Att E CLE Schedule.pdf
PDF 549 KB Posted
- Solicitation number
- S-P03062-00016905
- Issued by
- Clackamas County, Oregon
About this file
This document is a detailed construction schedule (GMP Schedule Version 1.0) for the Oregon City School District No. 62 (OCSD) Candy Lane Elementary School project, prepared by Howard S. Wright Construction and dated April 21, 2026. The schedule outlines a comprehensive renovation and expansion project spanning from the Notice to Proceed on August 4, 2025, through project closeout and substantial completion on July 22, 2027. Key project milestones include 50% Design Development by October 2, 2025; Design Development Package completion by November 14, 2025; 50% Construction Documents by February 2, 2026; Land Use Permit by May 15, 2026; Building Permit issuance by July 28, 2026; and Move-In for the 2027-2028 school year by August 19, 2027. The project encompasses multiple work streams including land use and permitting (124 days), abatement activities (45 days), civil work in two phases, cafeteria/kitchen addition construction (159 days), interior remodel work across three sectors, roofing work, mechanical and electrical equipment installation, commissioning, inspections, and final punchlist activities.
The schedule details numerous construction activities organized by sector and work type, including site work, demolition, structural framing, MEP (mechanical, electrical, plumbing) installations, finishes, and equipment procurement. Critical path activities include mechanical equipment submittal and fabrication (120 days), electrical equipment submittal and fabrication (140 days), roof truss fabrication (100 days), and walk-in cooler fabrication (130 days), with procurement activities running from March 6, 2026, through March 15, 2027. The project includes three interior remodel sectors (A, B, and C) with varying durations and overlapping schedules, commissioning activities for mechanical equipment across all sectors, and final inspection and closeout procedures. The schedule incorporates a ten-day allowance for inclement weather delays and establishes substantial completion as a critical milestone on July 22, 2027, with move-in activities scheduled for July 23 through August 19, 2027.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Activity ID Activity Name Original
Duration
Start Finish
OCSD Candy Lane GMP Schedule Ver 1.0OCSD Candy Lane GMP Schedule Ver 1.0 518 04-Aug-25 19-Aug-27
MIlestonesMIlestones 518 04-Aug-25 19-Aug-27
Mile-100 Notice to Proceed 0 04-Aug-25
Mile-110 50% DD's 0 02-Oct-25
Mile-230 DD's Package 0 14-Nov-25
Mile-240 50% CD's 0 02-Feb-26
Mile-290 Land Use Permit 0 15-May-26
Mile-200 Last Day of School Year '25-'26 0 12-Jun-26*
Mile-250 CD's Complete 0 15-Jun-26
Mile-120 Move Out of Candy Lane ES 5 17-Jun-26* 23-Jun-26
Mile-280 Building Permit Issued 0 28-Jul-26
Mile-210 Start of School Year '26 - '27 0 08-Sep-26*
Mile-260 Mechanical Equip. On-Site 0 16-Oct-26
Mile-270 Electrical Equip. On-Site 0 13-Nov-26
Mile-340 Temp Roof at Cafeteria Complete 0 27-Jan-27
Mile-220 Substantial Completion 0 22-Jul-27
Mile-310 Move-In for 27-28 School Year 20 23-Jul-27 19-Aug-27
Summary ScheduleSummary Schedule 362 02-Feb-26 06-Jul-27
Sum- 105 Land Use & Permitting Process 124 02-Feb-26 27-Jul-26
Sum- 210 Abatement 45 24-Jun-26 26-Aug-26
Sum- 110 Civil Work - Phase 1 47 28-Jul-26 01-Oct-26
Sum- 100 Overall Construction 231 06-Aug-26 06-Jul-27
Sum- 140 Sector B Construction 115 01-Sep-26 16-Feb-27
Sum- 200 Cafeteria Addition 159 16-Oct-26 03-Jun-27
Sum- 130 Commissioning 121 05-Jan-27 24-Jun-27
Sum- 120 Civil Work - Phase 2 35 15-Apr-27 03-Jun-27
PreconstructionPreconstruction 406 04-Aug-25 15-Mar-27
DesignDesign 219 04-Aug-25 15-Jun-26
A1070 Design Development 74 04-Aug-25 14-Nov-25
A1090 50% DD's 0 02-Oct-25
A1080 Design Development Completed 0 14-Nov-25
A1100 Construction Documents 125 17-Nov-25 15-May-26
A1110 50% CD's 0 02-Feb-26
A1130 Permit Drawings Issued 0 27-Feb-26*
A1120 Construction Documents Completed 0 15-Jun-26
PermittingPermitting 124 02-Feb-26 27-Jul-26
Per-1130 Land Use Permit 65 02-Feb-26* 01-May-26
Per-1140 Building Permit Review 70 02-Mar-26* 08-Jun-26
Per-1170 * Land Use Public Hearing * 0 30-Apr-26*
Per-1190 *Land Use Decision* 10 01-May-26 14-May-26
Per-1180 * KPFF Address Conditions of Land Use Review * 10 15-May-26 29-May-26
