ARFQ DEP22-063 DEP Construction Bid Submission Review Form.pdf

PDF 266 KB Posted

Attached to
Farnsworth #2 Well Plugging API# 47-105-01379
Solicitation number
ARFQ 0313 DEP2200000063 6
Issued by
Wetzel County, West Virginia

About this file

This is a Construction Bid Submission Review Form created by the State of West Virginia Department of Environmental Protection (DEP) on August 11, 2017. The document serves as an informational guide for potential bidders on construction projects, outlining common issues that may result in bid disqualification. The form emphasizes that all bidders must thoroughly review the complete request for quotation (RFQ) documents, including all addenda, instructions, and supporting materials to identify specific bidding requirements for individual projects. The document does not establish itself as a comprehensive list of all bidding requirements but rather highlights frequent problems encountered during the construction bidding process. Failure to comply with stated requirements in the Bid Documents may result in immediate disqualification.

The form identifies two categories of disqualification errors: those resulting in immediate bid disqualification and those that may result in disqualification before contract award. Immediate disqualification errors include failure to attend mandatory pre-bid meetings, failure to sign required signature pages, failure to supply valid bid bonds, non-compliance with mandatory RFQ requirements, failure to acknowledge receipt of addenda (if required), late bid submission, federal or state debarment or suspension, outstanding environmental enforcement actions, and unresolved DEP vendor complaints. Potential disqualification errors before award include outstanding debt to the state or political subdivision, workers' compensation or unemployment compensation delinquency, failure to obtain required bonds and insurance, failure to provide a West Virginia contractor's license number within one day of request, failure to submit a signed drug-free workplace affidavit within one day of request, and failure to provide a subcontractor listing within one business day of bid opening or DEP request.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEP Construction Bid Submission Review Form Created August 11, 2017

State of West Virginia

Department of Environmental Protection

Construction Bid Submission Review Form

This list has been provided for informational purposes only and is not to be construed as a complete list of request for quotation or bidding requirements for any individual construction project. This list does not and cannot include every item, mistake or oversight that could cause a contractor’s bid to be disqualified. Rather, this list is intended to draw attention to some of the most common problems that occur in the bidding process for construction projects. All potential bidders must read the request for quotation, all additional documents, and all instructions relating thereto (“Bid Documents”) in their entirety to identify the actual request for quotation and bidding requirements. Failure to read the Bid Documents in their entirety and comply with the stated requirements contained therein may result in bid disqualification.

Errors that shall be reason for immediate bid disqualification

1. Failure to attend a mandatory pre-bid meeting

2. Failure to sign the signature page on the Bidder’s Instructions

3. Failure to supply a valid bid bond

4. Failure to meet any mandatory requirement of the RFQ

5. Failure to acknowledge receipt of Addenda (only if stipulated as mandatory)

6. Failure to submit bid prior to the bid closing date and time

7. Federal debarment

8. State of West Virginia debarment or suspension

9. Outstanding environmental enforcement actions

10. Unresolved DEP vendor complaints

Errors that May Be Reason for Bid Disqualification Before Contract Award

1. Debt to the State or Political Subdivision (must be resolved prior to award)

2. Workers’ Compensation or Unemployment Compensation delinquency (must be resolved prior to award)

3. Failure to obtain required bonds and/or insurance

4. Failure to supply West Virginia contractor's license number with bid or within one day of DEP request to do so.

5.

Failure to supply a signed drug free workplace affidavit with bid or within one day of the DEP request to do so.

Failure to provide sub contractor listing within one business day of bid opening or one business day of request to do so by DEP