Tobyhanna Army Depot Standard Operating Procedure
For
Excavation/Excavation Permits
This document is intended for use at Tobyhanna Army Depot
Contractors are expected to comply with Pa state law.
(Pennsylvania One Call System)
This procedure applies to any excavation deeper than 6 inches including boring, drilling, augering and driving stakes.
1. The excavator is required to outline the proposed excavation site with white markings before requesting a permit
2. Call Pennsylvania One Call System at 800-242-1776 or 811
3. Pa One Call will notify Tobyhanna (Facility Owner) via fax.
4. TYAD will mark utilities and provide a signed permit to the excavator if approved.
5. TYAD has a maximum of ten working days to approve each permit
6. Any disapproval stops the permit process and requires a resubmission
7. Excavator must have a signed permit on the job site at all times
8. The permit is valid for thirty (30) days
9. The excavator is responsible for maintaining any markings made by the facility owner.
10. The excavator is expected to hand dig within thirty (30) inches of marked facilities. (See figure on page 2).
Temporary Facility Marking Responsibility by Facility Owners is:
To mark, stake, locate or otherwise provide the position of the underground utilities at the site within 30 inches* horizontally from the outside wall of the utilities in such a manner so as to enable the excavator, where appropriate within the tolerance zone, to employ prudent techniques, such as hand digging, to determine the precise location of the utility lines.
*Note: The 30 inch horizontal requirement is specific to Tobyhanna Army
Depot
PROCEDURES FOR EXCAVATION
IN ACCORDANCE
WITH PENNSYLVANIA ONE CALL (PA One Call) REQUIREMENTS
Tobyhanna Army Depot
TOBYHANNA ARMY DEPOT IN-HOUSE EXCAVATION PERMIT
For Excavation And Other Work in the Vicinity of Utilities
CALL 911 FOR EMERGENCIES
CHECK APPROPRIATE BOXES, FILL IN ALL SPACES AND SUBMIT TO THE
ENGINEERING BRANCH POC AT LEAST WORKING 3 DAYS PRIOR TO START OF
EXCAVATION. EXPLAIN ANY "NO" RESPONSE TO ANY ITEM BELOW IN
SECTION 6.
PROJECT: JOB ORDER NUMBER:
PROPOSED EXCAVATION START DATE/COMPLETION DATES:
1. EXCAVATION REQUIREMENTS DEFINED. -
2. PROPOSED EXCAVATION AREA MARKED WITH WHITE LINES.
3. CONTACT PA ONE-CALL SERVICE: 1-800-242-1776. - YES NO:
Date & Time Serial No.
(PA ONE-CALL covers all Natural Gas lines)
4. CONTROL CONSIDERATIONS
a. SAFETY MEASURES ARE IN PLACE TO ASSURE EXCAVATION AND PROCEDURES
MEET OR EXCEED ALL OSHA AND OTHER REQUIREMENTS.
b. LOCATION OF SHUT-OFF OR ISOLATION VALVES HAVE BEEN ESTABLISHED.
c. SOIL EROSION AND SEDIMENTATION CONTROLS WILL BE IMPLEMENTED
PROCEDURES FOR
EXCAVATION IN ACCORDANCE
WITH PENNSYLVANIA ONE CALL (PA One Call) REQUIREMENTS
Tobyhanna Army Depot
5. NOTES:
a. Work shall always proceed in an orderly and effective manner to preclude potential damage or problems.
b. When utilities have been located in the area to be excavated, hand digging will be used within 30 inches until the exact locations of all lines have been determined.
c. If differing site conditions are determined to exist, contact the Directorate of Installation Services Engineering Branch POC for possible additional precautionary measures to be employed.
6. REMARKS:
7. POC FROM Roads & Grounds Branch (equipment operator or person knowledgeable about the excavation):
8.
AUTHORIZED SIGNATURE (BRANCH CHIEF/LEADER) DATE
WITH PENNSYLVANIA ONE CALL (PA One Call) REQUIREMENTS Tobyhanna
Army Depot
THE FOLLOWING SECTIONS TO BE COMPLETED BY ENG BRANCH POC AFTER
RECEIPT OF PERMIT REQUEST:
9. DATE RECEIVED
10. DATE UTILITIES MARKED
11. UTILITIES IDENTIFIED ON-SITE:
POTENTIAL ASBESTOS
12. CONTROLS REQUIRED:
IMPLEMENTED:
MEASURES TO BE
PERMIT APPROVED -
AUTHORIZED SIGNATURE (Chief Eng Branch or Designated Alternate)
DATE
EXPIRATION DATE:
TOBYHANNA ARMY DEPOT
EXCAVATION PERMIT & RISK ASSESSMENT
For Excavation and Other Work in the Vicinity of Utilities
EMERGENCY PHONE NUMBER - 615-7300
CHECK APPROPRIATE BOXES, FILL IN ALL SPACES AND SUBMIT TO THE
CONTRACTING OFFICER'S REPRESENTATIVE (COR) AT LEAST 3 WORKING DAYS
PRIOR TO START OF EXCAVATION. WORK SHALL NOT PROCEED UNTIL PERMIT
IS ISSUED BY DIRECTORATE OF INSTALLATION SERVICES (D/IS). COPY OF
PERMIT SHALL BE KEPT ON SITE AT ALL TIMES. EXPLAIN ANY "NO"
RESPONSE TO ANY ITEM BELOW IN SECTION 12.
