This is a Statement of Work (DMSOW) for depot maintenance of the HH-60W helicopter, detailing requirements for Programmed Depot Maintenance (PDM) and Analytical Condition Inspection (ACI) to be performed by a depot facility. The document outlines comprehensive maintenance processes including inspection, repair, and testing requirements with target completion timeframes of 190 calendar flow days for PDM and 220 calendar flow days for ACI inductions.

The DMSOW specifies detailed requirements across six main sections: General Information/Instructions, Delivery/Arrival/Induction, Inspection/Maintenance/Repair Requirements, Assembly/Final Processing, Delivery/Departure, and Depot Field Team Support. Key requirements include aircraft structural inspections, component repairs, system checks, paint/finishing, and functional check flights. The depot facility must maintain technical data libraries, provide engineering support services, handle classified equipment, maintain aircraft records, and submit various reports including weekly status updates and final repair documentation. The work includes both scheduled maintenance and unscheduled repairs, with provisions for Depot Field Teams to provide on-site support at aircraft locations when needed. The program is managed by the AFLCMC/WIUBC Rotary Sustainment Section at Robins Air Force Base, with engineering authority maintained by AFLCMC/WIUE Engineering Branch.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

HH-60W Depot Maintenance Statement of Work (DMSOW)

Revision: Basic

Approved by:

ALAN A. OWENS

HH-60 Sustainment Chief AFLCMC/WIUBC Rotary Sustainment Section Date: 4 October 2024

HH-60W Depot Maintenance Statement of Work (DMSOW)

TABLE OF CONTENTS

Section 1 General Information and Instructions

Section 2 Delivery, Arrival, and Induction of Aircraft

Section 3 Inspection, Maintenance, and Repair Requirements

Section 4 Assembly and Final Processing

Section 5 Delivery and Departure of Aircraft

Section 6 Depot Field Team (DFT) Support

LIST OF FIGURES

Figure 1 Typical DLM Process Flow

Figure 2 Milestone and Schedule Report Formats for Programmed Depot Maintenance (PDM) and Analytical Condition Inspection (ACI)

LIST OF APPENDICES

A HH-60W Depot Maintenance Work Specification (DMSPEC)

B HH-60W List of Sensitive Items for Secure Storage

C HH-60W Checklist for Unit Depot Drop-Off / Pick-Up Procedures

1. GENERAL INFORMATION AND INSTRUCTIONS

1.1. Program Description: This Depot Maintenance Statement of Work (DMSOW) provides an overview of the standard Depot Level Maintenance (DLM) rework requirements for the Air Force HH-60W model rotary aircraft. DLM is the accomplishment of depot-level rework of the HH-60W helicopter airframe and repair of defects to ensure safe operation of the aircraft during its operational life. This section contains general information for the depot facility to manage the HH-60W DLM process.

1.2. Scope: The DLM program includes Programmed Depot Maintenance (PDM) and Analytical Condition Inspection (ACI) aircraft inductions as defined below. Upon completion of the PDM and ACI DLM process, the 720-hour phase inspection requirement is satisfied. The PDM and ACI DLM rework process consists of disassembly of the aircraft to the maximum extent practical to conduct a nose-to-tail inspection of the entire airframe for condition and security with identification and correction of defects in accordance with (IAW) the attached Appendix A, HH-60W Depot Maintenance Work Specification (DMSPEC), HH-60W-24-010-001. The DLM process includes fixed and variable tasks IAW the DMSPEC paragraph 1.5. The DLM program also includes maintenance actions such as component-level rework or test, Time Compliance Technical Order (TCTO) modifications and special inspections, and Unscheduled Depot Level Maintenance (UDLM) drop-in inductions and the deployment of Depot Field Teams (DFT).

1.2.1. PDM is the inspection and correction of defects that require skills, equipment, or facilities not normally possessed by operating locations.

1.2.2. ACI is an in-depth condition inspection to uncover hidden defects that are not detectable through normal inspection programs. ACIs generate data for engineering and technical evaluation of the relative aircraft condition resulting from corrosion, overstress, wear, and other effects caused by aircraft age, operational usage and environmental exposure.

1.2.3. UDLM requirements may include but are not limited to:

• Battle damage repair

• Crash damage repair

• Damage to primary structural elements

• Maintenance induced damage

• Corrosion damage repair and parts replacement

• Hard landing assessments

• TCTO Modifications

1.2.4. Drop-in UDLM will be performed on aircraft or aircraft components received from the aircraft owning activity that require maintenance at a depth and skill level greater than that available at the Organizational/Intermediate (O/I)-level.

1.2.5. DFT UDLM will be performed at off-site owning activity field locations in cases where an HH-60W is not safe for flight. DFTs will be responsible for performing all maintenance related tasks as defined by the individual engineering statement of work disposition IAW T.O. 00-25-107 and Section 6 of this DMSOW.

1.3. Authority: This DMSOW has been reviewed and approved by the AFLCMC/WIUBC HH-60 Sustainment Chief for the United States Air Force (USAF) and is authorized for use on all USAF HH-60W aircraft. Management and execution of the DLM process is the responsibility of the USAF Program Authority (PA) and may be monitored by an on-site USAF Field Authority (FA).

All requirements contained within this DMSOW and the DMSPEC are mandatory unless otherwise directed in writing by the USAF PA or USAF Engineering Authority (EA).

