APPENDIX_5_-_Utility_Work_Schedules-Combined.pdf
PDF 5 MB Posted
- Attached to
- Countywide Mast Arms - Group 3 (Rebid)
- Solicitation number
- 24-0633-ITB-C
- Issued by
- Pinellas County, Clewiston City, Florida
About this file
The attached document is a comprehensive Utility Work Schedule for Pinellas County, Florida, involving multiple utility agencies including Crown Castle, Duke Energy Distribution, Frontier, Spectrum Sunshine State LLC, Knology Broadband (WOW!), TECO Peoples Gas, and Uniti Fiber/Southern Light. The document details utility relocation and adjustment work for a countywide mast arm signalization project at five intersections: Lake St. George Drive at Tampa Road, West Lake Road at Tampa Road, 113th Street at 54th Avenue North, Park Boulevard at Ridge Road, and Park Boulevard at Seminole Boulevard. The project involves raising, adjusting, and transferring utility infrastructure, including overhead lines, conduits, poles, and fiber optic cables to accommodate new mast arm signal installations and minor roadway improvements.
The utility work schedules outline specific requirements for each utility agency, including normal business hours, emergency contact information, and detailed work activities. Most agencies have estimated non-construction times ranging from 30-85 calendar days, with construction activities estimated between 0-26 calendar days. Special conditions include coordinating with roadway contractors, maintaining facility access, using extreme caution during excavation, and securing joint use agreements with Duke Energy for pole attachments. The schedules emphasize the need for advance notifications, adherence to safety protocols, and coordination to minimize service disruptions. Funding and specific budget details are not explicitly stated in the document, but the work appears to be part of a coordinated infrastructure improvement initiative by Pinellas County.
View the file
Other files
Show all 27
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Page 1 of 3 PINELLAS COUNTY 11/19//2019
UTILITY WORK SCHEDULE
COUNTY PROJECT #: 004183E PROJECT TITLE: Signalization Plans – Tampa Road and Lake St. George Drive
UTILITY AGENCY/OWNER (UAO): Crown Castle
A. Summary of Utility Work and Execution
NON-CONSTRUCTION ITEMS
ESTIMATED *CALENDAR
DAYS
CONSTRUCTION ITEMS
Total Preliminary 0 Prior to Pinellas County Project Construction 0 Total Material Procurement 0 During Pinellas County Project Construction 7 Total Right-of-Way Permitting 0 Total NON-Construction Time 0 * Calendar Days = UAO Work Days x 7/5 and takes into consideration simultaneous activities listed on Part “C” of this Schedule
This document has been developed as the method for a Utility Agency/Owner (UAO) to transmit to Pinellas County, the roadway contractor and other right-of-way users, the location, relocation, adjustment, installation and/or protection of their facilities on this Pinellas County project.
The following data is based on Pinellas County final design phase construction plans dated 1/12/2022. Any deviation by Pinellas County or its contractor from the plans, as provided, may require assessment and negotiation of a new work schedule. This UAO is not responsible for events beyond their control and that could not be reasonably anticipated and avoided with the exercise of due diligence. The UAO agrees to notify Pinellas County in writing prior to starting, stopping, resuming or completing work.
UAO Project Representative: Chris Perkins Telephone Number: 717-856-6486 UAO Field Representative: Marshall Hall Telephone Number: 863-698-0567
No changes to forms document.
Appendix “Changes to Forms Document” is attached. Number of Attachment Pages.
Authorized Utility Agent: Engineer of Record: Acceptance by Pinellas County:
(Signature) (Signature) (Signature)
Christopher Perkins
Tim Messina
(Printed Name) (Printed Name) (Printed Name)
Operations Manager
Utility Coordinator
(Title) (Title) (Title)
08/30/2022
(Date) (Date) (Date)
Benjamin Rodgers
Traffic Engineer
9/1/2022
Christopher Perkins
Digitally signed by Christopher Perkins Date: 2022.08.30 08:36:02 -04'00'
Digitally signed by Benjamin S Rodgers Date: 2022.09.01 10:34:29-04'00' Scott Baird Digitally signed by Scott Baird
Date: 2022.09.01 10:52:54 -04'00'
Page 2 of 3 PINELLAS COUNTY 11/19//2019
B. Special Conditions / Constraints
1. Prior to construction or excavation around or near Crown Castle underground fiber optic facilities, call Sunshine State One Call of Florida dba Sunshine 811 at 1- 800-432-4770 and Crown Castle Network Operations center at 866-553-4237.