PROJECT: CONTRACT NUMBER:
PROPOSED EXCAVATION START DATE/COMPLETION DATES:
1. EXCAVATION DETAILS AND DRAWINGS ESTABLISHED. -
2. PROPOSED EXCAVATION AREA MARKED WITH WHITE LINES.-
3. CONTACT PA ONE-CALL SERVICE: 1-800-242-1776. -
Date & Time
Serial No.
(PA ONE-CALL also covers all GAS lines on the installation)
4. UTILITIES IDENTIFIED ON-SITE:
5. DATE UTILITIES MARKED AND METHOD OF MARKING
PA ONE CALL-
OTHER -
6. LEVEL OF RISK: (Based upon personnel safety and consequences of utility outages.)
7. CONTROLS REQUIRED:
feet of GAS line.
8. CONTRACTOR'S EMERGENCY NOTIFICATION PHONE NUMBER OR PAGER:
9. CONTRACTOR'S CONTROL CONSIDERATIONS
a. SAFETY MEASURES ARE IN PLACE TO ASSURE EXCAVATION AND PROCEDURES
MEET OR EXCEED ALL OSHA AND OTHER REQUIREMENTS.
b. LOCATION OF SHUT-OFF OR ISOLATION VALVES HAVE BEEN ESTABLISHED.
c. SOIL EROSION AND SEDIMENTATION CONTROLS WILL BE IMPLEMENTED
d. CONTINGENCY PLANS AND ACTIONS TO BE TAKEN IN THE EVENT OF AN
INCIDENT RESULTING IN UTILITIES INTERUPTION OR DAMAGE TO
FACILITIES.
(Attach additional sheets as necessary).
10. NOTES:
a. Receipt of a permit from the government does not relieve the contractor from responsibility for damage to utilities. Work shall always proceed in an orderly and effective manner to preclude potential damage or problems. The contractor will be liable for all damages to persons or property that occurs as a result of the contractor's fault or negligence.
b. When utilities have been located in the area to be excavated, hand digging will be used within 30 inches until the exact locations of all lines have been determined.
c. The Government reserves the right to specify additional precautionary measures to be employed if differing site conditions are determined to exist.
11. Remarks:
THE INFORMATION NOTED ABOVE IS ACCURATE AND TRUE AND THE WORK IS
READY TO PROCEED:
AUTHORIZED CONTRACTOR SIGNATURE DATE PROCEDURES FOR EXCAVATION IN
ACCORDANCE WITH PENNSYLVANIA ONE CALL (PA One Call) REQUIREMENTS
**************TO BE COMPLETED BY TYAD REPRESENTATIVE*********
PERMIT APPROVED - YES NO (see cover letter for reasons and corrective actions required with time frames)
AUTHORIZED D/IS SIGNATURE AND DATE: EXPIRATION DATE: SPECIAL
CONDITIONS OR PRECAUTIONARY MEASURES TO BE IMPLEMENTED:
THE FOLLOWING SECTIONS TO BE COMPLETED BY ENG DIV POC AFTER
RECEIPT OF PERMIT REQUEST:
12. DATE RECEIVED
13. DATE UTILITIES MARKED
14. UTILITIES IDENTIFIED ON-SITE:
POTENTIAL ASBESTOS
15. CONTROLS REQUIRED:
MEASURES TO BE
IMPLEMENTED:
PERMIT APPROVED -
AUTHORIZED SIGNATURE (Chief Eng Branch or Designated Alternate)
DATE
EXPIRATION DATE:
NOTICE to ALL CONTRACTORS INTALLING NEW UNDERGROUND
UTILITIES
All new underground utilities within the construction area shall be located and identified on as-built drawings using the Pennsylvania (North)
State Plane coordinate system (North American Datum
1983 Feet (NAD83)) to obtain a NORTHING and EASTING.
While vertical surveys will use the North American
Vertical Datum (NAVD) 1988 coordinate system for an
ELEVATION. Refer to Scope of work Section
17 Deliverables Section C paragraphs 1 through 9 for details.
Providing survey date is not a substitute for other marking methods. Contractors are responsible for implementing other markings such as tracing wire or tape as required