1.3.1. USAF Program Authority (PA): The PA is responsible for maintaining the DLM program management. They are responsible for determining logistic requirements, negotiating Contract and Depot Maintenance Interservice Agreement (DMISA) requirements as applicable, reviewing budgets and funding requirements, and coordinating necessary program and material management to support the DLM process. The PA is responsible for aircraft scheduling and coordinating all program matters with the depot facility, the aircraft owning activities, aircraft gaining custodians, Major Commands (MAJCOM), and other AFLCMC/WIU program office entities. The designated USAF PA is the Special Operations Forces (SOF)/Personnel Recovery (PR) Rotary Division System Program Office (SPO) AFLCMC/WIUBC Sustainment Section, Robins Air Force Base, Georgia. The USAF PA can delegate select authority to an on-site USAF Field Authority (FA) representative for certain tasks. Delegation will be documented and approved per a delegation memo.

1.3.2. USAF Field Authority (FA): The FA is the on-site USAF representative. The FA is responsible for monitoring the DLM process and ensuring compliance with the requirements detailed in this DMSOW and the DMSPEC. The FA shall report to the PA. Select authority may be delegated to the FA via an approved delegation memo.

1.3.3. USAF Engineering Authority (EA): The EA is responsible for Operational Safety, Suitability and Effectiveness (OSS&E) and airworthiness of the aircraft while ensuring all USAF interests are met and all requirements of the DLM process are accomplished IAW the DMSPEC. The EA is also assigned the responsibility and the authority to approve all or portions of in-service engineering functions and technical requirements. In addition, the EA is responsible for monitoring and evaluating the maintenance effort. The EA will determine effectiveness and efficiency of the depot facility in accomplishing the required depot-level maintenance tasks, in maintaining acceptable quality standards, and in meeting required delivery schedules. The EA will assist in determining logistic requirements, negotiating contractual requirements, reviewing budgets and funding requirements, and coordinating necessary program and material management to support the DLM process. The designated USAF EA is the Special Operations Forces (SOF)/Personnel Recovery (PR) Rotary Division System Program Office (SPO) AFLCMC/WIUE Engineering Branch, Robins Air Force Base, Georgia. The EA can delegate certain authority to an on-site engineering entity for certain tasks. Delegation will be documented and approved per a delegation memo.

1.4. Depot Level Maintenance Intervals: The HH-60W aircraft are on a fixed 68-month DLM cycle IAW Technical Order (T.O.) 00-25-4.

1.5. Depot Level Maintenance Process: Detailed policies and guidance not provided within this DMSOW are provided in the DMSPEC. The DMSPEC consists of nine sections and is organized to reflect the rework process flow as follows:

• Section 1 – General Instructions

• Section 2 – Preparation for Induction

• Section 3 – Aircraft Induction

• Section 4 – Structural Inspection Requirements

• Section 5 – Maintenance and Repair

• Section 6 – Preparation for Delivery

• Section 7 – Aircraft Delivery

• Section 8 – Quality Assurance

• Section 9 – Terms and References

1.6. Aircraft Security: The depot facility shall be responsible for the aircraft physical security from time of aircraft arrival from the owning activity until time of aircraft departure to the post- DLM location.

1.7. Sequence of Work: Figure 1 below is a generalization of the DLM process from receipt of the aircraft from the owning activity to the final acceptance and delivery of the aircraft to the gaining custodian.

Figure 1. Typical DLM Process Flow

PREP FOR INDUCTION

INDUCTION

DISASSEMBLY

CLEAN / STRIP

INSPECTION

MAINTENANCE / REPAIR

ASSEMBLY

GROUND CHECKS

FLIGHT TEST

PAINT

PREP FOR DELIVERY

ACCEPTANCE / DEPARTURE

1.8. Flow Days: The target goal for completion of the DLM process of USAF HH-60W helicopters is 190 calendar flow days for PDM inductions and 220 calendar flow days for ACI inductions. If necessary, additional flow day requirements will be negotiated based on the results of the aircraft inspections during the initial 45-day assessment period and a revised Estimated Completion Date (ECD) determined for the aircraft delivery. If additional workload requirements are discovered after the initial assessment period, the depot facility may renegotiate the aircraft flow days and ECD a second time. Any requirement for additional flow days shall be negotiated IAW AFMCI 21-118 Aircraft Maintenance Production/Compression Report (AMREP). The depot facility shall submit for approval an Aircraft AMREP Schedule Extension Request Form to the USAF PA identifying the number of additional flow days being requested, the associated task requirements, and the revised aircraft ECD.

1.9. Shall, Should, May, and Will Compliance: The intended meaning of terms that specify compliance with procedures or requirements is as follows:

• “Shall” has been used only when application of a procedure is mandatory.

• “Should” has been used only when application of a procedure is recommended.

• “May” and “need not” have been used only when application of a procedure is optional.

• “Will” has been used only to indicate futurity, never to indicate any degree of requirement for application of a procedure.

1.10. Technical Data: Use of approved and published USAF technical data, manuals, publications, and engineering data is mandatory IAW the DMSPEC. Throughout this document use of the term "maintenance manuals" will mean USAF T.O.s.

