ARFQ DEP18-52 Construction Bid Submission Review Form 8.11.17.pdf

PDF 257 KB Posted

Attached to
Addendum #2 Belle Contracting S-6020-87 Water Treatment Proj
Solicitation number
ARFQ 0313 DEP1800000052 3
Issued by
Preston County, West Virginia

About this file

This is a Construction Bid Submission Review Form created by the State of West Virginia Department of Environmental Protection (DEP) on August 11, 2017. The document serves as an informational guide for potential bidders on construction projects and outlines common bidding process problems rather than project-specific details. The form emphasizes that all potential bidders must thoroughly review the complete request for quotation (RFQ) documents, including all additional documents and instructions, as this checklist does not constitute a comprehensive list of all bidding requirements. The document explicitly states that failure to read and comply with all stated requirements in the bid documents may result in automatic bid disqualification.

The form identifies two categories of errors: those that result in immediate bid disqualification and those that may result in disqualification before contract award. Immediate disqualification errors include failure to attend mandatory pre-bid meetings, failure to sign required signature pages, failure to provide valid bid bonds, failure to meet any mandatory RFQ requirement, failure to acknowledge receipt of addenda if required, late bid submission, federal debarment, West Virginia state debarment or suspension, outstanding environmental enforcement actions, and unresolved DEP vendor complaints. Errors that may cause disqualification before award include outstanding debt to the state or political subdivision, workers' compensation or unemployment compensation delinquency, failure to obtain required bonds and insurance, failure to provide a West Virginia contractor's license number within one day of request, failure to submit a signed drug-free workplace affidavit within one day of request, and failure to provide subcontractor listings within one business day of bid opening or DEP request.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEP Construction Bid Submission Review Form Created August 11, 2017

State of West Virginia

Department of Environmental Protection

Construction Bid Submission Review Form

This list has been provided for informational purposes only and is not to be construed as a complete list of request for quotation or bidding requirements for any individual construction project. This list does not and cannot include every item, mistake or oversight that could cause a contractor’s bid to be disqualified. Rather, this list is intended to draw attention to some of the most common problems that occur in the bidding process for construction projects. All potential bidders must read the request for quotation, all additional documents, and all instructions relating thereto (“Bid Documents”) in their entirety to identify the actual request for quotation and bidding requirements. Failure to read the Bid Documents in their entirety and comply with the stated requirements contained therein may result in bid disqualification.

Errors that shall be reason for immediate bid disqualification

1. Failure to attend a mandatory pre-bid meeting

2. Failure to sign the signature page on the Bidder’s Instructions

3. Failure to supply a valid bid bond

4. Failure to meet any mandatory requirement of the RFQ

5. Failure to acknowledge receipt of Addenda (only if stipulated as mandatory)

6. Failure to submit bid prior to the bid closing date and time

7. Federal debarment

8. State of West Virginia debarment or suspension

9. Outstanding environmental enforcement actions

10. Unresolved DEP vendor complaints

Errors that May Be Reason for Bid Disqualification Before Contract Award

1. Debt to the State or Political Subdivision (must be resolved prior to award)

2. Workers’ Compensation or Unemployment Compensation delinquency (must be resolved prior to award)

3. Failure to obtain required bonds and/or insurance

4. Failure to supply West Virginia contractor's license number with bid or within one day of DEP request to do so.

5.

Failure to supply a signed drug free workplace affidavit with bid or within one day of the DEP request to do so.

Failure to provide sub contractor listing within one business day of bid opening or one business day of request to do so by DEP

6.