2. Crown Castle requests a 5 day notice to be given prior to construction near Crown Castle assets. Please contact Chris Perkins 717-856-6486 Christopher.perkins@crowncastle.com
3. In case of emergency call Crown Castle Network Operations center at 866-553-4237.
Definitions:
Locating: The use of test holes by vacuum excavation or comparable non-destructive equipment at critical point along a subsurface utility facility’s path thus exposing the underground facility and allowing the precise measurements of the depth and horizontal position to be made.
Designating: Utilizing electromagnetic, magnetic, sonic, and other energy fields for determining the existence and approximate horizontal location of underground utility facilities. Underground facilities will be marked by stakes, flags, paint or other suitable materials in varying combinations dependent upon surface conditions using American Public Works Association Utility Location Coordination Council Color Codes.
Hold/Guard/Protect: Shall include, but not be limited to, permittee’s use of an onsite representative during active construction operations. During excavation operations, Representative may be required to physically expose underground facilities, provide any necessary support to the Facilities, and/or cover aerial facilities as deemed necessary to aid construction.
Page 3 of 3 PINELLAS COUNTY 11/19//2019
SECTION C: UAO’s WORK ACTIVITIES
Action
Utility Facility (Type, Size, Material, Status)
From Station/ Offset
To Station/ Offset
Utility Work Description Dependent Activity TCP Phase
Consecutive Days
Prior To During
1 Strand and FOC 180-4854 182-1854 Raise strand and FOC for Mast Arm Installation Pinellas County Notification NA 0 7
180+48 / 54'RT 182+18 / 54'RT
Page 1 of 3 PINELLAS COUNTY 07/20//2022
COUNTY PROJECT #: 004183 PROJECT TITLE: COUNTRYWIDE MAST ARM SIGNAL HARDENING AND
INTERSECTION IMPROVEMENT – TAMPA RD AND LAKE ST GEORGE DR INTERSECTION
UTILITY AGENCY/OWNER (UAO): DUKE DISTRIBUTION
A. Summary of Utility Work and Execution
NON-CONSTRUCTION ITEMS ESTIMATED *CALENDAR
DAYS
CONSTRUCTION ITEMS ESTIMATED *CALENDAR
DAYS
Total Preliminary Prior to Pinellas County Project Construction 0 Total Material Procurement 30 During Pinellas County Project Construction 8 Total Right-of-Way Permitting 30 Total NON-Construction Time 60 * Calendar Days = UAO Work Days x 7/5 and takes into consideration simultaneous activities listed on Part “C” of this Schedule
This document has been developed as the method for a Utility Agency/Owner (UAO) to transmit to Pinellas County, the roadway contractor and other right-of-way users, the location, relocation, adjustment, installation and/or protection of their facilities on this Pinellas County project.
The following data is based on Pinellas County final design phase construction plans dated 12/2021 . Any deviation by Pinellas County or its contractor from the plans, as provided, may require assessment and negotiation of a new work schedule. This UAO is not responsible for events beyond their control and that could not be reasonably anticipated and avoided with the exercise of due diligence. The UAO agrees to notify Pinellas County in writing prior to starting, stopping, resuming or completing work.
UAO Project Representative: Bill Ruland Telephone Number: 727-820-4641 UAO Field Representative: Bill Ruland Telephone Number: 727-820-4641
No changes to forms document.
Appendix “Changes to Forms Document” is attached. Number of Attachment Pages.