1.10.1. Technical Documents: All technical documents required for accomplishment of the DLM process are identified in the DMSPEC Section 9, Table 4 Listing of Applicable Publications (LOAP). In the absence of published technical data, which is needed to maintain or repair the aircraft, the USAF EA shall be notified by the depot facility via the Engineer Technical Assistance Request (ETAR) process. All ETARs shall be submitted to the USAF EA electronically via the Air Force Product Lifecycle Management (AF-PLM) system. AF-PLM can be accessed via https://usaf.dps.mil/sites/AF_PLM_PASS. Emailed .pdf forms will only be accepted on an emergency basis if the AF-PLM system is unavailable.

1.10.1.1. Photographs: At least 3 basic photographs shall be attached to each ETAR. One wide angle, one medium shot to help with perspective, and one of just the actual defect. Additional photographs shall be provided as needed to capture the entire problem. Photographs shall be attached as a PowerPoint .pptx or Adobe .pdf and shall include applicable part numbers, next higher assembly, the Station (STA), Butt Line (BL), and Water Line (WL) info as well as orientation/perspective (i.e. aft, fwd, outboard/inboard), and the applicable maintenance manual reference(s).

Proposed repair actions and available material and hardware as applicable shall also be provided.

https://usaf.dps.mil/sites/AF_PLM_PASS

1.10.2. Drawing Configuration Management: The depot facility shall use only approved engineering drawings from DoD drawing repositories and shall maintain a configuration management process IAW the DMSPEC.

1.10.3. Technical Data Library: The depot facility is responsible for developing and maintaining a technical library to support the DLM process IAW the DMSPEC. The depot facility shall ensure that all applicable and current technical data is presented to the applicable depot artisans IAW T.O. 00-5-1 and T.O. 00-5-3 daily.

1.11. Engineering Support Services: The depot facility shall provide engineering support services to resolve technical and engineering issues that arise during the DLM process.

1.11.1. Process Engineering Support: The depot facility shall provide on-site engineering support to resolve technical and engineering process issues and provide continuous surveillance of all DLM processes, and develop procedures, processes or repairs not provided by applicable USAF maintenance manuals. Recommendations for a waiver, deviation, or change to a required process or procedure shall be submitted to the USAF EA for approval via ETAR.

1.11.2. HH-60W Aircraft, Systems, and Component Engineering Support: The depot facility shall provide on-site engineering capability necessary for supporting DLM inspection and repair requirements for the HH-60W aircraft structure, aircraft systems, mission systems, and aircraft components. Any repair deemed necessary, but which is not covered by applicable USAF maintenance manuals, must be approved by the USAF EA via ETAR.

1.12. Functional Check Flights (FCF) and Operational Checks: Each aircraft shall be subjected to post-DLM operational checks and an FCF by a qualified check flight pilot and crew with demonstrated expertise in HH-60W model aircraft. Operational checks and FCFs shall be accomplished at the depot facility prior to aircraft acceptance and departure to the gaining custodian IAW the DMSPEC.

1.13. Depot Level Maintenance Tasks, Policies and Practices: The DLM work tasks shall be executed IAW the DMSPEC and shall consist of a thorough and comprehensive inspection of the aircraft structure, and repair of identified defects. The depot facility shall accomplish all maintenance and expired calendar, scheduled, or time/fatigue life-limited inspections, all phase inspections, and all daily and turnaround inspections. Any time change components that will exceed their service life or that are within ±10 percent of expiration at the time of aircraft delivery to the gaining custodian shall be replaced by the depot facility. General policies and practices regarding the management of the DLM process are IAW the DMSPEC. All aircraft undergoing the scheduled DLM rework process shall undergo clean, strip, and paint.

1.13.1. Defect Classification: The method for classifying corrosion, critical, major, and minor defects to determine the required maintenance actions under the DLM process is IAW the DMSPEC Section 1 and Figure 2 Defect Classifications.

1.13.2. Noted But Not Corrected (NBNC) Defects: NBNC defects are O/I-level defects not authorized to be corrected IAW this DMSOW and the DMSPEC or other defects that have been approved for non-correction by the USAF PA or EA for a specific aircraft due to supply, cost, or time constraints. The depot facility shall include all NBNC defects on the NBNC Report IAW paragraph 1.17.7 of this DMSOW.

1.13.2.1. An O/I-level defect that meets the definition of NBNC but is in an area of the aircraft that is not normally exposed or easily accessible by the owning activity shall be repaired by the depot facility.

1.13.3. Workmanship and Repair Standards: The depot facility shall ensure that all maintenance tasks are assigned to and performed by personnel with appropriate experience, qualifications, and supervision to accomplish the tasks IAW the standards and criteria specified in the DMSPEC.

1.14. Over and Above (O&A) Maintenance: Only maintenance tasks accomplished solely as part of the USAF PA signed and approved AFTO Form 103, and not negotiated as part of this DMSOW or the DMSPEC, will be considered O&A maintenance. TCTO modifications or special inspections may be required on an O&A basis and will be annotated on the PA approved AFTO Form 103. All O&A maintenance must be approved by the PA.

