This document is an amendment to a solicitation for the design and construction of a new building automation system for the Northern California TRACON facility. The amendment provides responses to vendor questions, including confirmation that mechanical drawings have been added to the solicitation appendices and clarification that teaming agreements do not count against page limits. Offerors must submit any additional questions by April 23, 2021 and finalize proposals by May 5, 2021 to the contracting officer at the Federal Aviation Administration. Site visits are scheduled for April 13-14, 2021 with a maximum of four attendees per vendor. The selected vendor will replace the building automation system at the Northern California TRACON located in Mather, California, in accordance with the terms of the solicitation and subsequent amendments.

View the file

Other files

File Type Posted
APPENDIX K SECTION 10270 - ACCESS FLOORING.pdf PDF
APPENDIX L Ops Room VAVs Pictures.pdf PDF
697DCK-21-R-00041 Amendment 0005.pdf PDF
APPENDIX J Sequences of Operation.pdf PDF
APPENDIX B - AS BUILT CONTROL DRAWINGS_Revised.pdf PDF
Site Visit Attendee Log.pdf PDF
697DCK-21-R-00041_Amendment 0004.pdf PDF
ADDPENDIX J Sequences of Operation.pdf PDF
697DCK-21-R-00041 Amendment 0004.pdf PDF
SIR 697DCK-21-R-00041.pdf PDF
APPENDIX I SECTION 01 31 00 S Proj Mgmt and Coord for Sustainable Design.pdf PDF
697DCK-21-R-00041_Amendment 0004.pdf PDF
SIR 697DCK-21-R-00041.pdf PDF
APPENDIX H NCT Mechanical Plans.pdf PDF
Questions and Responses April 27 2021.pdf PDF
SIR 697DCK-21-R-00041 Amendment 0002.pdf PDF
SF330.pdf PDF
SIR 697DCK-21-R-00041_Amendment 0001.pdf PDF
SIR 697DCK-21-R-00041.pdf PDF
SIR 697DCK-21-R-00041.pdf PDF
Corporate Experience Form.pdf PDF
Past Performance Questionnaire.pdf PDF
APPENDIX B - AS BUILT CONTROL DRAWINGS.pdf PDF
APPENDIX G - 01 74 19 construction waste management and disposal.pdf PDF
APPENDIX E - 23 09 23 Instrumentation and Controls.pdf PDF
APPENDIX D - COVID-19 Contractual Requirement (1).pdf PDF
Attachment J-1 Scope of Work.pdf PDF
APPENDIX F - ORM Concepts.pdf PDF
SIR 697DCK-21-R-00041.pdf PDF
APPENDIX C - AS BUILT COOLING TOWERS.pdf PDF
Attachment J-2 Wage Determiantion CA20200007.pdf PDF
APPENDIX A - AS BUILT MECHANICAL DRAWINGS SCHEDULE.pdf PDF
Show all 32

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE

5. PROJECT NO. (If applicable)2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ.NO.

PAGE OF PAGES

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6)

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

CODE

9A. AMENDMENT OF SOLICITATION NO.

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

Items 8 and 15, and returning is extended, is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required.)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

(x) A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO THE AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14.

E. IMPORTANT: Contractor is not, is required to sign this document and return

ORDER NO. IN ITEM 10A.

1 2

0003 05/04/2021

FEDERAL AVIATION ADMINISTRATION

AAQ-500 - REGIONAL ACQUISITIONS

1701 COLUMBIA AVENUE

COLLEGE PARK GA 30337

AAQ510ATL-AFN

x

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

separate letter or telegram which includes a reference to the solicitation and amendment number. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT

THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By ___________ x x

697DCK-21-R-00041

copies to the issuing office.

03/17/2021

(x)

Amendment 0003 is issued for the following reasons:

1. Question: Can we get a complete set of mechanical drawings?

Response: APPENDIX H NCT Mechanical Plans has been added to Section J.

2. Question: Are teaming agreements necessary or are we able to state which contractors are on teaming agreements and for what scope? Alternatively, can the teaming agreement be in an appendix that is not page limited?

Response: In accordance with M.2 VOLUME I & II, Factor 4 provide a teaming agreement for

Continued ...

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. CONTRACT AUTHORITY 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

Katherine Fogle

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

NAME OF OFFEROR OR CONTRACTOR

2 2

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

697DCK-21-R-00041/0003

major subcontractors and the portion of the work performed by the major subcontractor. Team agreements will NOT be counted in the page limit.

All other terms and conditions remain unchanged.

File details come from the government source that posted it. Updated .