Att E CLE Schedule.pdf

PDF 549 KB Posted

Attached to
RFP B12-2026 Special Testing and Inspection Services
Solicitation number
S-P03062-00016905
Issued by
Clackamas County, Oregon

About this file

This document is a detailed construction schedule (GMP Schedule Version 1.0) for the Oregon City School District No. 62 (OCSD) Candy Lane Elementary School project, prepared by Howard S. Wright Construction and dated April 21, 2026. The schedule outlines a comprehensive renovation and expansion project spanning from the Notice to Proceed on August 4, 2025, through project closeout and substantial completion on July 22, 2027. Key project milestones include 50% Design Development by October 2, 2025; Design Development Package completion by November 14, 2025; 50% Construction Documents by February 2, 2026; Land Use Permit by May 15, 2026; Building Permit issuance by July 28, 2026; and Move-In for the 2027-2028 school year by August 19, 2027. The project encompasses multiple work streams including land use and permitting (124 days), abatement activities (45 days), civil work in two phases, cafeteria/kitchen addition construction (159 days), interior remodel work across three sectors, roofing work, mechanical and electrical equipment installation, commissioning, inspections, and final punchlist activities.

The schedule details numerous construction activities organized by sector and work type, including site work, demolition, structural framing, MEP (mechanical, electrical, plumbing) installations, finishes, and equipment procurement. Critical path activities include mechanical equipment submittal and fabrication (120 days), electrical equipment submittal and fabrication (140 days), roof truss fabrication (100 days), and walk-in cooler fabrication (130 days), with procurement activities running from March 6, 2026, through March 15, 2027. The project includes three interior remodel sectors (A, B, and C) with varying durations and overlapping schedules, commissioning activities for mechanical equipment across all sectors, and final inspection and closeout procedures. The schedule incorporates a ten-day allowance for inclement weather delays and establishes substantial completion as a critical milestone on July 22, 2027, with move-in activities scheduled for July 23 through August 19, 2027.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Activity ID Activity Name Original

Duration

Start Finish

OCSD Candy Lane GMP Schedule Ver 1.0OCSD Candy Lane GMP Schedule Ver 1.0 518 04-Aug-25 19-Aug-27