1.14.1. Special Work Requests: The owning activity shall prepare and submit the AFTO Form 103, Aircraft/Missile Data Condition, to the USAF PA through their lead MAJCOM within 60 days prior to the scheduled aircraft induction date. The USAF PA shall provide the signed and approved AFTO Form 103 to the depot facility within 45 days prior to the scheduled aircraft induction date. A special work request entry on the AFTO Form 103 for inspection or maintenance actions that are not negotiated as part of the DLM process IAW this DMSOW or the DMSPEC shall be considered O&A maintenance and shall be negotiated separately between the depot facility and the USAF PA only. The owning activity is not authorized to dictate nor determine any maintenance or repair requirements or obligate the expenditure of funds. A special work request shall be accomplished only if agreed upon by the depot facility and approved and funded by the USAF PA.

1.14.2. Safety Compliance Technical Orders (TCTOs): The depot facility shall automatically comply with all Immediate Action, Urgent Action, Safety Inspection, Routine Safety, and Flight Safety TCTOs on an O&A basis when issued after the aircraft induction / during the DLM process without submission of an AFTO Form 103. The depot facility shall be responsible for ensuring timely notification of safety TCTO issuance to the applicable depot artisans and immediate incorporation of safety TCTOs into the DLM process through the depot facility’s technical library IAW paragraph 1.10.3 of this DMSOW.

1.15. COMSEC and Classified Material Handling and Storage: The depot facility shall maintain the capability to store, install, and operationally check in secure mode all classified systems such as defensive systems, receivers, displays, and radios. All classified equipment shall be removed from the aircraft by the depot facility and stored with appropriate safeguards IAW the DMSPEC. Custody of all classified systems shall be transferred from/to the owning activity/gaining custodian IAW the DMSPEC and the DMSOW Appendix B HH-60W List of Sensitive Items for Secure Storage.

1.16. Aircraft Maintenance Logs, Records, Forms, and Historical Documents: The depot facility shall review, update, maintain, and prepare for transfer all aircraft maintenance logs, records, forms, and historical documents; engine logs and records; and component records IAW the DMSPEC. Upon induction of the aircraft into DLM rework at the depot facility, and prior to delivery of the aircraft following completion of DLM rework, a review of the aircraft logs, records, forms, and historical documents shall be performed jointly by the depot facility and owning activity/gaining custodian IAW the DMSPEC.

1.16.1. USAF logs and records shall be electronically updated by the depot facility IAW T.O.

00-20-1 using the applicable Maintenance Information System (MIS). The owning activity shall be responsible for transferring MIS access to the aircraft records to the depot facility upon aircraft arrival IAW the DMSOW Appendix C HH-60W Checklist for Unit Depot Drop-Off / Pick- Up Procedures. The depot facility shall transfer back MIS access to the aircraft records to the gaining custodian at completion of the aircraft acceptance and delivery.

1.17. DLM Reports and Documentation: The depot facility shall perform and participate in reporting functions required to ensure technical accuracy, quality, timeliness, effectiveness, efficiency, and safety of the DLM process. The responsible office at the depot facility shall prepare reports IAW the requirements specified in this DMSOW and the DMSPEC. All reports required by this DMSOW shall be submitted to the USAF PA. The depot facility shall maintain thorough records of all DLM actions accomplished during the DLM process. All reports shall include thorough and complete documentation of all inspections, testing, quality control tasks, material and parts requirements, and maintenance procedures and actions accomplished by the depot facility. This documentation shall be used by the depot facility and the USAF PA and EA to verify that repair, inspection, and quality control tasks, are accomplished satisfactorily and as required.

1.17.1. DLM Initial Evaluator and Estimator (E&E) Repair Report: A DLM Initial E&E Repair Report, which identifies a complete list of the specific maintenance actions and defects that were identified for correction during the initial aircraft inspection and testing for each aircraft induction, shall be submitted by the depot facility to the USAF PA. This information and data shall be used by the depot facility and the USAF PA and EA to determine the extent of repair, modification, or replacement necessary to make the aircraft serviceable IAW the DMSPEC. This information and data shall also be used by the depot facility for preparing man hour and cost estimates, determining material and parts requirements, and assessing if additional flow days are necessary for completion of the DLM process. At a minimum, all data will include a detailed description of the discrepancy (crack, wear, corrosion etc.), size (length, width, depth etc.), and location (WL, FS, BL coordinates) to include the associated man hours and applicable part numbers. The DLM Initial E&E Repair Report shall also include an initial itemized materials list which identifies all material and parts requirements by nomenclature, part number, national stock number (NSN), quantity, and associated cost per item. This DLM data shall be captured in an electronic database and submitted in electronic format (Excel) no later than 45 days after aircraft induction.

1.17.2. DLM Final Evaluator and Estimator (E&E) Repair Report: A DLM Final E&E Repair Report, which identifies a complete list of the specific maintenance actions and defects that were corrected during the DLM process for each aircraft induction, shall be submitted by the depot facility to the USAF PA. At a minimum, all data will include a detailed description of the discrepancy (crack, wear, corrosion etc.), size (length, width, depth etc.), and location (WL, FS, BL coordinates) to include the associated man hours and applicable part numbers. The DLM Final E&E Repair Report shall also include a final itemized materials list which identifies all material and parts requirements by nomenclature, part number, national stock number (NSN), quantity, and associated cost per item. This DLM data shall be captured in an electronic database and submitted in electronic format (Excel) no later than 30 days after aircraft delivery following completion of the DLM rework.

