12639524R0019-0002.pdf

PDF 322 KB Posted

Attached to
Runway Repair, Moore Air Base, Edinburg, TX
Solicitation number
12639524R0019
Issued by

About this file

This document is an amendment to Solicitation 12639524R0019 for a Design-Build project to repair the runway and taxiway at Moore Air Base in Edinburg, Texas. The amendment replaces page 2 of the Statement of Work. The key details are:

The purpose of the project is to provide design, labor, materials, equipment, and construction services to repair the runway at Moore Air Base. The Design-Build contractor is responsible for developing the 65% design documents from the 35% design provided, as well as submitting 95% and final 100% design submissions for review. The design must comply with USDA Facilities Design Standards (2024). The project scope includes repairing the runway, taxiway, and fencing. The amendment extends the contract period and requires the contractor to include details for grading the runway edges to improve drainage and submit an updated cost estimate.

View the file

Other files

File Type Posted
RFIs and Responses.docx DOCX document
RFIs and Responses.docx DOCX document
Airfield Repair RFIs.docx DOCX document
Runway Project Sign In Sheet 8-15-24.pdf PDF
12639524R0019-0001.pdf PDF
Atch 3_MAB Runway Study_redacted.pdf PDF
Atch 2_specs and drawings.pdf PDF
12639524R0019.pdf PDF
Atch 1_SOW_MAB Runway Repair.docx DOCX document
Atch 4_Federal Construction Wage Rates_Hidalgo County.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

12639524R0019 x x copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

APHIS-MN-126395

08/27/20240002

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

USDA APHIS

250 MARQUETTE AVE

SUITE 410

MINNEAPOLIS MN 55401

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

07/31/2024

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

This amendment is written to replace page 2 of the statement of work. See next page.

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

JAMES G. ROLOFF

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

08/27/2024

Solicitation 12639524R0019, Design-Build Project, MAB Runway Repair, Attachment 1 Amendment 0002 and taxiway D, and fencing.

1.0 PROJECT SCOPE:

The purpose of this SOW is to provide design, all labor, materials, equipment, and DOR services to deliver a Design-Build of MAB Runway repair in accordance with the contract documents.

The Design-Build Contractor's work responsibility shall include Design, DOR, and Construction services necessary to provide all work as specified by the documents for the construction of the MAB Runway Repair .

The design task consists of developing the 35% Design documents, prepared by JMc dated 08/14/2024, to a full range construction document per the Submission schedule in Section 4.1.

The Design-Build Contractor shall start design using the provided documents listed below through 100% Final design.

Also, A/E shall include details of grading the edges of the Runway to mitigate significant turf build up that could restrict drainage from the pavement. Also, A-E shall submit an updated cost estimate based on current cost parameters.

The Design-Build Contractor shall be responsible for completion of the following Design task for the Construction of the MAB Runway Repair:

1.1 Design Submissions: The A/E shall provide the following services marked by an "X".

[X] 65% Design services developed from the 35% document prepared by Johnson McAdams.

[X] 95% Design submission for review and comment [X] Final /100% submission for interim review and submission

2.0 PROJECT DATA:

2.1 DESIGN CRITERIA:

The following information and design criteria are available for the A/E’s use and compliance:

• USDA Facilities Design Standards (2024)

2024-08-27T08:10:32-0500
JAMES ROLOFF

File details come from the government source that posted it. Updated .