This is a cost breakdown template (Appendix A) for construction proposals submitted to Columbus Air Force Base. The template is designed for the "Repair Kidde Pool, B948" project under solicitation number FA302226R0002. Vendors must complete the form with their company information, NAICS code, CAGE code, and proposed period of performance, along with the number of days the proposal and price remain valid.
The cost breakdown structure requires vendors to itemize costs across multiple categories: bonds and insurance (certificate of insurance, performance bonds, payment bonds, and bid bonds); mobilization; architecture and engineering design (at 35%, 65%, 95%, and 100% completion levels); materials; equipment; labor hours with associated rates; miscellaneous charges including Mississippi state tax; and a final construction project total. The template emphasizes that offerors bear sole responsibility for providing adequate supporting data and documentation, and must demonstrate the reasonableness of all proposed pricing through comprehensive basis and rationale statements. Government personnel will use the completed worksheets to evaluate proposals, requiring that all cost information be current, complete, accurate, and fully supportable.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFI Answer FAP Catch Up Approval Memo - 19 May 23.pdf | ||
| RFI Answer.docx | DOCX document | |
| CAFB Standards.pdf | ||
| EAL Form.pdf | ||
| Solicitation - FA302226R0009.pdf | ||
| Contractors CUI Training Slides.pptx | PPTX presentation | |
| Wage Determination.pdf | ||
| SOW Replace Fire Alarms.pdf | ||
| MFR CUI Contractor Training Acknowledgment July 2024.pdf | ||
| AF Form 66 Template.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CAFB
| Appendix A - COLUMBUS AIR FORCE BASE | |||||
| INSTRUCTIONS: Please provide information that properly reflects the total cost of the project. Refer to the Statement of Work and Sections L and M in the solicitation to ensure that your proposal meets the requirementsof this project. | |||||
| SOLICITATION NUMBER: | |||||
| CONSTRUCTION PRICE PROPOSAL BREAKDOWN | |||||
| VENDOR'S INFORMATION | |||||
| Name: | |||||
| Address: | |||||
| Phone Number: | |||||
| Email: | |||||
| NAICS Code | |||||
| Cage Code: | |||||
| SOLICITATION INFORMATION | |||||
| Title of Project: Repair Kidde Pool, B948 | |||||
| Solicitation Number: FA302226R0002 | |||||
| Proposed Period of Performance: | |||||
| Number of Days Proposal and Price are Valid: | |||||
| BONDS AND INSURANCE | QTY | UNIT OF ISSUE | PRICE | TOTAL | |
| Certificate of Insurance | 1 | ||||
| Performance Bonds | 1 | ||||
| Payment Bonds | 1 | ||||
| Bid Bonds | 1 | ||||
| subtotal | |||||
| MOBILIZATION | QTY | UNIT OF ISSUE | PRICE | TOTAL | |
| subtotal | |||||
| ARCHITECTURE AND ENGINEERING DESIGN | QTY | UNIT OF ISSUE | PRICE | TOTAL | |
| 35% Design | |||||
| 65% Design | |||||
| 95% Design | |||||
| 100% Design (Construction Set) | |||||
| subtotal | |||||
| MATERIAL | QTY | UNIT OF ISSUE | PRICE | TOTAL | |
| subtotal | |||||
| EQUIPMENT | QTY | UNIT OF ISSUE | PRICE | TOTAL | |
| subtotal | |||||
| LABOR | HOURS | UNIT OF ISSUE | RATE | AMOUNT | |
| subtotal | |||||
| MISCELLANEOUS CHARGES | QTY | UNIT OF ISSUE | PRICE | TOTAL | |
| Misissippi State Tax | |||||
| subtotal | |||||
| CONSTRUCTION PROJECT | TOTAL PROJECT PRICE |
| GENERAL INFORMATION |
| The purpose of the requested information in the attached worksheets is to assist government personnel in the review and evaluation of proposals submitted by offerors. Offerors are reminded that the responsibility for providing adequate supporting data and attachments lies solely with them. Further, the offeror must also bear the burden of proof in establishing reasonableness of proposed pricing; therefore, it is in the offeror’s best interest to submit a fully supportable and well-prepared cost proposal that reflects the total cost of the project. The basis and rationale for all proposed costs should be provided as part of the proposal so that Government personnel can place reliance on the information as current, complete and accurate. |