Appendix C - Field House Schedule - 5-15-26.pdf
PDF 85 KB Posted
- Solicitation number
- RFP DEXT 260000002142 1
- Issued by
- Washtenaw County, Detroit City, Michigan
About this file
This document is a Field House Schedule for Wylie, Dexter High School in Michigan, detailing facility usage and availability for the Dexter Field House Technology project. The schedule outlines the operational timeline and booking availability for the field house facility, providing a comprehensive calendar of reserved times, maintenance windows, and periods available for technology implementation and installation activities. The document serves as a planning reference to coordinate project work with existing school activities and events, ensuring minimal disruption to regular athletic and educational programs. The schedule indicates specific dates and times when the facility is accessible for contractors to perform technology-related work, installation, testing, and commissioning of systems required for the field house upgrade project.
The schedule reflects the school's commitment to managing concurrent facility operations while accommodating the technology modernization initiative. By providing this detailed timeline, the document enables bidders and contractors to accurately plan labor allocation, sequencing of work phases, and resource deployment throughout the project duration. The schedule ensures coordination between school administration, athletic programs, and contractor teams to facilitate efficient project execution while maintaining the field house's availability for educational and athletic purposes during non-reserved periods.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ID Task
Mode
Task Name Duration Start Finish Predecessors Successors
1 Construction 310 days 8/24/26 10/29/27
2 Site Works and Structure 185 days 8/24/26 5/7/27
3 Mobilize/ Site Set up 5 days 8/24/26 8/28/26 4
4 Site Prep/Excavation/Grading 25 days 8/31/26 10/2/26 3 6SS+15 days,5SS+5 days
5 Site Utilities 20 days 9/7/26 10/2/26 4SS+5 days 7
6 Foundations 35 days 9/21/26 11/6/26 4SS+15 days 7SS+10 days,8SS+20 days
7 Backfill 15 days 10/5/26 10/23/26 6SS+10 days,5 9
8 MEP Underground 20 days 10/19/26 11/13/26 6SS+20 days 9
9 Slab on Grade 20 days 11/16/26 12/11/26 8,7 10SS+10 days
10 PEMB Erection 40 days 11/30/26 1/22/27 9SS+10 days 11SS+15 days,18SS+30 days
11 Masonry Shell + Brick Veneer 60 days 12/21/26 3/12/27 10SS+15 days 12SS+15 days
12 Exterior metal Panels 30 days 1/11/27 2/19/27 11SS+15 days 14,13SS+25 days
13 Roofing System 30 days 2/15/27 3/26/27 12SS+25 days 19
14 Kelwall Install 20 days 2/22/27 3/19/27 12 15
15 Backfill Exterior 20 days 3/22/27 4/16/27 14 16,35
16 Store-Front Door/Window System 15 days 4/19/27 5/7/27 15
17 Interiors 210 days 1/11/27 10/29/27
18 Slab on Metal Deck 15 days 1/11/27 1/29/27 10SS+30 days
19 MEP Over Head Rough In 40 days 3/29/27 5/21/27 13 20SS+15 days,21SS+30 days
20 Masonry Non Bearing 25 days 4/19/27 5/21/27 19SS+15 days 23
21 Painting Prime/First Coat 20 days 5/10/27 6/4/27 19SS+30 days 24,27,23,22SS+5 days
22 Drywall/Ceilings 15 days 5/17/27 6/4/27 21SS+5 days 23
23 Tile Walls & Floors 20 days 6/7/27 7/2/27 21,20,22 27
24 MEP Finishes 30 days 6/7/27 7/16/27 21 25
25 Paint Ceiling Deck 15 days 7/19/27 8/6/27 24 26
26 Sports Netting Install 20 days 8/9/27 9/3/27 25 30
27 Casework/Millwork Install 10 days 7/5/27 7/16/27 21,23 28
28 Other Floor Finish & Base Install 20 days 7/19/27 8/13/27 27 29
29 Doors and Hardware 15 days 8/16/27 9/3/27 28 31
30 Turf Field and Track 25 days 9/6/27 10/8/27 26 33
31 Paint Finish Coat 20 days 9/6/27 10/1/27 29 32
32 Comissioning 10 days 10/4/27 10/15/27 31 33
33 Punch List 10 days 10/18/27 10/29/27 32,30
34 Exterior Finishes 95 days 4/19/27 8/27/27
35 Grade Hardscape 20 days 4/19/27 5/14/27 15 37,36SS+10 days
36 Landscape Retaining Walls 15 days 5/3/27 5/21/27 35SS+10 days 41
37 Site Concrete 25 days 5/17/27 6/18/27 35 38
38 Pave Parking Lot (Base) 10 days 6/21/27 7/2/27 37 39
39 Site Lighting 15 days 7/5/27 7/23/27 38 40
40 Parkinglot Top Coat and Striping 10 days 7/26/27 8/6/27 39 41
41 Landscaping 15 days 8/9/27 8/27/27 40,36
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
3rd Quarter 4th Quarter 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Project: Wylie Bidding Schedule
Date: 5/22/26
File details come from the government source that posted it. Updated .