Atch 3 Drawings 06032025.pdf

PDF 2 MB Posted

Attached to
Y1DA--621-22-129 - Bldg 160 Kitchen AHU-4 Replacement Federal contract opportunity
Solicitation number
36C24925B0005
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 9

About this file

These are architectural and mechanical engineering drawings for the Bldg. 160 Kitchen AHU-4 Replacement project at the James H. Quillen VA Medical Center in Johnson City, Tennessee. The drawings detail the replacement of an Air Handling Unit (AHU) in the mechanical room, including specific technical specifications such as installing a new 8000 CFM AHU, connecting to existing outside air supply and louver, installing new supply ductwork (26x26 and 10x10), connecting to existing chilled water and steam piping, and implementing new air balancing dampers. The project involves electrical connections to Panel EQP circuit #9, installation of duct smoke detectors, and AHU controls using Computrols system. The project number is 621-22-129, with bid documents dated October 15, 2024, and a planned performance period of 180 calendar days after Notice to Proceed.

View the file

Other files for this federal contract opportunity

Other files attached to Y1DA--621-22-129 - Bldg 160 Kitchen AHU-4 Replacement, newest first.
File Type Posted
Atch 9 Sign In Sheet 06162025.pdf PDF
Atch 1 WD Washington County Building TN20250191 dated 06062025.pdf PDF
36C24925B0005 0001.docx DOCX document
Atch 8 RFI Form.docx DOCX document
Atch 7 Price Breakout Schedule.xlsx XLSX spreadsheet
Atch 2 Specifications 05282025.pdf PDF
Atch 5 Contractor EMR Certification Form.docx DOCX document
Atch 1 WD Washington County Building TN20250191 dated 05022025.pdf PDF
36C24925B0005_1.docx DOCX document
Atch 6 General Conditions Breakout.xlsx XLSX spreadsheet
Atch 4 Calculation of Contractor Self Performed Work.xlsx XLSX spreadsheet
Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Location:

Site:

Drawn:

Project Title:

Checked: Approved:

Project No.

Drawing No.

Date

Building:

Scale:

JAMES H. QUILLEN

MOUNTAIN HOME VAMC

Drawing Title:

Revisions DateApprovals Date

MOUNTAIN HOME

Floor:

6.3.2025

G-1 160 4th

NTS

COVER SHEET

Department of Veterans Affairs

JAMES H. QUILLEN VA MEDICAL CENTER

LAMONT STREET & VETERANS WAY

BID DOCUMENTS

Approved: Name & Title Date

Approved: Name & Title Date

Approved: Name & Title Date

Approved: Name & Title Date

JOHNSON CITY, TN 37604

BID DOCUMENTS

VICINITY MAP LOCATION MAPPROJECT LOCATION PROJECT LOCATION

SHEET INDEX

SHEET

NUMBER SHEET NAME

GENERAL

G- COVER SHEET

G-004 GENERAL PROJECT NOTES & CODE SUMMARY

CIVIL

C-001 GENERAL NOTES, LEGEND, & ABBREVIATIONS

C-110 DEMOLITION, SITE, UTILITY, & EROSION CONTROL PLAN

C-501 CONSTRUCTION & EROSION CONTROL DETAILS

C-502 CONSTRUCTION & EROSION CONTROL DETAILS

C-503 CONSTRUCTION & EROSION CONTROL DETAILS

STRUCTURAL

S-001 GENERAL STRUCTURAL NOTES AND ABBREVIATIONS

S-100 PLAN OF NEW CHILLER AND SECTION

SF101 MECHANICAL ROOM FRAMING PLAN

ARCHITECTURE

A-001 MATERIALS LEGEND, ABBREVIATIONS & SYMBOLS

AD101 DEMOLITION PLAN - FIRST FLOOR - MAIN BUILDING

AD102 DEMOLITION PLAN - FIRST FLOOR TUNNEL

AD131 DEMOLITION PLAN - RCP FIRST FLOOR - MAIN BUILDING

AD132 DEMOLITION PLAN - RCP FIRST FLOOR TUNNEL

AE101 FLOOR PLAN - FIRST FLOOR - MAIN BUILDING

AE102 FLOOR PLAN - FIRST FLOOR TUNNEL

AC131 REFLECTED CEILING PLAN - FIRST FLOOR - MAIN BUILDING

AC132 REFLECTED CEILING PLAN - FIRST FLOOR TUNNEL

FIRE PROTECTION

FA001 FIRE ALARM GENERAL NOTES & LEGEND

FA101 FIRE ALARM FLOOR PLAN - MECHANICAL ROOM N174

FX001 FIRE SUPPRESSION GENERAL NOTES & LEGEND

FX101 FIRE SUPPRESSION FLOOR PLAN - OVERALL

FX102 FIRE SUPPRESSION FLOOR PLAN - MECHANICAL ROOM N174

MECHANICAL

M-001 MECHANICAL GENERAL NOTES AND DESIGN CRITERIA

M-002 MECHANICAL ABBREVIATIONS AND LEGENDS

MD101 FIRST FLOOR MECHANICAL DEMOLITION PLAN

MD102 ENLARGED MECHANICAL DEMOLITION PLAN - MAIN BUILDING

MD103 ENLARGED MECHANICAL DEMOLITION PLAN - MECHANICAL

ROOM

MD104 ENLARGED MECHANICAL DEMOLITION PLAN - NORTH TUNNEL

MH101 FIRST FLOOR MECHANICAL PLAN

MH102 ENLARGED MECHANICAL PLAN - MAIN BUILDING

MH103 ENLARGED MECHANICAL PLAN - EAST WING

MH104 ENLARGED MECHANICAL PLAN - NORTH TUNNEL

MP101 MECHANICAL PIPING PLAN - GROUND LEVEL - CHILLER YARD

MP102 MECHANICAL PIPING PLAN - FIRST FLOOR - MAIN BUILDING

M-301 MECHANICAL SECTIONS

M-501 MECHANICAL DETAILS

M-502 MECHANICAL DETAILS

M-503 MECHANICAL DETAILS

M-601 MECHANICAL SCHEDULES

M-602 MECHANICAL SCHEDULES

MI701 MECHANICAL CONTROLS

MI702 MECHANICAL CONTROLS

MI703 MECHANICAL CONTROLS

MI704 MECHANICAL CONTROLS

MI705 MECHANICAL CONTROLS

MI706 MECHANICAL CONTROLS

MI707 MECHANICAL CONTROLS

MI708 MECHANICAL CONTROLS

ELECTRICAL

E-001 ELECTRICAL GENERAL NOTES AND ABBREVIATIONS

E-002 ELECTRICAL LEGEND

ED101 ELECTRICAL DEMOLITION PLAN - MAIN BUILDING

ED102 ELECTRICAL DEMOLITION PLAN - TUNNEL

EL101 LIGHTING PLAN - MAIN BUILDING

EL102 LIGHTING PLAN - TUNNEL

EP121 MECHANICAL POWER PLAN

EP122 MECHANICAL POWER PLAN - CHILLER YARD

EY101 AUXILIARY SYSTEMS PLAN - MAIN BUILDING

EY102 AUXILIARY SYSTEMS PLAN - TUNNEL

E-621 ELECTRICAL SCHEDULES

PROJECT #

MECHANICAL

M-1 MECHANICAL PLANS

OCTOBER 15, 2024

KSG

621-22-129

BLDG. 160 KITCHEN AHU-4

REPLACEMENT

621-22-129

BLDG. 160 KITCHEN AHU-4 REPLACEMENT

Location:

Site:

Drawn:

Project Title:

Checked: Approved:

Project No.

Drawing No.

Date

Building:

Scale:

JAMES H. QUILLEN

MOUNTAIN HOME VAMC

Drawing Title:

Revisions DateApprovals Date

MOUNTAIN HOME

Floor:

KSG

BLDG. 160 KITCHEN AHU-4

REPLACEMENT

621-22-129

6.3.2025

M-1 160 4th

NTS

NEW WORK PLAN

1 NEW OUTSIDE AIR SUPPLY. CONNECT TO EXISTING LOUVER

2 NEW 8000 CFM AHU. SEE AHU SCHEDULE.

3 NEW 26X26 SUPPLY DUCT. CONNECT OT EXISTING 12X36.

4 NEW 10X10 SUPPLY DUCT. CONNECT OT EXISTING 12X12.

6 CONNECT TO EXISTING CW SUPPLY AND RETURN PIPING.

7 CONNECT TO EXISTING STEAM AND CONDENSATE PIPING.

5 DEMO EXISTING 26X26 & 10X10 BACK TO POINT OF CONNECTION.

8 CONNECT POWER TO PANEL EQP CIRCUIT #9 15A 460V 3 PHASE

N500 MECHANICAL ROOM (USE TO BE EF-12). PANEL EQP IS FED

FROM PANEL EQD GROUND FLOOR ROOM N054.

9 INSTALL AIR BALANCING DAMPERS TO REQUIRED CFM. Left duct to 5,400 CFM and right duct to 525 CFM.

26 x 26

10 x 10

10 DUCT SMOKE DETECTORS.

x

10 x 10

C F

M

C F

M

8,000 CFM TOTAL

SUPPLY AIR

KEYNOTES

11 AHU CONTROLS (COMPUTROLS).

11 5

COVER SHEET
Mtn Home VHA Title Block-Layout1
M-1
Mtn Home VHA Title Block-Layout1

File details come from the government source that posted it. Updated .