Authorized Utility Agent: Engineer of Record: Acceptance by Pinellas County:
(Signature) (Signature) (Signature)
William Ruland (Printed Name) (Printed Name) (Printed Name)
Senior Engineering Technologist (Title) (Title) (Title)
7/20/22 (Date) (Date) (Date)
Authorized Utility Agent:
(Signature)
Benjamin Rodgers
Traffic Engineer
8/12/2022
Scott Baird Digitally signed by Scott Baird Date: 2022.08.15 07:21:05 -04'00'
Page 2 of 3 PINELLAS COUNTY 07/20//2022
COUNTY PROJECT #: 004183 PROJECT TITLE: COUNTRYWIDE MAST ARM SIGNAL HARDENING AND
INTERSECTION IMPROVEMENT – TAMPA RD AND LAKE ST GEORGE DR INTERSECTION
UTILITY AGENCY/OWNER (UAO): DUKE DISTRIBUTION
B. Special Conditions / Constraints
• THIS PROJECT WILL RELOCATE FACILITIES IN CONFLICT WITH: COUNTRYWIDE MAST ARM SIGNAL HARDENING AND
INTERSECTION IMPROVEMENT – TAMPA RD AND LAKE ST GEORGE DR INTERSECTION.
• All Duke Energy facilities are energized at 12,470V. “Minimum Clearance Distances” specified in Subpart CC of OSHA Rule 29 CFR Part 1926 (as they pertain to crane/derrick operations), and/or those minimum distances specified in 29 CFR 1910.33©(3) for work in proximity to power lines not covered by this Subpart CC, MUST be maintained
• During Construction – The contractor shall allow Duke Energy personnel to access their facilities at all times.
• All Duke Energy relocation activities are intended to be done during its regular scheduled, non-weekend or observed holiday, working hours. Exceptions may be coordinated for specific project needs if prior arrangements have been agreed to by both Duke Energy and Pinellas County. No nighttime relocation activities involving energized conductors or equipment will be performed, with exception of outage restoration or other emergency type work, per the Duke Energy Safety Manual regulations.
• All NESC and OSHA required clearances from energized covering does not decrease the required code clearances conductors and equipment should be maintained. Covering of conductors will not be performed by Duke Energy as covering does not decrease the required code clearances.
• Bucket truck access must be maintained to all of Duke Energy’s existing and proposed equipment locations throughout the duration of project construction for maintenance and outage construction restoration.
• Upon completion of any or all of relocations, as described in this approved Utility Work Schedule, any additional relocation of newly installed system that is required due to deviation by Pinellas County or its roadway contractor from the plans dated 12/2021 as provided to Duke Energy will be done at the expense of Pinellas County or its roadway contractor. Upon notification of such change, Duke Energy will proceed with the design and construction of the additional relocation within the standard work schedule.
• Duke Energy Distribution cannot remove old facilities until new facilities are energized and existing customers services have been relocated
• Work estimated in “Consecutive Calendar Days” is assumed to be non-inclement weather days. Duke Energy’s resources can also be affected by weather not directly contacting the Florida region as the company supports (MUTUAL AID) other utility companies in surrounding areas and states.
• De-energization of electric facilities shall be determined solely by Duke Energy and dependent upon distribution system conditions at the time of request.
• Duke Energy poles scheduled to be removed, will be removed once they are cleared by all joint users and notification by Pinellas County, or its contractor, is provided to Duke Energy’s representative.
• Duke Energy requests Pinellas County, or its contractor, to provide right-of-way staking prior to Duke Energy relocations.
• Duke Energy requires one hundred twenty (120) working days, to the start of project construction by the road contractor for Duke Energy relocation work identified as “prior to construction” to secure construction resources. These additional days have been added to “Total NON-Construction Time”
• Duke Energy requires that a trench box be utilized during the construction of underground pipe whenever the construction takes place adjacent to its existing or proposed facilities to negate the need for bracing/holding. Duke Energy Distribution will not be responsible for the bracing/holding of poles once DE facilities have been removed and Joint User/Tenant facilities remain; this will be the responsibility of the Joint Users.