MIlestonesMIlestones 518 04-Aug-25 19-Aug-27

Mile-100 Notice to Proceed 0 04-Aug-25

Mile-110 50% DD's 0 02-Oct-25

Mile-230 DD's Package 0 14-Nov-25

Mile-240 50% CD's 0 02-Feb-26

Mile-290 Land Use Permit 0 15-May-26

Mile-200 Last Day of School Year '25-'26 0 12-Jun-26*

Mile-250 CD's Complete 0 15-Jun-26

Mile-120 Move Out of Candy Lane ES 5 17-Jun-26* 23-Jun-26

Mile-280 Building Permit Issued 0 28-Jul-26

Mile-210 Start of School Year '26 - '27 0 08-Sep-26*

Mile-260 Mechanical Equip. On-Site 0 16-Oct-26

Mile-270 Electrical Equip. On-Site 0 13-Nov-26

Mile-340 Temp Roof at Cafeteria Complete 0 27-Jan-27

Mile-220 Substantial Completion 0 22-Jul-27

Mile-310 Move-In for 27-28 School Year 20 23-Jul-27 19-Aug-27

Summary ScheduleSummary Schedule 362 02-Feb-26 06-Jul-27

Sum- 105 Land Use & Permitting Process 124 02-Feb-26 27-Jul-26

Sum- 210 Abatement 45 24-Jun-26 26-Aug-26

Sum- 110 Civil Work - Phase 1 47 28-Jul-26 01-Oct-26

Sum- 100 Overall Construction 231 06-Aug-26 06-Jul-27

Sum- 140 Sector B Construction 115 01-Sep-26 16-Feb-27

Sum- 200 Cafeteria Addition 159 16-Oct-26 03-Jun-27

Sum- 130 Commissioning 121 05-Jan-27 24-Jun-27

Sum- 120 Civil Work - Phase 2 35 15-Apr-27 03-Jun-27

PreconstructionPreconstruction 406 04-Aug-25 15-Mar-27

DesignDesign 219 04-Aug-25 15-Jun-26

A1070 Design Development 74 04-Aug-25 14-Nov-25

A1090 50% DD's 0 02-Oct-25

A1080 Design Development Completed 0 14-Nov-25

A1100 Construction Documents 125 17-Nov-25 15-May-26

A1110 50% CD's 0 02-Feb-26

A1130 Permit Drawings Issued 0 27-Feb-26*

A1120 Construction Documents Completed 0 15-Jun-26

PermittingPermitting 124 02-Feb-26 27-Jul-26

Per-1130 Land Use Permit 65 02-Feb-26* 01-May-26

Per-1140 Building Permit Review 70 02-Mar-26* 08-Jun-26

Per-1170 * Land Use Public Hearing * 0 30-Apr-26*

Per-1190 *Land Use Decision* 10 01-May-26 14-May-26

Per-1180 * KPFF Address Conditions of Land Use Review * 10 15-May-26 29-May-26

Per-1160 * Development Permit Timeline * 40 01-Jun-26 27-Jul-26

Per-1150 *Building Permit Issued* 0 27-Jul-26

ProcurementProcurement 258 06-Mar-26 15-Mar-27

A1210 Bid Package 22 06-Mar-26 06-Apr-26

A1220 Interview & Select Critical Contractors 9 07-Apr-26 17-Apr-26

A1270 Unit Ventilators Bidding & Leveling 30 07-Apr-26 18-May-26

A1310 Present GMP 0 17-Apr-26

A1320 GMP Presented to School Board 0 27-Apr-26*

A1230 Mechanical Equip. Submittals & Fabrication 120 28-Apr-26 15-Oct-26

A1240 Electrical Equip. Submittals & Fabrication 140 28-Apr-26 12-Nov-26

A1280 Unit Ventilators Submittal Package Prep. 15 19-May-26 09-Jun-26

A1290 Unit Ventilator Submittal Review & Approval 20 10-Jun-26 08-Jul-26

A1300 Unit Ventilator Fabrication & Delivery 80 09-Jul-26 29-Oct-26

A1260 Roof Truss Submittals & Fabrication 100 27-Jul-26 17-Dec-26

A1250 Walk-In Cooler Selection, Submittals & Fabrication 130 04-Sep-26 15-Mar-27

ConstructionConstruction 280 15-Jun-26 22-Jul-27

Candy Lane Site WorkCandy Lane Site Work 280 15-Jun-26 22-Jul-27

MobilizationMobilization 37 15-Jun-26 05-Aug-26

Mob-1040 Grade & Rock Craft Parking (inc. Erosion Control) 10 15-Jun-26* 26-Jun-26

Mob-1060 Temp Fence at Craft Parking Area 5 17-Jun-26 23-Jun-26

Mob-1010 Set-Up Construction Trailers 3 24-Jun-26 26-Jun-26

Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep

2025 2026 2027

Notice to Proceed

50% DD's

DD's Package

50% CD's

Land Use Permit

Last Day of School Year '25-'26

CD's Complete

Move Out of Candy Lane ES

Building Permit Issued

Start of School Year '26 - '27

Mechanical Equip. On-Site

Electrical Equip. On-Site

Temp Roof at Cafeteria Complete

Substantial Completion

Move-In for 27-28 School Year

Land Use & Permitting Process

Abatement

Civil Work - Phase 1

Overall Construction

Sector B Construction

Cafeteria Addition

Commissioning

Civil Work - Phase 2

Design Development

50% DD's

Design Development Completed

Construction Documents

50% CD's

Permit Drawings Issued

Construction Documents Completed

Land Use Permit

Building Permit Review

* Land Use Public Hearing *

*Land Use Decision*

* KPFF Address Conditions of Land Use Review *

* Development Permit Timeline *

*Building Permit Issued*

Bid Package

Interview & Select Critical Contractors

Unit Ventilators Bidding & Leveling

Present GMP

GMP Presented to School Board

Mechanical Equip. Submittals & Fabrication

Electrical Equip. Submittals & Fabrication

Unit Ventilators Submittal Package Prep.

Unit Ventilator Submittal Review & Approval

Unit Ventilator Fabrication & Delivery

Roof Truss Submittals & Fabrication

Walk-In Cooler Selection, Submittals & Fabrication

Grade & Rock Craft Parking (inc. Erosion Control)

Temp Fence at Craft Parking Area

Set-Up Construction Trailers

OCSD Candy Lane GMP Schedule Ver 1.0 Howard S. Wright Construction 21-Apr-26 10:51

Remaining Level of Effort

Actual Level of Effort

Actual Work

Remaining Work

Critical Remaining Work

Milestone

OCSD Candy Lane GMP Schedule Ver 1.0

Start Finish

Mob-1030 Temp Power to Trailer 3 25-Jun-26 29-Jun-26

Mob-1070 Mob to Site Trailer 2 30-Jun-26 01-Jul-26

Mob-1080 Temp Power For Building 5 28-Jul-26 03-Aug-26

Mob-1000 Temp Construction Fence (around the school) 5 30-Jul-26 05-Aug-26

Mob-1050 Erect Temp Stair Tower to Roof 3 30-Jul-26 03-Aug-26

Site WorkSite Work 218 28-Jul-26 07-Jun-27

Site-0100 Erosion Control 2 28-Jul-26 29-Jul-26

Site-0105 Remove Play Ground Equipment 10 30-Jul-26 12-Aug-26

Site-0120 Remove Trees 5 03-Aug-26 07-Aug-26

Site-1000 Grade / Excav. New Parent Loop Extension 15 10-Aug-26 28-Aug-26

Site-0110 Relocate Building Transformer 25 13-Aug-26 17-Sep-26

Site-0111 New Unground Primary Feeder Conduit 5 13-Aug-26 19-Aug-26

Site-0140 Demo Site Utilities 10 17-Aug-26 28-Aug-26

Site-0112 PGE Inspection & Approval of Primary Conduit 5 20-Aug-26 26-Aug-26

Site-0150 Build Rain Garden 15 24-Aug-26 14-Sep-26

Site-0113 Backfill Primary Conduit 5 27-Aug-26 02-Sep-26

Site-1030 New Drive Approach 10 27-Aug-26 10-Sep-26

Site-0130 New Storm Line w/ Catch Basins 12 31-Aug-26 16-Sep-26

Site-0114 CT Cabinet & Main Disconnect 7 01-Sep-26 10-Sep-26

Site-0160 New Sanitary & Water Lines 15 08-Sep-26 28-Sep-26

Site-0133 PGE Moves Transformer & Pulls Primary 5 11-Sep-26 17-Sep-26

Site-1010 Finish Grade Parent Loop & Parking Lot 10 11-Sep-26 24-Sep-26

Site-0180 New Fire Water Vault & Line 10 18-Sep-26 01-Oct-26

Site-1020 1st Lift of Pavement at Parent Loop/Parking lot 5 25-Sep-26 01-Oct-26

Site-1070 Build New Cover Walkway at Portables 60 29-Sep-26 23-Dec-26

Site-1040 Cut & Remove Pavement for Curbs in Parking Lot 5 15-Apr-27 21-Apr-27

Site-1050 Build Soft Play Area 25 22-Apr-27 26-May-27

Site-1060 F & P Curbs & Gutters 15 22-Apr-27 12-May-27

Site-1100 F/P Sidewalks 15 29-Apr-27 19-May-27

Site-0170 F/P New Curb & Patch Sidewalk at Front Loop 10 13-May-27 26-May-27

Site-1080 2nd Lift of Pavement at Parent Loop/Parking 5 20-May-27 26-May-27

Site-1110 Remove Half Street (Hull Ave) 5 20-May-27 26-May-27

Site-1090 Stripe Parent Loop/Parking 5 27-May-27 03-Jun-27

Site-1120 Pave Half Street (Hull Ave) 7 27-May-27 07-Jun-27

AbatementAbatement 45 24-Jun-26 26-Aug-26

Abate-1010 Abate & Soft Demo Sector A - Restroom & Hallway Flooring & Fittings 10 24-Jun-26 08-Jul-26

Abate-1080 Abate & Soft Demo Sector A - Pipe / Duct Fittings at Mech. Mezzanine 5 01-Jul-26 08-Jul-26

Abate-1040 Abate & Soft Demo Sector A - Cafeteria/Kitchen Fittings 5 09-Jul-26 15-Jul-26

Abate-1020 Abate & Soft Demo Sector C - Walls & Fixtures & F it tings 15 16-Jul-26 05-Aug-26

Abate-1000 Abate & Soft Demo Sector B - Flooring & Fittings in Classrooms & Hallway 15 06-Aug-26 26-Aug-26

Cafeteria / Kitchen AdditionCafeteria / Kitchen Addition 159 16-Oct-26 03-Jun-27

ExteriorExterior 104 16-Oct-26 17-Mar-27

Add-1190 Build Building Pad 3 16-Oct-26 20-Oct-26

Add-1200 Excavate Footings 5 21-Oct-26 27-Oct-26

Add-1210 F/R/P Footings 10 26-Oct-26 06-Nov-26

Add-1215 Under Slab Utilities 15 02-Nov-26 20-Nov-26

Add-1220 Grade, Rock & Vapor Barrier for SOG 10 09-Nov-26 20-Nov-26

Add-1230 F/R/P SOG 8 17-Nov-26 30-Nov-26

Add-1110 Frame Exterior & Interior Struct. Wood Stud Walls 10 01-Dec-26 14-Dec-26

Add-1120 Frame Separation Wall - Metal Studs 5 10-Dec-26 16-Dec-26

Add-1150 Set Roof Trusses & Framing 10 17-Dec-26 31-Dec-26

Add-1130 Exterior Sheathing 10 29-Dec-26 12-Jan-27

Add-1160 Roof Sheathing - Lower Roof 5 04-Jan-27 08-Jan-27

Add-1140 WRB at Exterior Walls 10 06-Jan-27 20-Jan-27

Add-1165 Roof Sheathing - High Roof - Car Decking 7 11-Jan-27 20-Jan-27

Add-1170 Frame Parapet Walls 5 11-Jan-27 15-Jan-27

Add-1270 Install Storefront Glazing System 10 14-Jan-27 28-Jan-27

Add-1180 Roofing Vapor Barrier - Temp Roof 5 21-Jan-27 27-Jan-27

Add-1050 Roofing 15 28-Jan-27 17-Feb-27

Add-1280 Masonry Veneer 20 29-Jan-27 25-Feb-27

Add-1100 Install Mechanical Rooftop Equip. 20 18-Feb-27 17-Mar-27

Add-1290 Metal Siding & Wall Cap 15 19-Feb-27 11-Mar-27

InteriorInterior 102 11-Jan-27 03-Jun-27

Add-1060 Interior Overhead Rough-Ins 20 11-Jan-27 08-Feb-27

Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep

2025 2026 2027

Temp Power to Trailer

Mob to Site Trailer

Temp Power For Building

Temp Construction Fence (around the school)

Erect Temp Stair Tower to Roof

Erosion Control

Remove Play Ground Equipment

Remove Trees

Grade / Excav. New Parent Loop Extension

Relocate Building Transformer

New Unground Primary Feeder Conduit

Demo Site Utilities

PGE Inspection & Approval of Primary Conduit

Build Rain Garden

Backfill Primary Conduit

New Drive Approach

New Storm Line w/ Catch Basins

CT Cabinet & Main Disconnect

New Sanitary & Water Lines

PGE Moves Transformer & Pulls Primary

Finish Grade Parent Loop & Parking Lot

New Fire Water Vault & Line

1st Lift of Pavement at Parent Loop/Parking lot

Build New Cover Walkway at Portables

Cut & Remove Pavement for Curbs in Parking Lot

Build Soft Play Area

F & P Curbs & Gutters

F/P Sidewalks

F/P New Curb & Patch Sidewalk at Front Loop

2nd Lift of Pavement at Parent Loop/Parking

Remove Half Street (Hull Ave)

