This document is a Screening Information Request (SIR) for a Federal Aviation Administration (FAA) contract to provide a variety of operational and administrative support services across seven functional areas, including Executive Support Services, Infrastructure Protection Program Support Services, Business and Mission Program Support Services, and others. The contract will be an indefinite delivery, indefinite quantity (IDIQ) contract with a one-year base period and four one-year option periods. The SIR outlines the required deliverables and associated due dates for each functional area, such as monthly status reports, quarterly security review meetings, and annual security assessment reports. The contract opportunity is open to all business sizes, and the FAA will not reimburse offerors for any costs associated with responding to the SIR. The acquisition strategy is an open competition, and the period of performance is five years if all options are exercised.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| ASH-IV SIR SEC E_POSTED.pdf | ||
| ASH-IV SIR SEC M_POSTED.pdf | ||
| ASH-IV SIR SEC K_POSTED.pdf | ||
| ASH-IV SIR SEC L_POSTED.pdf | ||
| ASH-IV SIR SEC C_POSTED.pdf | ||
| ASH-IV SIR SEC H_POSTED.pdf | ||
| ASH-IV SIR SEC G_POSTED.pdf | ||
| ASH-IV SIR SEC I_POSTED.pdf | ||
| ASH-IV SIR SEC D_POSTED.pdf | ||
| ASH-IV SIR SEC A_POSTED.pdf | ||
| ASH-IV SIR SEC B_POSTED.pdf | ||
| ASH-IV SIR SEC J_POSTED.pdf | ||
| ASH-IV Attachment L.2 Price Model_Posted.xlsx | XLSX spreadsheet |
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SCREENING INFORMATION REQUEST (SIR)
NUMBER 693KA9-24-R-00004
PART I – SECTION F
DELIVERIES OR PERFORMANCE
F-1
F.1 AMS 3.1-1 CLAUSES AND PROVISIONS INCORPORATED BY REFERENCE (July 2019)
This screening information request (SIR) or contract, as applicable, incorporates by reference the provisions or clauses listed below with the same force and effect as if they were given in full text.
Upon request, the Contracting Officer will make the full text available, or offerors and contractors may obtain the full text via Internet at: https://fast.faa.gov/contractclauses.cfm. (End of clause)
AMS 3.10.1-9 Stop Work Order (October 1996) AMS 3.10.1-24 Notice of Delay (March 2009) AMS 3.11-34 F.O. B. Destination (April 1999)
F.2 AMS CLAUSES AND PROVISIONS INCORPORATED IN FULL TEXT
AMS 3.8.2-22 Substitution or Addition of Personnel (October 2006)
(1) The Contractor must assign only those individuals whose resumes, personnel data, or personnel qualification statements have been submitted and determined by the Contracting Officer to meet the minimum requirements of the contract. The Contractor must not substitute or add personnel except in accordance with this clause.
(2) Substitution of Personnel.
(a) For the first-year contract performance, the Contractor must not substitute personnel for the individuals whose resumes or other personal qualification were submitted with its offer and that were determined by the Contracting Officer to be acceptable at the time of contract award, unless such substitutions are because of an individual's sudden illness, death, or termination of employment. In any of these events, the Contractor must promptly notify the Contracting Officer and propose substitute personnel as required by paragraph (4) below.
(b) If an individual becomes, for whatever reason, unavailable for work under the contract for a continuous period exceeding thirty (30) working days or is expected to devote substantially less effort to the planned work, the Contractor must propose a substitute personnel as required by paragraph (4) below.
(3) Addition of Personnel. If an FAA requirement will increase the specified level of effort for a designated labor category, but not the overall level of effort of the contract, then the Contractor must notify the Contracting Officer to add personnel to the designated labor category. The Contractor must request added personnel as required by paragraph (4) below.
(4) Request and Review. The Contractor must submit the request for substitute or added personnel in writing to the Contracting Officer at least [CO to insert information] days (if a security clearance must be obtained, at least [CO to insert information] days) before the proposed date of substitution or addition. The Contractor's request must provide a detailed explanation of the circumstances causing the proposed substitution or addition, a complete resume for the proposed substitute or added personnel, and any additional information required by the Contracting Officer. Proposed substitutes and added personnel must have qualifications equal to or higher than those stated in the contract for the labor category. The Contracting Officer will evaluate the Contractor's request and promptly notify the Contractor of the decision to accept or reject the qualifications of the substitute or added personnel.
(5) The Contracting Officer may terminate the contract if the Contractor has not made suitable, timely, and reasonably forthcoming replacement of personnel who have been reassigned or terminated or otherwise become unavailable to work under the contract or the resulting loss of productive effort would impair the successful completion of the contract. Alternatively, if the Contracting Officer finds the Contractor to be at fault for the condition, then the Contracting Officer
F-2 may equitably adjust (downward) the contract price or fixed fee to compensate the Government for any delay, loss or damage as a result of the Contractor's action.
F.3 PERIOD OF PERFORMANCE
The period of performance for this contract will be for five years from _______________ to ____________, provided all options are exercised. The contract will consist of a one (1) year base period with four (4) one (1) year option periods.
F.4 PLACE OF PERFORMANCE
Services required under this contract must be performed at the Contractor's facility, FAA sites, or other Government locations as directed by the Contracting Officer. FAA facilities include but are not limited to the following: HQ FAA Building, all Regional Offices, the MMAC, WJHTC, and contractor offsite facilities, as needed.
F.5 DELIVERY ITEMS
Any delivery items will be identified in each Delivery Order under the Contract. Delivery Order tasks will also contain descriptions of the deliverable and date of delivery. Deliverable items when appropriate and not necessary to be delivered in hard copy, can be emailed to the COR, with a courtesy copy emailed to the CO. Further correspondence procedures are outlined in Section G.3.
Deliverable Due Date Description Reference SOW para C.5 All Support Services areas
Monthly Status Reports (MSRs) No later than the 10th calendar day of following month
Status of Work Assignments in accordance with SOW Section C.5.1 thru C.5.7 - including work performed, milestones reached, problems encountered, and projected work
Weekly Status Reports On Tuesday of following week Technical POCs shall receive weekly status reports
Ad-hoc and additional status reports
As requested by CO or COR
Reference SOW para C.5.2 Infrastructure Protection Program Support Services
Quarterly Security Review Meetings
No later than the 20th calendar day of the month following each quarter
Reference SOW para C.5.3 Business and Mission Program Support Services
Quarterly Program Management Reviews (PMRs)
No later than the 20th calendar day of the month following each quarter
Monthly Purchase Reports Submit on the first Monday of each month
Monthly Business Plan Updates No later than the 25th calendar
F-3 day of each month Reference SOW para C.5.5 Personnel Security and ID Media Program Support Services
PIV Card Issuers (PCI) control assessment report
Every Three Years Per NIST Special Publication 800-79 and FIPS-201
PKI Registration Authority Assessment Report
Annually Per FIPS 201
Reference SOW para C.5.6 Security Applications Support Services
Monthly Call Summary – Application Support Calls
No later than the 10th calendar day of each month
Security Assessment Report - WISDOM ITI System
January 18, each year Per NIST 800-53, NIST 800-37 Risk Management Framework (RMF), and FAA 1370.121
Security Assessment Report - CAVE System
January 18, each year Per NIST 800-53, NIST 800-37 Risk Management Framework (RMF), and FAA 1370.121
Security Assessment Report - ITS System
February 4, each year Per NIST 800-53, NIST 800-37 Risk Management Framework (RMF), and FAA 1370.121
Security Assessment Report - ASH External Web Portals (EWP) System
April 18, each year Per NIST 800-53, NIST 800-37 Risk Management Framework (RMF), and FAA 1370.121
Security Assessment Report - IDMS System
June 17, each year Per NIST 800-53, NIST 800-37 Risk Management Framework (RMF), and FAA 1370.121
Security Assessment Report - ASH Web Portals (AWP) System
July 4, each year Per NIST 800-53, NIST 800-37 Risk Management Framework (RMF), and FAA 1370.121
Reference SOW para C.5.7 Security Solutions Development Support Services
Requirements Documents As required Create and maintain for new applications, enhancements, and/or changes.
Testing Documentation and Test results
As required Create and maintain for new applications, enhancements, and/or changes.
Project Plans, Standard Operating Procedures, and Training Documents
As required Create and maintain for new applications, enhancements, and/or changes.
Cloud Migration Plan and Briefing
Annually Per AXM-400 Annual Plan approved by AXM-1.
F.6 PLACE OF DELIVERY
The Place of delivery items must be delivered as specified in the individual Delivery Order.