This document contains a construction cost estimate breakdown form and details for a federal contract opportunity to repair the HVAC system at a youth center on Patrick Air Force Base in Florida. The construction cost estimate form provides a template for contractors to estimate costs by line item for materials, labor, equipment, and other direct costs. The related federal contract opportunity solicits bids to replace HVAC system components in building 3656 and extend the mechanical room to accommodate a new government-furnished chiller. An organized pre-bid site visit is scheduled for July 23, 2020 and contractors must submit any questions in writing by July 28, 2020. Final bids are due on August 17, 2020. The soliciting agency is the Department of the Air Force Space Command for this HVAC repair project located at Patrick Air Force Base.
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AF3052
| CONSTRUCTION COST ESTIMATE BREAKDOWN | ||||||||||
| CONTRACTOR | ADDRESS | |||||||||
| CONTRACT FOR | PROPOSED TOTAL CONTRACT PRICE | |||||||||
| Contract No. | $0 | |||||||||
| PURCHASE REQUEST FORM | PROJECT NUMBER | WORK LOCATION | ||||||||
| MATERIAL COST | LABOR COST | |||||||||
| UNIT | OTHER | |||||||||
| LINE | ITEM | OF | QUANTITY | MANHOURS | AVERAGE | TOTAL | DIRECT | LINE | ||
| NO. | MEASURE | UNIT | TOTAL | MANDAYS | RATE | COSTS | TOTAL | |||
| (1) | (2) | (3) | (4) | (5) | (6) | (7) | (8) | (9) | (10) | |
| 0.00 | 0.00 | 0.00 | 0.00 | |||||||
| 0.00 | 0.00 | 0.00 | ||||||||
| 0.00 | 0.00 | 0.00 | ||||||||
| 0.00 | 0.00 | 0.00 | ||||||||
| 0.00 | 0.00 | 0.00 | ||||||||
| 0.00 | 0.00 | 0.00 | ||||||||
| 0.00 | ||||||||||
| 0.00 | ||||||||||
| 0 | 0.00 | |||||||||
| 0.00 | 0.00 | 0.00 | ||||||||
| 0.00 | 0.00 | 0.00 | ||||||||
| 0.00 | 0.00 | 0.00 | ||||||||
| 0.00 | 0.00 | 0.00 | ||||||||
| 0.00 | 0.00 | 0.00 | ||||||||
| 0.00 | 0.00 | 0.00 | ||||||||
| 0.00 | ||||||||||
| 0.00 | 0.00 | 0.00 | ||||||||
| 0.00 | 0.00 | 0.00 | ||||||||
| CECC FORM 3052 | PAGE 1 | |||||||||
| INSTRUCTIONS FOR COMPLETING AF FORM 3052 | ||||||||||
| Col 1 Item. Description of materials required, work to be done, special equipment needed, etc. Breakdown should be in sufficient | ||||||||||
| detail to permit itemizing of all direct costs. | ||||||||||
| Col 2 Unit of Measure. Description of the unit in which each item is to be estimated (examples--square yards--SY, cubic yards-- | ||||||||||
| CY, square feet--SF, linear feet--LF, board feet--BF, each--EA, pound--LB). | ||||||||||
| Col 3 Quantity. Constractor's estimate of quantity required in terms of unit of measure (couldmn 2). Itms and units of measure will | ||||||||||
| be furnished by the Government. Quantity estimates will be furnished by the Government only when it is anticipated that a unit price | ||||||||||
| contract will be issued. Otherwise, the contractor is responsible for determining quantity estimates. | ||||||||||
| Col 4 and 5 Material Costs. Enter unit cost (Col 4) of material to be supplied and total costs (Col 5) for items listed in column 1. | ||||||||||
| Col 6, 7 and 8 Labor Costs. Enter in col 6 the estimated number of manhours or mandays needed to perform the work listed in | ||||||||||
| column 1. Enter in col 7 the average rate per manhour (manday) and in col 8 the total labor cost. | ||||||||||
| Col 9 Other Direct Costs. Enter estimated costs of special equipment and other items (listed in column 1) which are special to the | ||||||||||
| contract and of significant dollar value. | ||||||||||
| Col 10 Line Total. Self-explanatory. | ||||||||||
| NOTE: In addition to other totals entered on various pages, the grand total of column 10, plus overhead and profit will be shown on | ||||||||||
| the last page as follows. | ||||||||||
| TOTAL MATERIAL COSTS | $ | |||||||||
| TOTAL LABOR COSTS | $ | |||||||||
| TOTAL OTHER DIRECT COSTS | $ | |||||||||
| TOAL DIRECT COSTS | $ | |||||||||
| OVERHEAD | $ | |||||||||
| SUBTOTAL | $ | |||||||||
| PROFIT | $ | |||||||||
| TOTAL PRICE | $ | |||||||||
| DATE | FIRM NAME | |||||||||
| TITLE | BY | |||||||||
| (Signature) | ||||||||||
| INSTRUCTIONS TO OFFERORS | ||||||||||
| 1. The purpose of this form is to provide a standard format by which the offeror submits to the Government a summary of | ||||||||||
| incurred and estimated costs (and attached supporting information) suitable for detailed review and analysis. Prior to the award | ||||||||||
| of a contract resulting from this proposal the offeror shall, under the conditions stated in ASPR 3-807.3, be required to submit a | ||||||||||
| certificate of current cost or pricing data (see ASPR 3-807.3(e) and 3.807.4). | ||||||||||
| 2. In addition to the specific information required by this form, the offeror is expected, in good faith, to incorporate in and submit | ||||||||||
| with this form any additional data, supporting schedules, or substantiation which are reasonably required for the conduct of an | ||||||||||
| appropriate review and analysis in the light of the specific facts of this procurement. For effective negotiations, it is essential that | ||||||||||
| there be a clear understanding of | ||||||||||
| a. The existing, verifiable data | ||||||||||
| b. The judgmental factors applied in projecting from known data to the estimate, and | ||||||||||
| c. The contingencies used by the offeror in his proposed price. | ||||||||||
| In short, the offeror's estimating process itself needs to be disclosed. | ||||||||||
| 3. When attachment of supporting cost or pricing data to this form is impracticalbe, the data will be described (with schdules as | ||||||||||
| appropriate), and made available to the contracting officer or his authorized representative on request. | ||||||||||
| 4. By submission of this proposal the offeror grants to the contracting officer, or his authorized representative, the right to examine, | ||||||||||
| for the purpose of verifying the cost or pricing data submitted, those books, records, documents, and other supporting data which | ||||||||||
| will permit adequate evaluation of such cost or pricing data, along with the computations and projections used therein. This right | ||||||||||
| may be exercised in connection with any negotiations prior to contract award. | ||||||||||
| (Reverse of AF Form 3052, Jan 88) | ||||||||||
| *U.S. GOVERNMENT PRINTING OFFICE: 1988-24D-979:51319 |