Stripe Parent Loop/Parking

Pave Half Street (Hull Ave)

Abate & Soft Demo Sector A - Restroom & Hallway Flooring & Fittings

Abate & Soft Demo Sector A - Pipe / Duct Fittings at Mech. Mezzanine

Abate & Soft Demo Sector A - Cafeteria/Kitchen Fittings

Abate & Soft Demo Sector C - Walls & Fixtures & F it tings

Abate & Soft Demo Sector B - Flooring & Fittings in Classrooms & Hallway

Build Building Pad

Excavate Footings

F/R/P Footings

Under Slab Utilities

Grade, Rock & Vapor Barrier for SOG

F/R/P SOG

Frame Exterior & Interior Struct. Wood Stud Walls

Frame Separation Wall - Metal Studs

Set Roof Trusses & Framing

Exterior Sheathing

Roof Sheathing - Lower Roof

WRB at Exterior Walls

Roof Sheathing - High Roof - Car Decking

Frame Parapet Walls

Install Storefront Glazing System

Roofing Vapor Barrier - Temp Roof

Roofing

Masonry Veneer

Install Mechanical Rooftop Equip.

Metal Siding & Wall Cap

Interior Overhead Rough-Ins

OCSD Candy Lane GMP Schedule Ver 1.0 Howard S. Wright Construction 21-Apr-26 10:51

Remaining Level of Effort

Actual Level of Effort

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Start Finish

Add-1240 Frame Interior Partition Walls 6 11-Jan-27 19-Jan-27

Add-1260 Frame Soffits & Hard Lids 8 19-Jan-27 28-Jan-27

Add-1250 MEP Wall & Ceiling Rough-Ins 15 28-Jan-27 17-Feb-27

Add-1070 Interior Walls /Soffits/Ceilings 45 04-Feb-27 07-Apr-27

Add-1300 Rock, Tape & Finish Kitchen Walls & Ceilings 15 11-Feb-27 03-Mar-27

Add-1310 Rock, Tape & Finish Cafeteria Walls & Ceilings 15 19-Feb-27 11-Mar-27

Add-1330 Prime & Paint Kitchen Walls & Ceilings 7 04-Mar-27 12-Mar-27

Add-1500 Tile Restroom Walls 8 11-Mar-27 22-Mar-27

Add-1350 Prime / Paint Cafeteria Walls & Ceilings 7 12-Mar-27 22-Mar-27

Add-1320 Kitchen Overhead Doors 5 15-Mar-27 19-Mar-27

Add-1430 Walk-In Cooler 10 15-Mar-27 26-Mar-27

Add-1340 Kitchen Fluid Applied Flooring 8 22-Mar-27 31-Mar-27

Add-1390 Cafeteria Ceiling Grid 3 23-Mar-27 25-Mar-27

Add-1510 Restroom Sheet Vinyl Flooring 3 23-Mar-27 25-Mar-27

Add-1370 Cafeteria Light Fixture 5 26-Mar-27 01-Apr-27

Add-1410 Cafeteria Mech. Ceiling & Wall Trim 5 26-Mar-27 01-Apr-27

Add-1520 Restroom Plumbing Fixtures 3 26-Mar-27 30-Mar-27

Add-1380 Cafeteria Wall Graphics 10 29-Mar-27 09-Apr-27

Add-1530 Restroom MEP/F Finish Trim 3 31-Mar-27 02-Apr-27

Add-1460 Kitchen Ceiling Grid 5 01-Apr-27 07-Apr-27

Add-1400 Cafeteria Ceiling Tile 3 02-Apr-27 06-Apr-27

Add-1540 Restroom Accessories 3 05-Apr-27 07-Apr-27

Add-1470 Kitchen Mech, Elect & Fire Ceiling Trim 7 08-Apr-27 16-Apr-27

Add-1360 Polish Cafeteria Floor 6 12-Apr-27 19-Apr-27

Add-1480 Kitchen Ceiling Tile 5 19-Apr-27 23-Apr-27

Add-1420 Cafeteria Plumbing Fixtures 5 20-Apr-27 26-Apr-27

Add-1440 Seal Kitchen Concrete Floors 3 26-Apr-27 28-Apr-27

Add-1450 Kitchen Equipment & Wall Cover ings 20 29-Apr-27 26-May-27

Add-1490 Kitchen MEP Trim & Connections 10 20-May-27 03-Jun-27

Add-1550 Kitchen Doors & Hardware 5 27-May-27 03-Jun-27

Interior RemodelInterior Remodel 184 28-Jul-26 19-Apr-27

Demo WorkDemo Work 51 28-Jul-26 07-Oct-26

Sector ASector A 33 28-Jul-26 11-Sep-26

DemoA-1170 Safe Off MEP - Ceilings & Walls 3 28-Jul-26 30-Jul-26

DemoA-1010 Shore Library & Restroom Roof (Hallway Block Wall Demo) 2 31-Jul-26 03-Aug-26

