This is MIL-HDBK-423, a military handbook providing design guidance and examples of good practice for implementing high-altitude electromagnetic pulse (HEMP) hardening and testing requirements. Published May 15, 1993, the handbook is approved for use by all Department of Defense departments and agencies and reflects the requirements of MIL-STD-188-125 (HEMP Protection for Ground-Based C4I Facilities).
The handbook covers comprehensive HEMP protection implementation across multiple domains: the HEMP environment and system response characteristics; low-risk hardening approaches using electromagnetic barriers; barrier topology development; HEMP shield design and construction including material selection, welding techniques, and seam construction methods; architectural, mechanical, structural, and electrical points-of-entry (POEs) and their protective treatments; grounding and bonding requirements; special protective measures for equipment outside or incompatible with the primary barrier; corrosion control strategies; and testing methodologies including quality assurance, acceptance, and hardness verification testing. The handbook provides detailed guidance on electronic surge arresters, electrical filters, power apparatus for isolation, optical isolation devices, waveguides-below-cutoff, shielded doors, and penetration protection devices. Additionally, it addresses reliability and maintainability, testability design, safety and human engineering considerations, configuration management, hardness maintenance and surveillance (HM/HS) program development, and program management across the facility life cycle. Appendix A contains sample construction specifications for HEMP protection subsystems; Appendix B provides cost data for HEMP protection programs; and Appendix C lists applicable data item descriptions for contract documentation.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| HEMP Q and A.pdf | ||
| CDRL Listing Ex A.pdf | ||
| Att 4 PWS Feb 2026.pdf | ||
| Solicitation Amendment - FA460026R00020002.pdf | ||
| Site Visit Sign In Sheet.pdf | ||
| FA460026R00020001.pdf | ||
| FA460026R0002.pdf | ||
| Att 3 Price Model Final.xlsx | XLSX spreadsheet | |
| CDRL Listing ExA.pdf | ||
| Att 7 Wage Determination.pdf | ||
| Att 2 - NCIC Screening_Pass Request.pdf | ||
| Att 4 PWS Jan 2026.pdf | ||
| Att 1 - NDA - Solicitation.pdf | ||
| Att 6 SB_Subcontracting Plan Review Checklist.xlsx | XLSX spreadsheet |
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MIL-HNDBK-423
May 15, 1993
Scanned by Mission Research Corporation
MIL-HDBK-423
F O R E W O R D
1. This military handbook is approved for use by all Departments and Agencies of the
Department of Defense.
2. Beneficial comments (recommendations, additions, deletions) and any pertinent data which may be of use in improving this document should be addressed to: AFC4A/ TNAB, 607
Pierce Street, Room 300, Scott AFB, IL 62225-5421, by using the Standardization Document
Improvement Proposal (DD Form 1426) appearing at the end of this document or by letter.
3. This document provides design guidance and examples of good practice to support the implementation of high-altitude electromagnetic pulse (HEMP) hardening and testing requirements of MIL-STD-188-125. It also includes management guidance for HEMP protection acquisition programs and hardness maintenance and hardness surveillance for operational facilities.
4. This handbook reflects the 26 June 1990 issue of MIL-STD-188-125.
ii
C O N T E N T S
PARAGRAPH PAGE
1. SCOPE
1.1 Purpose
1.2 Content
1.3 Applications
1.4 Objectives
2. APPLICABLE DOCUMENTS
2.1 Government documents
2.1.1 Specifications, standards, and handbooks
2.1.2 Other Government documents, drawings, and publications
2.2 Non-Government publications
2.3 Order of Precedence
3. DEFINITIONS
3.1 Abbreviations and acronyms used in this handbook
3.2 Definitions
4. HOW TO USE THIS HANDBOOK
4.1 Introduction
4.2 Handbook content
4.3 Handbook arrangement
4.4 Guide to the HEMP protection program
4.5 Brief descriptions of HEMP protection program tasks
5. THE HEMP ENVIRONMENT AND SYSTEM RESPONSE
5.1 Introduction
5.2 History of recognition of the HEMP threat
5.3 The HEMP environment
5.3.1 HEMP generation and characteristics
5.3.1.1 Early-time HEMP
5.3.1.2 Intermediate-time HEMP
5.3.1.3 Late-time HEMP
5.3.2 HEMP environment specifications
5.3.2.1 The DoD standard environment
5.3.2.2 Earlier HEMP environment criteria
5.3.3 HEMP compared with lightning
iii
PARAGRAPH PAGE
5.4 System response to HEMP
5.4.1 HEMP-induced stresses
5.4.1.1 Long-line coupling
5.4.1.2 Antenna coupling
5.4.1.3 Intrasite conductor coupling
5.4.1.4 Shield coupling
5.4.1.5 Interior stresses
5.4.1.5.1 Long-line contributions
5.4.1.5.2 Antenna contributions
5.4.1.5.3 Intrasite line contributions
5.4.1.5.4 Shield leakage contribution
5.4.2 System susceptibility
5.5 References
6. HEMP HARDENING AND THE LOW-RISK APPROACH
6.1 Basic principles
6.1.1 System susceptibility and the need for hardening
6.1.2 Hardening strategy
6.1.3 Facility hardening program goal and objectives
6.2 HEMP hardening
6.2.1 General principles of hardening
6.2.2 The HEMP barrier
6.2.3 Generalized hardening approach
6.3 The low-risk hardening approach
6.3.1 Fundamentals of low-risk hardening
6.3.2 The low-risk approach as applied in MIL-STD-188-125
6.3.2.1 Hardening design features
6.3.2.2 Support for hardening program objectives
6.3.2.3 Advantages
6.3.2.4 Relationship of low-risk approach to other HEMP hardening approaches
6.4 References
IV
PARAGRAPH PAGE
7. BARRIER TOPOLOGY DEVELOPMENT
7.1 Basic principles
7.2 MIL-STD-188-125 requirements