Page 3 of 3 PINELLAS COUNTY 07/20//2022
COUNTY PROJECT #: 004183 PROJECT TITLE: COUNTRYWIDE MAST ARM SIGNAL HARDENING AND
INTERSECTION IMPROVEMENT – TAMPA RD AND LAKE ST GEORGE DR INTERSECTION
UTILITY AGENCY/OWNER (UAO): DUKE DISTRIBUTION
SECTION C: UAO’s WORK ACTIVITIES
Action
Utility Facility (Type, Size, Material, Status)
From Station/ Offset
To Station / Offset
Utility Work Description Dependent Activity TCP Phase
Consecutive Days
Prior To During
1 OH Secondary Conductor, Existing
180+55.7
OFF 60.5 L
181+73.8 OFF 60.5 L REMOVE OH secondary span N/A During 3
2 Pedestal 179+32.9 OFF 40.5 R INSTALL pedestal ROW staked per Section B During 5
Page 1 of 3 PINELLAS COUNTY 11/19//2019
COUNTY PROJECT #: 004183E PROJECT TITLE: Countywide Mast Arm Hardening Lake St George at Tampa Rd Intersection Improvements
UTILITY AGENCY/OWNER (UAO): Frontier
A. Summary of Utility Work and Execution
NON-CONSTRUCTION ITEMS ESTIMATED *CALENDAR
DAYS
CONSTRUCTION ITEMS ESTIMATED *CALENDAR
DAYS
Total Preliminary 30 Prior to Pinellas County Project Construction 0 Total Material Procurement 0 During Pinellas County Project Construction 4 Total Right-of-Way Permitting 0 Total NON-Construction Time 30 * Calendar Days = UAO Work Days x 7/5 and takes into consideration simultaneous activities listed on Part “C” of this Schedule
This document has been developed as the method for a Utility Agency/Owner (UAO) to transmit to Pinellas County, the roadway contractor and other right-of-way users, the location, relocation, adjustment, installation and/or protection of their facilities on this Pinellas County project.
The following data is based on Pinellas County final design phase construction plans dated December 03, 2021. Any deviation by Pinellas County or its contractor from the plans, as provided, may require assessment and negotiation of a new work schedule. This UAO is not responsible for events beyond their control and that could not be reasonably anticipated and avoided with the exercise of due diligence. The UAO agrees to notify Pinellas County in writing prior to starting, stopping, resuming or completing work.
UAO Project Representative: Kyle Perkins Telephone Number: 727-313-6167 UAO Field Representative: Vernon Burrell Telephone Number: 813-486-4650
No changes to forms document.
Appendix “Changes to Forms Document” is attached. Number of Attachment Pages.
Authorized Utility Agent: Engineer of Record: Acceptance by Pinellas County:
(Signature) (Signature) (Signature)
Kyle Perkins Ben Rodgers, P.E. Tim Messina (Printed Name) (Printed Name) (Printed Name)
Frontier Engineer Engineer of Record Utility Coordinator (Title) (Title) (Title)
(Date) (Date) (Date)
(Signature)
8/12/2022
Scott Baird Digitally signed by Scott Baird Date: 2022.08.15 07:21:30 -04'00'
Page 2 of 3 PINELLAS COUNTY 11/19//2019
COUNTY PROJECT #: 004183E PROJECT TITLE: Countywide Mast Arm Hardening Lake St George at Tampa Rd Intersection Improvements
UTILITY AGENCY/OWNER (UAO): Frontier
B. Special Conditions / Constraints
Frontier and Frontier Contractor's normal business hours are from 8am to 5pm, Monday through Friday (excluding Holidays).
Any work outside of normal business hours to be scheduled a minimum of 72 hours in advance.
The road Contractor is to notify Frontier at 813-486-4650 48 hours prior to start of construction.
Extreme caution is to be used when excavating near or around Frontier facilities.
Frontier inspector is to be the point of contact during construction and to be notified when working within 2' of Frontier facilities.
Frontier is to have access throughout the duration of the project to monitor and maintain facilities for the ability to provide service.
Page 3 of 3 PINELLAS COUNTY 11/19//2019
COUNTY PROJECT #: 004183E PROJECT TITLE: Countywide Mast Arm Hardening Lake St George at Tampa Rd Intersection Improvements
UTILITY AGENCY/OWNER (UAO): Frontier
SECTION C: UAO’s WORK ACTIVITIES
Action
Utility Facility (Type, Size, Material, Status)
From Station/ Offset
To Station/ Offset
Utility Work Description Dependent Activity TCP Phase
Consecutive Days
Prior to During Const Const
All Frontier facilities within project limits are To Remain unless otherwise noted:
N/A N/A To Remain None N/A 0 0
1.
