APPENDIX G - 01 74 19 construction waste management and disposal.pdf
PDF 49 KB Posted
- Solicitation number
- 697DCK-21-R-00041
About this file
This document contains an appendix and solicitation for a federal contract opportunity to design and construct a new building automation system for the Northern California TRACON facility located in Mather, California. The solicitation requires replacing the existing BAS with a new BACnet-compliant system and provides relevant details on the project scope, submission requirements, and evaluation criteria. Offerors must submit qualifications by May 5, 2021 and are invited to individual site visits on April 13-14, 2021 to inspect the facility. The selected contractor will be responsible for designing, installing, testing and commissioning a turnkey BAS solution that meets the requirements outlined in the appendix and solicitation documents.
View the file
Other files
Show all 32
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NORTHERN CALIFORNIA TRACON (NCT) FEB 8, 2021
BUILDING AUTOMATION SYSTEM REPLACEMENT
MATHER, CA
CONSTRUCTION WASTE MANAGEMENT 01 74 19 - 1
SECTION 01 74 19 - CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
PART 1 - GENERAL
1.1 SUMMARY
A. If the value of this contract when awarded is less than $100,000, this section does not take effect in this contract.
B. Section includes administrative and procedural requirements for the following:
1. Salvaging nonhazardous demolition and construction waste.
2. Recycling nonhazardous demolition and construction waste.
3. Disposing of nonhazardous demolition and construction waste.
1.2 DEFINITIONS
A. Construction Waste: Building, structure, and site improvement materials and other solid waste resulting from construction, remodeling, renovation, or repair operations. Construction waste includes packaging.
B. Demolition Waste: Building, structure, and site improvement materials resulting from demolition operations.
C. Disposal: Removal of demolition or construction waste and subsequent salvage, sale, recycling, or deposit in landfill, incinerator acceptable to authorities having jurisdiction.
D. Recycle: Recovery of demolition or construction waste for subsequent processing in preparation for reuse.
E. Salvage: Recovery of demolition or construction waste and subsequent sale or reuse in another facility.
F. Salvage and Reuse: Recovery of demolition or construction waste and subsequent incorporation into the Work.
1.3 MATERIALS OWNERSHIP
A. Unless otherwise indicated, demolition and construction waste becomes property of Contractor.
1.4 ACTION SUBMITTALS
A. Waste Management Plan: Submit plan at the Preinstallation Conference before each construction activity.
CONSTRUCTION WASTE MANAGEMENT 01 74 19 - 2
1.5 INFORMATIONAL SUBMITTALS
A. Waste Reduction Progress Reports: The Contractor must document all C&D disposal and diversion efforts and submit a Waste Diversion Summary Report to the COR Monthly. A copy of the report must also be submitted to the EOSH Services construction waste management address at 9-AJW-ConstructionWaste@faa.gov. Use construction/demolition waste form at the end of this section or equal. Include the following information:
1. Material category.
2. Total quantity of waste in tons.
3. Quantity of actual waste salvaged.
4. Quantity of actual waste recycled.
5. Total quantity of waste recovered (salvaged plus recycled) in tons.
6. Total quantity of waste recovered (salvaged plus recycled) as a percentage of total waste.
B. Waste Reduction Calculations: Before request for Substantial Completion, submit calculated end-of-Project rates for salvage, recycling, and disposal as a percentage of total waste generated by the Work.
C. Records of Donations: Indicate receipt and acceptance of salvageable waste donated to individuals and organizations. Indicate whether organization is tax exempt.
D. Records of Sales: Indicate receipt and acceptance of salvageable waste sold to individuals and organizations. Indicate whether organization is tax exempt.
E. Recycling and Processing Facility Records: Indicate receipt and acceptance of recyclable waste by recycling and processing facilities licensed to accept them. Include manifests, weight tickets, receipts, and invoices.
F. Landfill and Incinerator Disposal Records: Indicate receipt and acceptance of waste by landfills and incinerator facilities licensed to accept them. Include manifests, weight tickets, receipts, and invoices.