DemoA-1080 Remove Wheelchair Lift 3 31-Jul-26 04-Aug-26

DemoA-1100 Remove Exterior Siding at Mechanical Mezzanine 3 31-Jul-26 04-Aug-26

DemoA-1020 Demo Hallway & Restroom Ceilings 5 04-Aug-26 10-Aug-26

DemoA-1105 Remove Library Sliding Doors 5 04-Aug-26 10-Aug-26

DemoA-1090 Remove Concrete Stairs - Gym Hallway 5 05-Aug-26 11-Aug-26

DemoA-1130 Remove Air Handler & Ductwork at Mechanical Mezzanne 5 05-Aug-26 11-Aug-26

DemoA-1030 Demo Cricket Section of Roof (Library Hallway) 5 06-Aug-26 12-Aug-26

DemoA-1110 Demo Kitchen Walls & Cabinets 5 11-Aug-26 17-Aug-26

DemoA-1150 Shore Restroom Roof for Block Removal 2 11-Aug-26 12-Aug-26

DemoA-1160 Remove (E) Water Lines 8 11-Aug-26 20-Aug-26

DemoA-1060 Remove AHU & Ductwork - Above Gym Hallway 7 12-Aug-26 20-Aug-26

DemoA-1040 Remove Block Walls & Doors - Library Hallway 4 13-Aug-26 18-Aug-26

DemoA-1135 Remove Wood Floor & Wall at Custodial Space 5 18-Aug-26 24-Aug-26

DemoA-1050 Remove Block Walls & Fixtures - Sector A Restroom 8 19-Aug-26 28-Aug-26

DemoA-1070 Remove Block Walls & Ceilings - Gym Hallway 5 21-Aug-26 27-Aug-26

DemoA-1120 Remove Block Walls - Family Resource 5 28-Aug-26 03-Sep-26

DemoA-1140 Remove Block Wall for New Exterior Gym Door 5 04-Sep-26 11-Sep-26

Sector BSector B 23 27-Aug-26 29-Sep-26

DemoB-1060 Safe Off MEP 3 27-Aug-26 31-Aug-26

DemoB-1020 Demo Hallway Ceiling 4 01-Sep-26 04-Sep-26

DemoB-1010 Remove (E) Water Lines 6 08-Sep-26 15-Sep-26

DemoB-1030 Remove (E) Unit Ventilators 5 16-Sep-26 22-Sep-26

DemoB-1040 Remove (E) Classroom Cabinets 10 16-Sep-26 29-Sep-26

Sector CSector C 48 31-Jul-26 07-Oct-26

DemoC-1050 Safe Off - MEP 3 31-Jul-26 04-Aug-26

DemoC-1030 Demo Ceilings 10 05-Aug-26 18-Aug-26

DemoC-1040 Clear Out Ceiling Space of MEP 15 12-Aug-26 01-Sep-26

DemoC-1020 Remove (E) Interior Walls & Cabinets 15 02-Sep-26 23-Sep-26

DemoC-1070 Demo Exterior Walls for Unit Ventilators 10 24-Sep-26 07-Oct-26

Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep

2025 2026 2027

Frame Interior Partition Walls

Frame Soffits & Hard Lids

MEP Wall & Ceiling Rough-Ins

Interior Walls /Soffits/Ceilings

Rock, Tape & Finish Kitchen Walls & Ceilings

Rock, Tape & Finish Cafeteria Walls & Ceilings

Prime & Paint Kitchen Walls & Ceilings

Tile Restroom Walls

Prime / Paint Cafeteria Walls & Ceilings

Kitchen Overhead Doors

Walk-In Cooler

Kitchen Fluid Applied Flooring

Cafeteria Ceiling Grid

Restroom Sheet Vinyl Flooring

Cafeteria Light Fixture

Cafeteria Mech. Ceiling & Wall Trim

Restroom Plumbing Fixtures

Cafeteria Wall Graphics

Restroom MEP/F Finish Trim

Kitchen Ceiling Grid

Cafeteria Ceiling Tile

Restroom Accessories

Kitchen Mech, Elect & Fire Ceiling Trim

Polish Cafeteria Floor

Kitchen Ceiling Tile

Cafeteria Plumbing Fixtures

Seal Kitchen Concrete Floors

Kitchen Equipment & Wall Cover ings

Kitchen MEP Trim & Connections

Kitchen Doors & Hardware

Safe Off MEP - Ceilings & Walls

Shore Library & Restroom Roof (Hallway Block Wall Demo)

Remove Wheelchair Lift

Remove Exterior Siding at Mechanical Mezzanine

Demo Hallway & Restroom Ceilings

Remove Library Sliding Doors

Remove Concrete Stairs - Gym Hallway

Remove Air Handler & Ductwork at Mechanical Mezzanne

Demo Cricket Section of Roof (Library Hallway)

Demo Kitchen Walls & Cabinets

Shore Restroom Roof for Block Removal

Remove (E) Water Lines

Remove AHU & Ductwork - Above Gym Hallway

Remove Block Walls & Doors - Library Hallway

Remove Wood Floor & Wall at Custodial Space

Remove Block Walls & Fixtures - Sector A Restroom

Remove Block Walls & Ceilings - Gym Hallway

Remove Block Walls - Family Resource

Remove Block Wall for New Exterior Gym Door

Safe Off MEP

Demo Hallway Ceiling

Remove (E) Water Lines

Remove (E) Unit Ventilators

Remove (E) Classroom Cabinets

Safe Off - MEP

Demo Ceilings

Clear Out Ceiling Space of MEP

Remove (E) Interior Walls & Cabinets

Demo Exterior Walls for Unit Ventilators

OCSD Candy Lane GMP Schedule Ver 1.0 Howard S. Wright Construction 21-Apr-26 10:51

Remaining Level of Effort

Actual Level of Effort

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Start Finish

Sector A - Remodel WorkSector A - Remodel Work 162 19-Aug-26 09-Apr-27

NewA-1010 Saw Cut for New Plumbing 3 19-Aug-26 21-Aug-26

NewA-1030 Underslab Plumbing 6 24-Aug-26 31-Aug-26

NewA-1220 Structural Supports to Gym Roof (PV Array) 10 24-Aug-26 04-Sep-26

NewA-1020 Frame New Walls, Soffits & Hard Lids 25 01-Sep-26 06-Oct-26

NewA-1050 Concrete at Plumbing Trenches 3 01-Sep-26 03-Sep-26

NewA-1060 First Polish of Concrete Floors 8 04-Sep-26 16-Sep-26

NewA-1240 New Exterior Gym Door & Hardware 10 14-Sep-26 25-Sep-26

NewA-1070 Over Head Rough-Ins 20 16-Sep-26 13-Oct-26

NewA-1040 Wall Rough-Ins 20 18-Sep-26 15-Oct-26

NewA-1090 Re-Lights & Door Frames 8 07-Oct-26 16-Oct-26

NewA-1250 F/R/P New Concrete Ramp 10 14-Oct-26 27-Oct-26

NewA-1080 Rock, Tape & Finish Walls & Hard Lids 30 19-Oct-26 01-Dec-26

NewA-1260 Set New Electrical Gear (800amps) 10 13-Nov-26 30-Nov-26

NewA-1100 Prime & 1st Coat Paint 10 02-Dec-26 15-Dec-26

NewA-1110 Ceiling Grid 10 16-Dec-26 30-Dec-26

NewA-1120 Ceiling MEPF Trim 20 24-Dec-26 25-Jan-27

NewA-1130 Casework 12 11-Jan-27 27-Jan-27

NewA-1150 Carpet & VCT 12 26-Jan-27 10-Feb-27

NewA-1140 Ceiling Tile 10 11-Feb-27 24-Feb-27

NewA-1170 Finish Coat of Paint 10 18-Feb-27 03-Mar-27

NewA-1180 Finish Polish of Floors & Seal 5 25-Feb-27 03-Mar-27

NewA-1160 Restroom Partitions 5 04-Mar-27 10-Mar-27

NewA-1200 MEPF Finish Trim 15 04-Mar-27 24-Mar-27

NewA-1190 Plumbing Fixtures at Restroom 5 11-Mar-27 17-Mar-27

NewA-1210 Doors & Hardware 7 18-Mar-27 26-Mar-27

NewA-1230 Final Clean 10 29-Mar-27 09-Apr-27

Library AreaLibrary Area 166 18-Aug-26 14-Apr-27

Libr-1010 MEPF Overhead Rough-Ins 20 18-Aug-26 15-Sep-26

Libr-1020 Frame New Walls & Soffits 10 16-Sep-26 29-Sep-26

Libr-1030 Wall Rough-Ins 10 30-Sep-26 13-Oct-26

Libr-1040 Rock, Tape & Finish Walls & Soffits 15 14-Oct-26 03-Nov-26

Libr-1060 Prime & 1st Coat Paint - Walls, Soffits & Ceiling 10 04-Nov-26 17-Nov-26

