This document is a VHA Pre-Construction Risk Assessment (PCRA) for a small-scale construction project at the Joliet VA Community Based Outpatient Clinic. The project involves installing condensate pumps, replacing variable frequency drives (VFDs) at air handlers 5, 6, and 7 in the mechanical room, replacing the domestic water make-up feed system in the boiler plant, and installing variable air volume (VAV) units with reheat steam coils and creating steam connections in basement rooms B013, B014, and B015.

The PCRA details the risk assessment and control measures for the project, categorizing it as a small-scale construction activity. Key requirements include weekly site visits, a site-specific safety plan, hazard communication, chemical inventory, hot work permits, lock-out/tag-out procedures, and daily site inspections. The work area is currently impacted by an active parking expansion project, and an Infection Control Risk Assessment (ICRA) is required. The project will be managed by Amanda Logan, with Christopher Jay from Infection Prevention and Control involved in the assessment.

View the file

Other files for this federal contract opportunity

Other files attached to 578-25-013 Joliet VFD Replacement, newest first.
File Type Posted
S06 Amendment A0003.docx DOCX document
P09 Revised SOW 9.18.25.docx DOCX document
S02 2nd Prebid Site Visit Sign-In Sheet 9.17.25.pdf PDF
Att-18 M2.3 PART SCND FLR NEW WRK PLN-DUCTWRK.PDF PDF
S06 Amendment A0002.docx DOCX document
S05 Pre-Bid RFIs 9.15.25.xlsx XLSX spreadsheet
S02 Prebid Site Visit Sign-In Sheet 9.3.25.pdf PDF
S05 Pre-Bid RFIs 8.27.25.xlsx XLSX spreadsheet
S06 Amendment A0001.docx DOCX document
Att-1 Contractor Badging Forms.pdf PDF
Att-2 Emergency Contact List.pdf PDF
Att-17 Specifications Book.pdf PDF
S02 Solicitation 36C25225B0023.docx DOCX document
Att-6 Infection Control Barrier Sample.pdf PDF
Att-8 Above Ceiling Entry and Wall Construction Permits.pdf PDF
Att-4 Hines COVID-19 Guidelines.pdf PDF
Att-5 Safety and Health During Construction Activities.pdf PDF
Att-10 Pre-Construction Checklist.pdf PDF
Att-12 Interim Life Safety Measures -ILSM-.pdf PDF
Att-13 Infection Control Risk Assessment -ICRA 1-3-.pdf PDF
Att-14 Joliet CBOC Floor Plans.pdf PDF
Att-16 Joliet CBOC Mechanical Drawings.pdf PDF
P07 Wage Determination.pdf PDF
Att-3 No Smoking Policy 10-1-19.pdf PDF
Att-7 Cutting Welding and Other Hot Work.pdf PDF
Att-9 OIT Horizontal Cable Requirements.pdf PDF
Att-15 Current Conditions Photos.pdf PDF
Show all 27

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

VHA Pre-Construction Risk Assessment (PCRA)

VHA PCRA-1.1 (May 21, 2024) Page 1 of 5

PCRA Introductory Information and Instructions

Use this template as a baseline for performing facility Pre-Construction Risk Assessments (PCRA) for Construction, Renovation, and Maintenance . The template provides minimum requirements for categorizing activity type(s) and safety risk to determine the level of precautions needed to prevent impact related to Construction, Renovation and Maintenance on patients, employees, and contractors.

Ensure that the activity statement of work and any drawings available are used for the PCRA assessment and included in the project file with the completed PCRA.

Communication and coordination of all types of activity with affected areas are to be included among the control measures. The development of communication and coordination plans must begin during the activity planning phase.

Facilities may customize this template to incorporate site-specific information and requirements.

NOTE: This VHA PCRA template pertains specifically to non-infection-related safety for Construction, Renovation, and Maintenance activities. It must be used in conjunction with the VHA Infection Control Risk Assessment (ICRA) for the activity, if required, which specifically addresses infection risks outside the scope of this PCRA.

PERMIT: See the last page of this document for a fillable permit form to be used for posting at the activity site.

Activity Location:

Activity Name, Number, and/or Brief Description:

Table 1 - Construction, Renovation, and/or Maintenance Activity Type and Control Measures

NOTE: If any of the bulleted criteria in a higher activity type pertains to the work that will be done (even if the other criteria are in a lower type), use the higher activity type for the VHA PCRA.

Controls defined in Table 1 for the activity must be in place before the activity begins and maintained until work is completed and the area is activated. Control measures for each activity must also include the control measures in the preceding row(s).

As the activity progresses, a full re-evaluation of remaining activity type and risk is required prior to changing the level of control measures.

Activity Type determined from Table 1:

Activity Type and Description Control Measures

Inspection/upkeep generally defined as follows:

Work can be completed in a single shift, not to exceed 10 hours.

Patients, employees and/or visitors may be in the area depending on the activity.

Work that does not create dust or debris.

Work that does not create vapors or fumes.

Removal of ceiling tile or access to mechanical or electrical chase for visual inspection that will not impair fire safety

1. Immediately replace any ceiling tile, close access panels, etc., upon completion of work.

2. Site visits of construction area are required weekly by member of multi-disciplinary team.

Site visits will be documented on standard checklist.

3. Site specific safety plan, task hazard analysis, and hazard communication required to be provided by the contractor and approved where a contact is in place. For internal work the

Small Scale Construction

Joliet VA Community Based Outpatient Clinic

578-M25110 Joliet VFD Replacement: Install condensate pumps and replace the VFDs at air handlers 5,6, and 7 in the mechanical room. Replace the domestic water make-up feed system in the boiler plant. Remove the pneumatic HVAC system and install VAVs with reheat steam coil and create a steam connection in basement rooms B013, B014, B015.

578-25-013 -

VHA PCRA-1.1 (May 21, 2024) Page 2 of 5 systems and are limited to 1 tile per 50 square feet with limited exposure time (not to exceed an hour for each tile) within the shift.

Minor interior updates (e.g., replacing floor or ceiling tiles, carpentry work to include hanging signage, and painting with hand tools) that do not create vibration or noise.

Limited building system maintenance that does not require Lock Out Tag Out (LOTO) such as plumbing on potable systems limited to faucet replacement, steam trap replacement etc. and electrical work such as replacement of bulbs, receptacles, or switches.

shop involved must work with Safety to ensure proper precautions are in place.

4. Must address identified hazards and controls that will be implemented to ensure minimal impact to patients, employees, contractors and facility.

5. Communication and coordination plan for all affected areas

Small scale Construction, Renovation and general maintenance/repair work, generally defined as follows:

Prolonged work that may take longer than a single shift but not exceeding six months.

Patients and employees are not to be in the area until activity is completed.

Work that creates some noise and vibration due to power tool use.

Selective demolition/removal of preexisting floor covering, casework, lay-in ceiling, or other architectural elements that may o disturb asbestos, lead or silica o create the potential for falling objects o create vibration and/or noise in excess of 80 dB(A) in surrounding areas.

o cause penetrations in fire or smoke barrier

Plumbing work such as the installation of new sinks, showers and toilets and associated plumbing that requires utility outages or work on the steam system that may require:

o LOTO o The use of compressed gas cylinders

Electrical work such as installation of conduit and wire for lighting, receptacles and switches for an area, the installation of conduit and wire for new devices such as terminal units, fans etc. Electrical work such as installation of cabling/wiring/conduit for a single device, installation of new device such as a light fixture that require LOTO.

Air Handler and/or fan shutdown/startup and HVAC work such as replacement of a single diffuser, single terminal unit, a single device and the installation of ductwork, diffusers, and terminal units for an area that may require:

o Work on ladders o Rigging, hoisting or lifting of equipment or materials overhead Modification of existing fire alarm and suppression systems requiring system outages and ILSMs or obstruction of exits and or impact on corridors.

Architectural, structural, or any other work that may cause vapors or fumes such as:

o Roofing work o Flooring work o Painting or other large-scale use of such substances.

All control measures in the row above and the following:

1. Hazard communication chemical inventory required to be provided by the contractor and approved.

2. Where construction, Renovation and maintenance are done in an accredited facility, and ILSM assessment is required to be done and ILSMs put into place in accordance with TJC LS.01.02.01 and the local facility policy including Fire watch if necessary. Staff is trained and the ILSM is verified regularly

3. Hot Work or burn permits in place and staff trained

4. LOTO procedures in place and staff trained on their use

5. Site visits will be reviewed using the criteria in standardized guide.

6. Daily inspections of the site are to be conducted by the General Contractor or shop supervisor and documented on their daily log.

Large-scale construction, renovation, or maintenance generally defined as follows:

Work exceeding 6 months in duration.

All control measures in the two rows above and the following Activity Hazard Analyses and Control Plans (check all that apply):

1. Excavation safety plan in place

VHA PCRA-1.1 (May 21, 2024) Page 3 of 5

Patients and employees are not to be in the area until activity is completed.

Excavation or heavy equipment use taking place o Dig safe required utility location o Trench safety o Dust control plan o Equipment exhaust, Noise, Vibration

Confined space entry required (permit required or not)

Requires crane work o General crane work o Lift over buildings

Includes elevated work o Roof work, fall protection o Window work, scaffolding and fall protection o Odor control

Welding, cutting or use of torches requiring burn permits

Demolition of building components and infrastructure including removal of multiple doors, walls, framing, ceilings, flooring, piping, electrical and HVAC that may o require asbestos, lead or silica abatement o create the potential for falling objects o create vibration and/or noise in excess of 90 dB(A) in surrounding areas.

o cause breaches to fire or smoke barrier

The installation building components such as new walls, ceilings and doors including framing, drywall and associated plaster work that requires transport of significant materials through building and up elevators i.e., weight limits of floors and elevators

Plumbing work requiring LOTO and system shutdown and startup such as the installation of:

o new medical gas systems, o steam/heating hot water, condensate systems, o Potable water and sanitary drainage, multiple sinks, showers and toilets including associated plumbing.

Electrical work such as installation of electrical feeders, distribution panels, conduit and wire for lighting, receptacles and switches for an area, the installation of conduit and wire for new devices such as terminal units, fans etc. requiring LOTO and system isolation.

Installation of fire alarm and suppression systems requiring outages of those systems and ILSMs or closure of exits/corridors

Mechanical work such as the installation of air handling equipment, associated ductwork, diffusers, heat exchangers, terminal units and controls requiring lifting and support of equipment and systems.

2. Dust control plan in place

3. Pollution prevention plan in place

4. Dig safe paper work in place

5. Crane lift plan in place

a. Crane placement

b. Crane swing

c. Crane load evaluation

6. Fall protection plan in place and staff trained

7. Confined entry plan in place and staff trained

Table 2. Affected Adjacent Area Assessment

In addition to the minimum precautions noted above for the Activity Type, it is critical that the activity be coordinated with the areas adjacent to the activity to ensure operations in those areas are not disrupted or impacted. List the adjacent areas in Table 2 below and develop activity-specific coordination plans and associated communication plans with each area to address activity work that could impact or disrupt the operation of the areas, in general as follows:

VHA PCRA-1.1 (May 21, 2024) Page 4 of 5

If adjacent area is vacant (e.g., work outside, construction of new building, etc.):

o Coordination is typically not necessary other than potentially traffic flow and pedestrian access.

If adjacent area is non-continuously occupied (e.g., areas where outpatient care is provided, employee health, etc.):

o Develop a list of activities that will potentially impact or disrupt the operation of the area (e.g., work involving noise, vibration or exit obstruction) and meet with POC to coordinate execution of work in a way that mitigates the impact (e.g., conduct work after hours).

If adjacent area is occupied continuously (e.g., areas where inpatient care is provided, residential areas such as Community Living Centers, etc.):

o Develop a list of activities that will potentially impact or disrupt the operation of the area (e.g., work involving noise, vibration or exit obstruction) and meet with POC to coordinate execution of work in a way that mitigates the impact (e.g., move affected party temporarily).

Area Service(s)/Type(s) of Area(s)

(e.g., OR, Unit/Ward, Sterile Processing, Administrative, etc)*

Point of Contact

(POC)

POC Contact Information

Construction plan communicated to

POC?

Activity Area** Nurse Manager/ Medical Director

Sharon Gunderson Sharon.Gunderson@va.go v

Yes

Area Above Audiology/exam rooms and sound booths

Dr. Melissa Welch Dr. Martinique Wood melissa.welch@va.gov martinique.wood@va.gov

Yes

Area Below NA

Adjacent Area 1 HBPC/Offices Megan McVane megan.mcvane@va.gov Yes

Adjacent Area 2 NA

Adjacent Area 3 NA

Adjacent Area 4 NA

* There may be more than one Service/type of area for each row. List all. The information entered on this table must be used in the ICRA if required.

** List the area(s) in which the construction/renovation/maintenance activity will occur.

Infection Control Risk Assessment (ICRA)

Consult with Infection Prevention and Control regarding the assessment of potential patient infection risks associated with the activity and the need for control measures. For example, activities such as a boiler plant project and/or facility steam shutdown, if properly planned, should have minimal to no patient infection risk impacts and likely do not require an ICRA. See VHA Directive 7715 and the VHA ICRA Template for more information.

Is an ICRA required for the Activity? Yes No

VHA PCRA-1.1 (May 21, 2024)

Pre-Construction Risk Assessment (PCRA) Permit This page must be posted at the entrance to the project area, or other designated area

Unique permit number:

Location and brief description of construction/renovation/maintenance

Install condensate pumps and replace the VFDs at air handlers 5,6, and 7 in the mechanical room. Replace the domestic water make-up feed system in the boiler plant. Install VAVs with reheat steam coil and create a steam connection in basement rooms B013, B014, B015.

Project manager Amanda Logan Project start date Contact phone number 708-397-1281 Completion date Contractor or lead shop Permit expiration date

Activity Type Inspection/Upkeep, Small-scale, or Large-scale) Small Scale

Activity Type Control measures to be in place for the duration of the activity (Check the box for the Activity Type to indicate the Control Measures)

Inspection/Upkeep

1. Immediately replace any ceiling tile, close access panels, etc., upon completion of work.

2. Site visits of construction area are required weekly by member of multi-disciplinary team. Site visits will be documented on standard checklist.

3. Site specific safety plan, task hazard analysis, and hazard communication required to be provided by the contractor and approved.

4. Must address identified hazards and controls that will be implemented to ensure minimal impact patients, employees, contractors and facility.

5. Communication and coordination plan for all affected areas

Small-scale All control measures in the row above and the following:

1. Hazard communication chemical inventory required to be provided by the contractor and approved.

2. ILSMs in place and staff trained on situation

3. Hot Work or burn permits in place and staff trained

4. LOTO procedures in place and staff trained on their use

5. Site visits will be reviewed using the criteria in standardized guide.

6. Daily inspections of the site are to be conducted by the General Contractor and documented on their daily log.

Large-scale All control measures in both rows above and the following Activity Hazard Analyses and Control Plans as applicable (check all that apply):

1. Excavation safety plan in place

2. Dust control plan in place

3. Pollution prevention plan in place

4. Dig safe paperwork in place

5. Crane lift plan in place

a. Crane placement

b. Crane swing

c. Crane load evaluation

6. Fall protection plan in place and staff trained

7. Confined entry plan in place and staff trained

*The location of all Activity Hazard Analyses and Control Plans (excavation, dust, pollution, etc.) as applicable shall be identified on this permit and shall be made available to all workers on the job.

Additional requirements: The work area for rooms B013, B014, B015 are currently impacted by the active construction project 578-371 Parking Expansion at Joliet CBOC. Rooms are inside the work area and already planned to be under infection control measures.

Is an Infection Control Risk Assessment (ICRA) required for the Activity? Yes No

Infection Prevention and Control signature:

Date:

Project Manager signature Date

Safety Officer signature Date

Chair, Construction Safety Committee signature