This is a GMP Contract Schedule for Oregon City School District No. 62 (OCSD) CTE (Career and Technical Education) projects, prepared by Howard S. Wright Construction. The schedule outlines a comprehensive renovation and construction program spanning from November 17, 2025, through September 8, 2026, encompassing four primary CTE instructional areas: Intro to Digital Media, JROTC, Intro to Robotics, and Intro to Trades. The project progresses through multiple phases including design development (100% DD by November 17, 2025), construction documents (50% CD by December 15, 2025, and 100% CD by January 30, 2026), permitting (February 2 through May 1, 2026), GMP presentation to the School Board on April 13, 2026, and building permit issuance by May 1, 2026. Construction activities commence in mid-June 2026 following the end of the 2025-2026 school year (June 10, 2026), with individual program construction starting dates staggered between June 19 and July 1, 2026. All four instructional programs are scheduled to achieve substantial completion on August 26, 2026, allowing for district move-in between August 27 and September 4, 2026, and the first day of school for 2026-2027 on September 8, 2026.
The schedule provides detailed task-level activities for each program, including demolition, framing, mechanical/electrical/plumbing work, finishes, and architect punch list corrections, with durations ranging from two to eight days per task. Critical milestones include Spring Break (March 23-27, 2026), teacher return date (August 24, 2026), and completion of punch list activities by August 26, 2026. The schedule reflects a coordinated effort to minimize disruption to the school district's academic calendar while delivering four contemporaneous construction projects. Procurement activities occur from February 2 through March 20, 2026, including bid package assembly and GMP interviews. This schedule version 1.0 was prepared by Howard S. Wright Construction on March 24, 2026, at 15:05.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Activity ID Activity Name Original
Duration
Start Finish
OCSD - CTE GMP Contract Schedule Ver 1.0OCSD - CTE GMP Contract Schedule Ver 1.0 202 17-Nov-25 08-Sep-26
MilestonesMilestones 202 17-Nov-25 08-Sep-26
Mile-0210 100% DD'd 0 17-Nov-25*
Mile-0230 50% CD's 0 15-Dec-25*
Mile-0240 100% CD's 0 30-Jan-26*
Mile-0170 Spring Break 5 23-Mar-26* 27-Mar-26
PROC-1030 GMP Presented to the School Board 0 13-Apr-26*
Mile-0250 Building Permit Issued 0 01-May-26
Mile-0160 Last Day of School Year '25-'26 0 10-Jun-26*
Mile-0180 District Move Out 2 11-Jun-26 12-Jun-26
Mile-0260 Demo Start 0 15-Jun-26
Mile-0270 Start of Construction - Intro to Robotics 0 19-Jun-26
Mile-0280 Start of Construction - JROTC 0 22-Jun-26
Mile-0290 Start of Construction - Intro to Trades 0 30-Jun-26
Mile-4020 Start of Construction - Intro to Digital Media 0 01-Jul-26
Mile-0200 Teachers Back in School for '26 - '27 0 24-Aug-26
Mile-4000 Intro to Digital Media Substantial Completetion 0 26-Aug-26
Mile-4010 JROTC Substantial Completetion 0 26-Aug-26
Mile-4030 Intro to Robotics Substantial Completetion 0 26-Aug-26
Mile-4050 Intro to Trades Substantial Completetion 0 26-Aug-26
Mile-0220 District Move In for School '26-'27 7 27-Aug-26 04-Sep-26
Mile-0190 First Day of School '26 - '27 0 08-Sep-26*