7.2.1 General barrier requirements
7.2.2 Barrier topology requirements
7.2.3 Special protective barrier requirements
7.3 Applications
7.3.1 Identification and location of mission-essential equipment
7.3.2 Shield topology definition
7.3.2.1 Shield topology options
7.3.2.2 Shield topology tradeoffs
7.3.3 POE identification and placement
7.3.3.1 POE types
7.3.3.2 Identification of POEs
7.3.3.3 POE location and grouping
7.3.3.4 POE control procedures
7.3.4 Special protective measures and volumes
7.3.5 Power generation and distribution system
7.4 References
8. SHIELDS AND SHIELDING
8.1 Basic principles
8.2 MIL-STD-188-125 requirements
8.3 Applications
8.3.1 Shield material and thickness
8.3.2 Welding
8.3.2.1 Shielded metal-arc welding
8.3.2.2 Gas metal-arc welding
8.3.2.3 Gas tungsten-arc welding
8.3.2.4 Special considerations in welding stainless steels
8.3.3 Shield seam construction
8.3.3.1 Sheet metal pan
8.3.3.2 Butt-welded seams
8.3.3.3 Lap-welded seams
8.3.3.4 Corner seams
8.3.4 The shield/POE interface
PARAGRAPH PAGE
8.3.5 Metal warpage and buckling
8.3.6 Copper shields
8.4 References
9. ARCHITECTURAL POINTS-OF-ENTRY
9.1 Basic principles
9.1.1 Introduction
9.1.2 Aperture points-of-entry
9.1.3 Waveguides-below-cutoff
9.1.4 Electromagnetic closure of openings in the shield
9.2 MIL-STD-188-125 requirements
9.3 Applications
9.3.1 General design guidance
9.3.2 Architectural POE testing
9.3.3 Personnel entryways
9.3.3.1 Waveguide-below-cutoff entryway
9.3.3.1.1 Waveguide entryway shield
9.3.3.1.2 Waveguide entryway electrical installations
9.3.3.2 Vestibule entryway
9.3.3.3 Shielded doors
9.3.3.3.1 Shielded doors with rf gasketed seals
9.3.3.3.2 Fingerstock shielded doors
9.3.3.3.3 Bellows-operated shielded doors
9.3.3.3.4 Magnetic shielded doors
9.3.3.3.5 Shielded door selection
9.3.3.4 Door interlock and alarm circuits
9.3.3.5 Entryway shield points-of-entry
9.3.4 Equipment accesses
9.3.5 Specifications for architectural POEs
9.4 References
10. MECHANICAL POINTS-OF-ENTRY
10.1 Basic principles
10.2 MIL-STD-188-125 requirements
10.3 Applications
10.3.1 General guidance
VI
PARAGRAPH PAGE
10.3.2 Piping penetrations
10.3.2.1 Chilled water penetrations
10.3.2.2 Sprinkler pipe penetrations
10.3.2.3 Copper piping systems
10.3.2.4 Drain lines
10.3.2.5 Generator and boiler exhausts
10.3.3 Heating, ventilating, and air conditioning system penetrations . . . 186
10.3.3.1 Welded WBC ventilation panel
10.3.3.2 Commercial honeycomb WBC ventilation panel
10.3.4 Mechanical POE protection in copper shields
10.4 References
11. STRUCTURAL POINTS-OF-ENTRY
11.1 Basic principles
11.2 MIL-STD-188-125 requirements
11.3 Applications
11.3.1 General guidance
11.3.2 Shielded building concept
11.3.3 Expansion joints
11.3.4 Interior support columns
11.3.5 Interior walls
11.3.6 Beams
11.3.7 Attachment to the floor slab
11.3.8 Attachments to the shield surface
11.3.9 Copper shields
11.4 References
12. ELECTRICAL POINTS-OF-ENTRY
12.1 Basic principles
12.1.1 Introduction and overview
12.1.1.1 Stress on electrical POEs
12.1.1.2 Protection strategy
12.1.1.3 Time-domain circuit analysis
12.1.2 Electronic surge arresters
12.1.2.1 Basic principles
12.1.2.1.1 Principles of crowbar devices
vii
PARAGRAPH PAGE
12.1.2.1.2 Principles of voltage-clamping devices
12.1,2.2 Device characteristics
12.1.2.2.1 Technology of crowbars
12.1.2.2.2 Technology of clamps
12.1.2.2.3 Device applications
12.1.2.3 Advantages and limitations
12.1.2.3.1 Advantages and limitations of crowbars
12.1.2.3.2 Advantages and limitations of clamps
12.1.2.4 Device selection criteria
12.1.2.4.1 Crowbar selection criteria
12.1.2.4.2 Clamp selection criteria
12.1.2.5 Hybrid series combinations
12.1.2.5.1 General
12.1.2.5.2 Basic design and application considerations
12.1.2.6 Hybrid parallel combinations
12.1.2.6.1 General
12.1.2.6.2 Example of the principle of coordination
12.1.2.7 Failure modes
12.1.2.7.1 Device failure modes
12.1.2.7.2 Excessively low clamping voltage versus reliability
12.1.2.8 Packaging and mounting
12.1.3 Filters
12.1.3.1 Basic principles
12.1.3.2 Filter design and operation
12.1.3.3 Insertion loss
12.1.3.3.1 Power line filters
12.1.3.3.2 Signal line filters
12.1.3.4 Capacitive-input filters
12.1.3.4.1 Short pulse response of filter
12.1.3.4.2 Intermediate pulse response
12.1.3.4.3 Long pulse response
12.1.3.5 Inductive-input filters
12.1.3.5.1 Short pulse response
12.1.3.5.2 Intermediate and long pulse
12.1.3.6 Effect of source and load impedances
12.1.3.7 Filter design information
viii
PARAGRAPH PAGE
12.1.3.8 Military specifications and standards applicable to filters
12.1.3.9 Packaging constraints
12.1.4 Power apparatus for isolation
12.1.4.1 Transformers
12.1.4.1.1 Power transformers
12.1.4.1.2 Isolation transformers
12.1.4.2 Motor-generators
12.1.4.3 Contactors, circuit breakers, and fuses
12.1.4.3.1 Fuses
12.1.4.3.2 Circuit breakers
12.1.4.3.3 Contactors
12.1.5 Optical isolation devices
12.1.5.1 Fiber optic cable
12.1.5.2 Optoelectronic converters
12.1.5.3 Reliability
12.2 MIL-STD-188-125 general requirements for electrical POEs
12.3 Applications
12.3.1 Treatment of commercial power line POEs
12.3.1.1 MIL-STD-188-125 requirements for commercial power line POEs
12.3.1.2 Short pulse treatment
12.3.1.3 Intermediate pulse treatment
12.3.1.4 Long pulse treatment
12.3.1.5 Hardness critical items in power feeder protection
12.3.2 Treatment of intrasite facility power POEs
12.3.2.1 MIL-STD-188-125 requirements for intrasite power line POEs . . . 292
12.3.2.2 Penetration protection for intrasite facility power POEs
12.3.3 Treatment of intersite telephone audio/data line POEs
12.3.3.1 MIL-STD-188-125 requirements for intersite audio/data line POEs . . . 295
12.3.3.2 Fiber optic isolation for audio/data lines
12.3.3.2.1 Power for the Optoelectronic converter
12.3.3.2.2 Grounding
12.3.3.3 Penetration protection for nonstandard audio and data lines
12.3.3.3.1 Short and intermediate pulse protection
12.3.3.3.2 Long pulse protection
IX
PARAGRAPH PAGE
12.3.4 Treatment of intrasite control and signal line POEs
12.3.4.1 MIL-STD-188-125 requirements for control/signal line POEs . . . 304
12.3.4.2 Penetration protection for control/signal line POEs
12.3.5 Treatment of antenna line POEs
12.3.5.1 MIL-STD-188-125 requirements for antenna line POEs
12.3.5.2 Penetration protection for antenna line POEs
12.3.5.2.1 Shield bonding
12.3.5.2.2 MF and lower frequency antenna cables
12.3.5.2.3 HF antenna cables
12.3.5.2.4 VHF antenna cables
12.3.5.2.5 UHF antenna cables
12.3.6 HEMP protection using conduit shielding
12.3.6.1 MIL-STD-188-125 requirements for conduit shielding
12.3.6.2 Conduit protection methods
12.3.7 Penetration entry area
12.3.7.1 MIL-STD-188-125 requirements for the penetration entry area . . . 324
12.3.7.2 Penetration entry area design
12.4 References
13. GROUNDING AND BONDING
13.1 Basic principles
13.2 MIL-STD-188-125 requirements
13.3 Applications
13.3.1 Grounding
13.3.2 Bonding
13.3.2.1 Bonding of power filters to the HEMP shield
13.3.2.2 Bonding of conductors to the HEMP shield
13.3.2.3 Impedance of bonding straps
13.4 References
14. SPECIAL PROTECTIVE MEASURES
14.1 Basic principles
14.1.1 Introduction
14.1.2 Requirements for special protection
14.1.2.1 Mission-essential equipment outside the electromagnetic barrier . . 342
PARAGRAPH PAGE
14.1.2.2 Sensitive mission-essential equipment inside the electro-magnetic barrier . . . 344
14.1.2.3 Special protective volumes and barriers
14.1.3 Specification approaches for special protective measures
14.1.4 Design approach for special protective measures
14.1.4.1 Environments analysis
14.1.4.2 Coupling experiments and analysis
14.1.4.3 Equipment vulnerability experiments and analysis
14.1.4.4 Special protective design development
14.1.5 Testing concepts for special protective measures
14.2 MIL-STD-188-125 requirements
14.3 Applications
14.3.1 General design guidance
14.3.2 Testing requirements
14.3.3 Hardening mission-essential equipment outside the electromagnetic barrier
14.3.4 Hardening sensitive mission-essential equipment inside the barrier
14.3.5 Special protective barrier design and construction
14.3.5.1 Special protective barriers for piping POEs
14.3.5.2 Special protective barriers for electrical POEs
14.3.5.3 Hardening mission-essential equipment in a special protective volume . . . 372
14.3.6 Fielded system examples
14.4 References
15. CORROSION CONTROL
15.1 Basic principles
15.1.1 Uniform attack
15.1.2 Crevice corrosion
15.1.3 Pitting
15.1.4 Intergranular corrosion
15.1.5 Selective leaching or parting
15.1.6 Erosion corrosion
15.1.7 Stress corrosion
15.1.8 Galvanic or two-metal corrosion
XI
PARAGRAPH PAGE
15.1.9 Facility corrosion protection methods
15.2 MIL-STD-188-125 requirements
15.3 Applications
15.3.1 Metals and their corrosion characteristics
15.3.1.1 Iron and iron alloys
15.3.1.1.1 Cast irons
15.3.1.1.2 Carbon steels and irons
15.3.1.1.3 Stainless steels
15.3.1.1.4 Welding and stainless steels
15.3.1.2 Copper and its alloys
15.3.2 Environmental control
15.3.3 Material selection
15.3.4 Cathodic protection
15.3.5 Corrosion protection with a barrier coating
15.3.6 Corrosion protection of bonds
15.3.7 Corrosion control plan
15.4 References
16. TESTING
16.1 Basic principles
16.1.1 Test philosophy and types of tests
16.1.1.1 Testing during construction
16.1.1.2 Hardness verification tests
16.2 MIL-STD-188-125 general test requirements
16.3 Applications
16.3.1 Quality assurance testing
16.3.1.1 MIL-STD-188-125 quality assurance test requirements
16.3.1.2 Quality assurance program
16.3.1.3 Quality assurance principles
16.3.1.4 Quality assurance documents
16.3.1.4.1 Project QC specifications
16.3.1.4.2 HEMP QC plan
16.3.1.4.3 Submittal review
16.3.1.5 Storage inspections
16.3.1.6 Receiving inspections
xii
PARAGRAPH PAGE
16.3.1.7 Welding inspections and tests
16.3.1.7.1 Visual inspections
16.3.1.7.2 Magnetic particle testing
16.3.1.7.3 Dye penetrant inspection
16.3.1.7.4 Other weld test methods
16.3.1.8 SELDS tests
16.3.1.8.1 SELDS test method
16.3.1.8.2 Permanently installed SELDS
16.3.1.8.3 Limitations and attributes of SELDS method
16.3.1.9 Factory inspections and tests
16.3.1.10 Shielding effectiveness survey
16.3.1.11 Government quality assurance
16.3.2 HEMP acceptance testing
16.3.2.1 MIL-STD-188-125 acceptance test requirements
16.3.2.2 HEMP acceptance testing overview
16.3.2.3 Shielding effectiveness acceptance testing
16.3.2.3.1 Principles
16.3.2.3.2 Scheduling
16.3.2.3.3 Facility configuration
16.3.2.3.4 Test equipment
16.3.2.3.5 Test planning and execution
16.3.2.3.6 Data recording, format, and disposition
16.3.2.4 Pulsed current injection acceptance testing
16.3.2.4.1 Principles
16.3.2.4.2 Scheduling
16.3.2.4.3 Facility configuration
16.3.2.4.4 Test equipment
16.3.2.4.5 Test planning and execution
16.3.2.4.6 Data recording, format, and disposition
16.3.3 Hardness verification testing
16.3.3.1 MIL-STD-188-125 verification test requirements
16.3.3.2 Verification test overview
16.3.3.3 Continuous wave immersion tests
16.3.3.3.1 Principles of cw immersion testing
16.3.3.3.2 Practical cw immersion issues
16.3.3.3.3 Uncertainties
xiii
PARAGRAPH PAGE
16.3.3.4 Shielding effectiveness verification testing
16.3.3.5 Pulsed current injection verification testing
16.3.3.5.1 Principles
16.3.3.5.2 Operating state analysis
16.3.3.5.3 Test equipment
16.3.3.5.4 Test planning and execution
16.3.3.5.5 Data recording, format, and disposition
16.3.3.6 Verification of special protective measures
16.3.3.6.1 Hardening using special protective measures
16.3.3.6.2 Overview of verification for SPMs
16.3.3.6.3 Coupling measurements
16.3.3.6.4 Coupling measurement uncertainties
16.3.3.6.5 Verification of MEE outside the HEMP barrier
16.3.3.6.6 Verification of susceptible MEE inside the HEMP barrier
16.3.3.6.7 Special protective volumes
16.3.3.7 Statement of hardness verification
16.3.3.7.1 Hardness criteria
16.3.3.7.2 Reporting requirements
16.3.3.7.3 Discussion
16.3.3.8 Other useful tests
16.3.3.8.1 Preliminary tests
16.3.3.8.2 Evaluation of safety margin
16.4 References
17. RELIABILITY, MAINTAINABILITY, AND TESTABILITY
17.1 Basic principles
17.1.1 Reliability, maintainability, and testability principles
17.1.2 Reliability, maintainability, and testability source documents . . . 494
17.2 Reliability and maintainability
17.2.1 MIL-STD-188-125 requirements
17.2.2 General design guidance
17.2.3 Reliability and maintainability programs
17.2.4 Provisioning
17.2.4.1 Spares and repair parts
17.2.4.2 Special tools and test equipment
xiv
PARAGRAPH PAGE
17.3 Testability
17.3.1 MIL-STD-188-125 requirements
17.3.2 General design guidance
17.3.3 Access for visual inspection
17.3.4 Shielding effectiveness testability
17.3.5 Built-in shield monitor
17.3.5.1 Qualitative monitoring systems
17.3.5.2 Quantitative monitoring systems
17.3.6 Pulsed current injection testability
17.3.6.1 Circuit flexibility
17.3.6.2 Electrical system design
17.3.6.3 Penetration entry area design
17.3.6.4 Filter/surge arrester assembly design
17.3.7 Continuous wave immersion testability
17.4 References
18. SAFETY AND HUMAN ENGINEERING
18.1 Basic principles
18.1.1 Safety and human engineering principles
18.1.2 Safety and human engineering source documents
18.2 MIL-STD-188-125 requirements
18.3 Applications
18.3.1 General design guidance
18.3.2 Personnel entryway and shielded door design
18.3.2.1 Number and types of entryways
18.3.2.2 Entryway lighting and ventilation
18.3.2.3 Shielded doors
18.3.2.4 Shielded door interlocks and alarms
18.3.3 Equipment access POE cover design
18.3.4 Filter/ESA assembly designs
18.3.4.1 Filter and ESA selection
18.3.4.2 Filter/ESA enclosure
18.3.5 Shielded pull boxes and other small enclosures
18.3.6 Construction safety
18.3.7 Safety during acceptance and verification testing
xv
PARAGRAPH PAGE
18.3.8 Operations and maintenance safety
18.4 References
19. HEMP CONFIGURATION MANAGEMENT
19.1 Basic principles
19.1.1 Configuration management principles
19.1.2 HEMP configuration management
19.1.3 Configuration management source documents
19.2 MIL-STD-188-125 requirements
19.3 Applications
19.3.1 Configuration management during facility design
19.3.1.1 HEMP design analyses
19.3.1.2 Design drawings
19.3.1.3 Schedules
19.3.1.4 HEMP protection subsystem specifications
19.3.2 Configuration management in the construction phase
19.3.2.1 Configuration change control
19.3.2.2 Identification of installed HCIs
19.3.2.3 As-built drawings and other configuration documentation
19.3.3 Configuration management during equipment installation
19.3.4 Operations and support phase configuration management
19.3.4.1 HEMP configuration management plan
19.3.4.2 Implementation
19.4 References
20. HARDNESS MAINTENANCE/HARDNESS SURVEILLANCE . . . 559
20.1 Basic principles
20.1.1 Hardness critical items and assemblies
20.1.2 Hardness critical processes
20.1.3 Hardness maintenance
20.1.4 Hardness surveillance
20.2 MIL-STD-188-125 requirements
20.3 Applications
20.3.1 General guidance
20.3.2 HM/HS concept development
xvi
PARAGRAPH PAGE
20.3.3 Reliability, maintainability, and testability in design and construction . . . 567
20.3.4 HEMP protection subsystem technical manual
20.3.5 Preventive maintenance and inspection procedures
20.3.5.1 HEMP shield
20.3.5.2 Shielded door assemblies
20.3.5.3 Shielded access covers
20.3.5.4 Piping WBC penetration protection
20.3.5.5 Ventilation and fiber optic WBC penetration protective devices . . 577
20.3.5.6 Filter/ESA assemblies
20.3.5.7 Conduit penetrations
20.3.5.8 Shielded enclosures
20.3.5.9 Special protective measures
20.3.5.10 PMI schedule
20.3.5.11 PMI manpower
20.3.6 Corrective maintenance
20.3.6.1 Required corrective maintenance procedures
20.3.6.2 Corrective maintenance procedure example
20.3.6.3 Corrective maintenance manpower requirements
20.3.7 Periodic hardness surveillance/reverification testing
20.3.7.1 Frequency of testing
20.3.7.2 Hardness surveillance survey
20.3.7.3 Test documentation
20.3.7.4 Surveillance/reverification test requirements
20.3.7.4.1 Barrier effectiveness testing
20.3.7.4.2 Pulsed current injection
20.3.7.4.3 Tests of special protective measures
20.3.8 Training
20.4 References
21. HEMP PROGRAM MANAGEMENT
21.1 Basic principles
21.1.1 The HEMP program manager
21.1.2 The facility life cycle
21.1.3 Facility acquisition organization
21.1.4 Military service differences
xvii
PARAGRAPH PAGE
21.2 MIL-STD-188-125 requirements
21.3 Planning, programming, and budgeting phase
21.3.1 Milestones
21.3.2 Execution
21.3.2.1 HEMP requirements definition
21.3.2.2 HEMP budget estimates
21.3.2.3 Facility HEMP requirements section
21.3.2.4 HEMP program plan
21.4 Design and specification development phase
21.4.1 Milestones
21.4.2 Execution
21.4.2.1 Design contractor qualifications
21.4.2.2 HEMP design reviews
21.4.2.3 HEMP specifications review
21.4.2.4 Preparations for future phases
21.5 Construction and acceptance testing phase
21.5.1 Milestones
21.5.2 Execution
21.5.2.1 Construction contractor qualifications
21.5.2.2 Review of construction contractor submittals
21.5.2.3 HEMP construction surveillance
21.5.2.4 HEMP review of proposed construction change orders
21.5.2.5 Acceptance testing
21.5.2.6 Preparations for future phases
21.6 C-E equipment installation and acceptance testing phase
21.6.1 Milestones
21.6.2 Execution
21.6.2.1 Installation plan development
21.6.2.2 Installation surveillance
21.6.2.3 Installation acceptance testing
21.6.2.4 Preparations for future phases
21.7 Verification testing phase
21.7.1 Milestones
21.7.2 Execution
21.7.2.1 Verification test plan
21.7.2.2 Verification test execution
xviii
PARAGRAPH PAGE
21.7.2.3 Verification test report
21.7.2.4 Correction of deficiencies
21.8 Operations and support phase
21.8.1 Milestones
21.8.2 Execution
21.8.2.1 HM/HS plan development
21.8.2.2 Organizational hardness maintenance and surveillance
21.8.2.3 Periodic hardness surveillance/reverification testing
21.8.2.4 Spare parts and special equipment
21.8.2.5 HEMP training
21.8.2.6 Configuration control and facility modifications
21.9 References
APPENDIX A SAMPLE CONSTRUCTION SPECIFICATIONS FOR THE
HEMP PROTECTION SUBSYSTEM
10. GENERAL REQUIREMENTS FOR THE HEMP PROTECTION
SUBSYSTEM
10.1 Applicable publications
10.1.1 American Institute of Steel Construction (AISC) publications . . . 650
10.1.2 American National Standards Institute (ANSI) publications
10.1.3 American Society for Testing and Materials (ASTM) publications
10.1.4 Military standards
10.1.5 Military specifications
10.1.6 Military handbooks
10.1.7 Federal specifications
10.2 General requirements
10.2.1 Scope
10.2.2 Performance requirements
10.2.2.1 Compliance with MIL-STD-188-125
10.2.2.2 Warranty
10.2.3 Shielding contractor
10.2.3.1 Qualifications
10.2.3.2 Responsibilities
10.2.3.3 Coordination
xix
PARAGRAPH PAGE
10.3 Components
10.3.1 Shield
10.3.2 Penetrations
10.3.2.1 Doors
10.3.2.2 Waveguide-below-cutoff penetrations
10.3.2.3 Electrical filters and electronic surge arresters (ESAs)
10.3.2.4 Shielded conduit system
10.3.2.5 Special protective components
10.3.3 Standard products
10.3.4 Standards compliance
10.3.5 Marking
10.3.6 Reliability
10.4 Delivery and storage
10.5 Installation
10.5.1 Workmanship
10.5.2 Maintainability and testability
10.5.3 Corrosion control
10.6 Quality control
10.6.1 General quality control requirements
10.6.1.1 Test procedures and results
10.6.1.2 Notification of inspections and tests
10.6.1.3 Site visits
10.6.1.4 Additional Government testing
10.6.2 Remedial action
10.7 Submittals
10.7.1 Qualifications
10.7.2 Shop drawings
10.7.2.1 Shield shop drawings
10.7.2.2 Ground system shop drawings
10.7.2.3 Shielded door shop drawings
10.7.2.4 Waveguide-below-cutoff penetration shop drawings
10.7.2.5 Filter/ESA assembly shop drawings
10.7.3 Quality control plan
10.7.4 Daily QC report requirements
10.7.5 Manufacturer's certificates of compliance
xx
10.7.6 Test plans and procedures
10.7.6.1 Acceptance test plan and procedures
10.7.6.2 Other test plans and procedures
10.7.7 Test reports
10.7.7.1 Acceptance test reports
10.7.7.2 Other test reports
10.7.8 Instruction handbook
10.7.9 Hardness maintenance procedures
20. HEMP SHIELD
20.1 General requirements
20.1.1 Performance requirements
20.1.1.1 Warranty
20.1.2 Qualifications
20.1.2.1 HEMP protection shielding contractor
20.1.2.2 Qualification of welders
20.1.3 Marking
20.2 Submittals
20.2.1 Qualification data
20.2.1.1 HEMP protection shielding contractor
20.2.1.2 Welder qualification certificates
20.2.2 Shop drawings
20.2.3 Certificates of compliance
20.2.4 Test plans and procedures
20.2.5 Test reports
20.2.6 Operation and maintenance instruction manuals
20.3 Requirements
20.3.1 Materials
20.3.1.1 Shield material
20.3.1.2 Welding materials
20.3.1.3 Miscellaneous materials and parts
20.3.2 Penetrations
20.3.2.1 Penetration identification
20.3.2.2 Penetration fixtures
20.4 Delivery and storage
xxi
MIL-HDBK-423
PARAGRAPH PAGE
20.5 Installation
20.5.1 Sequence of installation
20.5.1.1 Placement of floor shield
20.5.1.2 Protection during fabrication
20.5.1.3 Covering of shield work
20.5.2 Construction control
20.5.3 Welding for seam integrity
20.5.3.1 Welding method
20.5.3.2 Locations of welds
20.5.3.3 Weld quality
20.5.3.4 Weld defects
20.5.3.5 Welding safety
20.5.4 Control of warping
20.5.5 Shield penetrations
20.5.6 Grounding and bonding
20.5.6.1 Grounding
20.5.6.2 Bonding
20,5.7 Corrosion protection
20.6 Quality assurance
20.6.1 General requirements
20.6.2 Inspections and tests
20.6.2.1 In-progress weld inspections and tests
20.6.2.2 Complete (empty) shield effectiveness survey
20.6.3 Acceptance testing
30. SHIELDED DOORS AND ACCESS COVERS
30.1 General requirements
30.1.1 Scope
30.1.2 Performance requirements
30.1.2.1 Warranty
30.1.3 Qualifications
30.2 Marking
30.3 Submittals
30.3.1 Door manufacturer credentials
30.3.2 Shop drawings
30.3.3 Certificates of compliance
xxu
MIL-HDBK-423
PARAGRAPH PAGE
PARAGRAPH PAGE
30.3.4 Test plans and procedures
30.3.5 Test reports
30.3.6 Operation and maintenance instruction manuals
30.4 Requirements
30.4.1 Frames
30.4.2 Hinged fingerstock doors
30.4.2.1 Electromagnetic seal
30.4.2.2 Latching mechanism
30.4.2.3 Hinges
30.4.3 Sliding doors
30.4.3.1 Door and frame assembly
30.4.3.2 Electromagnetic seal
30.4.3.3 Sealing system
30.4.3.4 Power assist
30.4.3.5 Servicing
30.4.4 Magnetically operated doors
30.4.4.1 Frame and rails
30.4.4.2 Door leaf
30.4.4.3 Hinges
30.4.4.4 Operation
30.4.5 Locks and interlocks for all doors
30.4.5.1 Cypher locks
30.4.5.2 Interlocks
30.4.5.3 Electric connectivity
30.4.6 Threshold protectors
30.4.7 Painting
30.4.8 Spare parts, special tools, and supplies
30.5 Delivery and storage
30.6 Shielded door installation
30.6.1 Post-installation protection
30.7 Quality assurance
30.7.1 General requirements
30.7.2 Inspections
30.7.3 Factory testing
30.7.3.1 Swinging door static load test
30.7.3.2 Swinging door and hinged access cover sag test
xxm
PARAGRAPH PAGE
30.7.3.3 Power-operated door cycling test
30.7.3.4 Manually operated door handle pull test
30.7.4 On-site tests
30.7.4.1 Shielding effectiveness test
30.7.4.2 Interlock configuration tests
30.7.5 Acceptance testing
40. WAVEGUIDE-BELOW-CUTOFF PROTECTION
40.1 General requirements
40.1.1 Scope
40.1.2 Performance requirements
40.1.2.1 Warranty
40.1.3 Marking
40.2 Submittals
40.2.1 Manufacturer's data
40.2.2 Shop drawings
40.2.3 Test plans and procedures
40.2.4 Test reports
40.2.5 Operation and maintenance instruction manuals
40.3 Requirements
40,3.1 Piping penetration protection
40.3.1.1 Material and dimensions
40.3.1.2 Electromagnetic seal
40.3.1.3 Pipe sleeve
40.3.1.4 Weld plate
40.3.1.5 Exhausts
40.3.2 Ventilation penetration protection
40.3.2.1 WBC array construction and dimensions
40.3.2.2 Electromagnetic seal
40.3.2.3 Mounting frame
40.3.2.4 Pressure drop
40.3.2.5 Attachments
40.3.3 Fiber optic cable penetration protection
40.3.4 Microwave communications penetration
40.4 Delivery and storage
40.5 Installation
xxiv
PARAGRAPH PAGE
40.6 Quality assurance
40.6.1 General requirements
40.6.2 Inspections
40.6.3 Factory testing of commercially manufactured WBC protective devices 688
40.6.4 Acceptance testing
50. FILTER/ESA ASSEMBLIES
50.1 General requirements
50.1.1 Scope
50.1.2 Performance requirements
50.1.2.1 Warranty
50.1.3 Standard products
50.1.4 Standards compliance
50.2 Submittals
50.2.1 Manufacturer's data
50.2.2 Shop drawings
50.2.3 Certificates of compliance
50.2.4 Test plans and procedures
50.2.5 Test reports
50.2.6 Operation and maintenance instruction manuals
50.3 Requirements
50.3.1 Electrical filters
50.3.1.1 Filter construction
50.3.1.2 Filter mounting
50.3.1.3 Filter replaceability
50.3.1.4 Filter terminals
50.3.1.5 Bleeder resistor
50.3.1.6 Marking of filters
50.3.1.7 Voltage rating
50.3.1.8 Current rating
50.3.1.9 Operating frequency
50.3.1.10 Passband impedance
50.3.1.11 Insertion loss
50.3.1.12 Voltage drop
50.3.1.13 Insulation resistance
xxv
PARAGRAPH PAGE
50.3.1.14 Dielectric withstanding voltage
50.3.1.15 Current overload capability
50.3.1.16 Reactive shunt current
50.3.1.17 Parallel filters
50.3.1.18 Harmonic distortion
50.3.1.19 Operating temperature range
50.3.1.20 Temperature rise
50.3.1.21 Minimum life
50.3.2 Electronic surge arresters
50.3.2.1 ESA construction
50.3.2.2 ESA mounting
50.3.2.3 ESA replaceability
50.3.2.4 ESA terminals
50.3.2.5 Marking of ESAs
50.3.2.6 Voltage rating
50.3.2.7 Operating frequency
50.3.2.8 Varistor voltage at 1 mA dc current and spark gap dc breakdown voltage 695
50.3.2.9 ESA impulse sparkover voltage
50.3.2.10 ESA clamping voltage
50.3.2.11 ESA extinguishing characteristics
50.3.2.12 Extreme duty discharge capability
50.3.2.13 Operating temperature range
50.3.2.14 Minimum operating life
50.3.3 Filter/ESA enclosures
50.3.3.1 Enclosure construction
50.3.3.2 Enclosure configuration
50.3.3.3 Access openings and cover plates
50.3.3.4 Conduit connections
50.3.3.5 Ground bus
50.3.3.6 Enclosure mounting
50.3.3.7 Marking of enclosures
50.3.4 Filter/ESA assemblies
50.3.4.1 Insertion loss
50.3.4.2 Insulation resistance
xxvi
PARAGRAPH PAGE
50.3.4.3 Dielectric withstanding voltage
50.3.4.4 Operating temperature
50.3.4.5 Temperature rise
50.3.4.6 Pulsed current injection testing
50.3.4.7 Shielding effectiveness
50.4 Delivery and storage
50.5 Installation
50.6 Quality assurance
50.6.1 General requirements
50.6.2 Inspection and test requirements
50.6.2.1 Filters
50.6.2.2 ESAs
50.6.2.3 Enclosures
50.6.2.4 Filter/ESA assemblies
50.6.3 Test methods
50.6.3.1 Terminal strength test (filters and ESAs)
50.6.3.2 Filter insertion loss measurements
50.6.3.3 Filter voltage drop/dc resistance measurements
50.6.3.4 Filter insulation resistance measurements
50.6.3.5 Filter dielectric withstanding voltage test
50.6.3.6 Filter current overload test
50.6.3.7 Filter reactive shunt current measurement
50.6.3.8 Power filter current sharing measurements
50.6.3.9 Filter harmonic distortion measurements
50.6.3.10 Filter temperature rise measurements
50.6.3.11 Varistor voltage at 1 mA dc current and spark gap dc breakdown voltage measurements
50.6.3.12 ESA impulse sparkover voltage measurement . . . . . . . . . . . 7 04
50.6.3.13 ESA clamping voltage measurement
50.6.3.14 ESA extinguishing test
50.6.3.15 ESA extreme duty discharge measurements
50.6.3.16 ESA minimum operating life test
50.6.3.17 Filter/ESA assembly insertion loss measurements
50.6.3.18 Filter/ESA assembly insulation resistance measurements xxvii
PARAGRAPH PAGE
50.6.3.19 Filter/ESA dielectric withstanding voltage test
50.6.3.20 Filter/ESA assembly thermal measurements
60. SHIELDED CONDUITS AND PULL BOXES
60.1 General requirements
60.1.1 Marking
60.2 Requirements
60.2.1 Material and dimensions
60.2.2 Shielded conduit
60.2.3 Shielded pull boxes
60.2.4 Corrosion protection
60.3 Installation
60.4 Quality assurance
60.4.1 Inspections and tests
60.4.2 Acceptance testing
70. SPECIAL PROTECTIVE MEASURES FOR CONDENSING UNITS . . 709
70.1 General requirements
70.1.1 Marking
70.2 Requirements
70.2.1 Shielded conduits, pull boxes, and enclosures
70.2.2 Filter/ESA assemblies
70.2.3 Motor and sensor protection
70.3 Installation
70.3.1 Inspections and tests
70.3.2 Acceptance testing
80. HEMP PROTECTION SUBSYSTEM ACCEPTANCE TESTING . . 711
80.1 General requirements
80.1.1 Scope
80.1.2 Requirements
80.1.3 Qualifications
80.2 Submittals
80.2.1 Testing agency credentials
XXVlll
PARAGRAPH PAGE
80.2.2 Acceptance test plan and procedures
80.2.3 Acceptance test report
80.3 Requirements
80.3.1 General quality assurance requirements
80.3.2 Shielding effectiveness test
80.3.3 Pulsed current injection test
80.3.4 Condensing units
80.3.4.1 Shielded conduits and enclosures
80.3.4.2 Filter/ESA tests
APPENDIX B COST OF HEMP PROTECTION
10. GENERAL
10.1 Scope
10.2 Applications
20. INITIAL CONSTRUCTION, ACCEPTANCE TESTING, AND HEMP
COSTS
30. HEMP COST DURING COMMUNICATIONS-ELECTRONICS
EQUIPMENT INSTALLATION
40. HEMP VERIFICATION COST
50. HM/HS PLAN DEVELOPMENT COST
60. HARDNESS MAINTENANCE AND SURVEILLANCE COSTS . . . 720
APPENDIX C DATA ITEM DESCRIPTIONS
10. INTRODUCTION
20. DATA ITEM DESCRIPTION LISTS
20.1 Facility (nuclear survivability and HEMP) requirements
20.2 Nuclear survivability and HEMP program plan
20.3 Nuclear survivability and HEMP design report
20.4 Nuclear survivability and HEMP test plan and procedures
XXIX
PARAGRAPH PAGE
20.5 Nuclear survivabihty and HEMP test report
20.6 Nuclear survivability and HEMP hardness maintenance and
hardness surveillance plan
20.7 Configuration management plan
20.8 Reliability, maintainability, and testability program plans
30. REFERENCES
FIGURE
1 Overview of HEMP protection in facilities
2 HEMP ground coverage for bursts at various heights
3 Qualitative HEMP time history and spectrum
4 Compton collision process
5 Geometry for the production of early-time HEMP
6 HEMP source region
7 System response
8 Development of current induced in long lines
9 Coupling model for antenna response
10 Effective and ineffective HEMP barriers
11 Zonal or allocated hardening
12 Shield topology options
13 Typical POEs for a fixed ground-based facility
14 Penetration entry area and major aperture POE locations
15 Sample shield penetration schedule
16 Sample filter/ESA schedule
17 Simplified power generation and distribution schematic
18 Magnetic shielding effectiveness of spherical shell enclosure versus normalized frequency for various values of parameter K
19 Pan-welded shield seam
20 Pan-welded floor shield under raised floor
21 Floor shield pan joint with wear slab
22 Butt-welded shield seam
23 Butt-welded shield seam with plug welds
24 Butt-welded shield seam with steel backing
25 Basic lap-welded shield seam
XXX
FIGURE PAGE
26 Lap-welded preshaped sheets
27 Wall/floor shield joint
28 Wall/ceiling shield joint
29 Longitudinal and transverse shrinkage
30 Skip welding techniques
31 Longitudinal stress vs. bead length
32 Electromagnetic penetration of small apertures
33 Rectangular waveguide-below-cutoff
34 Electromagnetic closure
35 Electromagnetic seal with rf gasket
36 Typical fingerstock
37 Example of main personnel entryway
38 Waveguide entryway configurations
39 Waveguide entryway electrical installation without longitudinal conduits. 151
40 A lighting concept providing light transmission through acrylic tubes. . 152
41 Entryway lighting through waveguides-be low-cutoff
42 Two seal designs for fingerstock shielded doors
43 Two designs of bellows-sealed doors
44 Magnetically operated shielded door
45 Welded equipment access design
46 Gasketed equipment access design
47 Weld plates with WBC protective devices
48 Pipe penetration through a WBC sleeve
49 Chilled water pipe penetrations
50 Computer air conditioner drain line penetration details
51 Generator exhaust penetration
52 Boiler exhaust through the ceiling shield
53 Welded waveguide array panel
54 Welded WBC panel assembled from square metal tubes
55 Waveguide matrix detail
56 Installed WBC array
57 Alternate installation of a WBC array
58 Commercial honeycomb ventilation WBC array panel
59 Overall shield concept
60 Shield expansion joint
61 Shield configuration at an interior column with rigid attachments xxxi
FIGURE PAGE
62 Shield configuration at an interior column with no rigid attachments. . . 202
63 Plan and elevation drawings of a column shield assembly
64 Alternate treatment of a steel column at the floor shield
65 Partition wall installation
66 Steel beam incorporated into the HEMP barrier
67 Steel beam not incorporated into the HEMP barrier
68 Floor shield attachment to the slab
69 Typical techniques for attachments to the shield
70 Norton and Thevenin equivalent circuits for sources driving electrical
POEs
71 Basic multistage configuration of an ESA
72 Transient suppressor symbols
73 Simple configuration for a two-electrode gas tube
74 Volt-ampere characteristics of a gas tube
75 Voltage divider action between source impedance and clamp impedance. . . 226
76 Equivalent circuit of a varistor
77 V-I characteristic of a varistor
78 Differential mode surge created by different time to sparkover of two separate gas tubes
79 Mutual coupling between upstream and downstream loops
80 Pulse rating curves with "indefinite" rating added
81 Hybrid parallel combination of ESAs
82 Examples of fuse protection against ESA failure, 83 Insertion loss of filters
84 Insertion loss of capacitive-input filter for various source and load impedances
85 Acceptance test circuit
86 Capacitive-input power line filter—short pulse response (Ro = 50 fl, RL = 2ty
87 Capacitive-input filter response to intermediate pulse
(Ro = 50 f7, RL = 2fi)
88 Responses of capacitive-input filter to the long pulse (RQ = 3 n, RL = 2 f7). 251
89 Insertion loss of inductive-input filter for various (source/load) impedances. . . 252 xxxn
FIGURE PAGE
90 Responses of an inductive-input filter to a short pulse for 50 H and 300 0 source impedances and 2 (7 load
91 Responses of an inductive-input filter to the intermediate pulse for 50 f7 source impedance and 2 ft load
92 Principle of common mode rejection using transformer
93 Principle of common mode rejection and dc blocking with power transformer.
94 Magnitude of transfer function relating common mode primary voltage to common mode secondary voltage across a 100 f7 load for the test transformers (reference 12-
21)
95 Magnitude of transfer function relating common mode primary voltage to differential mode secondary voltage across a 100 fl load for the test transformers (reference
12-21)
96 Low-frequency equivalent circuit of a power transformer
97 Insertion loss of 500 kVA delta-wye shielded isolation transformer
98 Motor-generator used to eliminate electric power penetration
99 Hydraulic motor-generator set
100 Typical time-current curves for a 30-A fuse and a 30-A circuit breaker
101 Fiber optic conversion and shield protection
102 Sensitivity of a PIN photodiode and an avalanche photodiode (reference 12-22). 273
103 Variation of current impulses into filter with series inductance
104 Filter/MOV response to the intermediate pulse
105 Distribution transformer in configuration to serve as the long-pulse barrier
106 Overall arrangement of power service
107 Schematic diagram of distribution transformer configuration
108 Installation of MOV lightning arrester on transformer
109 Installation of MOV lightning arrester at last pole
110 Integrated power feeder protection
111 Special protective measures for optoelectronic converter on an audio/data cable
112 Power and grounding arrangement for optoelectronic converter on an audio/data cable xxxm
FIGURE PAGE
113 Example of a HEMP filter for high data rate communications circuits
114 Schematic of DNA high data rate filter (reference 12-8)
115 Isolation transformer for long pulse isolation (protected with a gas tube). . . 304
116 Feedthrough connector for bonding rf cable shield to shield
117 Bulkhead connector for bonding cable shield to shield
118 Protection elements for antenna lines operating at HF and lower
119 MF radio receiver HEMP protection device (reference 12-8)
120 One kilowatt HF transceiver HEMP protection device (reference 12-8). . . 316
121 VHF television receiver HEMP protection device (reference 12-8)
122 UHF receiver HEMP protection device (reference 12-8)
123 UHF antenna line protection
124 Shield and internal equipment excitation by external conductor currents
125 Use of single entry area to minimize external excitation of facility HEMP shield. 325
126 Schematic diagram of penetration entry area
127 Reentrant filter compartment
128 Protruding filter compartment
129 Filter and surge arrester compartment in penetration entry area
130 Proper bonding of ground conductor to shield
131 Grounding interface with the HEMP shield
132 Current paths for a low-pass filter
133 Typical exothermic bond configurations (reference 13-2)
134 Illustration of special protective requirements
135 Design approach
136 Environments analysis task
137 Typical damage thresholds (reference 14-5)
138 Special protective measures for an external antenna subsystem
139 Shield-within-a-shield
140 Techniques for eliminating oversized piping penetrations
141 Special protective barrier constructed with cable and equipment cabinet shields
142 Satellite antenna and antenna structural shield xxxiv
FIGURE PAGE
143 HEMP testing sequence
144 Examples of weld beads
145 Examples of unsatisfactory or poor welds
146 Magnetic particle testing
147 Typical shield drive SEEDS test setup
148 SELDS testing with loop excitation
149 Shielding effectiveness test geometry
150 Plane wave test configuration
151 Magnetic field test configuration
152 Shielding effectiveness measurements for a special protective volume. . . 428
153 Sample shielding effectiveness data sheet
154 PCI acceptance test wire-to-ground configuration
155 Double exponential waveform
156 Damped sinusoidal waveform
157 Typical PCI data recording system
158 PCI wire-to-shield acceptance test
159 PCI conduit-to-ground acceptance test
160 Additional PCI measurements for a special protective volume
161 Immersion test configuration (raw data)
162 Processing required from raw data to final result (only magnitudes are shown). . 460
163 Electric field measurements and the MIL-STD-188-125 pass/fail criterion
164 Transmitting antenna position selection
165 Power line common mode injection test
166 Earth terminal complex
167 Mission-essential motor protected with special protective measures
168 Verification for MEE located outside the electromagnetic barrier
169 Shielding effectiveness tests
170 Clear volumes for shielding effectiveness testability
171 Test penetrations
172 Built-in shield monitoring systems. . . . . . . . . . . . . . . . . . . 5 1 1
173 Typical PCI test configurations
174 Typical penetration entry area
175 Filter/ESA assembly configuration for PCI testing
176 Possible high-voltage, high-current filter/ESA assembly configuration. . 521 xxxv
FIGURE PAGE
177 Continuous wave immersion test configuration
178 Horizontal dipole antenna
179 "Imbedded" electrical POE protective device
180 Floor plan indicating the location of the electromagnetic barrier
181 Section drawing indicating the location of the electromagnetic barrier. . 548
182 HCI identification marking
183 Typical HCI list
184 Sample PMI procedure
185 Sample corrective maintenance procedure
186 Hardened facility life cycle diagram
187 HEMP activities in the PP&B phase
188 Estimate for verification test costs
189 Design phase HEMP activities
190 Construction phase HEMP activities
191 HEMP activities during C-E equipment installation phase
192 HEMP verification test activities
193 HEMP activities during O&S
194 Total building construction cost versus HEMP-protected floor area. . . 715
TABLE
I Major events
II HEMP generation regimes and mechanisms
III Double exponential waveform parameters
IV Reasonable worst case HEMP response for power and communication lines
V Reasonable worst case HEMP response for antennas
VI Shield seam construction methods. . . . . . . . . . . . . . . . . . I l l
VII Dielectric constants of liquids
VIII Parameters for the double exponential representation of the electrical
POE sources
IX Action and charge transfer of the HEMP-induced pulses and a lightning flash
X Peak voltage and current in a 50 H coaxial cable as a function of the rf power
XI Special protective measures for an external condensing unit xxxvi
XII Galvanic series of common metals and alloys
XIII Common types of stainless steels
XIV Shielding effectiveness test equipment requirements
XV PCI acceptance test amplitudes and waveforms
XVI Maximum allowable residual internal response characteristics for acceptance testing electrical POEs
XVII PCI acceptance test equipment requirements
XVIII MIL-STD-188-125 cw immersion measurements
XIX Penetration ratings by reliability/maintainability
XX Hardness configuration management plan outline
XXI HCI degradation mechanisms
XXII HEMP awareness training
XXIII Maintenance personnel training
XXIV Military Department information relevant to HEMP facility acquisition
XXV Content of the HEMP section in the facilities requirement document
XXVI HEMP program plan outline
XXVII Design checklist for preliminary and final reviews
XXVIII Construction surveillance checklist
XXIX Acceptance test plan outline
XXX Acceptance test report
XXXI HEMP verification test plan outline
XXXII HEMP verification test report outline
XXXIII HM/HS plan outline
XXXIV HEMP protection costs for U.S. ground-based facilities
XXXV Comparison of HEMP protection costs from independent sources. . . 719 xxxvii/xxxviii
MIL-HDBK-423
PAGE TABLE
1. SCOPE
1.1 Purpose. The two-volume MIL-HDBK-423 handbook set provides information to managers and engineers responsible for the design, construction, testing, and hardness maintenance/hardness surveillance of fixed and transportable ground-based facilities that must be hardened against the high-altitude electromagnetic pulse (HEMP). The primary purpose of this Volume I is to provide detailed guidance to implement HEMP protection of fixed facilities in accordance with the requirements of MIL-STD-188-125, "High-Altitude Electromagnetic Pulse (HEMP) Protection for
Ground-Based C I Facilities Performing Critical, Time-Urgent Missions." Volume II provides similar guidance for ground-mobile and transportable facilities.
1.2 Content. This handbook provides design guidance and examples of good practice to support compliance with the requirements stated in MIL-STD-188-125. That standard calls for the establishment of an electromag
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .