Atch 1_SOW_MAB Runway Repair.docx

DOCX document 42 KB Posted

Attached to
Runway Repair, Moore Air Base, Edinburg, TX
Solicitation number
12639524R0019
Issued by

About this file

This document is a Statement of Work (SOW) for a Design-Build contract to repair the runway at Moore Air Base (MAB) in Edinburg, Texas. The project scope includes developing 65%, 95%, and 100% design documents, and providing construction services to repair portions of runway 14/32, taxiways B, C, and D, and fencing. Key details include:

The Design-Build Contractor will be responsible for all design, construction, and Designer of Record (DOR) services necessary to complete the runway repair project. The contractor will start design using provided 35% design documents and progress through 100% final design. The SOW provides design criteria, project contacts, and other requirements such as submitting shop drawings, coordinating with a new water treatment plant upgrade, ensuring no service interruption, and preparing quality control and safety plans. USDA will provide additional construction inspection and administration services as needed. The project is part of a multi-year runway maintenance plan due to budget constraints, with this phase focused on repairing runway joints and other improvements.

View the file

Other files

File Type Posted
RFIs and Responses.docx DOCX document
RFIs and Responses.docx DOCX document
12639524R0019-0002.pdf PDF
Airfield Repair RFIs.docx DOCX document
Runway Project Sign In Sheet 8-15-24.pdf PDF
12639524R0019-0001.pdf PDF
Atch 3_MAB Runway Study_redacted.pdf PDF
Atch 2_specs and drawings.pdf PDF
12639524R0019.pdf PDF
Atch 4_Federal Construction Wage Rates_Hidalgo County.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation 12639524R0019, Design-Build Project, MAB Runway Repair, Attachment 1

Statement of Work for Design-Build Services August 15, 2024

1.0 PROJECT: Moore Air Base Runway Repair

2.0 LOCATION:

U.S. Department of Agriculture (USDA), Animal and Plant Health Inspection Service (APHIS), Plant Protection Quarantine (PPQ), Moore Air Base (MAB), 22675 N. Moorefield Road, Edinburg, Texas 78541

3.0 PROJECT BACKGROUND:

Moore Air Base (MAB) was originally constructed in the early 1940s and located fourteen miles northwest of Mission, Texas. The Base occupies approximately 630 acres area and consists of multiple structures, including aircraft Hangar.

MAB consist of three concrete Runways in a triangular configuration with each Runway being approximately 5,000 feet long and 300 feet wide. Five concrete taxiways currently connect the Runways to the flightline apron.

The existing Hangar, with an approximately area of 22,000 SF, parks two Baron G58, Cessna 206 and Cessna 188 aircrafts. At present, the facility operates up to 10 flights a day with these aircraft supporting the Plant Protection and Quarantine (PPQ) operations along the southern border to release by rearing sterilized fruit flies on-site and aerially depositing them in known areas of infestation.

USDA decided to repair the existing pavement including drainage edge, replace joint sealant, other improvements necessary to avoid potentially hazardous conditions for the aircraft and excessive maintenance requirements for the facility. In October 2022, Johnson McAdams Firm completed a study of the MAB Runway repair and recommended a multi-year maintenance plan based on budget availability. Accordingly, due to budget constraints, USDA decided to split the project into two phases. Phase I (current phase) constitutes repairing runway joints in portions of runway 14/32, taxiway B, taxiway C, and taxiway D, and fencing.

4.0 PROJECT SCOPE:

The purpose of this SOW is to provide design, all labor, materials, equipment, and DOR services to deliver a Design-Build of MAB Runway repair in accordance with the contract documents.

The Design-Build Contractor's work responsibility shall include Design, DOR, and Construction services necessary to provide all work as specified by the documents for the construction of the MAB Runway Repair .

The design task consists of developing the 35% Design documents, prepared by JMc dated 08/14/2024, to a full range construction document per the Submission schedule in Section 4.1.

The Design-Build Contractor shall start design using the provided documents listed below through 100% Final design.

Also, A/E shall include details of grading the edges of the Runway to mitigate significant turf build up that could restrict drainage from the pavement. Also, A-E shall submit an updated cost estimate based on current cost parameters.

The Design-Build Contractor shall be responsible for completion of the following Design task for the Construction of the MAB Runway Repair:

4.1 Design Submissions: The A/E shall provide the following services marked by an "X".

[X] 65% Design services developed from the 35% document prepared by Johnson McAdams.

[X] 95% Design submission for review and comment [X] Final /100% submission for interim review and submission

5.0 PROJECT DATA:

5.1 DESIGN CRITERIA:

The following information and design criteria are available for the A/E’s use and compliance:

· USDA Facilities Design Standards (2024) 242.1M-ARS 2024.pdf (usda.gov)

· USDA Directives https://www.usda.gov/directives/directives-categories

· Environmental Management https://www.usda.gov/directives/dr-5600-005 (2022)

· USDA Policies and Procedures on Biohazardous Waste Decontamination, Management, and Quality Controls at Laboratories and Technical Facilities (2009) https://www.usda.gov/directives/dr-9630-001

· Security, Suitability, and Incident Response Procedures for High and Maximum Containment Facilities (2022) https://www.usda.gov/directives/dm-9610-001

· Real Property Management (2023) https://www.usda.gov/directives/dr-5100-004

· Whole Building Design Guide Sustainability (2024) Sustainable | WBDG - Whole Building Design Guide

· Leadership in Energy & Environmental Design (LEED) (2024) LEED scorecard | U.S. Green Building Council (usgbc.org)

· Preferred Biobased Products (2024) BioPreferred|Product Categories

· Comprehensive Procurement Guidelines for Construction Products (2024) Comprehensive Procurement Guidelines for Construction Products | US EPA

· Sustainability and Environmental Management (2024) Sustainability and Environmental Management | GSA

· USDA Sustainable Buildings Implementation Plan (2022) U.S. Department of Agriculture 2022 Sustainability Plan

· Commissioning Documents: Process, Contents, And Acceptance (2022) https://www.wbdg.org/building-commissioning/commissioning-documents

· Energy efficient products, environmentally preferable products, Non-ozone depleting substances, Recycled content products, WaterSense and water efficient products) Buy green products | GSA

· Occupational Safety and Health Regulations (Standards - 29 CFR) 1910 | Occupational Safety and Health Administration (osha.gov)

In addition, A-E shall research all applicable codes, the design criteria, regulations and standards.

6.0 PROJECT CONTACTS

6.1 APHIS Contracting Officer (CO)

Jim Roloff

USDA, APHIS, MRPBS, AAMD

250 Marquette Avenue, Suite 410 Minneapolis, MN 55401-2329 Tel. No.: (612) 590-7603 Email: James.G.Roloff@usda.gov

6.2 APHIS Engineering Project Manager (EPM)

Fikru Taye, P.E.

USDA, APHIS, ASD, ESB

4700 River Road, Unit 115 (3A-03-41) Riverdale, MD 20737 - 1238 Tel. No.: (301) 851-2641 E-mail: Fikru.Taye@usda.gov

6.3 APHIS PPQ Facilities Manager (COR/FM)

Gabriel Lopez USDA, APHIS, PPQ Field Operations Moore Air Base 22675 North Moore Field, Building 6407 Edinburg, TX 78541 Tel. No.: (956) 205-7608 Cell No.: (956) 207-9594 Email: Gabriel.Lopez@usda.gov

6.4 APHIS PPQ National Facility Manager (NFM):

Ralph “Randy” O’Neal Plant Protection & Quarantine Raleigh, North Carolina 27606 Office (919) 855-7363 Moblie (919) 559-6152 Ralph.w.oneal@usda.gov

6.5 APHIS PPQ Program Specialist

Martha E. Garza USDA, APHIS, PPQ Field Operations 22675 North Moore Field Building 6407 Edinburg, TX 78541 Tel. No.: (956) 205-7604 Cell No.: (956) 292-1073 Email: Martha.Garza@usda.gov

7.0 OTHER PROJECT REQUIREMENTS:

7.1 Prior to construction, D-B Contractor shall submit manufactures’ catalog, cut-sheets, and Shop drawings for review and approval by the Design of Record. One set of shop drawings will be retained by the USDA-APHIS Engineering Branch.

7.2 The D-B Contractor shall examine all the documents and visit the site to fully understand all the conditions and limitations applied to the work. No subsequent cost allowance will be made to the D-B Contractor for neglect of the existing conditions

7.3 The D-B Contractor shall prepare and submit reports, bill of materials, product literature, drawings, specifications, quality control schedules, safety plan and construction costs.

7.4 The D-B Contractor shall comply with national codes, Environmental Protection Agency (EPA) regulations, and federal, state, and local laws.

7.5 The D-B Contractor shall coordinate with the new WTP upgrade to identify and report findings to the COR.

7.6 D-B Contractor shall ensure no service interruption occurs during construction. Coordinate staging area with security access for delivery and storage of material and equipment.

7.7 The D-B Contractor shall prepare and submit a Quality Control Schedule [QCS] and Project Safety Plan [PSP] to address the project. The QCS and PSP are intended to document the entire project from beginning to end.

7.8 The D-B Contractor is responsible for safety and shall comply with all local labor laws, regulations, customs and practices pertaining to labor, safety and similar matters. The D-B Contractor shall promptly report all accidents resulting in lost time, disabling, or fatal injuries to the COR.

7.9 The D-B Contractor shall at all times keep the work area free from accumulation of waste materials. Upon completing construction, the D-B Contractor shall hand over project site in a clean and orderly condition acceptable to the COR.

8.0 SUBMITTAL DISTRIBUTION:

Construction shop drawing submittals shall be reviewed and approved by the Designer of Record. A copy of the approved shop drawings shall be submitted as follows:

Contracting Officer1 electronic copy
Program Project Manager1 electronic copy
Engineering Project Manager6 paper copies

Upon completion of construction, D-B Contractor shall submit an As-Built Record set of drawings in AutoCAD (*.dwg. files) format as follows:

Program Project Manager1 copy
Engineering Project Manager1 copy, and 1 CD-ROM

9.0 TASK IDENTIFICATION

The Design-Build Contractor Services Contractor shall be responsible for completion of the following design tasks:

Design Tasks

The Design-Build Contractor shall provide the full range of services associated with the production of traditional design including:

65% Design services developed from completed 35% design submission that has already been completed, 95% Preliminary Construction Documents, and 100% Final Construction Documents.

The 65% Design services submittal shall include construction cost estimates that include all estimated general and special conditions, overhead, profit, other costs of construction.

Construction Tasks

Preconstruction Conference. The Design-Build Contractor, with the assistance of their subcontractor(s), shall conduct a preconstruction conference with USDA prior to the start of construction.

The Design-Build Contractor shall continuously monitor the construction activities of its construction sub-contractors(s). Performance shall be reviewed for compliance with all contractual terms, conditions, drawings, specifications, and codes.

The D-B Contractor’s superintendent shall observe the construction in progress as the nature of the work requires. The sub-contractors shall work closely with the Design-Build Contractor Project Superintendent to ensure that the construction work meets the requirements of the construction contract and construction documents.

Designer of Record Services

· Approve shop drawings, submittals, certificates, schedules, and results of quality control tests. Provide one information copy of all approvals to the CIC.

· Coordinate with CO, COR and respond to requests for information (RFI).

· Evaluate and provide written response to all Requests For Information (RFIs) from the contractor.

· Provide one information copy of all answered RFIs to the COR and CIC.

Construction Inspector Contractor Servies

· USDA will task additional supplement to DOR/CIC services to provide minimal DOR services, respond to RFIs and conduct other limited scope of Construction administration services upon approval by USDA.

· Additional CIC will be performed by COR as necessary.

· Design-Build Contractor should participate in Critical Inspections listed below [X] Inspection should be Coordinated with CO, COR, DOR and CIC.

[X] Per A-E’s Discretion [3 days] [X] Mid-point Inspection [X] Final Inspection

Final Inspection, Acceptance, and Closeout : The A/E shall Coordinate final inspection with DOR, CIC and COR image1.png