Appendix C_Sample Direct Labor Burden Calculation_CAVEA Lighting MSU Denver.docx
DOCX document 43 KB Posted
- Attached to
- CAVEA Lighting
- Solicitation number
- DQ1 GMAA 2027000142 1
- Issued by
- Denver County, Denver City, Colorado
About this file
This is a Direct Labor Burden Calculation form issued by the State of Colorado Office of the State Architect State Buildings Program for the CAVEA Lighting project at Metropolitan State University of Denver (Project No. 26PR05). The form requires contractors and major subcontractors to document their labor overhead costs as a percentage of total labor, including expenses such as payroll taxes, pension costs, health and dental insurance, life insurance, and other benefits paid to employees. The labor burden percentage must be agreed upon by both the contractor and the Principal Representative prior to contract execution and will be incorporated into the contract as part of Exhibit A. The calculation will be used for any future Change Order Proposals submitted under SC-6.312 Line 2 for the prime contractor and Line 10 for major subcontractors including electricians, plumbers, mechanical contractors, excavators, millwork, and concrete contractors.
The form requires submission of one Labor Burden Calculation Sheet per contractor and for each subcontractor involved in the project. The State of Colorado reserves the right to require backup documentation and verification of all information included in the labor burden calculations. The document includes a blank calculation template with line items for payroll taxes, pension costs, health insurance, dental insurance, life insurance, and other specified costs, with a total labor burden percentage field. The form was issued in August 2023 under State Form SBP-6.18.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATE OF COLORADO
OFFICE OF THE STATE ARCHITECT
STATE BUILDINGS PROGRAM
DIRECT LABOR BURDEN CALCULATION
| Institution/Agency: |
| Metropolitan State University of Denver |
| Project No./Name: |
| 26PR05 / CAVEA Lighting |
This form is required to be submitted for review prior to execution of a construction agreement.
List items below by the percentage of what makes up the total labor overhead; Items include benefits that a contractor pays to employees on their payroll. Examples include taxes, pension cost, health and dental insurance etc. The Labor Burden percentage must be agreed to by both the contractor and Principal Representative and will be included in the contract as part of Exhibit A and will be used in the calculation of any future Change Order Proposals (SC-6.312) Line 2.
Major sub-contractors defined as electricians, plumbers, mechanical contractors, excavators, millwork, concrete, block layers etc. Please provide one (1) Labor Burden Calculation Sheet per contractor and for each sub-contractor. These labor burdens shall be used in the calculation of any future Change Order Proposals (SC-6.312) Line 10.
State reserves the right to require back-up confirmation of all information included in this calculation.
State Form SBP–6.18 Issued 8/2023 image1.jpg image2.emf
Microsoft_Excel_Worksheet.xlsx Sheet1
Contractor/Subcontractor Name:
Percent of Salary Paid
Payroll Taxes
Pension Costs
Health Insurance
Dental Insurance
Life Insurance
Other (Specify) Description: _________________________
Other (Specify) Description: _________________________
Total Labor Burden Percentage: 0%
File details come from the government source that posted it. Updated .