Libr-1050 Casework 10 18-Nov-26 03-Dec-26

Libr-1070 Flooring 15 04-Dec-26 24-Dec-26

Libr-1080 Finish Coat Paint 5 28-Dec-26 04-Jan-27

Libr-1090 Doors & Hardware 3 18-Mar-27 22-Mar-27

Libr-1100 MEPF Trim 10 25-Mar-27 07-Apr-27

Libr-1110 Final Clean 5 08-Apr-27 14-Apr-27

Sector B - Remodel WorkSector B - Remodel Work 88 27-Aug-26 04-Jan-27

NewB-1090 Rough Polish of Floors 15 27-Aug-26 17-Sep-26

NewB-1020 New Water Line in Hallway Ceiling (Overhead) 10 16-Sep-26 29-Sep-26

NewB-1010 Saw Cut Slab 2 18-Sep-26 21-Sep-26

NewB-1030 Underslab Plumbing 5 22-Sep-26 28-Sep-26

NewB-1040 Fire Sprinklers 15 23-Sep-26 13-Oct-26

NewB-1060 Roof Support Members for Rooftop Units 10 29-Sep-26 12-Oct-26

NewB-1080 Pour Back Plumbing Trenches 5 29-Sep-26 05-Oct-26

NewB-1070 New Exhaust / Ventilation 15 30-Sep-26 20-Oct-26

NewB-1100 New Classroom Casework 15 21-Oct-26 10-Nov-26

NewB-1050 Install Unit Ventilators & Line Sets 10 30-Oct-26 12-Nov-26

NewB-1110 Plumbing Fixture 10 11-Nov-26 24-Nov-26

NewB-1140 Teaching Walls 10 11-Nov-26 24-Nov-26

NewB-1120 Finish Polish of Floors 15 25-Nov-26 17-Dec-26

NewB-1130 Final Clean 10 18-Dec-26 04-Jan-27

Sector C - Remodel WorkSector C - Remodel Work 151 14-Sep-26 19-Apr-27

NewC-1065 Polish Floors - Rough Pass 15 14-Sep-26 02-Oct-26

NewC-1100 Spray Foam & Seal Perimiter Walls 10 24-Sep-26 07-Oct-26

NewC-1010 Layout New Walls 5 08-Oct-26 14-Oct-26

NewC-1020 Saw Cut Slab for Plumbing 7 13-Oct-26 21-Oct-26

NewC-1030 Frame New Walls 10 15-Oct-26 28-Oct-26

NewC-1040 Overhead Rough-Ins (MEPF) 25 15-Oct-26 18-Nov-26

NewC-1050 Underslab Plumbing 10 20-Oct-26 02-Nov-26

NewC-1110 Set HM Frames 5 20-Oct-26 26-Oct-26

NewC-1025 Saw Cut & Excav. Sabs for Shear Wall Footings 10 22-Oct-26 04-Nov-26

Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep

2025 2026 2027

Saw Cut for New Plumbing

Underslab Plumbing

Structural Supports to Gym Roof (PV Array)

Frame New Walls, Soffits & Hard Lids

Concrete at Plumbing Trenches

First Polish of Concrete Floors

New Exterior Gym Door & Hardware

Over Head Rough-Ins

Wall Rough-Ins

Re-Lights & Door Frames

F/R/P New Concrete Ramp

Rock, Tape & Finish Walls & Hard Lids

Set New Electrical Gear (800amps)

Prime & 1st Coat Paint

Ceiling Grid

Ceiling MEPF Trim

Casework

Carpet & VCT

Ceiling Tile

Finish Coat of Paint

Finish Polish of Floors & Seal

Restroom Partitions

MEPF Finish Trim

Plumbing Fixtures at Restroom

Doors & Hardware

Final Clean

MEPF Overhead Rough-Ins

Frame New Walls & Soffits

Wall Rough-Ins

Rock, Tape & Finish Walls & Soffits

Prime & 1st Coat Paint - Walls, Soffits & Ceiling

Casework

Flooring

Finish Coat Paint

Doors & Hardware

MEPF Trim

Final Clean

Rough Polish of Floors

New Water Line in Hallway Ceiling (Overhead)

Saw Cut Slab

Underslab Plumbing

Fire Sprinklers

Roof Support Members for Rooftop Units

Pour Back Plumbing Trenches

New Exhaust / Ventilation

New Classroom Casework

Install Unit Ventilators & Line Sets

Plumbing Fixture

Teaching Walls

Finish Polish of Floors

Final Clean

Polish Floors - Rough Pass

Spray Foam & Seal Perimiter Walls

Layout New Walls

Saw Cut Slab for Plumbing

Frame New Walls

Overhead Rough-Ins (MEPF)

Underslab Plumbing

Set HM Frames

Saw Cut & Excav. Sabs for Shear Wall Footings

OCSD Candy Lane GMP Schedule Ver 1.0 Howard S. Wright Construction 21-Apr-26 10:51

