470 SUB - Prepare & Submit Section 06 18 00 10 04/29/26 05/12/26
6480 A/E - Review Section 06 18 00 Submittal 10 05/13/26 05/26/26
6490 A/E - Approval Section 06 18 00 1 05/26/26 05/26/26
6500 SUB- Release Roofing Materials for Fabrications and Procurement 10 05/27/26 06/09/26
6510 Section 06 18 00 Materials Onsite 1 06/10/26 06/10/26
08 43 13 Aluminum-Framed Storefronts 41 05/13/26 07/08/26
6770 SUB - Prepare & Submit Section 08 43 13 10 05/13/26 05/26/26
6780 A/E - Review Section 08 43 13 Submittal 10 05/27/26 06/09/26
6790 A/E - Approval Section 08 43 13 1 06/09/26 06/09/26
6800 SUB- Release Section 08 43 13 Materials for Fabrications and Procurement 20 06/10/26 07/07/26
6810 Section 08 43 13 Materials Onsite 1 07/08/26 07/08/26
03 10 00 / 03 20 00 / 03 30 00 Form / Reinforce / Concrete 26 05/13/26 06/17/26
7070 SUB - Prepare & Submit Sections 03 10 00 / 03 20 00 / 03 30 00 5 05/13/26 05/19/26
7080 A/E - Review Section 03 10 00 / 03 20 00 / 03 30 00 Submittal 10 05/20/26 06/02/26
7090 A/E - Approval Section 03 10 00 / 03 20 00 / 03 30 00 1 06/02/26 06/02/26
7100 SUB- Release Section 03 10 00 / 03 20 00 / 03 30 00 Materials for Fabrications and Procurement 10 06/03/26 06/16/26
7110 Section 03 10 00 / 03 20 00 / 03 30 00 Materials Onsite 1 06/17/26 06/17/26
08 33 13 Coiling Counter Doors 41 05/13/26 07/08/26
6870 SUB - Prepare & Submit Section 08 33 13 10 05/13/26 05/26/26
6880 A/E - Review Section 08 33 13 Submittal 10 05/27/26 06/09/26
6890 A/E - Approval Section 08 33 13 1 06/09/26 06/09/26
6900 SUB- Release Section 08 33 13 Materials for Fabrications and Procurement 20 06/10/26 07/07/26
6910 Section 08 43 13 Materials Onsite 1 07/08/26 07/08/26
2026 2027 2028
P ro je ct
F in is h
D a ta
D a te
SUB- Release Section 08 14 16 Materials for Fabrications and Procureme
Section 08 14 16 Materials Onsite
SUB - Prepare & Submit Section 05 50 00
A/E - Review Section 05 50 00 Submittal
A/E - Approval Section 05 50 00
SUB- Release Section 05 50 00 Materials for Fabrications and Procureme
Section 05 50 00 Materials Onsite
SUB - Prepare & Submit Section 06 18 00
A/E - Review Section 06 18 00 Submittal
A/E - Approval Section 06 18 00
SUB- Release Roofing Materials for Fabrications and Procurement
Section 06 18 00 Materials Onsite
SUB - Prepare & Submit Section 08 43 13
A/E - Review Section 08 43 13 Submittal
A/E - Approval Section 08 43 13
SUB- Release Section 08 43 13 Materials for Fabrications and Procureme
Section 08 43 13 Materials Onsite
SUB - Prepare & Submit Sections 03 10 00 / 03 20 00 / 03 30 00
A/E - Review Section 03 10 00 / 03 20 00 / 03 30 00 Submittal
A/E - Approval Section 03 10 00 / 03 20 00 / 03 30 00
SUB- Release Section 03 10 00 / 03 20 00 / 03 30 00 Materials for Fabrica
Section 03 10 00 / 03 20 00 / 03 30 00 Materials Onsite
SUB - Prepare & Submit Section 08 33 13
A/E - Review Section 08 33 13 Submittal
A/E - Approval Section 08 33 13
SUB- Release Section 08 33 13 Materials for Fabrications and Procureme
Section 08 43 13 Materials Onsite
Start Date: 08/18/25
Finish Date: 09/07/27
Data Date: 04/24/26
Run Date: 04/29/26
JMES - Master - GMP Schedule (REV-6.1) 4.27.26.ppx
JOHN McLOUGHLIN ELEMENTARY SCHOOL
ADDITION & RENOVATION
Page 8A
Duration Start Finish
08 33 23 Overhead Coiling Doors 41 05/13/26 07/08/26
6920 SUB - Prepare & Submit Section 08 33 23 10 05/13/26 05/26/26
6930 A/E - Review Section 08 33 23 Submittal 10 05/27/26 06/09/26
6940 A/E - Approval Section 08 33 23 1 06/09/26 06/09/26
6950 SUB- Release Section 08 33 23 Materials for Fabrications and Procurement 20 06/10/26 07/07/26
6960 Section 08 33 23 Materials Onsite 1 07/08/26 07/08/26
08 80 00 Glazing 41 05/13/26 07/08/26
6970 SUB - Prepare & Submit Section 08 80 00 10 05/13/26 05/26/26
6980 A/E - Review Section 08 80 00 Submittal 10 05/27/26 06/09/26
6990 A/E - Approval Section 08 80 00 1 06/09/26 06/09/26
7000 SUB- Release Section 08 80 00 Materials for Fabrications and Procurement 20 06/10/26 07/07/26
7010 Section 08 80 00 Materials Onsite 1 07/08/26 07/08/26
09 84 30 Sound-Absorbing Wall and Ceiling Units 46 05/13/26 07/15/26
7020 SUB - Prepare & Submit Section 09 84 30 10 05/13/26 05/26/26
7030 A/E - Review Section 09 84 30 Submittal 10 05/27/26 06/09/26
7040 A/E - Approval Section 09 84 30 1 06/09/26 06/09/26
7050 SUB- Release Section 09 84 30 Materials for Fabrications and Procurement 25 06/10/26 07/14/26
7060 Section 09 84 30 Materials Onsite 1 07/15/26 07/15/26
06 41 00 Architectural Wood Casework 51 05/13/26 07/22/26
7120 SUB - Prepare & Submit Section 06 41 00 10 05/13/26 05/26/26
7130 A/E - Review Section 06 41 00 Submittal 10 05/27/26 06/09/26
7140 A/E - Approval Section 06 41 00 1 06/09/26 06/09/26
7150 SUB- Release Section 06 41 00 Materials for Fabrications and Procurement 30 06/10/26 07/21/26
7160 Section 06 41 00 Materials Onsite 1 07/22/26 07/22/26
26 31 00 Photovoltaic System 41 05/13/26 07/08/26
6570 SUB - Prepare & Submit Section 25 31 00 10 05/13/26 05/26/26
6580 A/E - Review Section 25 31 00 Submittal 10 05/27/26 06/09/26
6590 A/E - Approval Section 25 31 00 1 06/09/26 06/09/26
6600 SUB- Release Section 25 31 00 Materials for Fabrications and Procurement 20 06/10/26 07/07/26
6610 Section 25 31 00 Materials Onsite 1 07/08/26 07/08/26
Contractor Bidding 60 03/09/26A 05/29/26
1000 Contractor Bidding / Award Process 60 03/09/26A 05/29/26
2026 2027 2028
P ro je ct
F in is h
D a ta
D a te
SUB - Prepare & Submit Section 08 33 23
A/E - Review Section 08 33 23 Submittal
A/E - Approval Section 08 33 23
SUB- Release Section 08 33 23 Materials for Fabrications and Procureme
Section 08 33 23 Materials Onsite
SUB - Prepare & Submit Section 08 80 00
A/E - Review Section 08 80 00 Submittal
A/E - Approval Section 08 80 00
SUB- Release Section 08 80 00 Materials for Fabrications and Procureme
Section 08 80 00 Materials Onsite
SUB - Prepare & Submit Section 09 84 30
A/E - Review Section 09 84 30 Submittal
A/E - Approval Section 09 84 30
SUB- Release Section 09 84 30 Materials for Fabrications and Procurem
Section 09 84 30 Materials Onsite
SUB - Prepare & Submit Section 06 41 00
A/E - Review Section 06 41 00 Submittal
A/E - Approval Section 06 41 00
SUB- Release Section 06 41 00 Materials for Fabrications and Procurem
Section 06 41 00 Materials Onsite
SUB - Prepare & Submit Section 25 31 00
A/E - Review Section 25 31 00 Submittal
A/E - Approval Section 25 31 00
SUB- Release Section 25 31 00 Materials for Fabrications and Procureme
Section 25 31 00 Materials Onsite
Contractor Bidding / Award Process
Start Date: 08/18/25
Finish Date: 09/07/27
Data Date: 04/24/26
Run Date: 04/29/26
JMES - Master - GMP Schedule (REV-6.1) 4.27.26.ppx
JOHN McLOUGHLIN ELEMENTARY SCHOOL
ADDITION & RENOVATION
Page 9A
Duration Start Finish
Construction 335 05/11/26 08/20/27
MEP Start-Up 256 08/24/26 08/16/27
1097 (Phase 1 Summer)All MEPF/ IT Controls - Equipment Commissioned and Balanced 1 08/24/26 08/24/26
1098 Phase 1 All MEPF/ IT Controls - Equipment Commissioned and Balanced 1 12/07/26 12/07/26
1102 Music All MEPF/ IT Controls - Equipment Commissioned and Balanced 1 12/07/26 12/07/26
1099 Phase 2 All MEPF/ IT Controls - Equipment Commissioned and Balanced 1 06/15/27 06/15/27