Per-1160 * Development Permit Timeline * 40 01-Jun-26 27-Jul-26
Per-1150 *Building Permit Issued* 0 27-Jul-26
ProcurementProcurement 258 06-Mar-26 15-Mar-27
A1210 Bid Package 22 06-Mar-26 06-Apr-26
A1220 Interview & Select Critical Contractors 9 07-Apr-26 17-Apr-26
A1270 Unit Ventilators Bidding & Leveling 30 07-Apr-26 18-May-26
A1310 Present GMP 0 17-Apr-26
A1320 GMP Presented to School Board 0 27-Apr-26*
A1230 Mechanical Equip. Submittals & Fabrication 120 28-Apr-26 15-Oct-26
A1240 Electrical Equip. Submittals & Fabrication 140 28-Apr-26 12-Nov-26
A1280 Unit Ventilators Submittal Package Prep. 15 19-May-26 09-Jun-26
A1290 Unit Ventilator Submittal Review & Approval 20 10-Jun-26 08-Jul-26
A1300 Unit Ventilator Fabrication & Delivery 80 09-Jul-26 29-Oct-26
A1260 Roof Truss Submittals & Fabrication 100 27-Jul-26 17-Dec-26
A1250 Walk-In Cooler Selection, Submittals & Fabrication 130 04-Sep-26 15-Mar-27
ConstructionConstruction 280 15-Jun-26 22-Jul-27
Candy Lane Site WorkCandy Lane Site Work 280 15-Jun-26 22-Jul-27
MobilizationMobilization 37 15-Jun-26 05-Aug-26
Mob-1040 Grade & Rock Craft Parking (inc. Erosion Control) 10 15-Jun-26* 26-Jun-26
Mob-1060 Temp Fence at Craft Parking Area 5 17-Jun-26 23-Jun-26
Mob-1010 Set-Up Construction Trailers 3 24-Jun-26 26-Jun-26
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
2025 2026 2027
Notice to Proceed
50% DD's
DD's Package
50% CD's
Land Use Permit
Last Day of School Year '25-'26
CD's Complete
Move Out of Candy Lane ES
Building Permit Issued
Start of School Year '26 - '27
Mechanical Equip. On-Site
Electrical Equip. On-Site
Temp Roof at Cafeteria Complete
Substantial Completion
Move-In for 27-28 School Year
Land Use & Permitting Process
Abatement
Civil Work - Phase 1
Overall Construction
Sector B Construction
Cafeteria Addition
Commissioning
Civil Work - Phase 2
Design Development
50% DD's
Design Development Completed
Construction Documents
50% CD's
Permit Drawings Issued
Construction Documents Completed
Land Use Permit
Building Permit Review
* Land Use Public Hearing *
*Land Use Decision*
* KPFF Address Conditions of Land Use Review *
* Development Permit Timeline *
*Building Permit Issued*
Bid Package
Interview & Select Critical Contractors
Unit Ventilators Bidding & Leveling
Present GMP
GMP Presented to School Board
Mechanical Equip. Submittals & Fabrication
Electrical Equip. Submittals & Fabrication
Unit Ventilators Submittal Package Prep.
Unit Ventilator Submittal Review & Approval
Unit Ventilator Fabrication & Delivery
Roof Truss Submittals & Fabrication
Walk-In Cooler Selection, Submittals & Fabrication
Grade & Rock Craft Parking (inc. Erosion Control)
Temp Fence at Craft Parking Area
Set-Up Construction Trailers
OCSD Candy Lane GMP Schedule Ver 1.0 Howard S. Wright Construction 21-Apr-26 10:51
Remaining Level of Effort
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
OCSD Candy Lane GMP Schedule Ver 1.0
Start Finish
Mob-1030 Temp Power to Trailer 3 25-Jun-26 29-Jun-26
Mob-1070 Mob to Site Trailer 2 30-Jun-26 01-Jul-26
Mob-1080 Temp Power For Building 5 28-Jul-26 03-Aug-26
Mob-1000 Temp Construction Fence (around the school) 5 30-Jul-26 05-Aug-26
Mob-1050 Erect Temp Stair Tower to Roof 3 30-Jul-26 03-Aug-26
Site WorkSite Work 218 28-Jul-26 07-Jun-27
Site-0100 Erosion Control 2 28-Jul-26 29-Jul-26
Site-0105 Remove Play Ground Equipment 10 30-Jul-26 12-Aug-26
Site-0120 Remove Trees 5 03-Aug-26 07-Aug-26
Site-1000 Grade / Excav. New Parent Loop Extension 15 10-Aug-26 28-Aug-26
Site-0110 Relocate Building Transformer 25 13-Aug-26 17-Sep-26
Site-0111 New Unground Primary Feeder Conduit 5 13-Aug-26 19-Aug-26
Site-0140 Demo Site Utilities 10 17-Aug-26 28-Aug-26
Site-0112 PGE Inspection & Approval of Primary Conduit 5 20-Aug-26 26-Aug-26
Site-0150 Build Rain Garden 15 24-Aug-26 14-Sep-26
Site-0113 Backfill Primary Conduit 5 27-Aug-26 02-Sep-26
Site-1030 New Drive Approach 10 27-Aug-26 10-Sep-26
Site-0130 New Storm Line w/ Catch Basins 12 31-Aug-26 16-Sep-26
Site-0114 CT Cabinet & Main Disconnect 7 01-Sep-26 10-Sep-26
Site-0160 New Sanitary & Water Lines 15 08-Sep-26 28-Sep-26
Site-0133 PGE Moves Transformer & Pulls Primary 5 11-Sep-26 17-Sep-26
Site-1010 Finish Grade Parent Loop & Parking Lot 10 11-Sep-26 24-Sep-26
Site-0180 New Fire Water Vault & Line 10 18-Sep-26 01-Oct-26
Site-1020 1st Lift of Pavement at Parent Loop/Parking lot 5 25-Sep-26 01-Oct-26
Site-1070 Build New Cover Walkway at Portables 60 29-Sep-26 23-Dec-26
Site-1040 Cut & Remove Pavement for Curbs in Parking Lot 5 15-Apr-27 21-Apr-27
Site-1050 Build Soft Play Area 25 22-Apr-27 26-May-27
Site-1060 F & P Curbs & Gutters 15 22-Apr-27 12-May-27
Site-1100 F/P Sidewalks 15 29-Apr-27 19-May-27
Site-0170 F/P New Curb & Patch Sidewalk at Front Loop 10 13-May-27 26-May-27
Site-1080 2nd Lift of Pavement at Parent Loop/Parking 5 20-May-27 26-May-27
Site-1110 Remove Half Street (Hull Ave) 5 20-May-27 26-May-27
Site-1090 Stripe Parent Loop/Parking 5 27-May-27 03-Jun-27
Site-1120 Pave Half Street (Hull Ave) 7 27-May-27 07-Jun-27
AbatementAbatement 45 24-Jun-26 26-Aug-26
Abate-1010 Abate & Soft Demo Sector A - Restroom & Hallway Flooring & Fittings 10 24-Jun-26 08-Jul-26
Abate-1080 Abate & Soft Demo Sector A - Pipe / Duct Fittings at Mech. Mezzanine 5 01-Jul-26 08-Jul-26
Abate-1040 Abate & Soft Demo Sector A - Cafeteria/Kitchen Fittings 5 09-Jul-26 15-Jul-26
Abate-1020 Abate & Soft Demo Sector C - Walls & Fixtures & F it tings 15 16-Jul-26 05-Aug-26
Abate-1000 Abate & Soft Demo Sector B - Flooring & Fittings in Classrooms & Hallway 15 06-Aug-26 26-Aug-26
Cafeteria / Kitchen AdditionCafeteria / Kitchen Addition 159 16-Oct-26 03-Jun-27
ExteriorExterior 104 16-Oct-26 17-Mar-27
Add-1190 Build Building Pad 3 16-Oct-26 20-Oct-26
Add-1200 Excavate Footings 5 21-Oct-26 27-Oct-26
Add-1210 F/R/P Footings 10 26-Oct-26 06-Nov-26
Add-1215 Under Slab Utilities 15 02-Nov-26 20-Nov-26
Add-1220 Grade, Rock & Vapor Barrier for SOG 10 09-Nov-26 20-Nov-26
Add-1230 F/R/P SOG 8 17-Nov-26 30-Nov-26
Add-1110 Frame Exterior & Interior Struct. Wood Stud Walls 10 01-Dec-26 14-Dec-26
Add-1120 Frame Separation Wall - Metal Studs 5 10-Dec-26 16-Dec-26
Add-1150 Set Roof Trusses & Framing 10 17-Dec-26 31-Dec-26
Add-1130 Exterior Sheathing 10 29-Dec-26 12-Jan-27
Add-1160 Roof Sheathing - Lower Roof 5 04-Jan-27 08-Jan-27
Add-1140 WRB at Exterior Walls 10 06-Jan-27 20-Jan-27
Add-1165 Roof Sheathing - High Roof - Car Decking 7 11-Jan-27 20-Jan-27
Add-1170 Frame Parapet Walls 5 11-Jan-27 15-Jan-27
Add-1270 Install Storefront Glazing System 10 14-Jan-27 28-Jan-27
Add-1180 Roofing Vapor Barrier - Temp Roof 5 21-Jan-27 27-Jan-27
Add-1050 Roofing 15 28-Jan-27 17-Feb-27
Add-1280 Masonry Veneer 20 29-Jan-27 25-Feb-27
Add-1100 Install Mechanical Rooftop Equip. 20 18-Feb-27 17-Mar-27
Add-1290 Metal Siding & Wall Cap 15 19-Feb-27 11-Mar-27
InteriorInterior 102 11-Jan-27 03-Jun-27
Add-1060 Interior Overhead Rough-Ins 20 11-Jan-27 08-Feb-27
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
2025 2026 2027
Temp Power to Trailer
Mob to Site Trailer
Temp Power For Building
Temp Construction Fence (around the school)
Erect Temp Stair Tower to Roof
Erosion Control
Remove Play Ground Equipment
Remove Trees
Grade / Excav. New Parent Loop Extension
Relocate Building Transformer
New Unground Primary Feeder Conduit
Demo Site Utilities
PGE Inspection & Approval of Primary Conduit
Build Rain Garden
Backfill Primary Conduit
New Drive Approach
New Storm Line w/ Catch Basins
CT Cabinet & Main Disconnect
New Sanitary & Water Lines
PGE Moves Transformer & Pulls Primary
Finish Grade Parent Loop & Parking Lot
New Fire Water Vault & Line
1st Lift of Pavement at Parent Loop/Parking lot
Build New Cover Walkway at Portables
Cut & Remove Pavement for Curbs in Parking Lot
Build Soft Play Area
F & P Curbs & Gutters
F/P Sidewalks
F/P New Curb & Patch Sidewalk at Front Loop
2nd Lift of Pavement at Parent Loop/Parking
Remove Half Street (Hull Ave)
Stripe Parent Loop/Parking
Pave Half Street (Hull Ave)
Abate & Soft Demo Sector A - Restroom & Hallway Flooring & Fittings
Abate & Soft Demo Sector A - Pipe / Duct Fittings at Mech. Mezzanine
Abate & Soft Demo Sector A - Cafeteria/Kitchen Fittings
Abate & Soft Demo Sector C - Walls & Fixtures & F it tings
Abate & Soft Demo Sector B - Flooring & Fittings in Classrooms & Hallway
Build Building Pad
Excavate Footings
F/R/P Footings
Under Slab Utilities
Grade, Rock & Vapor Barrier for SOG
F/R/P SOG
Frame Exterior & Interior Struct. Wood Stud Walls
Frame Separation Wall - Metal Studs
Set Roof Trusses & Framing
Exterior Sheathing
Roof Sheathing - Lower Roof
WRB at Exterior Walls
Roof Sheathing - High Roof - Car Decking
Frame Parapet Walls
Install Storefront Glazing System
Roofing Vapor Barrier - Temp Roof
Roofing
Masonry Veneer
Install Mechanical Rooftop Equip.