G. Qualification Data: For waste management coordinator and refrigerant recovery technician (if equipment containing refrigerant is present).
H. Statement of Refrigerant Recovery: Signed by refrigerant recovery technician responsible for recovering refrigerant, stating that all refrigerant that was present was recovered and that recovery was performed according to EPA regulations. Include name and address of technician and date refrigerant was recovered.
1.6 QUALITY ASSURANCE
A. Refrigerant Recovery Technician Qualifications: Universal certified by EPA-approved certification program.
B. Regulatory Requirements: Comply with transportation and disposal regulations of authorities having jurisdiction.
CONSTRUCTION WASTE MANAGEMENT 01 74 19 - 3
C. Waste Management Conference(s): Conduct conference(s) at Project site to comply with requirements in Section 01 31 00 "Project Management and Coordination." Review methods and procedures related to waste management including, but not limited to, the following:
1. Review and discuss waste management plan including responsibilities of the contractor(s).
2. Review requirements for documenting quantities of each type of waste and its disposition.
3. Review and finalize procedures for materials separation and verify availability of containers and bins needed to avoid delays.
4. Review procedures for periodic waste collection and transportation to recycling and disposal facilities.
5. Review waste management requirements for each trade.
1.7 WASTE MANAGEMENT PLAN
A. General: Develop a waste management plan according to requirements in this Section. Plan shall consist of waste identification and waste reduction work plan. Indicate quantities by weight or volume, but use same units of measure throughout waste management plan.
B. Waste Identification: Indicate anticipated types and quantities of waste generated by the Work.
C. Waste Reduction Work Plan: List each type of waste and whether it will be salvaged, recycled, or disposed of in landfill or incinerator. Include total quantity of each type of waste, quantity for each means of recovery, and handling and transportation procedures.
1. Salvaged Materials for Donation: For materials that will be donated to individuals and organizations, include list of their names, addresses, and telephone numbers.
2. Recycled Materials: Include list of local receivers and processors and type of recycled materials each will accept. Include names, addresses, and telephone numbers.
3. Disposed Materials: Indicate how and where materials will be disposed of. Include name, address, and telephone number of each landfill and incinerator facility.
4. Handling and Transportation Procedures: Include method that will be used for separating recyclable waste including sizes of containers, container labeling, and designated location where materials separation will be performed.
PART 2 - PRODUCTS
2.1 PERFORMANCE REQUIREMENTS
A. General: Achieve end-of-Project rates for salvage/recycling of 50 percent by weight of total nonhazardous solid waste generated by the Work. Practice efficient waste management in the use of materials in the course of the Work. Use all reasonable means to divert construction and demolition waste from landfills and incinerators. Facilitate recycling and salvage of materials.
CONSTRUCTION WASTE MANAGEMENT 01 74 19 - 4
PART 3 - EXECUTION
3.1 PLAN IMPLEMENTATION
A. General: Implement approved waste management plan. Provide handling, containers, storage, signage, transportation, and other items as required to implement waste management plan during the entire duration of the Contract.
1. Comply with operation, termination, and removal requirements in Section 01 50 00 "Temporary Facilities and Controls."
B. Training: Train workers, subcontractors, and suppliers on proper waste management procedures, as appropriate for the Work.
1. Distribute waste management plan to everyone concerned within three days of submittal return.
2. Distribute waste management plan to entities when they first begin work on-site. Review plan procedures and locations established for salvage, recycling, and disposal.
C. Site Access and Temporary Controls: Conduct waste management operations to ensure minimum interference with roads, streets, walks, walkways, and other adjacent occupied and used facilities.
1. Designate and label specific areas on Project site necessary for separating materials that are to be salvaged and recycled.
2. Comply with Section 01 50 00 "Temporary Facilities and Controls" for controlling dust and dirt, environmental protection, and noise control.
3.2 RECYCLING DEMOLITION AND CONSTRUCTION WASTE, GENERAL
A. Preparation of Waste: Prepare and maintain recyclable waste materials according to recycling or reuse facility requirements. Maintain materials free of dirt, adhesives, solvents, petroleum contamination, and other substances deleterious to the recycling process.