Remaining Level of Effort

Actual Level of Effort

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Start Finish

NewC-1070 Frame Hard Lids 5 29-Oct-26 04-Nov-26

NewC-1080 Wall & Hard Lids Rough-Ins (MEPF) 25 29-Oct-26 04-Dec-26

NewC-1060 Place Plumbing Trench Concrete 3 03-Nov-26 05-Nov-26

NewC-1035 New Shear Wall Footings 10 05-Nov-26 18-Nov-26

NewC-1045 Build Shear Walls 7 12-Nov-26 20-Nov-26

NewC-1055 Wall Rough-Ins at Shear Walls 7 20-Nov-26 02-Dec-26

NewC-1090 Rock, Tape & Finish Walls & Hard Lids 30 30-Nov-26 12-Jan-27

NewC-1120 Prime & 1st Coat Paint 15 04-Jan-27 25-Jan-27

NewC-1130 Ceiling Grid 20 11-Jan-27 08-Feb-27

NewC-1150 Ceiling Grid MEPF Fixtures & Trim 20 19-Jan-27 15-Feb-27

NewC-1220 Toilet Partitions 5 19-Jan-27 25-Jan-27

NewC-1140 Casework 20 21-Jan-27 17-Feb-27

NewC-1170 Set New Unit Ventilators 10 26-Jan-27 08-Feb-27

NewC-1160 Drop Ceiling Tile 25 04-Feb-27 10-Mar-27

NewC-1260 Teaching Walls 15 18-Feb-27 10-Mar-27

NewC-1180 Paint Finish Coat 16 22-Feb-27 15-Mar-27

NewC-1190 Carpet in Classrooms 20 01-Mar-27 26-Mar-27

NewC-1240 Floor Polish Final Pass 7 11-Mar-27 19-Mar-27

NewC-1230 Set Plumbing Fixtures 8 16-Mar-27 25-Mar-27

NewC-1250 MEPF Finish Trim 15 16-Mar-27 05-Apr-27

NewC-1200 Doors & Hardware 10 17-Mar-27 30-Mar-27

NewC-1210 Final Clean - Sector C 10 06-Apr-27 19-Apr-27

RoofRoof 99 04-Aug-26 23-Dec-26

Sector A - RoofSector A - Roof 75 06-Aug-26 19-Nov-26

RoofA-1020 Demo Cricket Section of Roof Structure 5 06-Aug-26 12-Aug-26

RoofA-1030 Re-Build Roof Structure 3 08-Sep-26 10-Sep-26

RoofA-1010 Remove Old Roof 10 09-Sep-26 22-Sep-26

RoofA-1040 New Roof 15 01-Oct-26 21-Oct-26

RoofA-1050 Complete New Roof at New Roof Structure 6 22-Oct-26 29-Oct-26

RoofA-1060 New Rooftop Equipment 15 30-Oct-26 19-Nov-26

Sector B - RoofSector B - Roof 72 25-Aug-26 07-Dec-26

RoofB-1010 Demo Old Roof 10 25-Aug-26 08-Sep-26

RoofB-1020 New Roof 20 02-Sep-26 30-Sep-26

RoofB-1070 New Rooftop Units 10 20-Nov-26 07-Dec-26

Sector C - RoofSector C - Roof 99 04-Aug-26 23-Dec-26

RoofC-1030 Remove Existing Rooftop Unit & Structure 8 04-Aug-26 13-Aug-26

RoofC-1010 Demo Old Roof 7 14-Aug-26 24-Aug-26

RoofC-1020 New Roof 10 19-Aug-26 01-Sep-26

RoofC-1040 New Rooftop Equipment 12 08-Dec-26 23-Dec-26

PunchlistPunchlist 128 05-Jan-27 06-Jul-27

Pun-1040 Punch Classrooms - Sector B 10 05-Jan-27 19-Jan-27

Pun-1000 Punch Restrooms - Sector A 10 12-Apr-27 23-Apr-27

Pun-1090 Punch Sector A 10 12-Apr-27 23-Apr-27

Pun-1010 Punch Library Space 10 15-Apr-27 28-Apr-27

Pun-1030 Punch Restrooms - Sector C 10 20-Apr-27 03-May-27

Pun-1050 Punch Classrooms - Sector C 10 20-Apr-27 03-May-27

Pun-1070 Punch New Parent Loop / Parking Lot 5 04-Jun-27 10-Jun-27

Pun-1080 Punch Exterior / Site 5 04-Jun-27 10-Jun-27

Pun-1060 Punch Kitchen 10 22-Jun-27 06-Jul-27

Commissioning / Start-UpCommissioning / Start-Up 128 05-Jan-27 06-Jul-27

CXB-1190 Start-Up/Commissioning Mechanical Equipment - Sector B 10 05-Jan-27 19-Jan-27

CXA-1200 Start-Up/Commissioning Mechanical Equipment - Sector A 10 15-Apr-27 28-Apr-27

CXC-1020 Start-Up/Commissioning Mechanical Equipment - Sector C 10 20-Apr-27 03-May-27

CXA-1010 Start-Up/Commissioning Mechanical Equipment - Cafeteria 5 29-Apr-27 05-May-27

CXA-1000 Start-Up of Kitchen Equipment 15 04-Jun-27 24-Jun-27

CXA-1030 Commission Kitchen Equipment 10 22-Jun-27 06-Jul-27

Finial InspectionsFinial Inspections 46 04-May-27 08-Jul-27

A1060 Finial Inspections (FLS) - Sector C 5 04-May-27 10-May-27

A1040 Final Inspections of Kitchen FLS 5 01-Jul-27 08-Jul-27

Project CloseoutProject Closeout 10 09-Jul-27 22-Jul-27

A1140 Inclement Weather Delay 10 09-Jul-27 22-Jul-27

A1050 Substantial Completion 0 22-Jul-27

Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep

2025 2026 2027

Frame Hard Lids

Wall & Hard Lids Rough-Ins (MEPF)

Place Plumbing Trench Concrete

New Shear Wall Footings

Build Shear Walls

Wall Rough-Ins at Shear Walls

Rock, Tape & Finish Walls & Hard Lids

Prime & 1st Coat Paint

Ceiling Grid

Ceiling Grid MEPF Fixtures & Trim

Toilet Partitions

Casework

Set New Unit Ventilators

Drop Ceiling Tile

Teaching Walls

Paint Finish Coat

Carpet in Classrooms

Floor Polish Final Pass

Set Plumbing Fixtures

MEPF Finish Trim

Doors & Hardware

Final Clean - Sector C

Demo Cricket Section of Roof Structure

Re-Build Roof Structure

Remove Old Roof

New Roof

Complete New Roof at New Roof Structure

New Rooftop Equipment

Demo Old Roof

New Roof

New Rooftop Units

Remove Existing Rooftop Unit & Structure

Demo Old Roof

New Roof

New Rooftop Equipment

Punch Classrooms - Sector B

Punch Restrooms - Sector A

Punch Sector A

Punch Library Space

Punch Restrooms - Sector C

Punch Classrooms - Sector C

Punch New Parent Loop / Parking Lot

Punch Exterior / Site

Punch Kitchen

Start-Up/Commissioning Mechanical Equipment - Sector B

Start-Up/Commissioning Mechanical Equipment - Sector A

Start-Up/Commissioning Mechanical Equipment - Sector C

Start-Up/Commissioning Mechanical Equipment - Cafeteria

Start-Up of Kitchen Equipment

Commission Kitchen Equipment

Finial Inspections (FLS) - Sector C

Final Inspections of Kitchen FLS

Inclement Weather Delay

Substantial Completion

OCSD Candy Lane GMP Schedule Ver 1.0 Howard S. Wright Construction 21-Apr-26 10:51

Remaining Level of Effort

Actual Level of Effort

Actual Work

Remaining Work

Critical Remaining Work

Milestone

File details come from the government source that posted it. Updated .