Att_4_Boat Production and Delivery Schedule.xlsx

XLSX spreadsheet 23 KB Posted

Attached to
US Navy 8M and 11 M Rigid Inflatable Boat (RIB) and U. S. C. G. Special Purpose Craft Law Enforcement II RFP
Solicitation number
N0002421R2205
Issued by

About this file

This document contains a production schedule and delivery timeline for rigid inflatable boats (RIBs) to be procured by the U.S. Navy and U.S. Coast Guard over five years. The schedule outlines the proposed delivery dates for 110 RIBs, including 8-meter and 11-meter vessels for both the Navy and Coast Guard. Boats would be delivered in batches every 30 days following the prior delivery, with the option to schedule a 240-day break in production between major orders to accommodate changes in requirements or production needs. The related federal contract opportunity is a solicitation from the Naval Sea Systems Command for the RIBs and specialized Coast Guard law enforcement craft. The fixed price, indefinite delivery/indefinite quantity contract would be set aside for small businesses under NAICS code 336612. The solicitation seeks commercial boat designs constructed to specified government standards for delivery over five years.

View the file

Other files

File Type Posted
Att_11_QA_ 2021 0514.xlsx XLSX spreadsheet
Att_11_QA_ 2021_0513.xlsx XLSX spreadsheet
Att_8 - CLIN Pricing Sheet REV 2 _12 May 2021.xlsx XLSX spreadsheet
N0002421R2205 Amendment 7 Sec C Att 8 updates.pdf PDF
N0002421R2205 Amendment 6- Due Date May 17th 1 PM EST.pdf PDF
Att_11_QA_ 2021 0505.xlsx XLSX spreadsheet
N0002421R2205 Amendment 5 Extend Due Date.pdf PDF
Att_11_QA_ 2021 0429.xlsx XLSX spreadsheet
N0002421R2205 Amendment 4 Update Specification.pdf PDF
Att_11_QA_ 2021 0427.xlsx XLSX spreadsheet
Att_11_QA_ 2021 0420.xlsx XLSX spreadsheet
Att_11_QA_ 2021 0419.xlsx XLSX spreadsheet
N0002421R2205 Amendment 3 Update Quantities and Attachment 8 4.16.pdf PDF
Att_11_QA 2021 04 15.xlsx XLSX spreadsheet
Att_8 - CLIN Pricing Sheet REV 1.xlsx XLSX spreadsheet
N0002421R2205 Amendment 3 Update Quantities and Attachment 8.pdf PDF
N0002421R2205 Amendment 2 Update L3.1.1 Section E.docx DOCX document
N0002421R2205 Amendment 1-Update Preproposal Conference Date to April 14.docx DOCX document
Att_11_QA.xlsx XLSX spreadsheet
Att_5_-_Techncial_Data_Rights.pdf PDF
N00024-21-R-2205 RFP.pdf PDF
Att_8 - CLIN Pricing Sheet.xlsx XLSX spreadsheet
Att_3 - Boat Initial Spare Parts List.xlsx XLSX spreadsheet
Att_2 Specification Response Matrix.xlsx XLSX spreadsheet
Att_7_Warranty Rev A.docx DOCX document
Att_10_Non-Disclosure Statement for Covered Attachments.docx DOCX document
Att_6_ UID.pdf PDF
Att_9_Past Performance Information.docx DOCX document
Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Production Schedule

NSW SSC and USCG SPC-LE Production and Delivery Schedule (Production Base Contract)

Days After Contract Award (DAC)
ConfigurationDesign Maturity ReviewOrder
Major ItemsReceipt of Major ItemsStart
Hull FabricationInstall
EnginesSubmit
TDPConduct
PDITsDeliver
BoatNSW 11m OCC
*DeliveryNSW 8m OCC
*DeliveryUSCG 11m OCC

*Delivery

Boat 1NSW 11m OCC360 DAC
Boat 2USCG 11m OCCN/AN/AN/A360 DAC
Boat 3NSW 11m OCC390 DAC
Boat 4USCG 11m OCC390 DAC
Boat 5NSW 8m OCCN/AN/AN/A420 DAC
Boat 6USCG 11m OCCN/AN/AN/A420 DAC
Boat 7NSW 11m OCCN/AN/AN/A450 DAC
Boat 8USCG 11m OCCN/AN/AN/A450 DAC
Boat 9NSW 11m OCCN/AN/AN/A480 DAC
Boat 10NSW 11m OCCN/AN/AN/A480 DAC
Boat 11NSW 11m OCCN/AN/AN/A510 DAC
Boat 12NSW 11m OCCN/AN/AN/A510 DAC
Boat 13NSW 11m OCCN/AN/AN/A540 DAC
Boat 14NSW 11m OCCN/AN/AN/A540 DAC
* Government desired delivery dates
Notes:1. Add the planned number of days after contract award for each of the events in the cells above
2. Design Maturity Review is a desired one time event.
3. Major Items include engines, trailers and raw material suppliers (aluminum)

4. PDITs only occur for Boats #1, 3, 4

N00024-21-R-2205 Attachment 4

Delivery Schedule

NSW SSC and USCG SPC-LE Proposed Production and Delivery Schedule (Delivery Base and Follow-On Delivery Orders)

ORDERING PERIOD 1
DELIVERY ORDER 1
NSW 11m OCC SSC (Unless otherwise noted)USCG 11m OCC SPC-LE
Craft No.DestinationNotional Delivery Schedule
Proposed Delivery Schedule
Craft No.DestinationNotional Delivery Schedule
Proposed Delivery Schedule
Boat 1TBD360 DAYS AFTER ORDERBoat 1TBD360 DAYS AFTER ORDER
Boat 230 DAYS AFTER LAST BOATBoat 230 DAYS AFTER LAST BOAT
Boat 3 (8m OCC)TBD30 DAYS AFTER LAST BOATBoat 3TBD30 DAYS AFTER LAST BOAT
Boat 4TBD30 DAYS AFTER LAST BOATBoat 4TBD30 DAYS AFTER LAST BOAT
Boats 5-10 (2 per month)30 DAYS AFTER LAST BOAT
DELIVERY ORDER 2 (No Break in Production)
Craft No.DestinationNotional Delivery Schedule
Proposed Delivery Schedule
Craft No.DestinationNotional Delivery Schedule
Proposed Delivery Schedule
Boat 11TBD30 DAYS AFTER LAST BOATBoat 5TBDSame date as NSW Boat #11
Boat 12 (8m OCC)TBD30 DAYS AFTER LAST BOATBoat 6TBD30 DAYS AFTER LAST BOAT
Boat 13 (8m OCC)TBD30 DAYS AFTER LAST BOATBoat 7TBD30 DAYS AFTER LAST BOAT
Boat 14TBD30 DAYS AFTER LAST BOATBoat 8TBD30 DAYS AFTER LAST BOAT
Boat 15TBD30 DAYS AFTER LAST BOATBoat 9TBD30 DAYS AFTER LAST BOAT
Boat 16 (8m OCC)TBD30 DAYS AFTER LAST BOATBoat 1030 DAYS AFTER LAST BOAT
Boat 17 (8m OCC)TBD30 DAYS AFTER LAST BOAT
Boat 18TBDSame date as boat 17
Boats 19-20TBD30 DAYS AFTER LAST BOAT
ORDERING PERIOD 2
Craft No.DestinationNotional Delivery Schedule (No Break in Production)
Proposed Delivery Schedule (No Break in Production)
Craft No.DestinationNotional Delivery Schedule (No Break in Production)
Proposed Delivery Schedule (No Break in Production)
Boats 21-30 (boats 23-24 are 8m OCC)TBD30 DAYS AFTER LAST BOATBoats 11-20TBD30 DAYS AFTER LAST BOAT
Boats 21-30 (2 per month)TBD30 DAYS AFTER LAST BOAT
Craft No.DestinationNotional Delivery Schedule (Break in Production)
Proposed Delivery Schedule (Break in Production)
Craft No.DestinationNotional Delivery Schedule (Break in Production)
Proposed Delivery Schedule (Break in Production)
Boat 21TBD240 DAYS AFTER ORDERBoat 11TBD240 DAYS AFTER ORDER
Boats 22-30 (boats 23-24 are 8m OCC)TBD30 DAYS AFTER LAST BOATBoats 12-20TBD30 DAYS AFTER LAST BOAT
Boats 21-30 (2 per month)30 DAYS AFTER LAST BOAT
ORDERING PERIOD 3
Craft No.DestinationNotional Delivery Schedule (No Break in Production)
Proposed Delivery Schedule (No Break in Production)
Craft No.DestinationNotional Delivery Schedule (No Break in Production)
Proposed Delivery Schedule (No Break in Production)
Boats 31-40 (boats 33-34 are 8m Cabin)TBD30 DAYS AFTER LAST BOATBoats 31-40TBD30 DAYS AFTER LAST BOAT
Boats 41-50 (2 per month)30 DAYS AFTER LAST BOAT
Craft No.DestinationNotional Delivery Schedule (Break in Production)
Proposed Delivery Schedule (Break in Production)
Craft No.DestinationNotional Delivery Schedule (Break in Production)
Proposed Delivery Schedule (Break in Production)
Boat 31TBD240 DAYS AFTER ORDERBoat 31TBD240 DAYS AFTER ORDER
Boats 32-40 (boats 33-34 are 8m Cabin)TBD30 DAYS AFTER LAST BOATBoats 32-40TBD30 DAYS AFTER LAST BOAT
Boats 41-50 (2 per month)30 DAYS AFTER LAST BOAT
ORDERING PERIOD 4
Craft No.DestinationNotional Delivery Schedule
NO BREAK in ProductionProposed Delivery Schedule
NO BREAK in ProductionCraft No.DestinationNotional Delivery Schedule
NO BREAK in ProductionProposed Delivery Schedule

NO BREAK in Production

Boats 41-50 (boats 43-44 are 11m Cabin)TBD30 DAYS AFTER LAST BOATBoats 51-60TBD30 DAYS AFTER LAST BOAT
Craft No.DestinationNotional Delivery Schedule
BREAK in ProductionProposed Delivery Schedule
BREAK in ProductionCraft No.DestinationNotional Delivery Schedule
BREAK in ProductionProposed Delivery Schedule

BREAK in Production

Boat 41TBD240 DAYS AFTER ORDERBoat 51240 DAYS AFTER ORDERBoats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32
Boats 42-50 (boats 43-44 are 11m Cabin)TBD30 DAYS AFTER LAST BOATBoats 52-6030 DAYS AFTER LAST BOATBoats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32
DEFINITIONS:DEFINITIONS:
BREAK in Production: If a Delivery Order is issued after 120 days from the date of delivery of the last boat on order. (Example: Last boat on current order delivery date: 15 July 2019, new order placed any time after 15 March 2019 would be defined as a BREAK in production. Boat 1 of the new Delivery Order would have a delivery date of 240 days after placement of new Delivery Order)

NO BREAK in Production: If a Delivery Order is issued before 120 days from delivery of last boat on order. (Example: Last boat on current order delivery date 15 July 2019, new order placed any time before 14 March 2019 would be defined as NO BREAK in production. Boat 1 on the new Delivery Order would have a delivery date of 15 August 2019)