1105 Phase 3 All MEPF/ IT Controls - Equipment Commissioned and Balanced 1 08/16/27 08/16/27
Construction Phase 1 320 05/11/26 07/30/27
MOB 60 05/11/26 07/31/26
Site 60 05/11/26 07/31/26
1110 Install Temp Services 10 05/11/26 05/22/26
1120 Install Breakers for Temp Power (Coordinate with PGE) 2 05/18/26 05/19/26
1100 Moblize Lewis Office 1 05/26/26 05/26/26
1140 Pothole Sewer Connection 5 06/15/26 06/19/26
1150 Sub Trailers 5 06/15/26 06/19/26
1165 Prairie Install Disconnects/ IT for Temp Classroom Modulars 10 06/15/26 06/26/26
1130 City Fire / Water Line Tap Install 5 06/22/26 06/26/26
1170 Install School Modulars 15 07/13/26 07/31/26
Demo 20 06/15/26 07/10/26
Site 15 06/15/26 07/03/26
1180 Demo Hardscapes / Landscaping / Prep for Modulars 15 06/15/26 07/03/26
Abatement 9 06/15/26 06/25/26
1190 Remove Ceiling Tile - (Library New Soffit Location?) 5 06/15/26 06/19/26
1200 Remove Floor Tile and Sinks (Area 1- Fire A122) 5 Days Includes Clearance 5 06/15/26 06/19/26
1210 Remove Floor Tile (Area 2) 6 Days Includes Clearance 6 06/18/26 06/25/26
East Side Classrooms / Restrooms / ERC / Library 20 06/15/26 07/10/26
1220 Safe Off MEPF Systems 10 06/15/26 06/26/26
1230 Install Temp Protections 5 06/15/26 06/19/26
1240 Interior / MEP Demo 10 06/15/26 06/26/26
1250 Structural Demo / Shoring 15 06/22/26 07/10/26
2026 2027 2028
P ro je ct
F in is h
D a ta
D a te
(Phase 1 Summer)All MEPF/ IT Controls - Equipment Commissioned a
Phase 1 All MEPF/ IT Controls - Equipment Commissioned and
Music All MEPF/ IT Controls - Equipment Commissioned and
Phase 2 All MEPF/ IT Controls - Equipment Comm
Phase 3 All MEPF/ IT Controls - Equipment C
Install Temp Services
Install Breakers for Temp Power (Coordinate with PGE)
Moblize Lewis Office
Pothole Sewer Connection
Sub Trailers
Prairie Install Disconnects/ IT for Temp Classroom Modulars
City Fire / Water Line Tap Install
Install School Modulars
Demo Hardscapes / Landscaping / Prep for Modulars
Remove Ceiling Tile - (Library New Soffit Location?)
Remove Floor Tile and Sinks (Area 1- Fire A122) 5 Days Includes Clearance
Remove Floor Tile (Area 2) 6 Days Includes Clearance
Safe Off MEPF Systems
Install Temp Protections
Interior / MEP Demo
Structural Demo / Shoring
Start Date: 08/18/25
Finish Date: 09/07/27
Data Date: 04/24/26
Run Date: 04/29/26
JMES - Master - GMP Schedule (REV-6.1) 4.27.26.ppx
JOHN McLOUGHLIN ELEMENTARY SCHOOL
ADDITION & RENOVATION
Page 10A
Duration Start Finish
Music / Cafeteria / Kitchen / OT/PT / Storage / Existing MDF 12 06/15/26 06/30/26
1260 Safe Off MEPF Systems 2 06/15/26 06/16/26
1270 Install Temp Protections 3 06/15/26 06/17/26
1280 Temp Support System for Existing MDF Gear and Cabling 10 06/15/26 06/26/26
1290 Interior Demo (Remove Section of Kitchen Ceiling - Demo Existing Duct) 8 06/17/26 06/26/26
1307 Demo Existing West Mechanical Rm 8 06/17/26 06/26/26
1300 Structural Demo / Shoring 7 06/22/26 06/30/26
1305 Demo Storage Rms 123 and 126 5 06/22/26 06/26/26
Exterior Demo / Prep for DX Units 15 06/22/26 07/10/26
1310 Demo Openings For New Unit Ventilators (Secure Openings) 15 06/22/26 07/10/26
1320 Demo New South Entrance Door Opening - Sector C 5 06/22/26 06/26/26
1330 Demo New North Entrance Door Opening - Sector C 5 06/22/26 06/26/26
Construction 295 06/15/26 07/30/27
Site 40 06/15/26 08/07/26
New South Entrance Sector C 25 06/29/26 07/31/26
1340 Excavate Footings / Reroute Any Existing Underground 5 06/29/26 07/03/26
1345 Install New Storm Line 5 06/29/26 07/03/26
1350 FRPS Retaining Wall Footings 5 07/06/26 07/10/26
1360 Backfill / Prep Sidewalk 5 07/13/26 07/17/26
1370 FRPS - Sidewalk 5 07/20/26 07/24/26
1380 Install New Guardrail 5 07/27/26 07/31/26
Craft Parking and Laydown 15 07/20/26 08/07/26
1390 Prep and Gravel Craft Parking Area (Fence Modification) 15 07/20/26 08/07/26
North / West Side 40 06/15/26 08/07/26
1400 Install Grease Interceptor and New Sewer Line 15 06/15/26 07/03/26
1410 Install New FDC and Fire Line (SUPA Work)(Asphalt Patchback) 40 06/15/26 08/07/26
1430 Salvage Fencing / Grub / Gravel Modular Areas 10 06/15/26 06/26/26
1420 Salvage and Relocate Existing Playground Equipment 10 06/29/26 07/10/26
East Side Classrooms / Restrooms / ERC / Library 125 06/22/26 12/11/26
Structural 30 06/22/26 07/31/26
2026 2027 2028
P ro je ct
F in is h
D a ta
D a te
Safe Off MEPF Systems
Install Temp Protections
Temp Support System for Existing MDF Gear and Cabling
Interior Demo (Remove Section of Kitchen Ceiling - Demo Existing Duct)
Demo Existing West Mechanical Rm
Structural Demo / Shoring
Demo Storage Rms 123 and 126
Demo Openings For New Unit Ventilators (Secure Openings)
Demo New South Entrance Door Opening - Sector C
Demo New North Entrance Door Opening - Sector C
Excavate Footings / Reroute Any Existing Underground
Install New Storm Line
FRPS Retaining Wall Footings
Backfill / Prep Sidewalk
FRPS - Sidewalk
Install New Guardrail
Prep and Gravel Craft Parking Area (Fence Modification)
Install Grease Interceptor and New Sewer Line
Install New FDC and Fire Line (SUPA Work)(Asphalt Patchback)
Salvage Fencing / Grub / Gravel Modular Areas
Salvage and Relocate Existing Playground Equipment
Start Date: 08/18/25
Finish Date: 09/07/27
Data Date: 04/24/26
Run Date: 04/29/26
JMES - Master - GMP Schedule (REV-6.1) 4.27.26.ppx
JOHN McLOUGHLIN ELEMENTARY SCHOOL
ADDITION & RENOVATION
Page 11A
Duration Start Finish
1440 Structural Upgrades 20 06/22/26 07/17/26
1450 Saw Cut / Excavate - Footings / MEP 10 06/29/26 07/10/26
1460 FRPS Footings / MEP Pourbacks 20 06/29/26 07/24/26
1470 CDF Fill Underground Duct 5 06/29/26 07/03/26
1505 Frame New Exterior Openings 10 06/29/26 07/10/26
1480 Under Slab MEP 10 07/06/26 07/17/26
1490 Frame New Shear Wall / Roof Openings 15 07/13/26 07/31/26
1500 Install New HSS Columns 2 07/13/26 07/14/26
Interior Buildout 108 07/15/26 12/11/26
Classrooms C104,C105, C110, C111, C114, C117, C118, B106, B107 108 07/15/26 12/11/26
1510 Frame Walls / Set Door Frames 15 07/15/26 08/04/26
1520 MEP Wall Rough-In 20 07/29/26 08/25/26
1530 MEPF/ LV Overhead Rough-In 20 07/29/26 08/25/26
1675 Polish Concrete - Grind, Repair, Grout 7 08/10/26 08/18/26
1540 Hang Drywall 6 08/26/26 09/02/26
1550 Tape and Finish 7 09/02/26 09/10/26
1560 Prime / First Coat 6 09/11/26 09/18/26
1570 Install Ceiling Grid 5 09/18/26 09/24/26
1580 Install Wall Finishes (TS-1 MB-1) 10 09/18/26 10/01/26
1590 Install Casework 15 09/23/26 10/13/26
1600 MEPF Trim at Ceiling Grid 15 09/25/26 10/15/26
1610 Drop Ceiling Tile 5 10/16/26 10/22/26
1620 Polish Concrete - Final Grind 5 10/19/26 10/23/26
1630 Swing Doors / Hardware 5 10/27/26 11/02/26
1640 Final Paint 5 11/03/26 11/09/26
1650 Final Clean 5 11/10/26 11/16/26
1660 OAC Punch Process 10 11/17/26 11/30/26
1670 City / OAC Acceptance of Space (Move-In Ready) 5 12/07/26 12/11/26
Special ED Classroom C114, Sensory C115, ERC C112, C113 108 07/15/26 12/11/26
1680 Frame Walls / Set Door Frames 15 07/15/26 08/04/26
1690 MEP Wall Rough-In 20 07/29/26 08/25/26
1700 MEPF/ LV Overhead Rough-In 20 07/29/26 08/25/26
1845 Polish Concrete - Grind, Repair, Grout 7 08/10/26 08/18/26
2026 2027 2028
P ro je ct
F in is h
D a ta
D a te
Structural Upgrades
Saw Cut / Excavate - Footings / MEP
FRPS Footings / MEP Pourbacks
CDF Fill Underground Duct
Frame New Exterior Openings
Under Slab MEP
Frame New Shear Wall / Roof Openings
Install New HSS Columns
Frame Walls / Set Door Frames
MEP Wall Rough-In
MEPF/ LV Overhead Rough-In
Polish Concrete - Grind, Repair, Grout
Hang Drywall
Tape and Finish
Prime / First Coat
Install Ceiling Grid
Install Wall Finishes (TS-1 MB-1)
Install Casework
MEPF Trim at Ceiling Grid
Drop Ceiling Tile
Polish Concrete - Final Grind
Swing Doors / Hardware
Final Paint
Final Clean
OAC Punch Process
City / OAC Acceptance of Space (Move-In Ready)
Frame Walls / Set Door Frames
MEP Wall Rough-In
MEPF/ LV Overhead Rough-In
Polish Concrete - Grind, Repair, Grout
Start Date: 08/18/25
Finish Date: 09/07/27
Data Date: 04/24/26
Run Date: 04/29/26
JMES - Master - GMP Schedule (REV-6.1) 4.27.26.ppx
JOHN McLOUGHLIN ELEMENTARY SCHOOL
ADDITION & RENOVATION
Page 12A
Duration Start Finish
1710 Hang Drywall 6 08/26/26 09/02/26
1720 Tape and Finish 7 09/02/26 09/10/26
1730 Prime / First Coat 6 09/11/26 09/18/26
1740 Install Ceiling Grid 7 09/18/26 09/28/26
1750 Install Wall Finishes (TS-1 MB-1) 10 09/18/26 10/01/26
1760 Install Casework 15 09/23/26 10/13/26
1770 MEPF Trim at Ceiling Grid 15 09/25/26 10/15/26
1780 Drop Ceiling Tile 5 10/16/26 10/22/26
1790 Polish Concrete - Final Grind 5 10/19/26 10/23/26
1800 Swing Doors / Hardware 5 10/27/26 11/02/26
1810 Final Paint 5 11/03/26 11/09/26
1820 Final Clean 5 11/10/26 11/16/26
1830 OAC Punch Process 10 11/17/26 11/30/26
1840 City / OAC Acceptance of Space (Move-In Ready) 5 12/07/26 12/11/26
Restrooms C106, C109, C108, C118 108 07/15/26 12/11/26
1850 Frame Walls / Set Door Frames 10 07/15/26 07/28/26
1860 Set Carriers 2 07/22/26 07/23/26
1870 MEP Wall Rough-In 15 07/29/26 08/18/26
1880 MEPF/LV Overhead Rough-In 15 07/29/26 08/18/26
1890 Frame Hard lids 5 08/19/26 08/25/26
1900 MEPF/LV Rough-In at Hard lids 5 08/26/26 09/01/26
1910 Hang Drywall 5 09/02/26 09/08/26
1920 Tape and Finish 7 09/09/26 09/17/26
1930 Prime / First Coat Paint 5 09/18/26 09/24/26
1940 Install Ceramic Wall Tile 10 09/25/26 10/08/26
1950 Install MEP Trim 6 10/09/26 10/16/26
1955 Install Sheet Vinyl 2 10/12/26 10/13/26
1960 Set Plumbing Fixtures 5 10/12/26 10/16/26
1970 Install Toilet Partitions 5 10/19/26 10/23/26
1980 Install Restroom Accessories 5 10/19/26 10/23/26
1990 Swing Doors / Hardware 5 10/27/26 11/02/26
2000 Final Paint 5 11/03/26 11/09/26
2010 Final Clean 5 11/10/26 11/16/26
2020 OAC Punch Process 10 11/17/26 11/30/26
2026 2027 2028
P ro je ct
F in is h
D a ta
D a te
Hang Drywall
Tape and Finish
Prime / First Coat
Install Ceiling Grid
Install Wall Finishes (TS-1 MB-1)
Install Casework
MEPF Trim at Ceiling Grid
Drop Ceiling Tile
Polish Concrete - Final Grind
Swing Doors / Hardware
Final Paint
Final Clean
OAC Punch Process
City / OAC Acceptance of Space (Move-In Ready)
Frame Walls / Set Door Frames
Set Carriers
MEP Wall Rough-In
MEPF/LV Overhead Rough-In
Frame Hard lids
MEPF/LV Rough-In at Hard lids
Hang Drywall
Tape and Finish
Prime / First Coat Paint
Install Ceramic Wall Tile
Install MEP Trim
Install Sheet Vinyl
Set Plumbing Fixtures
Install Toilet Partitions
Install Restroom Accessories
Swing Doors / Hardware
Final Paint
Final Clean
OAC Punch Process
Start Date: 08/18/25
Finish Date: 09/07/27
Data Date: 04/24/26
Run Date: 04/29/26
JMES - Master - GMP Schedule (REV-6.1) 4.27.26.ppx
JOHN McLOUGHLIN ELEMENTARY SCHOOL
ADDITION & RENOVATION
Page 13A
Duration Start Finish
2030 City / OAC Acceptance of Space (Move-In Ready) 5 12/07/26 12/11/26
Restroom C101 108 07/15/26 12/11/26
2040 Frame Walls / Set Door Frames 10 07/15/26 07/28/26
2050 Set Carriers 2 07/22/26 07/23/26
2060 MEP Wall Rough-In 15 07/29/26 08/18/26
2070 MEPF/LV Overhead Rough-In 15 07/29/26 08/18/26
2212 Polish Concrete - Grind, Repair, Grout 7 08/10/26 08/18/26
2080 Frame Hard lids 3 08/19/26 08/21/26
2090 MEPF/LV Rough-In at Hard lids 5 08/24/26 08/28/26
2100 Hang Drywall 5 08/31/26 09/04/26
2110 Tape and Finish 7 09/07/26 09/15/26
2120 Prime / First Coat Paint 5 09/16/26 09/22/26
2130 Install Ceramic Wall Tile 10 09/23/26 10/06/26
2140 Install MEP Trim 5 10/07/26 10/13/26
2135 Polish Concrete - Final Grind 5 10/19/26 10/23/26
2150 Install Plumbing Fixtures 5 10/19/26 10/23/26
2160 Install Toilet Partitions 5 10/26/26 10/30/26
2170 Install Restroom Accessories 5 10/26/26 10/30/26
2180 Final Paint 5 11/03/26 11/09/26
2190 Final Clean 5 11/10/26 11/16/26
2200 OAC Punch Process 10 11/17/26 11/30/26
2210 City / OAC Acceptance of Space (Move-In Ready) 5 12/07/26 12/11/26
Cust / Stor C119 108 07/15/26 12/11/26
2220 Frame Walls / Set Door Frames 10 07/15/26 07/28/26
2230 MEP Wall Rough-In 20 07/29/26 08/25/26
2240 MEPF/LV Overhead Rough-In 20 07/29/26 08/25/26
2250 Hang Drywall 6 08/26/26 09/02/26
2260 Tape and Finish 7 09/02/26 09/10/26
2270 Prime / First Coat Paint 6 09/11/26 09/18/26
2280 Install FRP / MOP Sink 5 09/21/26 09/25/26
2290 Swing Doors / Hardware 5 10/27/26 11/02/26
2305 Seal Concrete 2 10/27/26 10/28/26
2300 Final Paint 5 11/03/26 11/09/26
2026 2027 2028
P ro je ct
F in is h
D a ta
D a te
City / OAC Acceptance of Space (Move-In Ready)
Frame Walls / Set Door Frames
Set Carriers
MEP Wall Rough-In
MEPF/LV Overhead Rough-In
Polish Concrete - Grind, Repair, Grout
Frame Hard lids
MEPF/LV Rough-In at Hard lids
Hang Drywall
Tape and Finish
Prime / First Coat Paint
Install Ceramic Wall Tile
Install MEP Trim
Polish Concrete - Final Grind
Install Plumbing Fixtures
Install Toilet Partitions
Install Restroom Accessories
Final Paint
Final Clean
OAC Punch Process
City / OAC Acceptance of Space (Move-In Ready)
Frame Walls / Set Door Frames
MEP Wall Rough-In
MEPF/LV Overhead Rough-In
Hang Drywall
Tape and Finish
Prime / First Coat Paint
Install FRP / MOP Sink
Swing Doors / Hardware
Seal Concrete
Final Paint
Start Date: 08/18/25
Finish Date: 09/07/27
Data Date: 04/24/26
Run Date: 04/29/26
JMES - Master - GMP Schedule (REV-6.1) 4.27.26.ppx
JOHN McLOUGHLIN ELEMENTARY SCHOOL
ADDITION & RENOVATION
Page 14A
Duration Start Finish
2310 Final Clean 5 11/10/26 11/16/26
2320 OAC Punch Process 10 11/17/26 11/30/26
2330 City / OAC Acceptance of Space (Move-In Ready) 5 12/07/26 12/11/26
Library C102 108 07/15/26 12/11/26
2340 Frame Walls / Set Door Frames / Relites 10 07/15/26 07/28/26
2350 MEP Wall Rough-In 20 07/29/26 08/25/26
2360 MEPF/LV Overhead Rough-In 20 07/29/26 08/25/26
2370 Hang Drywall 6 08/26/26 09/02/26
2380 Frame and Dry Wall Soffit 5 08/26/26 09/01/26
2390 Tape and Finish 7 09/02/26 09/10/26
2400 Prime / First Coat Paint 6 09/11/26 09/18/26
2410 Install Ceiling Grid 7 09/18/26 09/28/26
2420 MEPF Trim at Ceiling Grid 15 09/22/26 10/12/26
2430 Install Casework 15 09/23/26 10/13/26
2440 Install Wall Finishes (TS-1 MB-1) 10 09/25/26 10/08/26
2450 Drop Ceiling Tile 5 10/13/26 10/19/26
2460 Install Carpet Tile and Base 7 10/20/26 10/28/26
2470 Swing Doors / Hardware 5 10/27/26 11/02/26
2490 Final Clean 5 11/10/26 11/16/26
2500 OAC Punch Process 10 11/17/26 11/30/26
2510 City / OAC Acceptance of Space (Move-In Ready) 5 12/07/26 12/11/26
Hallway C001 98 07/29/26 12/11/26
2520 MEP Wall Rough-In 20 07/29/26 08/25/26
2530 MEPF/LV Overhead Rough-In 20 07/29/26 08/25/26
2685 Polish Concrete - Grind, Repair, Grout 7 08/10/26 08/18/26
2540 Hang Drywall 6 08/26/26 09/02/26
2550 Tape and Finish 7 09/02/26 09/10/26
2590 Install Finishes at Portals 10 09/02/26 09/15/26
2570 Prime / First Coat Paint 6 09/11/26 09/18/26
2580 Install Ceiling Grid 7 09/18/26 09/28/26
2600 Install Drinking Fountain 5 09/21/26 09/25/26
2610 MEPF Trim at Ceiling Grid 15 09/23/26 10/13/26
2620 Install Wall Finishes WCT-2 / WCT-1 / TS-3 10 09/25/26 10/08/26
2026 2027 2028
P ro je ct
F in is h
D a ta
D a te
Final Clean
OAC Punch Process
City / OAC Acceptance of Space (Move-In Ready)
Frame Walls / Set Door Frames / Relites
MEP Wall Rough-In
MEPF/LV Overhead Rough-In
Hang Drywall
Frame and Dry Wall Soffit
Tape and Finish
Prime / First Coat Paint
Install Ceiling Grid
MEPF Trim at Ceiling Grid
Install Casework
Install Wall Finishes (TS-1 MB-1)
Drop Ceiling Tile
Install Carpet Tile and Base
Swing Doors / Hardware
Final Clean
OAC Punch Process
City / OAC Acceptance of Space (Move-In Ready)
MEP Wall Rough-In
MEPF/LV Overhead Rough-In
Polish Concrete - Grind, Repair, Grout
Hang Drywall
Tape and Finish
Install Finishes at Portals
Prime / First Coat Paint
Install Ceiling Grid
Install Drinking Fountain
MEPF Trim at Ceiling Grid
Install Wall Finishes WCT-2 / WCT-1 / TS-3
Start Date: 08/18/25
Finish Date: 09/07/27
Data Date: 04/24/26
Run Date: 04/29/26
JMES - Master - GMP Schedule (REV-6.1) 4.27.26.ppx
JOHN McLOUGHLIN ELEMENTARY SCHOOL
ADDITION & RENOVATION
Page 15A
Duration Start Finish
2630 Install Wall Base 2 10/09/26 10/12/26
2640 Drop Ceiling Tile 5 10/14/26 10/20/26
2642 Polish Concrete - Final Grind 5 10/19/26 10/23/26
2650 Final Paint 5 11/03/26 11/09/26
2660 Final Clean 5 11/10/26 11/16/26
2670 OAC Punch Process 10 11/17/26 11/30/26
2680 City / OAC Acceptance of Space (Move-In Ready) 5 12/07/26 12/11/26
Exterior Upgrades 50 07/20/26 09/25/26
2690 Exterior Finishes 50 07/20/26 09/25/26
2695 Weather Barrier / Steel Lintel / Brick Repair at New Door and Window Openings 15 07/20/26 08/07/26
2698 Weather Barrier / Brick Repair / Stucco Repair at New Unit Ventilators 15 07/20/26 08/07/26
2699 Install New Storefront / Windows 15 07/20/26 08/07/26
Cafeteria / Music / New Corridor / Gym 295 06/15/26 07/30/27
Structural 16 07/01/26 07/22/26
2700 Saw Cut / Excavate 3 07/01/26 07/03/26
2710 Backfill Underground Duct 3 07/01/26 07/03/26
2720 Under Slab MEP 3 07/03/26 07/07/26
2730 FRPS Footings / Pourbacks 4 07/06/26 07/09/26
2740 Frame New Shear Wall / Roof Openings 6 07/10/26 07/17/26
2750 Install New HSS Columns 3 07/10/26 07/14/26
2760 MEP Shear Wall Rough In 4 07/15/26 07/20/26
2770 Sheet Shear Wall 2 07/21/26 07/22/26
Interior Buildout 295 06/15/26 07/30/27
Kitchen 131, A137, A132 55 06/15/26 08/28/26
2780 Interior Buildout (Summer Scope) 50 06/15/26 08/21/26
2790 Temporary Patch Ceiling / Lighting 10 07/29/26 08/11/26
2800 Summer Clean 5 08/24/26 08/28/26
2810 City / OAC Acceptance of Space (Move-In Ready) 5 08/24/26 08/28/26
Cafeteria A138 33 07/15/26 08/28/26
2820 Frame Walls / Set Door Frames / Relites 5 07/15/26 07/21/26
2830 MEPF/LV Overhead Rough-In 10 07/15/26 07/28/26
2840 MEP Wall Rough-In 8 07/21/26 07/30/26
2026 2027 2028
P ro je ct
F in is h
D a ta
D a te
Install Wall Base
Drop Ceiling Tile
Polish Concrete - Final Grind
Final Paint
Final Clean
OAC Punch Process
City / OAC Acceptance of Space (Move-In Ready)
Exterior Finishes
Weather Barrier / Steel Lintel / Brick Repair at New Door and Window
Weather Barrier / Brick Repair / Stucco Repair at New Unit Ventilators
Install New Storefront / Windows
Saw Cut / Excavate
Backfill Underground Duct
Under Slab MEP
FRPS Footings / Pourbacks
Frame New Shear Wall / Roof Openings
Install New HSS Columns
MEP Shear Wall Rough In
Sheet Shear Wall
Interior Buildout (Summer Scope)
Temporary Patch Ceiling / Lighting
Summer Clean
City / OAC Acceptance of Space (Move-In Ready)
Frame Walls / Set Door Frames / Relites
MEPF/LV Overhead Rough-In
MEP Wall Rough-In
Start Date: 08/18/25
Finish Date: 09/07/27
Data Date: 04/24/26
Run Date: 04/29/26
JMES - Master - GMP Schedule (REV-6.1) 4.27.26.ppx
JOHN McLOUGHLIN ELEMENTARY SCHOOL
ADDITION & RENOVATION
Page 16A
Duration Start Finish
2850 Hang Drywall / Tape Finish 7 07/30/26 08/07/26
2860 Prime / First Coat Paint 4 08/10/26 08/13/26
2875 Start-Up New Mechanical System 5 08/12/26 08/18/26
2870 Complete All Necessary Finishes 5 08/14/26 08/20/26
2880 Summer Clean 5 08/24/26 08/28/26
2890 City / OAC Acceptance of Space (Move-In Ready) 5 08/24/26 08/28/26
2900 Reopen Cafeteria / Kitchen / New Corridor 1 08/28/26 08/28/26
Gymnasium 33 07/15/26 08/28/26
2905 Install Sprinklers 15 07/15/26 08/04/26
2906 MEPF/LV Overhead Rough-In 15 07/15/26 08/04/26
2907 Start-Up New Mechanical System 5 08/12/26 08/18/26
2908 Summer Clean 5 08/24/26 08/28/26
2909 Reopen Gym 1 08/28/26 08/28/26
Music A130 109 07/13/26 12/10/26
2910 Reframe Door Opening / Install New Frame and Door 5 07/13/26 07/17/26
3580 MEP Wall Rough-In 15 07/27/26 08/14/26
3590 MEPF/LV Overhead Rough-In 20 07/27/26 08/21/26
2920 Install New UV-1 and RH (Temp Ceiling Connection) 10 08/03/26 08/14/26
3600 Hang Drywall / Patch 3 08/26/26 08/28/26
3610 Tape and Finish 8 08/31/26 09/09/26
3620 Prime / First Coat Paint 3 09/10/26 09/14/26
3630 Install Ceiling Grid 2 09/17/26 09/18/26
3660 MEPF Trim at Ceiling Grid 10 09/21/26 10/02/26
3640 Install Wall Finishes (TS-1/ MB-1 / AWP-3 / AWP-2) 10 09/25/26 10/08/26
3670 Drop Ceiling Tile 1 10/05/26 10/05/26
3650 Install Casework 11 10/07/26 10/21/26
3680 Install Carpet Tile and Base 3 10/22/26 10/26/26
3690 Final Paint 2 10/27/26 10/28/26
3700 Final Clean 1 10/29/26 10/29/26
3720 OAC Punch Process 10 11/17/26 11/30/26
3710 City / OAC Acceptance of Space (Move-In Ready) 4 12/07/26 12/10/26
MDF A134 273 07/15/26 07/30/27
2950 Frame Walls / Set Door Frames 5 07/15/26 07/21/26
2026 2027 2028
P ro je ct
F in is h
D a ta
D a te
Hang Drywall / Tape Finish
Prime / First Coat Paint
Start-Up New Mechanical System
Complete All Necessary Finishes
Summer Clean
City / OAC Acceptance of Space (Move-In Ready)
Reopen Cafeteria / Kitchen / New Corridor
Install Sprinklers
MEPF/LV Overhead Rough-In
Start-Up New Mechanical System
Summer Clean
Reopen Gym
Reframe Door Opening / Install New Frame and Door
MEP Wall Rough-In
MEPF/LV Overhead Rough-In
Install New UV-1 and RH (Temp Ceiling Connection)
Hang Drywall / Patch
Tape and Finish
Prime / First Coat Paint
Install Ceiling Grid
MEPF Trim at Ceiling Grid
Install Wall Finishes (TS-1/ MB-1 / AWP-3 / AWP-2)
Drop Ceiling Tile
Install Casework
Install Carpet Tile and Base
Final Paint
Final Clean
OAC Punch Process
City / OAC Acceptance of Space (Move-In Ready)
Frame Walls / Set Door Frames
Start Date: 08/18/25
Finish Date: 09/07/27
Data Date: 04/24/26
Run Date: 04/29/26
JMES - Master - GMP Schedule (REV-6.1) 4.27.26.ppx
JOHN McLOUGHLIN ELEMENTARY SCHOOL
ADDITION & RENOVATION
Page 17A
Duration Start Finish
2960 MEPF/ LV Overhead Rough-In 10 07/15/26 07/28/26
2970 MEP Wall Rough-In 8 07/21/26 07/30/26
2980 Hang Drywall / Tape and Finish 7 07/30/26 08/07/26
2990 Prime / First Coat 4 08/10/26 08/13/26
3000 Install…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .