- Amendment 03: Replace Underground Storage Tank (UST) at Launch Facility (LF) D-02 (Banner County, NE)
- Solicitation number
- FA461326R0002
About this file
Statement of Work Summary: Replace UST at D02
This is a Statement of Work (SOW) for the removal and replacement of an underground storage tank (UST) at Launch Facility D02, located in Kimball County, Nebraska, approximately 78 miles from F.E. Warren Air Force Base in Wyoming. The project (GHLN 25-5143) has a Period of Performance of 350 calendar days and is prepared by the 90 Civil Engineer Squadron Missile Engineering Flight.
Scope and Key Requirements
The contractor must remove a 1960s-era waterproofed UST, remediate approximately 100 gallons of diesel-contaminated soil, and install a new 4,000-gallon fiberglass Xerxes UST with double-wall dry interstitial space, spill bucket, and monitoring components. Environmental testing and sampling must be completed within 35 days of Notice to Proceed, with drilling to 12-16 feet depth to determine contamination extent and quantity. The contractor must order the new UST within one week of NTP and complete installation and access road restoration within 50 calendar days of UST delivery. Critical contractor responsibilities include: obtaining all necessary State of Nebraska permits and certifications; managing asbestos-containing materials (fuel lines and gaskets) and 600 gallons of existing sludge; conducting soil density testing on 8-inch lifts; maintaining licensed State of Nebraska UST installer/closer personnel; and restoring the site to pre-project conditions with all components placed within one-quarter inch of original locations.
Compliance and Administrative Requirements
The work must comply with Federal, State (Nebraska), and Local regulations including EPA standards for hazardous waste, OSHA requirements, and Nebraska Department of Environmental Quality rules. Fill material placement must meet specified gradation and compaction requirements (95-100% modified proctor density depending on location). The contractor is responsible for all hazardous materials coordination, waste disposal documentation, spill response, and environmental compliance including NPDES permits if applicable. Security requirements mandate Real ID-compliant identification for all personnel, Entry Authority List (EAL) submissions 31 days prior to site access, and compliance with OPSEC and CUI safeguarding protocols. Working hours are 7:30 a.m. to 4:00 p.m. excluding weekends and Federal holidays, with mandatory coordination with 90 CES/CEM and the Contracting Officer requiring minimum 10 working days' advance notice. Warranties must be provided for all equipment and systems, guaranteed for not less than 12 months from acceptance.
View the file
Other files
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
Replace UST at D02
PROJECT No: GHLN 25-5143
Prepared By:
90 CES/CEM
Missile Engineering
F.E. Warren Air Force Base, Wyoming
Alexander M. McGrew, PE
Civil Engineer 3 Apr 2026
SOW
TABLE OF CONTENTS
OVERVIEW
SCOPE OF WORK
SECURITY REQUIREMENTS
PRINCIPLE FEATURES OF WORK PER CSI DIVISION
CSI 01 – General Requirements
CSI 02 – Existing Conditions
F.E. Warren AFB Environmental Specifications
CSI 02 65 00 – Underground Storage Tank Removal
CSI 26 00 00 – Electrical
CSI 27 21 00 – Monitoring System
CSI 28 00 00 – Electrical Safety and Security
CSI 03 00 00 – Concrete
CSI 23 11 - Facility Fuel Piping
CSI 31 00 00 – Earthwork
CSI 33 68 13 – Soil and Rock Anchors
CSI 33 56 10 – Utilities – Factory Fabricated Fuel Storage Tanks
ATTACHMENT 1 – LF Limit of Potential Ground Disturbance
APPENDIX 1 – REFERENCES
Statement of Work
Replace UST at D02
Project No: GHLN 25-5143
3 Apr 2026
OVERVIEW
1. This project includes the removal and replacement of the existing 1960s era underground storage tank (UST) and remediation of soil contaminated with about 100 gallons of diesel fuel at LF D02. The Launch Facility (LF) is under the control of F.E. Warren Air Force Base, Wyoming. These specifications describe the components and requirements for the work under this contract.
2. The Period of Performance (PoP) for this project shall be 350 calendar days.
3. The work shall be performed at the LF located in Nebraska. The distance from F.E. Warren AFB is indicated below.
SITE COUNTY STATE DISTANCE (MILES)
D02 Kimball NE 78
SCOPE OF WORK
1. The Contractor shall provide all labor, materials, equipment, and transportation necessary for removing a 1960s era waterproofed UST, remediate soils contaminated with diesel, and install a new UST in accordance with laws, regulations, as specified in this Statement of Work. Works shall be completed in strict compliance with the specifications, applicable drawings, attachment, and the Terms and Conditions of the Contract as well as all applicable building codes, standards, manufacturer specifications and recommendations, and practices in the industry. The scope of the project shall include all the below and any other incidental work tasks needed to complete this project:
a. Overall Requirements
i. The contractor shall complete all parts of this project are in general accordance with current ASTM standards, current ASSHTO standards, current ACI Standards, Local State, and Federal regulations.
ii. All waste materials shall be disposed off-Air Force Property with documentation from accepting facility(ies), as needed.
iii. The contractor shall coordinate with adjacent landowners for land use within limits of Attachment 1 for this project.
For this proposal and cost estimate, the Contractor Shall assume access to adjacent land based on landowner approval.
90 CES/CEM will provide landowner contact information after contract award.
iv. The contractor shall submit all documentation associated with this project to 90
CES/CEM and the CO.
Documents the contractor submits to local, state, or federal regulators [Third
Party(ies)] for review shall be submitted to 90 CES/CEM once documents are approved by the Third Party(ies).
a. 90 CES/CEM will not request revisions to these documents.
90 CES/CEM will only review submittals and / or documents for revision NOT reviewed by Third Parties for approval.
v. The contractor shall be responsible for all fluids management associated with and / or impacted by this project except groundwater intrusion into the excavation.
vi. The contractor shall limit land disturbances to less than 1-acre.
b. Contamination Testing
i. The contractor shall retain a qualified environmental testing organization to complete sampling and testing to determine extent and quantity of contaminated soils within the defined excavation limits.
Testing shall include:
a. Contamination due to a one hundred gallon (100 gal) diesel leak.
b. Contamination due to UST installed in the 1960s.
ii. The sampling shall be completed within thirty-five (35) days of notice to proceed.
iii. The sampling shall be obtained by drilling.
The drill samples shall not exceed sixteen feet (16’) below existing grade and minimum sample depth shall be twelve feet (12’) below existing grade.
iv. Sampling shall be completed so that:
The approximate location of the fuel leak can be identified.
Determination for soil contamination from the UST installed in the 1960s.
v. All samples shall have a traceable chain of custody.
The contractor shall provide the chain of custody documentation to 90 CES/CEM in the testing reports.
vi. Test results shall include:
Quantification of contaminated soils in cubic yards.
Soil samples shall be analyzed to determine likely contamination above regulatory limits as required by the State of Nebraska and as is typical for fill around a UST installed in the 1960s.
All other needed results.
vii. The qualified environmental testing organization shall provide the contractor with the following:
Approximate location and quantity of contaminated soils.
Delineate approximate location of contaminated soils and specify if contaminated soils are within or out of the specified excavation limits.
Provide regulatory requirements to remediate contaminated soils.
Required regulatory processes and associated documentation based on contamination.
Any other information needed for effective project planning and decision making.
c. Known Soil Contamination or Hazardous Materials
i. Materials requiring remediation and / or disposal:
The contractor shall dispose all asbestos containing material(s) (ACMs) as appropriate.
The contractor shall abandon in place existing fuel lines, from UST to LSB, after cleaning, packing, and capping the existing fuel lines.
a. Existing fuel lines are ACMs.
The contractor shall remove and dispose of all pumpable fluids and / or sludge in the UST, estimated to be six hundred gallons (600 gal).
ii. 100-gal fuel leak Final soil remediation quantity shall be determined by soil analysis.
d. Presumed Soil Contamination or Hazardous Materials
i. Soil remediation and / or disposal:
The contractor shall propose to remediate ten cubic yards (10yd^3) of soil due to diesel contamination; actual remediation quantity determined by soil analysis.
The Contractor shall complete all State of Nebraska soil contamination remediation due to a fuel spill and / or due to the 1960s UST.
The Contractor shall receive concurrence from the State of Nebraska regarding completed remediation, and no further fuel spill reporting from the USAF for the site.
e. 1960s UST Removal and Disposal
i. The contractor shall not relocate the existing UST from the existing UST location until all pumpable fluids or sludges are removed.
ii. The contractor shall remove all existing site components above the existing UST within the defined limits of excavation.
Existing concrete spill buckets, existing unused utilities within the excavation volume, the existing used underground conduit for reconnection, and other incidental unused site components.
iii. The contractor shall not begin soil excavation until arrival time of the new UST is known.
The contractor shall order the proposed UST within one (1) week of Notice to Proceed.
The contractor shall have the proposed UST installed and the access road restored to match existing conditions within fifty (50) calendar days of the site access road being closed due to excavation or other project activities.
iv. The Contractor shall partially fill in the excavation for a stable access road to allow all USAF wheeled vehicle, up to seventy-ton (70 tn), to access to the site if:
Work on site is planned to be stopped on site for fourteen (14) days.
Work has not occurred for fourteen (14) consecutive calendar days on site.
v. The contractor shall not exceed the defined excavation limits for this project. The excavation limits are:
The existing UST excavation area is fourteen feet by forty-seven and half feet (14’ x 47.5’) centered on the existing UST with a maximum excavation depth to 12’ or to the existing concrete anchor slabs; excavate to first depth limit encountered.
a. Total volume for this excavation is estimated at 225 cubic yards.
Excavation above the existing fuel lines and / or other connection to the proposed UST shall be sufficient width for the connections to be made and a depth that is one foot (1’) above the existing fuel lines or to match other existing connections elevations.
vi. The contractor shall abandon in place, in addition to above, the following:
The existing UST concrete slab anchor.
Any other unused conduits found in the excavation sides after caping exposed end.
vii. The contractor shall document existing connections between the LSB and the existing UST for like in kind replacement during the proposed UST installation.
viii. The contractor shall clean the existing UST prior to export for recycling or other disposal.
f. New UST Installation and Fill Placement
i. The contractor shall install a new four thousand (4,000)-gallon diesel fuel UST with a diameter of six feet (6’) and length of twenty feet eight inches (20’ – 8”) double-wall dry interstitial space, fiberglass Xerxes UST with spill bucket, Veeder-Root tube, fill tube, vent, and any other associated components as specified in this Statement of Work, in strict compliance with the specifications, applicable drawings, attachment, the Terms and Conditions of the Contract as well as all applicable current building codes, local, state, and federal regulations, and manufacturer specifications.
The contractor shall comply with all manufacturers’ specifications and / or recommendations so no part of the fuel system is voided by installation.
The Contractor shall install the proposed UST so at the end of the project all the functionality and capabilities of the existing UST are maintained after installation.
The Contractor shall test all system components for nominal operation verification with 90 CES/CEM observing all tests.
The contractor shall install the new UST to have top of tank elevation to ensure top of concrete elevation for spill buckets to match existing top of concrete elevation without the need for additional concrete than shown in the Drawings.
ii. The contractor shall provide additional clean imported select fill material due to USTs volume difference plus ten cubic yards (10 yd^3), from contaminated soil export.
iii. Fill Placement and Soil Laboratory Testing All soils used to backfill the excavations shall be tested by a qualified laboratory to verify compliance with manufacturer’s specification and / or recommendations and / or the specifications in this SOW.
iv. Soil Density Testing The contractor shall conduct in place soil density testing only on eight-inch (8”) lifts.
The Contractor shall conduct soil testing in accordance with the Project’s specifications or State of Nebraska Requirements.
The contractor shall provide in place soil density testing results daily or as soon as results are available.
v. Concrete Testing
Test ready mix concrete delivered to the site.
The contractor shall provide all testing written documentation after compressive strength test are complete.
a. The contractor shall provide verbal reporting of air entrainment and slump test results.
g. Return Site to Pre-Project Existing Condition
i. Contractor shall restore site to pre-project conditions with all site components placed within one quarter inch of pre-project location unless specified otherwise in the SOW or Drawings.
ii. All underground electrical conduit shall be restored or abandoned in place if not in use prior to project start.
The light pole will need electrical connection prior to the project site activities end.
The contractor shall provide location tape above all restored conduit runs.
iii. The Contractor shall ensure all site components have the same functionality as existing conditions prior to completing the site work portion of this project.
2. The Contractor is responsible for supplying and installing a turnkey, fully functional, tested, and operational product meeting the performance requirements outlined by these specifications. The Contractor will provide any special permits or licenses that may be required, obtain adequate insurance, and coordinate all inspections required by applicable laws and regulations, except as otherwise specified herein.
3. The Contractor will keep a copy of the most current Statement of Work and drawings on the jobsite.
4. Accomplish all work in accordance with the SAM Contract specifications.
5. The Project Coordinator shall be the Contracting Officer (CO) from the 90 Contracting Squadron, and the Project Manager shall be the 90 Civil Engineer Squadron/Missile Engineering Flight (90
CES/CEM).
6. In the case of the winter season that has direct impact to performing the work outlined in this SOW, the
Contractor shall notify the Government they can no longer perform work. 90 CES/CEM will validate that the weather no longer allows work to be performed within the specifications.
e. If the reason for stopping work is due to weather impacted material supplies, the Contractor shall provide a letter to support the winter suspension.
f. The project will be placed into suspension, and the remaining number of PoP days will be documented.
g. When weather conditions become favorable for work, the CO will begin coordinating with the contractor to establish a timeline for their return to work.
h. When the suspension is lifted, a new completion date will be established based on the remaining PoP days.
SECURITY REQUIREMENTS
1. The Contractor and their personnel, to include employees and any subcontractors, shall comply with pertinent Air Force security regulations while working on the project. Special security clearances such as Confidential, Secret, etc., are not required of the Contractor or Contractor representatives for the performance of this project.
2. Real-ID Compliance Identification: IAW DoDM 5200.08V2_DAFMAN31-101V3_DAFGM 2024- 01, Installation Perimeter Access Control.
a. Base access and Entry Authority Lists (EAL) requests will require Real ID-Compliant identification for base access and EAL creation.
b. Failure of the vendor to ensure personnel have Real ID-compliant identification will result in denial of base access and EAL requests.
c. Levels of Security: Individuals performing work under this contract shall comply with applicable program security requirements. Contractors will support the following levels of security: Unclassified and Unclassified But Sensitive.
3. Base Access: The Contractor shall request access onto F.E. Warren AFB through the CO or authorized representative a minimum of three (3) working days prior to needed entry.
a. One form of ID, as a legible photocopy or electronically scanned valid driver’s license, state photo ID card, or official state/federal photo ID card shall be submitted for each employee requiring base access.
4. Missile Field Access/EALs: Access to MAF/LF is controlled by the U.S. Air Force. All Contractor personnel, vehicles, and equipment entering the site shall be listed on an effective Entry Authority List (EAL), created by the Air Force.
a. The Contractor shall provide, via DoD SAFE, complete, valid, and legible data to be used to produce the initial EAL, prior to their initial commencement of work, and to maintain the EAL.
The standard processing time for all EAL actions is thirty (30) calendar days. Any request to create add to, modify, correct, or renew the EAL shall be submitted at least thirty-one (31) calendar days before needing entry to site. The Contractor shall remain current on information that may change or expire (e.g., IDs or license plates) during the contract period and shall submit updates accordingly. Any delays caused by the submission of incomplete, invalid, or illegible data will be at no cost to the Government. 90 CES/CEM will provide the expiration date for each EAL, when the date is made effective, to the Contractor and the CO.
b. The Contractor shall submit the following for each employee (to include prime, subcontractor, and delivery/testing services employees).
i. One form of ID, as a legible photocopy or electronically scanned valid driver’s license, state photo ID card, or official state/federal photo ID card. The same ID shall be shown for entrance onto site once the EAL is effective.
c. The Contractor shall submit the following for each vehicle and piece of equipment, to include trailers. Standard hand-held equipment is not required to be on an EAL.
i. Vehicle Type
ii. Make/Model
iii. Year
iv. Color
v. License plate state
vi. License plate # or VIN #
d. The Contractor shall submit the following for each camera.
i. Make/Model
ii. Serial number
5. Site Entry:
a. To gain entry onto site, Contractor personnel shall be
i. Listed on an effective EAL.
ii. Identified by Escort Official.
iii. Able to produce, for verification, the exact form of ID given for the EAL process.
iv. Submit to physical and electronic search of person and materials.
v. Physically escorted on-site by an authorized Escort Official and remain under constant escort surveillance while on site.
vi. Not in possession of any banned electronic devices.
vii. In possession of equipment/cameras listed on an effective EAL.
b. Upon arrival, the Escort Official will identify all Contractor personnel and verify identifications.
c. Contractor personnel not listed on the EAL or those who cannot provide proper identification shall not be permitted on site.
6. Vehicles/Equipment:
a. Contractor vehicles and equipment listed on an effective EAL will be allowed to park inside the security fence to support the work under this contract and shall be searched by Security personnel prior to entry.
i. The Contractor shall obtain approval from 90 CES/CEM prior to leaving vehicles and equipment parked overnight.
Overnight parking inside the security fence at the LFs will not be allowed.
ii. Contractor vehicles and equipment shall be placed so as not to interfere with gates, emergency escape routes, antenna, and other above ground structures.
b. The access road from the main road to site is controlled by the U.S. Air Force. The area adjacent to the access road is private, federal, state, or county property.
i. The Contractor shall obtain approval from 90 CES/CEM prior to parking vehicles and equipment on the access road.
Vehicles parked on the access road shall be clear of the perimeter fence or gate by a minimum of twenty-five feet (25’).
7. Contraband:
a. The Contractor shall ensure contraband items are not brought onto site by Contractor personnel.
The following items are considered contraband on MAF/LF sites.
i. Privately owned firearms to include rifles, shotguns, handguns, air/pellet guns, and sling shots.
ii. Privately owned ammunition or unauthorized ammunition.
iii. Knives less than four inches in length are permitted.
iv. Explosives, except for official use or storage.
v. Illegal drugs or controlled substances.
vi. Equipment/cameras not listed on an effective EAL.
b. Cellular phones are permitted in certain areas; however, the use of photographic capabilities is never permitted. The Escort Official and/or Security personnel will identify areas where cellular phones are/are not permitted and will confiscate improperly used cellular phones.
8. Anti-Terrorism:
a. Notifications: If the Contractor (contract employees/subcontractors) identify any suspicious activity, they shall contact the Base Defense Operations Center (BDOC) at 307-773-3501 (on-base)/Missile Security Control (MSC) at 307-773-2701 (off-base) and notify the CO and 90 CES/CEM that they contacted the BDOC and/or MSC.
b. Training: Contractor employees that require routine physical access to a Federally-controlled facility or military installation shall complete Level I antiterrorism awareness training within thirty (30) calendar days of requiring access and annually thereafter and send a copy of their employees’ training certificate(s) to the CO. Training is located at Joint Knowledge Online (JKO) website: https://jkodirect.jten.mil/Atlas2/page/login/Login.jsf
9. F.E. Warren AFB Communications: The majority of work will be at areas where commercial phone service is not available. The following phone numbers are provided for assistance in conducting on-base telephone communications.
OFFICE NUMBER
Emergency 911
Base Operator (307) 773-1110
Visitor Control Center (VCC) (307) 773-3694
Contracting Office (307) 773-3411/5751
Fire Department Tech Services (307) 773-5528
Civil Engineer Squadron (CES) (307) 773-3600
CES Missile Engineering (307) 773-2438
CES Customer Service (307) 773-3175
CES Environmental (307) 773-2594
Missile Wing Safety (307) 773-1842
Bioenvironmental Engineering (307) 773-3088
10. Interrupted Site Access: If existing access to the site is to be temporarily blocked, temporary access shall be properly provided by the Contractor. The Contractor shall notify the CO twenty-one (21) calendar days prior to any interruption of access to the site. The date, site(s) affected, length of time, and alternate entry method shall be submitted on a Site Interruption Plan for approval.
11. Vacating The Work Area: During exercises, natural disaster, and national emergencies or for security reasons, the Contractor may be required to vacate a work area.
https://jkodirect.jten.mil/Atlas2/page/login/Login.jsf
12. Staging/Storing: Materials and equipment not stored at Contractor’s facilities shall be stored on approved Air Force property or approved adjacent private or public properties.
a. Staging/Storing on Air Force Property:
i. The Contractor shall obtain approval from 90 CES/CEM prior to storing on Air Force property. Unkept, insecure, or unsightly storage shall not be allowed.
There is limited facility storage space at the MAFs and shall only be allowed on a case-by-case basis.
There is no facility storage space at the LFs.
ii. A storage plan may be required if storage containers are to be left on or near the site, for security considerations.
b. Staging/Storing on Adjacent Properties:
i. Contractors not storing on Air Force property shall store on adjacent private or public properties within the Limit of Potential Ground Disturbance as shown in Attachment 1.
ii. The Contractor shall obtain written consent of the landowner or leaseholder.
13. Adjacent, Private, &/or Public Property/Landowners/Leaseholders: Contractor shall obtain written agreements and lien releases with adjacent private and public landowners and leaseholders when operations require use of these properties for storage or access to Air Force property. Landowner Agreements will allow the use of property by Contractor, and the lien releases shall release the Air Force from any damage to private property because of Contractor operations. Where leaseholders are present on the property, the signatures of both landowners and leaseholders are required. Copies of agreements and lien releases shall be supplied to the CO prior to the start of work on each site. The Contractor will not be allowed to start work on a site until agreements are in place.
14. Operational Security (OPSEC): The Contractor shall adhere to the following minimum requirements in support of this requirement:
a. All contractors, subcontractors, their employees, associates, and consultants who have access to critical information and indicators shall comply with the Air Force-sponsored Operations Security (OPSEC) program.
b. OPSEC is an information-related capability that preserves friendly essential secrecy by using a process to identify, control, and protect critical information and indicators. If critical information and indicators are disclosed, it could allow adversaries or potential adversaries to identify and exploit friendly vulnerabilities leading to increased risk to mission failure or the loss of life. The desired effect of OPSEC is to influence the adversary’s behavior and actions by reducing the adversary’s ability to collect and exploit critical information and indicators about friendly activities.
c. Responsibilities:
i. The Contractor shall ensure employees receive OPSEC education that includes an overview of the OPSEC process; the definition of OPSEC; its purpose; what is critical information; the individual’s role in protecting critical information; and the general adversary threat to the AF’s critical information. Additionally, OPSEC education shall include updated threat information, changes to critical information and indicators, new procedures and/or OPSEC measures implemented, altered, or deleted by the organization.
ii. DoD Contractors with OPSEC requirements or those who have access to critical information and indictors shall complete initial and annually recurring refresher training.
Accomplishment of initial OPSEC training shall not exceed ninety (90) calendar days from initial assignment to a contract with OPSEC requirements. Access to mission-critical information will not be allowed until OPSEC education has been completed and documented.
iii. OPSEC education is a continuous requirement. The host unit OPSEC coordinator shall track OPSEC training statics to include the personnel working on the contract, when each individual has received the required initial OPSEC training, and when refresher training is due and/or completed.
iv. The Contractor’s personnel shall not discuss government operations in public or over unprotected or unencrypted communications. Controlled unclassified information (CUI) may only be transmitted as directed in this SOW.
v. The Contractor shall not post to company websites, publications, newsletters, or any other media any images, data, or any other information that reveals sensitive government operations, personnel, equipment, and/or classified or controlled unclassified information. When in doubt, the company press release related to this contract should be coordinated through the COR or CO, as applicable.
vi. Prior to seeking approval through F.E. Warren AFB Public Affairs, any information to be released outside of official U.S. Government channels, via any media to include electronic communication, shall be approved through an OPSEC review. All personnel shall promptly report OPSEC-related incidents, issues, and concerns to the host-unit OPSEC coordinator.
vii. The Contractor shall restrict access to those individuals with a valid need-to-know who are actually providing services under the contract. Further dissemination to other contractors, subcontractors, or any other government agencies and private individuals or organizations is prohibited unless authorized in writing.
viii. Because observation of events, operations, physical changes, etc. may reveal National Security Information, specific restrictions are needed to preclude unintentional release of this information to unauthorized parties. Unauthorized disclosure and transfer of National Security Information is punishable under 18 USC§793. Therefore, the Contract Personnel shall not disclose to unauthorized third parties, post to unofficial sites to include Social Networking sites any images, data/information, or observed events that reveal sensitive government operations, personnel, equipment, including but not limited to Tactics, techniques, and procedures, production, work schedules, any visible or concealed modifications, upgrades, additions to vessels, aircraft, or weapons or equipment; increases, change, or decrease in work/deployment frequency or government personnel, vehicles, vessel, and/or aircraft movements; specialized equipment orders, deliveries, shipments, etc. Unauthorized disclosures and attempts to solicit this type of information by unauthorized third parties or others not affiliated with this contract shall be reported to the COR or CO, as applicable.
Government issued badges, identification shall be removed and/or concealed from plain sight when off base and shall not be left in vehicles or unprotected areas.
Badges and passes may not be duplicated, copied, or loaned to others. Lost or stolen identification badges, vehicle passes, etc., will be immediately reported to the COR, CO, and/or installation Security Office.
15. Controlled Unclassified Information (CUI):
a. Contractors shall follow CUI safeguarding and dissemination controls in accordance with Part
2002 of Title 32 CFR DoDI 5200.48, Controlled Unclassified Information; and DoDI 5200.48_DAFI 16-1403, Controlled Unclassified Information.
i. Unlike classified information, an individual or organization generally does not need to demonstrate a need-to-know to access CUI, unless required by a law, regulation, or government-wide policy, but shall have a lawful government purpose for such access.
b. Marking Requirements: Contractors shall follow CUI marking requirements in accordance with DoDI 5200.48 and DoDI 5200.48_DAFI 16-1403.
c. Dissemination: Contractors shall follow CUI dissemination requirements in accordance with DoDI 5200.48 and DoDI 5200.48_DAFI 16-1403.
d. Storage: Contractors shall follow CUI storage requirements in accordance with DoDI 5200.48 and DoDI 5200.48_DAFI 16-1403.
i. During work hours, steps shall be taken to minimize the risk of access by unauthorized personnel, such as not reading, discussing, or leaving CUI information unattended where unauthorized personnel are present.
ii. After working hours, CUI information will be stored in unlocked containers, desks, or cabinets if the government or government-contract building provides security for continuous monitoring access. If the building security is not provided, the information shall be stored in locked desks, file cabinets, bookcases, locked rooms, or similarly secured areas.
e. Transmission: Contractors shall follow CUI transmission requirements in accordance with DoDI 5200.48 and DoDI 5200.48_DAFI 16-1403.
i. DoD SAFE shall be the primary method of submitting information and documentation.
f. Disposition: Contractors shall follow CUI disposition requirements in accordance with DoDI
5200.48 and DoDI 5200.48_DAFI 16-1403.
i. Record and non-record copies of CUI documents will be disposed of in accordance with
Chapter 33 of title 44, U.S.C. and the DoD Components’ records management directives.
When destroying CUI, including in an electronic form, agencies shall do so in a manner making it unreadable, indecipherable, and irrecoverable. If the law, regulation, or government-wide policy specifies a method of destruction, agencies shall use the method prescribed.
ii. Record and non-record copies of CUI documents may be destroyed by means approved for destroying classified information or by any other means making it unreadable, indecipherable, and irrecoverable the original information such as those identified in NIST SP 800-88 and in accordance with Section 2002.14 of Title 32, CFR.
g. Disclosure: Contractors shall follow CUI disclosure requirements in accordance with DoDI
5200.48 and DoDI 5200.48_DAFI 16-1403.
i. Contractors shall follow CUI disclosure requirements in in accordance with DoDI
5200.48 and DoDI 5200.48_DAFI 16-1403.
PRINCIPLE FEATURES OF WORK PER CSI DIVISION
NOTE: Refer to this Statement of Work, drawings, and attachment for complete details of work. This scope is a general overview of intended work.
CSI 01 – General Requirements
1. Project Scheduling: The Contractor shall submit project schedule to the CO within fifteen (15) working days after award of the Contract.
a. The project schedule will principally be based on the arrival of the new UST.
i. UST must be ordered by NTP plus seven calendar (7) days.
ii. All environmental sampling must be completed by NTP to plus thirty-five (35) calendar days.
iii. All environmental testing, analysis, reporting, and recommendations by NTP plus fifty
(50) calendar days.
iv. D2 access road is to only be closed between UST delivery to contractor plus fifty (50).
Closed access road is roadway inaccessible, no continuous bearing surface for standard wheeled vehicles, no stone layer at defined final grade with one foot (1”) depth, or otherwise not passable by all FE Warren wheeled vehicles, or as determined by 90
CES/CEM.
b. All project activities and / or requirements with be coordinated with the CO and 90 CES/CEM to verify that work can be performed as scheduled before traveling to the work site.
i. Provide a minimum of ten (10) working days’ notice, in writing, before beginning work.
ii. Provide a means for contact after normal working hours for notification of emergency changes to the schedule.
iii. If work is not coordinated as stated, Air Force personnel may not be available, work may not be permitted, and the Government shall not incur any additional cost as a result.
c. Working hours will be between the hours of 7:30 a.m. (start processing on site) and 4:00 p.m.
(terminated work off site) excluding Saturdays, Sundays, and Federal Holidays. An Escort
Official (i.e. 90 CES/CEM Inspector or other) will be provided during these work hours.
Processing onto and off site may require approximately thirty (30) minutes each and shall not be considered delay time.
i. Recognized Federal Holidays include:
New Year's Day (January 1).
Birthday of Martin Luther King, Jr. (third Monday in January).
Washington's Birthday (third Monday in February).
Memorial Day (last Monday in May).
Juneteenth National Independence Day (June 19).
Independence Day (July 4).
Labor Day (first Monday in September).
Columbus Day (second Monday in October).
Veterans Day (November 11).
Thanksgiving Day (fourth Thursday in November).
Christmas Day (December 25).
d. AF Form 3064 Contract Progress Schedule and AF Form 3065 Contract Progress Report shall be submitted monthly, or more frequently if required.
2. Submittals: Prior to starting any work and in accordance with AF Form 66 Schedule of Material
Submittals (aka “Submittal Register”), submit documentation (e.g., EAL information, plans, agreements, specifications, SDS, etc.) on AF Form 3000 Material Approval Submittal to the CO via
DoD SAFE in accordance with the requirements of these specifications.
a. Submittals shall be provided as one (1) searchable electronic copy via DoD SAFE. Submittals shall be marked with the appropriate classification.
b. Each Contractor-supplied item shall be submitted for approval and approved by the CO prior to installation. In no case shall materials be incorporated into the work unless prior written approval is obtained from the CO.
c. Include outlines, dimensional, assembly and subassembly drawings, parts list and other data required to completely describe each item to be used.
d. When more than one model, series or design is illustrated on any one submittal sheet, the item of intended use shall be highlighted and clearly marked with an arrow or asterisk to eliminate confusion as to the product to be approved. Any materials and/or methods not in strict conformance with the requirements of this contract shall also be submitted for review and approval.
e. All submittal information shall be provided by the Contractor, not less than forty five (45) working days prior to any site work or by the date determined by the CO at the pre-construction meeting. A signed and dated copy of the submittal shall be returned to the Contractor after approval or disapproval.
i. Exception for environmental sampling specified to be completed by NTP plus thirty-five
(35) calendar days.
3. Shop Drawings: Shop drawings, or other drawings, shall be submitted for all items or components to be fabricated or assembled and requiring detail drawings more than, or to complement, the general drawings and details included in the plans and / or SOW.
a. The plans shall be supplemented by shop drawings as necessary to adequately control the work.
Shop drawings may consist of drawings, diagrams, Safety Data Sheets (SDS), illustrations, schedules, calculations, or other data prepared by the Contractor, subcontractor, manufacturer, supplier, or distributor which illustrate specific portions of the work to be fabricated or installed in accordance with the plan details and specifications.
b. Any work done prior to approval of shop drawings shall be done at the Contractor's own risk.
4. Product Data: Manufacturer’s product data for all manufactured or processed products, components, devices, or distinct units shall be submitted by the Contractor for review prior to installation.
a. Product data includes catalog sheets, brochures, SDS, diagrams, schematics, schedules, performance starts, illustrations, specifications, and any other standard descriptive data.
b. All product data submitted shall be clearly marked to identify pertinent materials, products, or models to be incorporated in the work.
i. All dimensions, clearances, tolerances, performance characteristics, specifications, wiring diagrams, and other such pieces of information shall be clearly marked or highlighted.
5. Certificates of Compliance: A Manufacturer's certificate of compliance for all materials to be incorporated in the work shall be submitted to the CO prior to execution of the work.
a. Certificates shall certify compliance with project specifications, applicable reference standards or specifications, and test data requirements as required.
b. Certificates shall further contain the name, title and signature of the individual certifying the product, and the name and address of the corporation or business supplying the product and certificate.
6. Test Results: The Contractor shall complete testing in accordance with all project specifications, applicable State/Federal/Local rules or regulations, and industry standards (ASTMs, ACI, AASHTO) or manufacturers’ recommendations and submit results to the CO.
7. Quality Control: The Contractor shall provide and maintain an effective quality control program.
a. The Contractor shall comply with applicable references, standards, specifications, and manufacturers’ specifications and or recommendations, listed in Appendix 1.
i. The Contractor shall request clarification from the CO if the manufacturers’ instructions conflict with contract documents before proceeding.
8. Utility Services: The Contractor shall provide all utilities, to include but not limited to portable generators, water (drinking and construction), and phone services for Contractor personnel, as needed.
a. When working at the MAFs/LFs, limited utilities are available.
i. At the LFs, portable latrines are stationed and will be available for use by Contractor personnel.
b. The Contractor shall provide site facilities for lunch and break areas, as needed.
9. Equipment: Provide all equipment necessary to accomplish the contract work. Non-standard/non-hand-held equipment must be listed on an effective EAL.
a. Power equipment shall be equipped with safety, noise limiting, and fume control devices. The equipment shall be in a safe and efficient operating condition.
b. Only experienced operators shall be permitted to operate the equipment.
c. Plug-in power tools are preferred as wireless power tools are only permitted in certain areas.
d. Cameras are permitted in certain areas if listed on an effective EAL.
10. Excavation: No excavation, regardless of depth, will begin without first obtaining an approved AF
Form 103 Base Civil Engineering Work Clearance Request (aka “Dig Permit”). The Contractor shall submit Dig Permit request(s) to 90 CES Customer Service (307-773-3175) in Building 322 thirty (30) calendar days prior to the planned excavation date. Permits shall be renewed by the Contractor every fourteen (14) calendar days.
a. The Contractor shall provide the following to the Customer Service when planning an excavation:
i. A drawing showing the area to be excavated.
90 CES/CEM can provide an electronic site map to the Contractor for markup.
ii. The purpose of the excavation.
iii. Name, phone number, and organization of the Contractor’s point of contact.
b. The Contractor shall review the permit, keep signed copy on site and shall be responsible for maintaining utility markings during excavation.
c. The Contractor shall notify 90 CES/CEM prior to any excavation.
i. If ground water or landfill debris is encountered, the Contractor shall suspend excavation and notify 90 CES/CEM.
d. Exploratory excavation by hand or vacuum is required within five (5) feet of either side of marked underground utilities.
i. Hand digging or vacuum excavation is required when crossing underground utilities.
ii. If excavation is required parallel and within five (5) feet of an existing utility, exploratory excavation shall be performed by hand or vacuum until the location of the utilities is physically confirmed.
iii. After the location of the utility is physically confirmed, excavation may be performed by machine.
e. Exploratory potholes in roadway areas shall be restored using a flowable fill mixture.
i. In other areas, native backfill material shall be used. The surface condition shall be restored to the pre-existing state.
f. Items encountered and damaged within five (5) feet on either side of a marked line or around a marked items shall be repaired by the Contractor.
i. Items encountered and damaged outside of five (5) feet on either side of a marked line or around a marked point shall be repaired by the Air Force.
ii. In either case, the Contractor shall notify 90 CES/CEM immediately if any damage occurs.
11. Burning/Welding: The Contractor shall obtain an AF Form 592 Hot Work Permit (aka “Burn
Permit”), at least three (3) working days prior to work.
a. Coordinate with the onsite Escort Official or contact 90 CES/CEM at (307) 773-2438 for requirements, initiation, and completion of permit.
b. Contractor shall have the completed permit control number prior to any burning/welding operations.
12. Environmental Compliance: The Contractor is responsible for complying with the State of
Nebraska’s environmental quality regulations, and the Environmental Protection Agency (EPA) Region
7 or 8 Office in Denver for any National Pollutant Discharge Elimination System (NPDES)
Construction General Permits.
a. If a permit is not required by the affected State or Federal agency with jurisdiction on federal sites, the Contractor shall provide written documentation referencing reason for waiver.
13. Green Procurement Program (GPP): In performance of this contract, contractors shall use EPA designated recycled content products, Information Technology (IT) Energy Star products/appliances, Federal Energy Management Program (FEMP) Designated Energy Efficient Low Stand By Power products/appliances, U.S. Department of Agriculture (USDA) Bio based/Bio preferred products, Environmentally preferable products, Electronic Product Environmental Assessment Tool (EPEAT) registered products, Water Sense or other water efficient products, non- or Low Ozone depleting substances under the Significant New Alternatives Policy (SNAP), non or Low toxic or hazardous constituents (e.g. non-VOC paint) and any other environmentally sustainable product/method, to the greatest extent possible.
14. Hazardous Materials: The Contractor shall coordinate all hazardous materials (HAZMAT), to include each compound or chemical intended to be utilized on the site, with 90 CES Environmental
(307-773-2594) for review and approval prior to delivery and use on the site.
a. Hazardous material is defined in Federal Standard, FED/STD-313F (Tables I and II). The definition of materials presenting a health hazard or physical hazard is found in 29 CFR 1910.
b. Required HAZMAT documents shall be completed by a qualified individual.
c. The HAZMAT approval documentation shall be maintained on the site and all workers shall familiarize themselves with their contents.
d. The Contractor shall be responsible for establishing a system, which tracks the procurement, delivery to site, installation, and disposal of all hazardous materials including proper disposal documents.
e. The Contractor shall be held responsible for proper cleanup and disposal of any hazardous and
/ or toxic materials spilled while completing the work in this contract. All cleanups shall be accomplished in accordance with applicable Local, State, and Federal regulations at no cost to the Government.
f. No ozone depleting substances shall be used while completing the work in this contract.
i. This includes the exterior/interior of adjacent buildings and parking lot/access road.
15. Safety: The Contractor is solely responsible for all safety on the project including, but not limited to traffic control, trenching, confined space entry, equipment and materials storage, and compliance by all employees with Base and Department of War regulations.
a. Particular care shall be exercised in connection with the operation of vehicles and other equipment on the site.
b. Project safety shall be coordinated with the Air Force prior to commencing service.
c. The Contractor shall notify the CO of all modifications to the Safety Plan.
d. Contractor shall comply with the rules, regulations, standards, and requirements of the
Department of Defense (DoD) AFI 32-7002, Environmental Compliance and Pollution
Prevention, Section 1.3 for Statutes and Regulations (http://www.e-publishing.af.mil ), EPA
40 CFR Subchapter I, Part 260-268 and FED-STD-313C, Tables I and II and 20 CFR 1910, the
Occupational Safety and Health Administration (OSHA www.osha.gov ), USCE manual EMI
385-1-1, and other applicable Federal, State, and Local requirements regarding disturbing or removing hazardous materials.
e. The federal government is not exempt from compliance with environmental and labor regulations.
f. The Contractor shall notify the CO and 90 CES/CEM of any emergency situation(s).
g. The Contractor shall educate each employee to ensure clear understanding of the following:
i. A review of hazards inherent in the work environment and the precautions required to reduce the hazard.
ii. The Contractor shall always maintain a complete first aid kit.
Location of first aid and other emergency facilities shall be identified.
iii. Detailed description of what to do in case of injury, fire, or identification of a safety hazard.
iv. Review of daily cleanup procedures, including location and review of company safety rules (either posted or handout).
v. The Contractor shall provide all personal protective equipment (PPE) including, but not limited to, ear plugs, goggles, face shields, gloves, safety shoes, and hard-hats. Complete instructions on where and how to use all PPE shall be given by the Contractor.
vi. All personnel shall wear PPE when required by the Contractor or by 90 CES/CEM.
vii. Hospitals near various sites are noted below for emergency purposes.
Cheyenne Regional
Medical Center
Regional West
Medical Center
Sterling Regional
Medical Center
214 23rd St
Cheyenne, WY 82001
307-634-2273
4021 Avenue B
Scottsbluff, NE 69361
308-635-3711
615 Fairhurst St
Sterling, CO 80751
970-522-0122
16. Site Conditions: Daily, or more often as necessary, clean all work areas of debris as well as Contractor tools, equipment, and other materials.
a. This includes the exterior/interior of adjacent buildings and parking lot/access road.
b. The work site shall be returned to a like condition in which it was found prior to start of work or in better condition than commencement of work to the satisfaction of the CO and 90
CES/CEM.
c. Damage to Air Force property caused by Contractor vehicles, operations, equipment, or personnel shall be repaired at the Contractor's expense with no additional cost to the http://www.e-publishing.af.mil/ http://www.osha.gov/
Government. Skilled craftsmen in the trade shall repair such damage to the satisfaction of the
CO and 90 CES/CEM.
i. Any suspected damage to Air Force property shall be documented and submitted to CO with a detailed description of the type and location of damage within seventy-two (72) hours of damage.
d. The contractor is responsible for clearing or mitigating all slip, trips, or fall hazards for safety of Service Members and all federal employees present on site.
17. Request for Information (RFI): The Contractor shall submit RFIs to the CO via a Request for
Information form prior to any work proceeding.
a. The RFI shall include whether the information or solution requested will be an increase, decrease, or no change in contract cost.
b. Any work done prior to approval of the RFI shall be done at the Contractor's own risk.
18. Modifications: Any change in site conditions or work encountered outside the scope of this contract shall be presented to the CO.
a. A contract modification will be issued by the CO prior to any work proceeding.
19. Red Line Drawings: The Contractor shall submit post-construction (aka “red-lined”) drawings to the
CO prior to project close out.
a. Drawings shall include all changes, revisions, discrepancies, or clarifications encountered during construction.
b. Drawings shall be complete, showing all dimensions, geometry, locations, connections, and operations of elements.
i. The Contractor shall submit the corresponding digital files from electronic drafting software (e.g., AutoCAD or Autodesk) without proprietary features.
c. Drawings shall be marked with the appropriate classification.
20. Warranties: Thirty (30) calendar days prior to final acceptance of each delivery order, the Contractor shall obtain and submit written warranties for each equipment, product, good, or service supplied under this contract.
a. Each warranty shall include the name, address, and telephone number of the guarantor’s representative, who will honor the guarantee during the written guarantee period and will provide the service prescribed by the terms of the guarantee.
b. The equipment installed under this contract shall be guaranteed against defective materials, installation, and workmanship for a period of not less than twelve (12) months from the date of acceptance, either for beneficial use or final acceptance, whichever is the earliest, but not before the system has passed all specified tests and been deemed acceptable for operation.
c. The means and methods the contractor elects to use on to install all manufactured materials will not void the manufacturer’s warranty for any reason.
i. If the means and methods the voids the manufacturer’s warranty the contractor will replace the voided manufactured component(s) at no additional cost to the government.