1.17.3. Initial and Final Itemized Materials List: For each aircraft induction a list shall be developed by the depot facility to identify those aircraft parts and material that will require replacement. This list shall be provided by the depot facility to the USAF PA in electronic format (Excel) and shall include an itemized breakdown of all parts and material requirements and the associated part number, quantity, and cost. This list shall be provided IAW the DLM Initial and Final E&E Repair Reports.

1.17.4. Rough Order Of Magnitude (ROM) Cost Estimate: A ROM Cost Estimate shall be developed by the depot facility to estimate the costs of accomplishing all required DLM actions for each aircraft induction IAW the DLM Initial E&E Repair Report. The ROM cost estimate shall contain the cost of all material, labor, and include the associated man hours required to repair the aircraft IAW the DMSPEC. The ROM Cost Estimate shall also identify additional flow days if required and the corresponding revised ECD which will be negotiated IAW the AMREP process and AFMCI 21-118. Man hour cost estimates shall be derived from information gathered from the DLM Initial E&E Repair Report, the AFTO Form 103, and DLM requirements IAW the DMSPEC. The ROM Cost Estimate shall be captured in an electronic database and submitted in electronic format (Excel) by the depot facility to the USAF PA no later than 45 days after aircraft induction.

1.17.5. DLM Weekly Status Report: The depot facility shall submit a DLM Weekly Status Report which provides a detailed and informative narrative of the status of each aircraft in work. The DLM Weekly Status Report shall, at a minimum, thoroughly identify work currently being accomplished, list of all required TCTOs, list of internal and external parts cannibalization actions, and the Milestone and Schedule Report identified below in Figure 2.

The report shall further identify any known labor or material constraints which are negatively impacting, or may impact, the aircraft flow day delivery schedule. The DLM Weekly Status Report shall be submitted in electronic format (Excel) by the depot facility to the USAF PA each Wednesday.

1.17.6. Milestone and Schedule Report: For each aircraft in work, the depot facility shall develop a Milestone and Schedule Report which clearly identifies the aircraft delivery schedule broken out by process gates and flow days in the format shown below in Figure 2 Milestone and Schedule Report Formats for Programmed Depot Maintenance (PDM) and Analytical Condition Inspection (ACI). The depot facility shall develop the “Gate” sequence and the “Original” flow day schedule IAW their local process. The “Original” flow day schedule shall include all holidays, depot closure dates, and O&A requirements known at time of aircraft induction. When additional flow days are required for aircraft completion, the “Revised” flow day schedule shall be developed and submitted for USAF PA approval IAW AFMCI 21-118 and paragraph 1.8 of this DMSOW. The “Actual” flow day schedule shall be completely filled out and updated on a weekly basis to show on time or delayed aircraft progression. The “Variance” (Var) represents the positive or negative flow day difference between the “Actual” flow day schedule and the “Original” or “Revised” flow day schedule as applicable. The Milestone and Schedule Report shall be submitted in electronic format (Excel) by the depot facility to the USAF PA as part of the DLM Weekly Status Report.

Figure 2. Milestone and Schedule Report Formats for

Programmed Depot Maintenance (PDM) and Analytical Condition Inspection (ACI)

1.17.7. Noted But Not Corrected (NBNC) Defect Report: The depot facility shall submit a final NBNC Report for each aircraft which identifies all defects that were not corrected by the depot facility as defined and IAW paragraph 1.13.2 of this DMSOW. The NBNC defects shall be identified by type, location, and description on the NBNC Report and recorded in the aircraft 781 series forms for appropriate action by the aircraft gaining custodian. The depot facility shall provide a copy of the NBNC Report to the USAF PA and aircraft gaining custodian for review prior to aircraft acceptance and delivery.

1.17.8. Monthly Financial Status Report: The depot facility shall submit a Monthly Financial Status Report which identifies the cumulative cost and man hour expenditures for each open funding document. The Monthly Financial Status Report shall be submitted in electronic format (Excel) by the depot facility to the USAF PA no later than the 10th day of each month.

1.17.9. DLM Management Reports: The objective of the DLM program is to introduce mechanisms to reduce costs, manage materials, refine production flow day estimates, and permit control of the DLM process. To accomplish this objective, the USAF PA will require information from the depot facility in regard to costs, man-hours, materials, and scheduling.

Briefings or reports on the depot facility management of the DLM process shall be provided to the USAF PA upon request.

1.17.10. Accident Reports: The depot facility shall immediately notify the USAF PA of all accidents or incidents involving USAF property IAW DAFI 91-204.

1.17.11. Record of Work Accomplishment: The depot facility shall maintain records of work accomplished on all DLM aircraft inductions. Upon request, the USAF PA and EA shall have access to all depot facility records of any DLM aircraft. The depot facility shall ensure that all aircraft records and documentation are updated and accompany the aircraft when returned to the gaining custodian. The depot facility shall maintain archives of all maintenance performed IAW depot facility instructions.

1.18. Tools and Equipment: Tools and equipment required for repair of the HH-60W aircraft are listed in the applicable USAF maintenance manuals. The depot facility is responsible for maintenance, accountability, storage, security, and calibration of all tooling and equipment used in the accomplishment of the DLM rework process. A listing of USAF provided Government Furnished Equipment (GFE) is available in the Contract or DMISA Exhibit XVI as applicable.