4 - 4” Conduits w/
12-BFO, 1200-BT,
900-BT, 144-BFO
50+67, 48’ RT
50+80, 40’ RT Monitor & Adjust as Needed
Construction of Proposed Ped Pole Foundations and
Signal Conduit Phase I 0 2
2.
2 - 4” Conduits w/48-BFO &
1500-BT
49+33, 48’ RT
49+39, 53’ RT Monitor & Adjust as Needed Construction of Signal Pole
Foundation Phase I 0 2
Date: 2022.08.15 07:22:45 -04'00'
Date: 2022.08.19 07:35:50 -04'00'
Page 2 of 3 PINELLAS COUNTY 10/15//2019
COUNTY PROJECT #: 004183E PROJECT TITLE #: TAMPA RD / LAKE ST GEORGE DR
UTILITY AGENCY/OWNER (UAO): Knology Broadband of Florida D.B.A. WOW! (Wide Open West)
1: WOW! field inspector Dave Hamlin will be field point of contact for WOW! during construction duration of the project.
2: WOW! Working Days are during normal business hours, Monday – Friday, 7:30 am – 5:00 pm (excluding Holidays). WOW! will arrange any works after hour with an advance notice through WOW! field representative Dave Hamlin. Please call 48 hours prior to schedule any after hours work if needed. After hours emergency contact please call Richard LaGanga @ 727-422-8040 UAO project representative.
3: WOW! is to have access throughout the duration of the project to monitor and maintain WOW! facilities for the ability to provide service.
4: WOW! will need to coordinate with road contractor in advance for the adjustment it’s spans for signal pole #2.
5: WOW! BFOC fiber may require adjustments during construction.
Page 3 of 3 PINELLAS COUNTY 10/15//2019
COUNTY PROJECT #: 004183E PROJECT TITLE #: TAMPA RD / LAKE ST GEORGE DR
Utility Facility (Type, Size, Material, Status)
From Station/ Offset
To Station/ Offset
Utility Work Description Dependent Activity TCP Phase
Consecutive Days
Prior To During
1 WOW! OFOC & OTV 180+57,
49’ RT
182+13, 49’ RT RAISE/LOWER ADJUST DURNING CONST. CONSTRUCTION OF POLE #2
LOCATION DURING 0 4
2 WOW! OFOC & OTV 181+74,
102’ RT
181+74, 105’ LT RAISE/LOWER ADJUST DURNING CONST. CONSTRUCTION OF POLE #2
LOCATION DURING 0 4
3 WOW! BFOC 181+77,
94LR
182+18, 59’ LT ADJUST IF NEEDED DURING CONST. SIGNALIZATION CONDUIT
INSTALLATION DURING 0 4
TOTAL: TOTAL:
0 12
Page 1 of 3 PINELLAS COUNTY 11/19//2019
COUNTY PROJECT #: 004183F PROJECT TITLE: Signalization Plans – Tampa Road and West Lake Rd
Total Preliminary 0 Prior to Pinellas County Project Construction 0 Total Material Procurement 0 During Pinellas County Project Construction 7 Total Right-of-Way Permitting 0 Total NON-Construction Time 0 * Calendar Days = UAO Work Days x 7/5 and takes into consideration simultaneous activities listed on Part “C” of this Schedule
This document has been developed as the method for a Utility Agency/Owner (UAO) to transmit to Pinellas County, the roadway contractor and other right-of-way users, the location, relocation, adjustment, installation and/or protection of their facilities on this Pinellas County project.
The following data is based on Pinellas County final design phase construction plans dated 1/12/2022. Any deviation by Pinellas County or its contractor from the plans, as provided, may require assessment and negotiation of a new work schedule. This UAO is not responsible for events beyond their control and that could not be reasonably anticipated and avoided with the exercise of due diligence. The UAO agrees to notify Pinellas County in writing prior to starting, stopping, resuming or completing work.