PermittingPermitting 65 02-Feb-26 01-May-26
Perm-1000 Permitting Process 65 02-Feb-26 01-May-26
Summary ScheduleSummary Schedule 52 15-Jun-26 26-Aug-26
Sum-1020 Digital Media 52 15-Jun-26 26-Aug-26
Sum-1030 JROTC 52 15-Jun-26 26-Aug-26
Sum-1040 Intro to Robotics 52 15-Jun-26 26-Aug-26
Sum-1050 Intro to Trades 49 18-Jun-26 26-Aug-26
ProcurementProcurement 35 02-Feb-26 20-Mar-26
PROC-1000 Bid Building Package (100%CD's) 25 02-Feb-26 06-Mar-26
PROC-1010 Interview & Assemble GMP 10 09-Mar-26 20-Mar-26
PROC-1020 Present GMP 0 20-Mar-26
ConstructionConstruction 52 12-Jun-26 26-Aug-26
RemodelRemodel 52 12-Jun-26 26-Aug-26
Intro to Digital MediaIntro to Digital Media 52 15-Jun-26 26-Aug-26
IDM-0100 Safe Off & Demo Power & Water 3 15-Jun-26 17-Jun-26
IDM-0110 Demo Ceilings, Casework, Flrs & Walls 4 15-Jun-26 18-Jun-26
IDM-0130 Demo Lockers & Wall in Commons 4 18-Jun-26 23-Jun-26
IDM-0120 Demo Ductwork 2 19-Jun-26 22-Jun-26
IDM-0280 Re-Frame Common Area Walls 3 23-Jun-26 25-Jun-26
IDM-0140 New Ductwork & Lighting/Power Overhead 6 23-Jun-26 30-Jun-26
IDM-0150 Frame New Walls & HM Frames 5 25-Jun-26 01-Jul-26
IDM-0290 Wall Rough-Ins at Common Area 4 26-Jun-26 01-Jul-26
IDM-0160 Set New HM Frames 2 30-Jun-26 01-Jul-26
IDM-0220 Ceiling Framing 6 30-Jun-26 08-Jul-26
IDM-0170 Fire Sprinkler Mods 4 01-Jul-26 07-Jul-26
IDM-0260 Wall Rough-ins 5 01-Jul-26 08-Jul-26
IDM-0300 Rock, Tape & Finish Common Area 6 02-Jul-26 10-Jul-26
IDM-0180 Rock, Tape & Finish Walls 6 09-Jul-26 16-Jul-26
IDM-0310 Paint Common Area 4 13-Jul-26 16-Jul-26
IDM-0230 Rock & Tape Ceilings 5 14-Jul-26 20-Jul-26
IDM-0320 Display Case in Common Area 5 17-Jul-26 23-Jul-26
IDM-0190 Paint 6 20-Jul-26 27-Jul-26
IDM-0200 Casework 6 22-Jul-26 29-Jul-26
IDM-0330 Wall Treatment in Common Area 8 24-Jul-26 04-Aug-26
IDM-0240 Flooring (Sheet Goods) 7 29-Jul-26 06-Aug-26
IDM-0210 Wall Treatments 7 04-Aug-26 12-Aug-26
IDM-0340 Monitor at Common Area 2 05-Aug-26 06-Aug-26
IDM-0250 Doors, Hardware & Glazing 3 07-Aug-26 11-Aug-26
IDM-0270 Final Clean 3 12-Aug-26 14-Aug-26
IDM-3000 Architect Punchlist 2 17-Aug-26 18-Aug-26
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
100% DD'd
50% CD's
100% CD's
Spring Break
GMP Presented to the School Board
Building Permit Issued
Last Day of School Year '25-'26
District Move Out
Demo Start
Start of Construction - Intro to Robotics
Start of Construction - JROTC
Start of Construction - Intro to Trades
Start of Construction - Intro to Digital Media
Teachers Back in School for '26 - '27
Intro to Digital Media Substantial Completetion
JROTC Substantial Completetion
Intro to Robotics Substantial Completetion
Intro to Trades Substantial Completetion
District Move In for School '26-'27
First Day of School '26 - '27
Permitting Process
Digital Media
JROTC
Intro to Robotics
Intro to Trades
Bid Building Package (100%CD's)
Interview & Assemble GMP
Present GMP
Safe Off & Demo Power & Water
Demo Ceilings, Casework, Flrs & Walls
Demo Lockers & Wall in Commons
Demo Ductwork
Re-Frame Common Area Walls
New Ductwork & Lighting/Power Overhead
Frame New Walls & HM Frames
Wall Rough-Ins at Common Area
Set New HM Frames
Ceiling Framing
Fire Sprinkler Mods
Wall Rough-ins
Rock, Tape & Finish Common Area
Rock, Tape & Finish Walls
Paint Common Area
Rock & Tape Ceilings
Display Case in Common Area
Paint
Casework
Wall Treatment in Common Area
Flooring (Sheet Goods)
Wall Treatments
Monitor at Common Area
Doors, Hardware & Glazing
Final Clean
Architect Punchlist
OCSD - CTE GMP Contract Schedule Ver 1.0 Howard S. Wright Construction 24-Mar-26 15:05
Remaining Level of Effort
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
OCSD - CTE GMP Contract Schedule Ver 1.0
Start Finish
IDM-3010 Punchlist Corrections 6 19-Aug-26 26-Aug-26
IDM-4000 Intro to Digital Media Substantial Completetion 0 26-Aug-26
JROTCJROTC 52 12-Jun-26 26-Aug-26
JROTC-0100 Safe Off & Demo Power & Water 3 12-Jun-26 16-Jun-26
JROTC-0120 Demo Ceiling Tiles, Casework, Flrs & Walls 4 15-Jun-26 18-Jun-26
JROTC-0130 Demo Ductwork & Lighting 2 18-Jun-26 20-Jun-26
JROTC-0140 Demo Lockers & Wall in Commons 3 18-Jun-26 22-Jun-26
JROTC-0150 New Ductwork & Lighting/Power Overhead 5 20-Jun-26 26-Jun-26
JROTC-0250 Re-Frame Common Area Walls 3 22-Jun-26 25-Jun-26
JROTC-0160 Frame New Walls & HM Frames 4 25-Jun-26 30-Jun-26
JROTC-0290 Wall Rough-Ins at Common area 4 25-Jun-26 30-Jun-26
JROTC-0190 Fire Sprinkler Mods 3 29-Jun-26 01-Jul-26
JROTC-0170 Wall Rough-Ins 4 30-Jun-26 06-Jul-26
JROTC-0300 Rock, Tape & Finish Common Area 5 01-Jul-26 08-Jul-26
JROTC-0180 Rock, Tape & Finish Walls 6 07-Jul-26 14-Jul-26
JROTC-0310 Paint Common Area 5 09-Jul-26 15-Jul-26
JROTC-0200 Ceilings / Grills & Lights 6 14-Jul-26 21-Jul-26
JROTC-0210 Paint 6 15-Jul-26 22-Jul-26
JROTC-0320 Display Case 5 16-Jul-26 22-Jul-26
JROTC-0230 Chain Link Fence 4 20-Jul-26 23-Jul-26
JROTC-0330 Wall Treatment in Common Area 7 22-Jul-26 30-Jul-26
JROTC-0220 Casework 4 24-Jul-26 29-Jul-26
JROTC-0240 Clean & Polish Floors 5 29-Jul-26 04-Aug-26
JROTC-0340 Monitor in Common Area 2 31-Jul-26 03-Aug-26
JROTC-0260 Wall Treatments 4 04-Aug-26 08-Aug-26
JROTC-0270 Doors, Hardware & Glazing 5 08-Aug-26 14-Aug-26
JROTC-0280 Final Clean 3 13-Aug-26 17-Aug-26
JROTC-3000 Architect Punch JROTC 2 18-Aug-26 19-Aug-26
JROTC-3010 Completion of Punch List Activities 5 20-Aug-26 26-Aug-26
JROTC-4000 JROTC Substantial Completetion 0 26-Aug-26
Intro to RoboticsIntro to Robotics 52 15-Jun-26 26-Aug-26
IR-0100 Safe Off & Demo Power & Water 3 15-Jun-26 17-Jun-26
IR-0110 Demo Ceiling Tiles, Casework, Flrs & Walls 4 15-Jun-26 18-Jun-26
IR-0120 Demo Ductwork 3 19-Jun-26 23-Jun-26
IR-0130 Demo Lockers & Wall in Commons 3 19-Jun-26 23-Jun-26
IR-0140 New Ductwork & Lighting/Power Overhead 6 19-Jun-26 26-Jun-26
IR-0150 Frame Walls & HM Frames 3 24-Jun-26 26-Jun-26
IR-0260 Re-Frame Walls in Common Area 3 24-Jun-26 26-Jun-26
IR-0160 Fire Sprinkler Mods 3 26-Jun-26 30-Jun-26
IR-0170 Wall Rough-Ins 4 29-Jun-26 02-Jul-26
IR-0270 Wall Rough-Ins at Common Area 3 29-Jun-26 01-Jul-26
IR-0280 Rock, Tape & Finish Common Area 5 02-Jul-26 09-Jul-26
IR-0180 Rock, Tape & Finish Walls 6 06-Jul-26 13-Jul-26
IR-0290 Paint Common Area 4 10-Jul-26 15-Jul-26
IR-0200 Paint 4 14-Jul-26 17-Jul-26
IR-0300 Display Case Common Area 3 15-Jul-26 17-Jul-26
IR-0310 Wall Treatment in Common Area 7 15-Jul-26 23-Jul-26
IR-0190 Ceilings / Grills & Lights 6 16-Jul-26 23-Jul-26
IR-0210 Casework 8 20-Jul-26 29-Jul-26
IR-0320 Monitor in Common Area 2 24-Jul-26 27-Jul-26
IR-0220 Rubber Flooring 5 30-Jul-26 05-Aug-26
IR-0330 Start-Up & Commission New TU 5 30-Jul-26 05-Aug-26
IR-0230 Wall Treatments 5 06-Aug-26 12-Aug-26
IR-0240 Doors, Hardware & Glazing 4 06-Aug-26 11-Aug-26
IR-0250 Final Clean 3 13-Aug-26 17-Aug-26
IR-3000 Architect's Punchlist for Intro to Robotics 2 18-Aug-26 19-Aug-26
IR-3010 Completion of Punchlist Activities 5 20-Aug-26 26-Aug-26
IR-4000 Intro to Robotics Substantial Completetion 0 26-Aug-26
Intro to TradesIntro to Trades 49 18-Jun-26 26-Aug-26
ITT-0100 Safe Off Power & Water 3 18-Jun-26 22-Jun-26
ITT-0110 Demo Walls 5 23-Jun-26 29-Jun-26
ITT-0120 Frame New Plumbing Wall 3 30-Jun-26 02-Jul-26
ITT-0130 Rough-In Plumbing & Elect 6 06-Jul-26 13-Jul-26
ITT-0140 Rock, Tape & Finish Wall 7 13-Jul-26 21-Jul-26
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
Punchlist Corrections
Intro to Digital Media Substantial Completetion
Safe Off & Demo Power & Water
Demo Ceiling Tiles, Casework, Flrs & Walls
Demo Ductwork & Lighting
Demo Lockers & Wall in Commons
New Ductwork & Lighting/Power Overhead
Re-Frame Common Area Walls
Frame New Walls & HM Frames
Wall Rough-Ins at Common area
Fire Sprinkler Mods
Wall Rough-Ins
Rock, Tape & Finish Common Area
Rock, Tape & Finish Walls
Paint Common Area
Ceilings / Grills & Lights
Paint
Display Case
Chain Link Fence
Wall Treatment in Common Area
Casework
Clean & Polish Floors
Monitor in Common Area
Wall Treatments
Doors, Hardware & Glazing
Final Clean
Architect Punch JROTC
Completion of Punch List Activities
JROTC Substantial Completetion
Safe Off & Demo Power & Water
Demo Ceiling Tiles, Casework, Flrs & Walls
Demo Ductwork
Demo Lockers & Wall in Commons
New Ductwork & Lighting/Power Overhead
Frame Walls & HM Frames
Re-Frame Walls in Common Area
Fire Sprinkler Mods
Wall Rough-Ins
Wall Rough-Ins at Common Area
Rock, Tape & Finish Common Area
Rock, Tape & Finish Walls
Paint Common Area
Paint
Display Case Common Area
Wall Treatment in Common Area
Ceilings / Grills & Lights
Casework
Monitor in Common Area
Rubber Flooring
Start-Up & Commission New TU
Wall Treatments
Doors, Hardware & Glazing
Final Clean
Architect's Punchlist for Intro to Robotics
Completion of Punchlist Activities
Intro to Robotics Substantial Completetion
Safe Off Power & Water
Demo Walls
Frame New Plumbing Wall
Rough-In Plumbing & Elect
Rock, Tape & Finish Wall
OCSD - CTE GMP Contract Schedule Ver 1.0 Howard S. Wright Construction 24-Mar-26 15:05
Remaining Level of Effort
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Start Finish
ITT-0150 Wall Finishes (Paint & FRP) 6 22-Jul-26 29-Jul-26
ITT-0180 Clean & Seal Floor 4 30-Jul-26 04-Aug-26
ITT-0160 Install Plumbing Fixtures 4 05-Aug-26 10-Aug-26
ITT-0170 Casework 6 05-Aug-26 12-Aug-26
ITT-0190 Final Clean 3 13-Aug-26 17-Aug-26
ITT-3000 Architect's Punchlist for Intro to Trades 2 18-Aug-26 19-Aug-26
ITT-3010 Completion of Punchlist Activities 5 20-Aug-26 26-Aug-26
ITT-4000 Substantial Completetion of Intro to Trades 0 26-Aug-26
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
Wall Finishes (Paint & FRP)
Clean & Seal Floor
Install Plumbing Fixtures
Casework
Final Clean
Architect's Punchlist for Intro to Trades
Completion of Punchlist Activities
Substantial Completetion of Intro to Trades
OCSD - CTE GMP Contract Schedule Ver 1.0 Howard S. Wright Construction 24-Mar-26 15:05
Remaining Level of Effort
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone