XLSX spreadsheet 13 KB Posted
- Attached to
- RAINWATER Basin Wells and PUMPS Federal contract opportunity
- Solicitation number
- 140F0121R0062
About this file
This document includes an attachment with a bid schedule for replacing wells at two wetland areas, as well as information about a related federal contract opportunity. The bid schedule lists various line items and services required to decommission existing wells and install new wells and related infrastructure at the Harvard and Atlanta wetland project areas. Services include mobilization, permitting, well installation, discharge piping, electrical work, and connecting the new wells to the existing system. The federal contract opportunity is solicited by the U.S. Fish and Wildlife Service and seeks a contractor to provide all material, equipment, and labor to install two new wells, abandon existing wells, and connect the new wells to the existing system in accordance with the attached statement of work and drawings. The point of contact is provided for any questions.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amend_0002_Atch_1_Rainwater_Basin_Wells_Bid_Schedule_Rev_1_0002.xlsx | XLSX spreadsheet | |
| Sol_140F0121R0062_Amd_0002.pdf | ||
| Sol_140F0121R0062_Amd_0001.pdf | ||
| Atch_2_Rainwater_Basin_Wells_Submittals.pdf | ||
| Sol_140F0121R0062.pdf | ||
| Atch_3_Rainwater_Basin_Wells_DBA_Wage_Det_Nebraska_Heavy.pdf | ||
| Atch_5_Rainwater_Basin_Wells_Past_Perf_Quest.doc | DOC document | |
| Atch_1_Rainwater_Basin_Wells_SOW.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1 Project Description: Replace wells for two WPAs.
Furnish all labor, materials, and equipment to complete the following work in accordance with the attached specifications.
| Unit | Total | ||||
| QTY | Unit | Cost | Cost | ||
| WELL DECOMMISSION | |||||
| 1 | Harvard well and paperwork | 1 | LS | ||
| 2 | Atlanta well and paperwork | 1 | LS |
| Section Total | ||||
| HARVARD WPA | ||||
| 1 | Mobilization/Demobilization, Bonding, Overhead, & Profit | 1 | LS | |
| 2 | Well Permit to NRD | 1 | EA | |
| 3 | Harvard well and appurtenances | 1 | LS | |
| 4 | Harvard well discharge connection | 1 | LS | |
| 5 | Harvard electrical as defined in the SOW | 1 | LS |
| Section Total | ||||
| ATLANTA WPA | ||||
| 1 | Mobilization/Demobilization, Bonding, Overhead, & Profit | 1 | LS | |
| 2 | Well Permit to NRD | 1 | EA | |
| 3 | Atlanta well and appurtenances | 1 | LS | |
| 4 | Atlanta well discharge piping, valve, and appurtenances | 1 | LS | |
| 5 | Atlanta electrical as defined in the SOW | 1 | LS | |
| 6 | Atlanta power company cost | 1 | LS |
Section Total