Metal Siding & Wall Cap
Interior Overhead Rough-Ins
OCSD Candy Lane GMP Schedule Ver 1.0 Howard S. Wright Construction 21-Apr-26 10:51
Remaining Level of Effort
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Start Finish
Add-1240 Frame Interior Partition Walls 6 11-Jan-27 19-Jan-27
Add-1260 Frame Soffits & Hard Lids 8 19-Jan-27 28-Jan-27
Add-1250 MEP Wall & Ceiling Rough-Ins 15 28-Jan-27 17-Feb-27
Add-1070 Interior Walls /Soffits/Ceilings 45 04-Feb-27 07-Apr-27
Add-1300 Rock, Tape & Finish Kitchen Walls & Ceilings 15 11-Feb-27 03-Mar-27
Add-1310 Rock, Tape & Finish Cafeteria Walls & Ceilings 15 19-Feb-27 11-Mar-27
Add-1330 Prime & Paint Kitchen Walls & Ceilings 7 04-Mar-27 12-Mar-27
Add-1500 Tile Restroom Walls 8 11-Mar-27 22-Mar-27
Add-1350 Prime / Paint Cafeteria Walls & Ceilings 7 12-Mar-27 22-Mar-27
Add-1320 Kitchen Overhead Doors 5 15-Mar-27 19-Mar-27
Add-1430 Walk-In Cooler 10 15-Mar-27 26-Mar-27
Add-1340 Kitchen Fluid Applied Flooring 8 22-Mar-27 31-Mar-27
Add-1390 Cafeteria Ceiling Grid 3 23-Mar-27 25-Mar-27
Add-1510 Restroom Sheet Vinyl Flooring 3 23-Mar-27 25-Mar-27
Add-1370 Cafeteria Light Fixture 5 26-Mar-27 01-Apr-27
Add-1410 Cafeteria Mech. Ceiling & Wall Trim 5 26-Mar-27 01-Apr-27
Add-1520 Restroom Plumbing Fixtures 3 26-Mar-27 30-Mar-27
Add-1380 Cafeteria Wall Graphics 10 29-Mar-27 09-Apr-27
Add-1530 Restroom MEP/F Finish Trim 3 31-Mar-27 02-Apr-27
Add-1460 Kitchen Ceiling Grid 5 01-Apr-27 07-Apr-27
Add-1400 Cafeteria Ceiling Tile 3 02-Apr-27 06-Apr-27
Add-1540 Restroom Accessories 3 05-Apr-27 07-Apr-27
Add-1470 Kitchen Mech, Elect & Fire Ceiling Trim 7 08-Apr-27 16-Apr-27
Add-1360 Polish Cafeteria Floor 6 12-Apr-27 19-Apr-27
Add-1480 Kitchen Ceiling Tile 5 19-Apr-27 23-Apr-27
Add-1420 Cafeteria Plumbing Fixtures 5 20-Apr-27 26-Apr-27
Add-1440 Seal Kitchen Concrete Floors 3 26-Apr-27 28-Apr-27
Add-1450 Kitchen Equipment & Wall Cover ings 20 29-Apr-27 26-May-27
Add-1490 Kitchen MEP Trim & Connections 10 20-May-27 03-Jun-27
Add-1550 Kitchen Doors & Hardware 5 27-May-27 03-Jun-27
Interior RemodelInterior Remodel 184 28-Jul-26 19-Apr-27
Demo WorkDemo Work 51 28-Jul-26 07-Oct-26
Sector ASector A 33 28-Jul-26 11-Sep-26
DemoA-1170 Safe Off MEP - Ceilings & Walls 3 28-Jul-26 30-Jul-26
DemoA-1010 Shore Library & Restroom Roof (Hallway Block Wall Demo) 2 31-Jul-26 03-Aug-26
DemoA-1080 Remove Wheelchair Lift 3 31-Jul-26 04-Aug-26
DemoA-1100 Remove Exterior Siding at Mechanical Mezzanine 3 31-Jul-26 04-Aug-26
DemoA-1020 Demo Hallway & Restroom Ceilings 5 04-Aug-26 10-Aug-26
DemoA-1105 Remove Library Sliding Doors 5 04-Aug-26 10-Aug-26
DemoA-1090 Remove Concrete Stairs - Gym Hallway 5 05-Aug-26 11-Aug-26
DemoA-1130 Remove Air Handler & Ductwork at Mechanical Mezzanne 5 05-Aug-26 11-Aug-26
DemoA-1030 Demo Cricket Section of Roof (Library Hallway) 5 06-Aug-26 12-Aug-26
DemoA-1110 Demo Kitchen Walls & Cabinets 5 11-Aug-26 17-Aug-26
DemoA-1150 Shore Restroom Roof for Block Removal 2 11-Aug-26 12-Aug-26
DemoA-1160 Remove (E) Water Lines 8 11-Aug-26 20-Aug-26
DemoA-1060 Remove AHU & Ductwork - Above Gym Hallway 7 12-Aug-26 20-Aug-26
DemoA-1040 Remove Block Walls & Doors - Library Hallway 4 13-Aug-26 18-Aug-26
DemoA-1135 Remove Wood Floor & Wall at Custodial Space 5 18-Aug-26 24-Aug-26
DemoA-1050 Remove Block Walls & Fixtures - Sector A Restroom 8 19-Aug-26 28-Aug-26
DemoA-1070 Remove Block Walls & Ceilings - Gym Hallway 5 21-Aug-26 27-Aug-26
DemoA-1120 Remove Block Walls - Family Resource 5 28-Aug-26 03-Sep-26
DemoA-1140 Remove Block Wall for New Exterior Gym Door 5 04-Sep-26 11-Sep-26
Sector BSector B 23 27-Aug-26 29-Sep-26
DemoB-1060 Safe Off MEP 3 27-Aug-26 31-Aug-26
DemoB-1020 Demo Hallway Ceiling 4 01-Sep-26 04-Sep-26
DemoB-1010 Remove (E) Water Lines 6 08-Sep-26 15-Sep-26
DemoB-1030 Remove (E) Unit Ventilators 5 16-Sep-26 22-Sep-26
DemoB-1040 Remove (E) Classroom Cabinets 10 16-Sep-26 29-Sep-26
Sector CSector C 48 31-Jul-26 07-Oct-26
DemoC-1050 Safe Off - MEP 3 31-Jul-26 04-Aug-26
DemoC-1030 Demo Ceilings 10 05-Aug-26 18-Aug-26
DemoC-1040 Clear Out Ceiling Space of MEP 15 12-Aug-26 01-Sep-26
DemoC-1020 Remove (E) Interior Walls & Cabinets 15 02-Sep-26 23-Sep-26
DemoC-1070 Demo Exterior Walls for Unit Ventilators 10 24-Sep-26 07-Oct-26
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
2025 2026 2027
Frame Interior Partition Walls
Frame Soffits & Hard Lids
MEP Wall & Ceiling Rough-Ins
Interior Walls /Soffits/Ceilings
Rock, Tape & Finish Kitchen Walls & Ceilings
Rock, Tape & Finish Cafeteria Walls & Ceilings
Prime & Paint Kitchen Walls & Ceilings
Tile Restroom Walls
Prime / Paint Cafeteria Walls & Ceilings
Kitchen Overhead Doors
Walk-In Cooler
Kitchen Fluid Applied Flooring
Cafeteria Ceiling Grid
Restroom Sheet Vinyl Flooring
Cafeteria Light Fixture
Cafeteria Mech. Ceiling & Wall Trim
Restroom Plumbing Fixtures
Cafeteria Wall Graphics
Restroom MEP/F Finish Trim
Kitchen Ceiling Grid
Cafeteria Ceiling Tile
Restroom Accessories
Kitchen Mech, Elect & Fire Ceiling Trim
Polish Cafeteria Floor
Kitchen Ceiling Tile
Cafeteria Plumbing Fixtures
Seal Kitchen Concrete Floors
Kitchen Equipment & Wall Cover ings
Kitchen MEP Trim & Connections
Kitchen Doors & Hardware
Safe Off MEP - Ceilings & Walls
Shore Library & Restroom Roof (Hallway Block Wall Demo)
Remove Wheelchair Lift
Remove Exterior Siding at Mechanical Mezzanine
Demo Hallway & Restroom Ceilings
Remove Library Sliding Doors
Remove Concrete Stairs - Gym Hallway
Remove Air Handler & Ductwork at Mechanical Mezzanne
Demo Cricket Section of Roof (Library Hallway)
Demo Kitchen Walls & Cabinets
Shore Restroom Roof for Block Removal
Remove (E) Water Lines
Remove AHU & Ductwork - Above Gym Hallway
Remove Block Walls & Doors - Library Hallway
Remove Wood Floor & Wall at Custodial Space
Remove Block Walls & Fixtures - Sector A Restroom
Remove Block Walls & Ceilings - Gym Hallway
Remove Block Walls - Family Resource
Remove Block Wall for New Exterior Gym Door
Safe Off MEP
Demo Hallway Ceiling
Remove (E) Water Lines
Remove (E) Unit Ventilators
Remove (E) Classroom Cabinets
Safe Off - MEP
Demo Ceilings
Clear Out Ceiling Space of MEP
Remove (E) Interior Walls & Cabinets
Demo Exterior Walls for Unit Ventilators
OCSD Candy Lane GMP Schedule Ver 1.0 Howard S. Wright Construction 21-Apr-26 10:51
Remaining Level of Effort
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Start Finish
Sector A - Remodel WorkSector A - Remodel Work 162 19-Aug-26 09-Apr-27
NewA-1010 Saw Cut for New Plumbing 3 19-Aug-26 21-Aug-26
NewA-1030 Underslab Plumbing 6 24-Aug-26 31-Aug-26
NewA-1220 Structural Supports to Gym Roof (PV Array) 10 24-Aug-26 04-Sep-26
NewA-1020 Frame New Walls, Soffits & Hard Lids 25 01-Sep-26 06-Oct-26
NewA-1050 Concrete at Plumbing Trenches 3 01-Sep-26 03-Sep-26
NewA-1060 First Polish of Concrete Floors 8 04-Sep-26 16-Sep-26
NewA-1240 New Exterior Gym Door & Hardware 10 14-Sep-26 25-Sep-26
NewA-1070 Over Head Rough-Ins 20 16-Sep-26 13-Oct-26
NewA-1040 Wall Rough-Ins 20 18-Sep-26 15-Oct-26
NewA-1090 Re-Lights & Door Frames 8 07-Oct-26 16-Oct-26
NewA-1250 F/R/P New Concrete Ramp 10 14-Oct-26 27-Oct-26
NewA-1080 Rock, Tape & Finish Walls & Hard Lids 30 19-Oct-26 01-Dec-26
NewA-1260 Set New Electrical Gear (800amps) 10 13-Nov-26 30-Nov-26
NewA-1100 Prime & 1st Coat Paint 10 02-Dec-26 15-Dec-26
NewA-1110 Ceiling Grid 10 16-Dec-26 30-Dec-26
NewA-1120 Ceiling MEPF Trim 20 24-Dec-26 25-Jan-27
NewA-1130 Casework 12 11-Jan-27 27-Jan-27
NewA-1150 Carpet & VCT 12 26-Jan-27 10-Feb-27
NewA-1140 Ceiling Tile 10 11-Feb-27 24-Feb-27
NewA-1170 Finish Coat of Paint 10 18-Feb-27 03-Mar-27
NewA-1180 Finish Polish of Floors & Seal 5 25-Feb-27 03-Mar-27
NewA-1160 Restroom Partitions 5 04-Mar-27 10-Mar-27
NewA-1200 MEPF Finish Trim 15 04-Mar-27 24-Mar-27
NewA-1190 Plumbing Fixtures at Restroom 5 11-Mar-27 17-Mar-27
NewA-1210 Doors & Hardware 7 18-Mar-27 26-Mar-27
NewA-1230 Final Clean 10 29-Mar-27 09-Apr-27
Library AreaLibrary Area 166 18-Aug-26 14-Apr-27
Libr-1010 MEPF Overhead Rough-Ins 20 18-Aug-26 15-Sep-26
Libr-1020 Frame New Walls & Soffits 10 16-Sep-26 29-Sep-26
Libr-1030 Wall Rough-Ins 10 30-Sep-26 13-Oct-26
Libr-1040 Rock, Tape & Finish Walls & Soffits 15 14-Oct-26 03-Nov-26
Libr-1060 Prime & 1st Coat Paint - Walls, Soffits & Ceiling 10 04-Nov-26 17-Nov-26
Libr-1050 Casework 10 18-Nov-26 03-Dec-26
Libr-1070 Flooring 15 04-Dec-26 24-Dec-26
Libr-1080 Finish Coat Paint 5 28-Dec-26 04-Jan-27
Libr-1090 Doors & Hardware 3 18-Mar-27 22-Mar-27
Libr-1100 MEPF Trim 10 25-Mar-27 07-Apr-27
Libr-1110 Final Clean 5 08-Apr-27 14-Apr-27
Sector B - Remodel WorkSector B - Remodel Work 88 27-Aug-26 04-Jan-27
NewB-1090 Rough Polish of Floors 15 27-Aug-26 17-Sep-26
NewB-1020 New Water Line in Hallway Ceiling (Overhead) 10 16-Sep-26 29-Sep-26
NewB-1010 Saw Cut Slab 2 18-Sep-26 21-Sep-26
NewB-1030 Underslab Plumbing 5 22-Sep-26 28-Sep-26
NewB-1040 Fire Sprinklers 15 23-Sep-26 13-Oct-26
NewB-1060 Roof Support Members for Rooftop Units 10 29-Sep-26 12-Oct-26
NewB-1080 Pour Back Plumbing Trenches 5 29-Sep-26 05-Oct-26
NewB-1070 New Exhaust / Ventilation 15 30-Sep-26 20-Oct-26
NewB-1100 New Classroom Casework 15 21-Oct-26 10-Nov-26
NewB-1050 Install Unit Ventilators & Line Sets 10 30-Oct-26 12-Nov-26
NewB-1110 Plumbing Fixture 10 11-Nov-26 24-Nov-26
NewB-1140 Teaching Walls 10 11-Nov-26 24-Nov-26
NewB-1120 Finish Polish of Floors 15 25-Nov-26 17-Dec-26
NewB-1130 Final Clean 10 18-Dec-26 04-Jan-27
Sector C - Remodel WorkSector C - Remodel Work 151 14-Sep-26 19-Apr-27
NewC-1065 Polish Floors - Rough Pass 15 14-Sep-26 02-Oct-26
NewC-1100 Spray Foam & Seal Perimiter Walls 10 24-Sep-26 07-Oct-26
NewC-1010 Layout New Walls 5 08-Oct-26 14-Oct-26
NewC-1020 Saw Cut Slab for Plumbing 7 13-Oct-26 21-Oct-26
NewC-1030 Frame New Walls 10 15-Oct-26 28-Oct-26
NewC-1040 Overhead Rough-Ins (MEPF) 25 15-Oct-26 18-Nov-26
NewC-1050 Underslab Plumbing 10 20-Oct-26 02-Nov-26
NewC-1110 Set HM Frames 5 20-Oct-26 26-Oct-26
NewC-1025 Saw Cut & Excav. Sabs for Shear Wall Footings 10 22-Oct-26 04-Nov-26
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
2025 2026 2027
Saw Cut for New Plumbing
Underslab Plumbing
Structural Supports to Gym Roof (PV Array)
Frame New Walls, Soffits & Hard Lids
Concrete at Plumbing Trenches
First Polish of Concrete Floors
New Exterior Gym Door & Hardware
Over Head Rough-Ins
Wall Rough-Ins
Re-Lights & Door Frames
F/R/P New Concrete Ramp
Rock, Tape & Finish Walls & Hard Lids
Set New Electrical Gear (800amps)
Prime & 1st Coat Paint
Ceiling Grid
Ceiling MEPF Trim
Casework
Carpet & VCT
Ceiling Tile
Finish Coat of Paint
Finish Polish of Floors & Seal
Restroom Partitions
MEPF Finish Trim
Plumbing Fixtures at Restroom
Doors & Hardware
Final Clean
MEPF Overhead Rough-Ins
Frame New Walls & Soffits
Wall Rough-Ins
Rock, Tape & Finish Walls & Soffits
Prime & 1st Coat Paint - Walls, Soffits & Ceiling
Casework
Flooring
Finish Coat Paint
Doors & Hardware
MEPF Trim
Final Clean
Rough Polish of Floors
New Water Line in Hallway Ceiling (Overhead)
Saw Cut Slab
Underslab Plumbing
Fire Sprinklers
Roof Support Members for Rooftop Units
Pour Back Plumbing Trenches
New Exhaust / Ventilation
New Classroom Casework
Install Unit Ventilators & Line Sets
Plumbing Fixture
Teaching Walls
Finish Polish of Floors
Final Clean
Polish Floors - Rough Pass
Spray Foam & Seal Perimiter Walls
Layout New Walls
Saw Cut Slab for Plumbing
Frame New Walls
Overhead Rough-Ins (MEPF)
Underslab Plumbing
Set HM Frames
Saw Cut & Excav. Sabs for Shear Wall Footings
OCSD Candy Lane GMP Schedule Ver 1.0 Howard S. Wright Construction 21-Apr-26 10:51
Remaining Level of Effort
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Start Finish
NewC-1070 Frame Hard Lids 5 29-Oct-26 04-Nov-26
NewC-1080 Wall & Hard Lids Rough-Ins (MEPF) 25 29-Oct-26 04-Dec-26
NewC-1060 Place Plumbing Trench Concrete 3 03-Nov-26 05-Nov-26
NewC-1035 New Shear Wall Footings 10 05-Nov-26 18-Nov-26
NewC-1045 Build Shear Walls 7 12-Nov-26 20-Nov-26
NewC-1055 Wall Rough-Ins at Shear Walls 7 20-Nov-26 02-Dec-26
NewC-1090 Rock, Tape & Finish Walls & Hard Lids 30 30-Nov-26 12-Jan-27
NewC-1120 Prime & 1st Coat Paint 15 04-Jan-27 25-Jan-27
NewC-1130 Ceiling Grid 20 11-Jan-27 08-Feb-27
NewC-1150 Ceiling Grid MEPF Fixtures & Trim 20 19-Jan-27 15-Feb-27
NewC-1220 Toilet Partitions 5 19-Jan-27 25-Jan-27
NewC-1140 Casework 20 21-Jan-27 17-Feb-27
NewC-1170 Set New Unit Ventilators 10 26-Jan-27 08-Feb-27
NewC-1160 Drop Ceiling Tile 25 04-Feb-27 10-Mar-27
NewC-1260 Teaching Walls 15 18-Feb-27 10-Mar-27
NewC-1180 Paint Finish Coat 16 22-Feb-27 15-Mar-27
NewC-1190 Carpet in Classrooms 20 01-Mar-27 26-Mar-27
NewC-1240 Floor Polish Final Pass 7 11-Mar-27 19-Mar-27
NewC-1230 Set Plumbing Fixtures 8 16-Mar-27 25-Mar-27
NewC-1250 MEPF Finish Trim 15 16-Mar-27 05-Apr-27
NewC-1200 Doors & Hardware 10 17-Mar-27 30-Mar-27
NewC-1210 Final Clean - Sector C 10 06-Apr-27 19-Apr-27
RoofRoof 99 04-Aug-26 23-Dec-26
Sector A - RoofSector A - Roof 75 06-Aug-26 19-Nov-26
RoofA-1020 Demo Cricket Section of Roof Structure 5 06-Aug-26 12-Aug-26
RoofA-1030 Re-Build Roof Structure 3 08-Sep-26 10-Sep-26
RoofA-1010 Remove Old Roof 10 09-Sep-26 22-Sep-26
RoofA-1040 New Roof 15 01-Oct-26 21-Oct-26
RoofA-1050 Complete New Roof at New Roof Structure 6 22-Oct-26 29-Oct-26
RoofA-1060 New Rooftop Equipment 15 30-Oct-26 19-Nov-26
Sector B - RoofSector B - Roof 72 25-Aug-26 07-Dec-26
RoofB-1010 Demo Old Roof 10 25-Aug-26 08-Sep-26
RoofB-1020 New Roof 20 02-Sep-26 30-Sep-26
RoofB-1070 New Rooftop Units 10 20-Nov-26 07-Dec-26
Sector C - RoofSector C - Roof 99 04-Aug-26 23-Dec-26
RoofC-1030 Remove Existing Rooftop Unit & Structure 8 04-Aug-26 13-Aug-26
RoofC-1010 Demo Old Roof 7 14-Aug-26 24-Aug-26
RoofC-1020 New Roof 10 19-Aug-26 01-Sep-26
RoofC-1040 New Rooftop Equipment 12 08-Dec-26 23-Dec-26
PunchlistPunchlist 128 05-Jan-27 06-Jul-27
Pun-1040 Punch Classrooms - Sector B 10 05-Jan-27 19-Jan-27
Pun-1000 Punch Restrooms - Sector A 10 12-Apr-27 23-Apr-27
Pun-1090 Punch Sector A 10 12-Apr-27 23-Apr-27
Pun-1010 Punch Library Space 10 15-Apr-27 28-Apr-27
Pun-1030 Punch Restrooms - Sector C 10 20-Apr-27 03-May-27
Pun-1050 Punch Classrooms - Sector C 10 20-Apr-27 03-May-27
Pun-1070 Punch New Parent Loop / Parking Lot 5 04-Jun-27 10-Jun-27
Pun-1080 Punch Exterior / Site 5 04-Jun-27 10-Jun-27
Pun-1060 Punch Kitchen 10 22-Jun-27 06-Jul-27
Commissioning / Start-UpCommissioning / Start-Up 128 05-Jan-27 06-Jul-27
CXB-1190 Start-Up/Commissioning Mechanical Equipment - Sector B 10 05-Jan-27 19-Jan-27
CXA-1200 Start-Up/Commissioning Mechanical Equipment - Sector A 10 15-Apr-27 28-Apr-27
CXC-1020 Start-Up/Commissioning Mechanical Equipment - Sector C 10 20-Apr-27 03-May-27
CXA-1010 Start-Up/Commissioning Mechanical Equipment - Cafeteria 5 29-Apr-27 05-May-27
CXA-1000 Start-Up of Kitchen Equipment 15 04-Jun-27 24-Jun-27
CXA-1030 Commission Kitchen Equipment 10 22-Jun-27 06-Jul-27
Finial InspectionsFinial Inspections 46 04-May-27 08-Jul-27
A1060 Finial Inspections (FLS) - Sector C 5 04-May-27 10-May-27
A1040 Final Inspections of Kitchen FLS 5 01-Jul-27 08-Jul-27
Project CloseoutProject Closeout 10 09-Jul-27 22-Jul-27
A1140 Inclement Weather Delay 10 09-Jul-27 22-Jul-27
A1050 Substantial Completion 0 22-Jul-27
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
2025 2026 2027
Frame Hard Lids
Wall & Hard Lids Rough-Ins (MEPF)
Place Plumbing Trench Concrete
New Shear Wall Footings
Build Shear Walls
Wall Rough-Ins at Shear Walls
Rock, Tape & Finish Walls & Hard Lids
Prime & 1st Coat Paint
Ceiling Grid
Ceiling Grid MEPF Fixtures & Trim
Toilet Partitions
Casework
Set New Unit Ventilators
Drop Ceiling Tile
Teaching Walls
Paint Finish Coat
Carpet in Classrooms
Floor Polish Final Pass
Set Plumbing Fixtures
MEPF Finish Trim
Doors & Hardware
Final Clean - Sector C
Demo Cricket Section of Roof Structure
Re-Build Roof Structure
Remove Old Roof
New Roof
Complete New Roof at New Roof Structure
New Rooftop Equipment
Demo Old Roof
New Roof
New Rooftop Units
Remove Existing Rooftop Unit & Structure
Demo Old Roof
New Roof
New Rooftop Equipment
Punch Classrooms - Sector B
Punch Restrooms - Sector A
Punch Sector A
Punch Library Space
Punch Restrooms - Sector C
Punch Classrooms - Sector C
Punch New Parent Loop / Parking Lot
Punch Exterior / Site
Punch Kitchen
Start-Up/Commissioning Mechanical Equipment - Sector B
Start-Up/Commissioning Mechanical Equipment - Sector A
Start-Up/Commissioning Mechanical Equipment - Sector C
Start-Up/Commissioning Mechanical Equipment - Cafeteria
Start-Up of Kitchen Equipment
Commission Kitchen Equipment
Finial Inspections (FLS) - Sector C
Final Inspections of Kitchen FLS
Inclement Weather Delay
Substantial Completion
OCSD Candy Lane GMP Schedule Ver 1.0 Howard S. Wright Construction 21-Apr-26 10:51
Remaining Level of Effort
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
File details come from the government source that posted it. Updated .