B. Procedures: Separate recyclable waste from other waste materials, trash, and debris. Separate recyclable waste by type at Project site to the maximum extent practical according to approved construction waste management plan.
1. Provide appropriately marked containers or bins for controlling recyclable waste until removed from Project site. Include list of acceptable and unacceptable materials at each container and bin.
a. Inspect containers and bins for contamination and remove contaminated materials if found.
2. Stockpile processed materials on-site without intermixing with other materials. Place, grade, and shape stockpiles to drain surface water. Cover to prevent windblown dust.
CONSTRUCTION WASTE MANAGEMENT 01 74 19 - 5
3. Stockpile materials away from construction area. Do not store within drip line of remaining trees.
4. Store components off the ground and protect from the weather.
5. Remove recyclable waste from FAA's property and transport to recycling receiver or processor as often as required to prevent overfilling bins.
3.3 RECYCLING DEMOLITION WASTE
The lists of materials below are examples of recyclable waste material, not all the materials listed maybe present onsite.
A. Asphalt Paving: Break up and transport paving to asphalt-recycling facility.
B. Concrete: Remove reinforcement and other metals from concrete and sort with other metals.
1. Pulverize concrete to maximum size as required by recycling facility.
2. Crush concrete and screen as required by recycling facility.
C. Masonry: Remove metal reinforcement, anchors, and ties from masonry and sort with other metals.
1. Pulverize damaged masonry to maximum size as required by recycling facility.
2. Clean and stack undamaged, whole masonry units on wood pallets.
D. Wood Materials: Sort and stack members according to size, type, and length. Separate lumber, engineered wood products, panel products, and treated wood materials.
E. Metals: Separate metals by type.
1. Structural Steel: Stack members according to size, type of member, and length.
2. Remove and dispose of bolts, nuts, washers, and other rough hardware.
F. Gypsum Board: Stack large clean pieces on wood pallets or in container and store in a dry location. Remove edge trim and sort with other metals. Remove and dispose of fasteners.
G. Acoustical Ceiling Panels and Tile: Stack large clean pieces on wood pallets and store in a dry location.
H. Metal Suspension System: Separate metal members, including trim and other metals from acoustical panels and tile, and sort with other metals.
I. Carpet and Pad: Roll large pieces tightly after removing debris, trash, adhesive, and tack strips.
1. Store clean, dry carpet and pad in a closed container or trailer.
J. Carpet Tile: Remove debris, trash, and adhesive.
1. Stack tile on pallet and store clean, dry carpet in a closed container or trailer.
CONSTRUCTION WASTE MANAGEMENT 01 74 19 - 6
K. Piping: Reduce piping to straight lengths and store by material and size. Separate supports, hangers, valves, sprinklers, and other components by material and size.
L. Conduit: Reduce conduit to straight lengths and store by material and size.
M. Lamps: Separate lamps by type and store according to requirements in 40 CFR 273.
3.4 RECYCLING CONSTRUCTION WASTE
A. Packaging:
1. Cardboard and Boxes: Break down packaging into flat sheets. Bundle and store in a dry location.
2. Polystyrene Packaging: Separate and bag materials.
3. Pallets: As much as possible, require deliveries using pallets to remove pallets from
Project site. For pallets that remain on-site, break down pallets into component wood pieces and comply with requirements for recycling wood.
4. Crates: Break down crates into component wood pieces and comply with requirements for recycling wood.
B. Wood Materials:
1. Clean Cut-Offs of Lumber: Grind or chip into small pieces.
2. Clean Sawdust: Bag sawdust that does not contain painted or treated wood.
C. Gypsum Board: Stack large clean pieces on wood pallets or in container and store in a dry location.
1. Clean Gypsum Board: Grind scraps of clean gypsum board using small mobile chipper or hammer mill. Screen out paper after grinding.