UAO Project Representative: Chris Perkins Telephone Number: 717-856-6486 UAO Field Representative: Marshall Hall Telephone Number: 863-698-0567
Christopher Perkins
Operations Manager
08/30/2022
9/1/2022
Christopher Perkins
Digitally signed by Christopher Perkins Date: 2022.08.30 08:37:05 -04'00'
Digitally signed by Benjamin S Rodgers Date: 2022.09.01 10:35:42-04'00' Scott Baird Digitally signed by Scott Baird
Date: 2022.09.01 10:57:20
Page 2 of 3 PINELLAS COUNTY 11/19//2019
1. Prior to construction or excavation around or near Crown Castle underground fiber optic facilities, call Sunshine State One Call of Florida dba Sunshine 811 at 1- 800-432-4770 and Crown Castle Network Operations center at 866-553-4237.
2. Crown Castle requests a 5 day notice to be given prior to construction near Crown Castle assets. Please contact Chris Perkins 717-856-6486 Christopher.perkins@crowncastle.com
3. In case of emergency call Crown Castle Network Operations center at 866-553-4237.
Definitions:
Locating: The use of test holes by vacuum excavation or comparable non-destructive equipment at critical point along a subsurface utility facility’s path thus exposing the underground facility and allowing the precise measurements of the depth and horizontal position to be made.
Designating: Utilizing electromagnetic, magnetic, sonic, and other energy fields for determining the existence and approximate horizontal location of underground utility facilities. Underground facilities will be marked by stakes, flags, paint or other suitable materials in varying combinations dependent upon surface conditions using American Public Works Association Utility Location Coordination Council Color Codes.
Hold/Guard/Protect: Shall include, but not be limited to, permittee’s use of an onsite representative during active construction operations. During excavation operations, Representative may be required to physically expose underground facilities, provide any necessary support to the Facilities, and/or cover aerial facilities as deemed necessary to aid construction.
Page 3 of 3 PINELLAS COUNTY 11/19//2019
Utility Facility (Type, Size, Material, Status)
From Station/ Offset
To Station/ Offset
Utility Work Description Dependent Activity TCP Phase
Consecutive Days
Prior
1 Strand and FOC 141+2450 142+5950 Raise strand and FOC for Mast Arm Installation Pinellas County Notification NA 0 7
141+24 / 50'RT 142+59 / 50'RT
Page 1 of 3 PINELLAS COUNTY 07/20//2022
COUNTY PROJECT #: 004183 PROJECT TITLE: COUNTRYWIDE MAST ARM SIGNAL HARDENING AND
INTERSECTION IMPROVEMENT – TAMPA RD AND WEST LAKE RD INTERSECTION
UTILITY AGENCY/OWNER (UAO): DUKE DISTRIBUTION
A. Summary of Utility Work and Execution
NON-CONSTRUCTION ITEMS ESTIMATED *CALENDAR
DAYS
CONSTRUCTION ITEMS ESTIMATED *CALENDAR
DAYS
Total Preliminary Prior to Pinellas County Project Construction 0 Total Material Procurement 30 During Pinellas County Project Construction 22 Total Right-of-Way Permitting 30 Total NON-Construction Time 60 * Calendar Days = UAO Work Days x 7/5 and takes into consideration simultaneous activities listed on Part “C” of this Schedule
This document has been developed as the method for a Utility Agency/Owner (UAO) to transmit to Pinellas County, the roadway contractor and other right-of-way users, the location, relocation, adjustment, installation and/or protection of their facilities on this Pinellas County project.
The following data is based on Pinellas County final design phase construction plans dated 12/2021 . Any deviation by Pinellas County or its contractor from the plans, as provided, may require assessment and negotiation of a new work schedule. This UAO is not responsible for events beyond their control and that could not be reasonably anticipated and avoided with the exercise of due diligence. The UAO agrees to notify Pinellas County in writing prior to starting, stopping, resuming or completing work.
UAO Project Representative: Bill Ruland Telephone Number: 727-820-4641 UAO Field Representative: Bill Ruland Telephone Number: 727-820-4641
No changes to forms document.
