About this file

This is a Direct Labor Burden Calculation form issued by the State of Colorado Office of the State Architect State Buildings Program for the CAVEA Lighting project at Metropolitan State University of Denver (Project No. 26PR05). The form requires contractors and major subcontractors to document their labor overhead costs as a percentage of total labor, including expenses such as payroll taxes, pension costs, health and dental insurance, life insurance, and other benefits paid to employees. The labor burden percentage must be agreed upon by both the contractor and the Principal Representative prior to contract execution and will be incorporated into the contract as part of Exhibit A. The calculation will be used for any future Change Order Proposals submitted under SC-6.312 Line 2 for the prime contractor and Line 10 for major subcontractors including electricians, plumbers, mechanical contractors, excavators, millwork, and concrete contractors.

The form requires submission of one Labor Burden Calculation Sheet per contractor and for each subcontractor involved in the project. The State of Colorado reserves the right to require backup documentation and verification of all information included in the labor burden calculations. The document includes a blank calculation template with line items for payroll taxes, pension costs, health insurance, dental insurance, life insurance, and other specified costs, with a total labor burden percentage field. The form was issued in August 2023 under State Form SBP-6.18.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATE OF COLORADO

OFFICE OF THE STATE ARCHITECT

STATE BUILDINGS PROGRAM

DIRECT LABOR BURDEN CALCULATION

Institution/Agency:
Metropolitan State University of Denver
Project No./Name:
26PR05 / CAVEA Lighting

This form is required to be submitted for review prior to execution of a construction agreement.

List items below by the percentage of what makes up the total labor overhead; Items include benefits that a contractor pays to employees on their payroll. Examples include taxes, pension cost, health and dental insurance etc. The Labor Burden percentage must be agreed to by both the contractor and Principal Representative and will be included in the contract as part of Exhibit A and will be used in the calculation of any future Change Order Proposals (SC-6.312) Line 2.

Major sub-contractors defined as electricians, plumbers, mechanical contractors, excavators, millwork, concrete, block layers etc. Please provide one (1) Labor Burden Calculation Sheet per contractor and for each sub-contractor. These labor burdens shall be used in the calculation of any future Change Order Proposals (SC-6.312) Line 10.

State reserves the right to require back-up confirmation of all information included in this calculation.

State Form SBP–6.18 Issued 8/2023 image1.jpg image2.emf

Microsoft_Excel_Worksheet.xlsx Sheet1

Contractor/Subcontractor Name:

Percent of Salary Paid

Payroll Taxes

Pension Costs

Health Insurance

Dental Insurance

Life Insurance

Other (Specify) Description: _________________________

Other (Specify) Description: _________________________

Total Labor Burden Percentage: 0%