D. Paint: Seal containers and store by type.
3.5 DISPOSAL OF WASTE
A. General: Except for items or materials to be recycled, remove waste materials from Project site and legally dispose of them in a landfill or incinerator acceptable to authorities having jurisdiction.
1. Except as otherwise specified, do not allow waste materials that are to be disposed of accumulate on-site.
2. Remove and transport debris in a manner that will prevent spillage on adjacent surfaces and areas.
B. Burning: Do not burn waste materials.
CONSTRUCTION WASTE MANAGEMENT 01 74 19 - 7
3.6 ATTACHMENTS
A. Summary of C&D solid Waste Disposal and Diversion Form.
END OF SECTION 01 74 19
| PART 1 - GENERAL |
| 1.1 SUMMARY |
| A. If the value of this contract when awarded is less than $100,000, this section does not take effect in this contract. |
| B. Section includes administrative and procedural requirements for the following: |
| 1. Salvaging nonhazardous demolition and construction waste. |
| 2. Recycling nonhazardous demolition and construction waste. |
| 3. Disposing of nonhazardous demolition and construction waste. |
| 1.2 DEFINITIONS |
| A. Construction Waste: Building, structure, and site improvement materials and other solid waste resulting from construction, remodeling, renovation, or repair operations. Construction waste includes packaging. |
| B. Demolition Waste: Building, structure, and site improvement materials resulting from demolition operations. |
| C. Disposal: Removal of demolition or construction waste and subsequent salvage, sale, recycling, or deposit in landfill, incinerator acceptable to authorities having jurisdiction. |
| D. Recycle: Recovery of demolition or construction waste for subsequent processing in preparation for reuse. |
| E. Salvage: Recovery of demolition or construction waste and subsequent sale or reuse in another facility. |
| F. Salvage and Reuse: Recovery of demolition or construction waste and subsequent incorporation into the Work. |
| 1.3 MATERIALS OWNERSHIP |
| A. Unless otherwise indicated, demolition and construction waste becomes property of Contractor. |
| 1.4 ACTION SUBMITTALS |
| A. Waste Management Plan: Submit plan at the Preinstallation Conference before each construction activity. |
| 1.5 INFORMATIONAL SUBMITTALS |
| A. Waste Reduction Progress Reports: The Contractor must document all C&D disposal and diversion efforts and submit a Waste Diversion Summary Report to the COR Monthly. A copy of the report must also be submitted to the EOSH Services construction was... |
| 1. Material category. |
| 2. Total quantity of waste in tons. |
| 3. Quantity of actual waste salvaged. |
| 4. Quantity of actual waste recycled. |
| 5. Total quantity of waste recovered (salvaged plus recycled) in tons. |
| 6. Total quantity of waste recovered (salvaged plus recycled) as a percentage of total waste. |
| B. Waste Reduction Calculations: Before request for Substantial Completion, submit calculated end-of-Project rates for salvage, recycling, and disposal as a percentage of total waste generated by the Work. |
| C. Records of Donations: Indicate receipt and acceptance of salvageable waste donated to individuals and organizations. Indicate whether organization is tax exempt. |
| D. Records of Sales: Indicate receipt and acceptance of salvageable waste sold to individuals and organizations. Indicate whether organization is tax exempt. |
| E. Recycling and Processing Facility Records: Indicate receipt and acceptance of recyclable waste by recycling and processing facilities licensed to accept them. Include manifests, weight tickets, receipts, and invoices. |
| F. Landfill and Incinerator Disposal Records: Indicate receipt and acceptance of waste by landfills and incinerator facilities licensed to accept them. Include manifests, weight tickets, receipts, and invoices. |
| G. Qualification Data: For waste management coordinator and refrigerant recovery technician (if equipment containing refrigerant is present). |
| H. Statement of Refrigerant Recovery: Signed by refrigerant recovery technician responsible for recovering refrigerant, stating that all refrigerant that was present was recovered and that recovery was performed according to EPA regulations. Include n... |
| 1.6 QUALITY ASSURANCE |
| A. Refrigerant Recovery Technician Qualifications: Universal certified by EPA-approved certification program. |
| B. Regulatory Requirements: Comply with transportation and disposal regulations of authorities having jurisdiction. |
| C. Waste Management Conference(s): Conduct conference(s) at Project site to comply with requirements in Section 01 31 00 "Project Management and Coordination." Review methods and procedures related to waste management including, but not limited to, th... |
| 1. Review and discuss waste management plan including responsibilities of the contractor(s). |
| 2. Review requirements for documenting quantities of each type of waste and its disposition. |
| 3. Review and finalize procedures for materials separation and verify availability of containers and bins needed to avoid delays. |
| 4. Review procedures for periodic waste collection and transportation to recycling and disposal facilities. |
| 5. Review waste management requirements for each trade. |
| 1.7 WASTE MANAGEMENT PLAN |
| A. General: Develop a waste management plan according to requirements in this Section. Plan shall consist of waste identification and waste reduction work plan. Indicate quantities by weight or volume, but use same units of measure throughout waste ma... |
| B. Waste Identification: Indicate anticipated types and quantities of waste generated by the Work. |
| C. Waste Reduction Work Plan: List each type of waste and whether it will be salvaged, recycled, or disposed of in landfill or incinerator. Include total quantity of each type of waste, quantity for each means of recovery, and handling and transportat... |
| 1. Salvaged Materials for Donation: For materials that will be donated to individuals and organizations, include list of their names, addresses, and telephone numbers. |
| 2. Recycled Materials: Include list of local receivers and processors and type of recycled materials each will accept. Include names, addresses, and telephone numbers. |
| 3. Disposed Materials: Indicate how and where materials will be disposed of. Include name, address, and telephone number of each landfill and incinerator facility. |
| 4. Handling and Transportation Procedures: Include method that will be used for separating recyclable waste including sizes of containers, container labeling, and designated location where materials separation will be performed. |
| PART 2 - PRODUCTS |
| 2.1 PERFORMANCE REQUIREMENTS |
| A. General: Achieve end-of-Project rates for salvage/recycling of 50 percent by weight of total nonhazardous solid waste generated by the Work. Practice efficient waste management in the use of materials in the course of the Work. Use all reasonable m... |
| PART 3 - EXECUTION |
| 3.1 PLAN IMPLEMENTATION |
| A. General: Implement approved waste management plan. Provide handling, containers, storage, signage, transportation, and other items as required to implement waste management plan during the entire duration of the Contract. |
| 1. Comply with operation, termination, and removal requirements in Section 01 50 00 "Temporary Facilities and Controls." |
| B. Training: Train workers, subcontractors, and suppliers on proper waste management procedures, as appropriate for the Work. |
| 1. Distribute waste management plan to everyone concerned within three days of submittal return. |
| 2. Distribute waste management plan to entities when they first begin work on-site. Review plan procedures and locations established for salvage, recycling, and disposal. |
| C. Site Access and Temporary Controls: Conduct waste management operations to ensure minimum interference with roads, streets, walks, walkways, and other adjacent occupied and used facilities. |
| 1. Designate and label specific areas on Project site necessary for separating materials that are to be salvaged and recycled. |
| 2. Comply with Section 01 50 00 "Temporary Facilities and Controls" for controlling dust and dirt, environmental protection, and noise control. |
| 3.2 RECYCLING DEMOLITION AND CONSTRUCTION WASTE, GENERAL |
| A. Preparation of Waste: Prepare and maintain recyclable waste materials according to recycling or reuse facility requirements. Maintain materials free of dirt, adhesives, solvents, petroleum contamination, and other substances deleterious to the recy... |
| B. Procedures: Separate recyclable waste from other waste materials, trash, and debris. Separate recyclable waste by type at Project site to the maximum extent practical according to approved construction waste management plan. |
| 1. Provide appropriately marked containers or bins for controlling recyclable waste until removed from Project site. Include list of acceptable and unacceptable materials at each container and bin. |
| a. Inspect containers and bins for contamination and remove contaminated materials if found. |
| 2. Stockpile processed materials on-site without intermixing with other materials. Place, grade, and shape stockpiles to drain surface water. Cover to prevent windblown dust. |
| 3. Stockpile materials away from construction area. Do not store within drip line of remaining trees. |
| 4. Store components off the ground and protect from the weather. |
| 5. Remove recyclable waste from FAA's property and transport to recycling receiver or processor as often as required to prevent overfilling bins. |
| 3.3 RECYCLING DEMOLITION WASTE |
| The lists of materials below are examples of recyclable waste material, not all the materials listed maybe present onsite. |
| A. Asphalt Paving: Break up and transport paving to asphalt-recycling facility. |
| B. Concrete: Remove reinforcement and other metals from concrete and sort with other metals. |
| 1. Pulverize concrete to maximum size as required by recycling facility. |
| 2. Crush concrete and screen as required by recycling facility. |
| C. Masonry: Remove metal reinforcement, anchors, and ties from masonry and sort with other metals. |
| 1. Pulverize damaged masonry to maximum size as required by recycling facility. |
| 2. Clean and stack undamaged, whole masonry units on wood pallets. |
| D. Wood Materials: Sort and stack members according to size, type, and length. Separate lumber, engineered wood products, panel products, and treated wood materials. |
| E. Metals: Separate metals by type. |
| 1. Structural Steel: Stack members according to size, type of member, and length. |
| 2. Remove and dispose of bolts, nuts, washers, and other rough hardware. |
| F. Gypsum Board: Stack large clean pieces on wood pallets or in container and store in a dry location. Remove edge trim and sort with other metals. Remove and dispose of fasteners. |
| G. Acoustical Ceiling Panels and Tile: Stack large clean pieces on wood pallets and store in a dry location. |
| H. Metal Suspension System: Separate metal members, including trim and other metals from acoustical panels and tile, and sort with other metals. |
| I. Carpet and Pad: Roll large pieces tightly after removing debris, trash, adhesive, and tack strips. |
| 1. Store clean, dry carpet and pad in a closed container or trailer. |
| J. Carpet Tile: Remove debris, trash, and adhesive. |
| 1. Stack tile on pallet and store clean, dry carpet in a closed container or trailer. |
| K. Piping: Reduce piping to straight lengths and store by material and size. Separate supports, hangers, valves, sprinklers, and other components by material and size. |
| L. Conduit: Reduce conduit to straight lengths and store by material and size. |
| M. Lamps: Separate lamps by type and store according to requirements in 40 CFR 273. |
| 3.4 RECYCLING CONSTRUCTION WASTE |
| A. Packaging: |
| 1. Cardboard and Boxes: Break down packaging into flat sheets. Bundle and store in a dry location. |
| 2. Polystyrene Packaging: Separate and bag materials. |
| 3. Pallets: As much as possible, require deliveries using pallets to remove pallets from Project site. For pallets that remain on-site, break down pallets into component wood pieces and comply with requirements for recycling wood. |
| 4. Crates: Break down crates into component wood pieces and comply with requirements for recycling wood. |
| B. Wood Materials: |
| 1. Clean Cut-Offs of Lumber: Grind or chip into small pieces. |
| 2. Clean Sawdust: Bag sawdust that does not contain painted or treated wood. |
| C. Gypsum Board: Stack large clean pieces on wood pallets or in container and store in a dry location. |
| 1. Clean Gypsum Board: Grind scraps of clean gypsum board using small mobile chipper or hammer mill. Screen out paper after grinding. |
D. Paint: Seal containers and store by type.
| 3.5 DISPOSAL OF WASTE |
| A. General: Except for items or materials to be recycled, remove waste materials from Project site and legally dispose of them in a landfill or incinerator acceptable to authorities having jurisdiction. |
| 1. Except as otherwise specified, do not allow waste materials that are to be disposed of accumulate on-site. |
| 2. Remove and transport debris in a manner that will prevent spillage on adjacent surfaces and areas. |
B. Burning: Do not burn waste materials.
| 3.6 ATTACHMENTS |
| A. Summary of C&D solid Waste Disposal and Diversion Form. |