This is a Statement of Work for the replacement of an R22 HVAC system in Building 4983 at Joint Base San Antonio, Lackland, issued by the 502nd Civil Engineer Squadron.
The contractor shall remove the existing obsolete Rheem condenser (Model RAWE-180CAZ) and RUUD air-handling unit (Model RHCE-1582X) along with associated R22 refrigerant piping, the Honeywell controller, and incompatible ductwork. The contractor must then provide and install a complete, fully operational, code-compliant HVAC system including new refrigerant-based equipment sized to building load requirements, all electrical components with updated disconnects and wiring, new refrigerant and drain piping with overflow safety devices, unit suspension and mounting hardware, and a DDC controller with BACnet-compatible building automation interface. Installation includes controls integration, programming, testing, verification, and manufacturer's startup and commissioning with a commissioning report and system performance verification. Deliverables include as-built drawings, equipment and materials submittals, O&M manuals, preventive maintenance checklist, and warranty documentation. All work must comply with current UFC, ASHRAE, NFPA, ICC, OSHA, Air Force standards, 29 CFR 1910 & 1926, 48 CFR 52.225-9 and 52.246-12, AFI 32-7086, USACE EM 385-1-1, and base regulations. The contractor is responsible for all delivery, loading, unloading, and storage of materials. Work hours are 0700–1700, Monday–Friday, excluding federal holidays, with minimum one-week advance notice required prior to start. The period of performance is 45 days after award. A one-year manufacturer's warranty on parts, labor, and equipment is required. Final inspection and acceptance will be conducted by the designated Government Point of Contact.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
REPLACE R22 HVAC SYSTEM BUILDING 4983
JOINT BASE SAN ANTONIO, LACKLAND
P a g e 1 | 3
1. INTRODUCTION & BACKGROUND
The 502nd Civil Engineer Squadron requires replacement of the HVAC system in Building 4983 at
JBSA-Lackland. The existing split system operates on R22 refrigerant, which has been phased out, and consists of a Rheem condenser (Model No. RAWE-180CAZ, Serial No. 6698F010904536) and a RUUD air-handling unit (Model No. RHCE-1582X, Serial No. 1140829988299).
This project will remove the obsolete equipment and install a new, fully functional, code-compliant HVAC system equipped with modern Direct Digital Controls (DDC) and BACnet-compatible building automation capabilities.
2. PROJECT SCOPE
The contractor shall provide all labor, supervision, materials, equipment, tools, transportation, and quality assurance necessary to remove the existing HVAC system and install a new system meeting current Unified
Facilities Criteria (UFC), American Society of Heating, Refrigerating and Air-Conditioning Engineers
(ASHRAE), National Fire Protection Association (NFPA), International Code Council (ICC), Occupational
Safety and Health Administration (OSHA), and Air Force standards.
The contractor shall deliver a complete, operational, commissioned HVAC system.
3. EXISTING CONDITIONS
Existing equipment: Rheem Condenser, RUUD Air Handler unit.
• No front-end control system is installed.
• R22 refrigerant system requiring full replacement.
• Existing Honeywell controller and wiring to be removed
4. DETAILED SCOPE OF WORK
4.1 PRE-CONSTRUCTION.
• Conduct a site visit to verify field conditions.
• Coordinate with designated Government Point of Contact (GPOC) at least one (1) week before work begins
4.2 REMOVAL OF EXISTING EQUIPMENT.
• Remove existing air handler unit, condenser, refrigerant piping, and associated components.
• Remove Honeywell controller and wiring.
• Remove ductwork if determined incompatible with the new system.
• Perform lockout/tagout in coordination with designated GPOC.
4.3 INSTALLATION.
Provide and install a complete HVAC system including:
• New refrigerant-based HVAC equipment sized to meet building load requirements.
• All required electrical components, updated disconnects, conduit, wiring, and programming
• New refrigerant piping, insulation, drain piping, and overflow safety devices.
• Unit suspension and mounting hardware.
• DDC controller and BACnet-compatible interface.
• Verification of CAT communication line with designated GPOC.
P a g e 2 | 3
4.4 CONTROLS & INTEGRATION.
• Install and configure DDC controls.
• Ensure BACnet compatibility with GPOC.
• Provide programming, testing, and verification.
4.5 COMMISSIONING.
• Perform manufacturer’s startup and commissioning
• Provide commissioning report and system performance verification.
5. DELIVERABLES.
• As-built drawings.
• Submittals for equipment, controls, and materials.
• O&M manuals for all installed equipment
• Preventive maintenance checklist identifying tasks required by Government
• Warranty documentation.
6. CODES & STANDARDS.
All work shall comply with the latest versions of:
• 29 CFR 1910 & 1926 (OSHA)
• 48 CFR 52.225-9, 52.246-12
• UFC criteria
• AFIs and Air Force Manuals
• USACE EM 385-1-1
• AFCFS
• NFPA, ASHRAE, ICC codes
• Base regulations and Uniform Building Codes
7. SAFETY & ENVIRONMENTAL REQUIREMENTS.
• Comply with all OSHA and EM 385-1-1 safety requirements.
• Provide barricades and warning signs; maintain a clean site
• Identify, track, and report all HAZMAT in accordance with AFI 32-7086
• Submit AF Form 3952 for each HAZMAT item.
• Provide MSDS as needed
8. ADMINISTRATIVE REQUIREMENTS
8.1 BASE ACCESS & TRAFFIC.
• Comply with all base traffic regulations.
• Hands-free devices only while driving
8.2 DELIVERY & STORAGE.
• Contractor is responsible for all delivery, loading, unloading, and storage.
• Government will not accept freight or store materials
8.3 GOVERNMENT-FURNISHED SERVICES.
Water, electricity, and emergency services will be provided.
P a g e 3 | 3
9. HOURS OF WORK.
• Normal work hours: 0700–1700, Monday–Friday, excluding federal holidays.
• All coordination for work will need to be in writing to the designated GPOC.
10. PERIOD OF PERFORMANCE.
• The contractor shall provide a minimum of one (1) week advance notice prior to the start of work.
• Performance of period: 45-days after award.
11. INSPECTION & ACCEPTANCE.
• Final inspection will be conducted by the designated GPOC
• All discrepancies must be corrected prior to final payment.
12. WARRANTY.
Provide manufacturer’s parts, labor, and equipment warranties for a minimum of one (1) from date of completed installation.
END OF STATEMENT OF WORK