Requests by the depot facility to modify any GFE shall be submitted to the USAF EA via ETAR.

1.19. Severe Weather and Hurricane Evacuation: The depot facility shall be responsible for providing security of the aircraft during severe weather.

1.20. Airfield Requirements: Suitable airfield facilities capable of supporting C-5 or C-17 airlift operations shall be provided by and located at the depot facility. Airspace shall be available to perform required FCFs. Tie-down and ground run-up areas shall be provided.

1.21. Material Management: The depot facility shall procure all supplies, materials, and components required to complete the DLM process. The depot facility shall have material management processes and controls in place to ensure the proper security, storage, control, and accountability of aircraft parts and materials associated with the DLM process.

1.21.1. Components and Parts Segregation: The depot facility shall develop a process for segregating components and parts removed from aircraft during the DLM process.

1.21.2. Component Reuse: Components shall be reused to the maximum extent consistent with established standards and repair criteria IAW the DMSPEC.

1.21.3. Substitution of Parts: Replacement parts and material substitutions not specifically authorized by applicable USAF maintenance manuals shall be used only by authorization from the USAF EA via ETAR IAW the DMSPEC.

1.21.4. Cannibalization of Parts: External cannibalization of any aircraft parts, avionics, accessories, or components requested by an owning activity shall not be conducted without signed authorization from the USAF PA via submission of the AFLCMC/WIUB (Rotary Aircraft) Part CANN Request form. Internal cannibalization of aircraft parts, avionics, accessories, or components required by the depot facility to maintain aircraft delivery schedules is authorized and shall be executed per local depot facility instructions. All cannibalization actions shall be captured on the DLM Weekly Status Report IAW paragraph

1.17.5 of this DMSOW.

1.21.5. Nonconforming Material: The depot facility shall establish and maintain a system for controlling nonconforming material, including procedures for identification, segregation, and disposition of repaired supplies IAW the DMSPEC.

1.21.6. Reporting Material Deficiencies: The depot facility shall submit material deficiency reports in the Joint Deficiency Reporting System (JDRS) database IAW T.O. 00-35D-54 USAF Deficiency Reporting, Investigation, and Resolution (DRI&R). Any major or safety of flight defective materiel discovered on the aircraft during accomplishment of the DLM process shall be reported directly to the USAF EA via ETAR and substantiated by submission of a Product Quality Deficiency Report (PQDR) IAW AFI 21-115.

1.21.7. Economic Repair and Condemnation: Parts, components, subassemblies, or assemblies found worn or defective beyond economic repair shall be condemned and disposed of IAW the DMSPEC.

1.21.8. Hazardous Materials (HAZMAT): Handling and disposal of HAZMAT shall be IAW applicable Federal regulations and local depot facility instructions.

1.22. Quality Assurance Requirements: Quality assurance requirements shall be adhered to IAW the DMSPEC Section 8.

2. DELIVERY, ARRIVAL, AND INDUCTION OF AIRCRAFT

2.1. Preparation for Induction: Detailed tasks and requirements for the owning activity to accomplish prior to aircraft delivery to the depot facility are IAW the DMSPEC Section 2.1 and the DMSOW Appendix C HH-60W Checklist for Unit Depot Drop-Off / Pick-Up Procedures and include:

• Correct O/I-Level Discrepancies

• Incorporate Outstanding Technical Modifications/Inspections

• Update Logbooks And Records

• Perform a Check Flight

• Perform Balancing and Vibration Spectrum Analysis

• Remove Loose Mission Equipment and Gear (not required for flight)

• Remove CADs (not required for flight)

• Remove Classified Equipment And COMSEC (not required for flight)

• Transfer of COMSEC

• Provide Protective / Support Equipment

• Inventory Aircraft

• Review Emergency Equipment Records

• Submit DLM Special Work Requests (AFTO Form 103)

• Coordinate Aircraft Airlift (if applicable)

• Provide Minimum Delivery Crew

• Update Aircraft Status

2.2. Aircraft Arrival: Detailed joint pre-induction tasks and requirements for the depot facility and owning activity to accomplish together at aircraft arrival at the depot facility are IAW the DMSPEC Section 2.2 and the DMSOW Appendix C HH-60W Checklist for Unit Depot Drop-Off / Pick-Up Procedures and include:

• Provide Minimum Delivery Crew

• Review of Aircraft Discrepancies

• Review of Aircraft Component History Records

• Review Aircraft / Engine Logbooks and Records

• Review Vibration Analysis Cards

• Inventory Aircraft

• Aircraft Airlift Arrival (if applicable)

• Remove Classified Equipment And COMSEC

• Perform Oil Contamination Analysis

2.3. Aircraft Airlift Incoming: Aircraft arrival at the depot facility by C-5 or C-17 airlift shall be handled IAW the DMSPEC and the DMSOW Appendix C HH-60W Checklist for Unit Depot Drop-Off / Pick-Up Procedures.

2.4. Aircraft Induction: The aircraft induction date shall be considered the date that all pre-induction tasks are complete and/or the depot facility has full possession of the aircraft.

Detailed tasks and requirements for preparing the inducted aircraft for inspection and rework shall be IAW the DMSPEC Section 3.

2.4.1. Clean, Strip, and Depaint: The depot facility shall clean the aircraft and strip the exterior of paint and finishes to expose defects that may not otherwise be noticed during the inspections.

2.4.2. Disassembly: Aircraft components shall be removed IAW USAF maintenance manuals to facilitate individual inspections and repairs. Components shall be evaluated, and if serviceable, retained and preserved for reinstallation in or on the aircraft. Aircraft disassembly and component inspection, disposition, and preservation is IAW the DMSPEC Section 3 and the Addendum 1 Airframe Components to be Removed.

3. INSPECTION, MAINTENANCE, AND REPAIR REQUIREMENTS

3.1. Airframe Alignment and Verification: Verification of the airframe alignment shall be required for UDLM crash damage drop-in aircraft inductions. Aircraft inducted for ACI level inspections shall require alignment verification of the pylon, and fuselage and tail cone as one unit IAW the DMSPEC.

3.2. Inspection Requirements: Definitive inspection tasks are required to locate and identify all defects and to determine maintenance and repair requirements. These tasks shall be accomplished IAW the DMSPEC Section 4.

3.2.1. Zonal Inspections: The depot facility shall conduct zonal inspections for defects, security, cracks, corrosion, damage, delamination, foreign objects, distortion, interference, evidence of overheating and leakage, broken or missing parts, proper lubrication and bonding, and presence and legibility of markings. The zonal inspections shall be IAW the DMSPEC Section 4 and are detailed in the DMSPEC Figure 3 HH-60W Zone Areas and Table 2 HH-60W Zone Descriptions.

3.2.2. Structural Inspections: The depot facility shall conduct specific structural inspections for corrosion, cracks, distortion, damaged, loose and missing fasteners, defective sealant, and seals IAW the DMSPEC Addendum 2 PDM and ACI Zonal

Inspection Requirements which includes all inspections required by the 720-Hour Phase Inspection IAW 1H-60(H)W-2.

3.2.3. Other Inspections: The depot facility shall conduct additional inspections IAW the DMSPEC Section 4 on the following:

• Structures and Advanced Composites

• Skins

• Access Plates, Doors, Panels, and Cowlings

• Screens

• Fairings

• Transparent Assemblies

• Steps, Ladders, and Handholds

• Escape Hatches and Canopies

• Mechanical Linkages and Actuating Mechanisms

• Control Cables and Flexible Shafts

• Pulleys, Fairleads, Pressure Seals, Rub Strips, Cable End Fittings, and Conduits

• Flexible Hoses

• Tubing and Ducting

• Electrical and Electronic Equipment

• Wiring, Wiring Components, and Terminal Boards

• Instruments

• Anti-Friction Bearings

• Radome and Antenna Covers

• Driveshafts

• Mechanical Flight Controls

• Communications Systems

3.3. Nondestructive Inspection (NDI) Requirements: NDI inspection methods and requirements shall be IAW the DMSPEC Section 4. Personnel performing NDI shall be formally trained in the usage of the inspection equipment and possess certification of such training.

3.4. Maintenance and Repair: Specific maintenance and repair tasks and guidelines required to correct defects discovered during the inspection process shall be accomplished IAW the DMSPEC Section 5 and include:

• Structural, Metal and Airframe Repairs

• Hardware

• Pipe, Tubing, Hose, and Fitting Repairs

• Plastics and Fabrication Repairs

• Packing, Gaskets, and Seal Repairs

• Bearing Repairs

• Electrical Systems and Avionics Repairs

• Fuel System Repairs

• Flight Control Repairs

• Protective Coatings

4. ASSEMBLY AND FINAL PROCESSING

4.1. Aircraft Configuration: The aircraft shall be returned to the customer in the same configuration as received, with the same type components, accessories, and special equipment installed except as modified, removed, or added by requirements IAW the DMSPEC or as directed by the USAF EA.

4.2. Assembly: The depot facility shall reassemble and certify the aircraft as airworthy IAW the DMSPEC Section 6. Upon completion of the reassembly process, to include reinstallation of loose mission equipment and CADs, each aircraft shall be examined to ensure all quality characteristics conform fully to established quality requirements. The depot facility shall ensure that all work performed has been inspected or certified during the DLM process, and that characteristics relating to work performed are determined to be in conformance to the requirements of the DMSPEC.

4.3. Paint: The depot facility shall paint the aircraft and apply markings and insignias IAW the DMSPEC Section 6 and the Table 3 Drawings for Paint and Markings. Touch up of interior fuselage surfaces, covers, access panels, and floor panels shall be accomplished. Interior surface areas shall be refinished as needed when affected by compliance of the DLM process.

4.4. Logbooks and Records: The depot facility shall accomplish a complete aircraft component inventory prior to delivery of the aircraft to the gaining custodian. The depot facility shall review, update, and prepare for transfer aircraft forms, historical documents, logs, records, engine logs and records IAW the applicable maintenance manuals and the DMSPEC Section 6.

4.5. Technical Modifications / Inspections Verification: The depot facility shall verify that all required technical modifications/inspections have been accomplished. Accomplishment of technical modifications/inspections shall be recorded in the appropriate aircraft logs, records, forms, and historical documents IAW the DMSPEC Section 6.

4.6. Operational Checks and Functional Check Flight (FCF): Aircraft operational checks and a full profile FCF shall be performed at the depot facility upon completion of the rework process.

The FCF shall consist of a thorough inspection and airworthiness check of the aircraft before flight, during flight, and upon completion of the check flight IAW the DMSPEC Section 6.

4.7. Aircraft Cleaning and Servicing: The depot facility shall accomplish all servicing, cleaning, and flight preparation requirements prior to delivery of the aircraft to the gaining custodian IAW the DMSPEC Section 6.

4.8. Aircraft Ready for Pickup Notice: The depot facility shall send a seven-day notice confirming the estimated date that the aircraft will be ready for pickup by the gaining custodian.

The notice shall be sent via email to the USAF PA and the owning activity/gaining custodian.

4.9. Aircraft Airlift Preparation: The depot facility shall prepare aircraft that were airlifted to the depot facility for departure airlift IAW the DMSPEC Section 6. The depot facility shall send an airlift pick-up request notice to the USAF PA and the owning activity/gaining custodian at least 45 days prior to the aircraft projected ECD.

4.10. Aircraft Completion: The aircraft completion date shall be considered the date that all DLM tasks are complete, including completion of operational checks and full FCF IAW the above paragraph 4.6, and the aircraft is ready for acceptance and delivery to the gaining custodian. Detailed tasks and requirements for delivery of the aircraft shall be IAW the DMSPEC Section 7.

5. DELIVERY AND DEPARTURE OF AIRCRAFT

5.1. Aircraft Delivery: Detailed joint tasks and requirements for the depot facility and gaining custodian to accomplish together during aircraft delivery and departure from the depot facility shall be IAW the DMSPEC Section 7 and the DMSOW Appendix C HH-60W Checklist for Unit Depot Drop-Off / Pick-Up Procedures and include:

• Review NBNC Repot

• Review Logbooks, Records and Forms

• Review Weight and Balance

• Inventory of Aircraft Components and Equipment

• Inventory Removed Loose Components and Mission Equipment

• Provide Protective / Support Equipment

• Perform Acceptance Check Flight

• Aircraft Airlift Departure (if applicable)

• Transfer Aircraft / Engine Logbooks, Records, Forms and Historical Documents

• Update Aircraft Status

• Transfer of COMSEC

5.2. Acceptance Check Flight: When the FCF is performed by the depot facility IAW paragraph 4.6 of this DMSOW, the depot facility shall support an acceptance check flight performed by the gaining custodian prior to aircraft transfer of custody. The acceptance check flight shall consist of a thorough inspection and airworthiness check of the aircraft IAW the DMSPEC Section 7.

5.3. Aircraft Airlift Departure: Aircraft departure from the depot facility by C-5 or C-17 airlift shall be handled IAW the DMSPEC Section 7.

6. DEPOT FIELD TEAM (DFT) SUPPORT

6.1. Notification: DFT requirements are generated IAW T.O. 00-25-107 Maintenance Assistance ETARs by the aircraft owning unit and submitted to the USAF EA for disposition instructions. When DFT support from the depot facility is required, the USAF PA shall notify the depot facility via submission of engineering SOW.

6.2. Maintenance Response Plan: From the time of notification of a DFT requirement via receipt of the corresponding engineering SOW, the depot facility shall provide a Maintenance Response Plan to the USAF PA within the below timeline:

• Emergency/Urgent Request.........2 working days

- Emergency - Aircraft is in a grounding condition at a deployed combat environment or other operational tasking where the unit is operating/deployed at the direction of the MAJCOM or National Command Authority.

- Urgent - Aircraft is grounded at home station or deployed and not undergoing phase inspections or other major grounding event.

• Routine Request...........................3 working days

- Routine - Will be for all requests that do not fall into one of the above categories.

6.3. Cost Estimate: The Maintenance Response Plan shall include the team composition;

special equipment/tooling, itemized list of all parts/material requirements; and the projected start and completion dates of repair at the owning activity location. The Maintenance Response Plan shall also include the cost estimate which shall include itemized costs for travel, shipping, labor and associated man hours.

6.4. Engineering Support: In the event additional repair requirements are identified by the DFT, the USAF EA shall be notified by the depot facility via the ETAR process IAW the DMSPEC. Any work outside the scope of the engineering SOW shall not be accomplished without USAF EA approval and USAF PA coordination. The owning activity is not authorized to dictate nor determine any maintenance or repair requirements or obligate the expenditure of funds.

6.5. Funding: DFT support shall be funded as cost reimbursable. The USAF PA shall provide funding to the depot facility at the beginning of each fiscal year to avoid any delay in support due to funds availability.

6.6. Cost Tracking: The depot facility shall provide the USAF PA detailed, itemized cost information on the Monthly Financial Status Report for each DFT requirement/deployment separately. Cost information will include the aircraft tail number, location, dates of deployment, and total cost expenditures to include man hours.

6.7. Trip Report: When work is complete, the depot facility shall notify the USAF PA via email within 1 working day. A Trip Report, to include a detailed summary of the work completed, will be provided to the USAF PA within 10 calendar days of trip completion.

____________________________________________________________
HH-60W Depot Maintenance
Statement of Work (DMSOW)
Revision: Basic
Approved by:
______________________________________
AFLCMC/WIUBC Rotary Sustainment Section
TABLE OF CONTENTS
LIST OF FIGURES

LIST OF APPENDICES