Appendix “Changes to Forms Document” is attached. Number of Attachment Pages.
Authorized Utility Agent: Engineer of Record: Acceptance by Pinellas County:
(Signature) (Signature) (Signature)
William Ruland (Printed Name) (Printed Name) (Printed Name)
Senior Engineering Technologist (Title) (Title) (Title)
7/20/22 (Date) (Date) (Date)
Authorized Utility Agent:
(Signature)
Benjamin Rodgers
Traffic Engineer
8/12/2022
Scott Baird Digitally signed by Scott Baird Date: 2022.08.15 07:25:04
Page 2 of 3 PINELLAS COUNTY 07/20//2022
COUNTY PROJECT #: 004183 PROJECT TITLE: COUNTRYWIDE MAST ARM SIGNAL HARDENING AND
INTERSECTION IMPROVEMENT – TAMPA RD AND WEST LAKE RD INTERSECTION
UTILITY AGENCY/OWNER (UAO): DUKE DISTRIBUTION
B. Special Conditions / Constraints
• THIS PROJECT WILL RELOCATE FACILITIES IN CONFLICT WITH: COUNTRYWIDE MAST ARM SIGNAL HARDENING AND
INTERSECTION IMPROVEMENT – TAMPA RD AND WEST LAKE RD INTERSECTION.
• All Duke Energy facilities are energized at 12,470V. “Minimum Clearance Distances” specified in Subpart CC of OSHA Rule 29 CFR Part 1926 (as they pertain to crane/derrick operations), and/or those minimum distances specified in 29 CFR 1910.33©(3) for work in proximity to power lines not covered by this Subpart CC, MUST be maintained
• During Construction – The contractor shall allow Duke Energy personnel to access their facilities at all times.
• All Duke Energy relocation activities are intended to be done during its regular scheduled, non-weekend or observed holiday, working hours. Exceptions may be coordinated for specific project needs if prior arrangements have been agreed to by both Duke Energy and Pinellas County. No nighttime relocation activities involving energized conductors or equipment will be performed, with exception of outage restoration or other emergency type work, per the Duke Energy Safety Manual regulations.
• All NESC and OSHA required clearances from energized covering does not decrease the required code clearances conductors and equipment should be maintained. Covering of conductors will not be performed by Duke Energy as covering does not decrease the required code clearances.
• Bucket truck access must be maintained to all of Duke Energy’s existing and proposed equipment locations throughout the duration of project construction for maintenance and outage construction restoration.
• Upon completion of any or all of relocations, as described in this approved Utility Work Schedule, any additional relocation of newly installed system that is required due to deviation by Pinellas County or its roadway contractor from the plans dated 12/2021 as provided to Duke Energy will be done at the expense of Pinellas County or its roadway contractor. Upon notification of such change, Duke Energy will proceed with the design and construction of the additional relocation within the standard work schedule.
• Duke Energy Distribution cannot remove old facilities until new facilities are energized and existing customers services have been relocated
• Work estimated in “Consecutive Calendar Days” is assumed to be non-inclement weather days. Duke Energy’s resources can also be affected by weather not directly contacting the Florida region as the company supports (MUTUAL AID) other utility companies in surrounding areas and states.
• De-energization of electric facilities shall be determined solely by Duke Energy and dependent upon distribution system conditions at the time of request.
• Duke Energy poles scheduled to be removed, will be removed once they are cleared by all joint users and notification by Pinellas County, or its contractor, is provided to Duke Energy’s representative.
• Duke Energy requests Pinellas County, or its contractor, to provide right-of-way staking prior to Duke Energy relocations.
• Duke Energy requires one hundred twenty (120) working days, to the start of project construction by the road contractor for Duke Energy relocation work identified as “prior to construction” to secure construction resources. These additional days have been added to “Total NON-Construction Time”
• Duke Energy requires that a trench box be utilized during the construction of underground pipe whenever the construction takes place adjacent to its existing or proposed facilities to negate the need for bracing/holding. Duke Energy Distribution will not be responsible for the bracing/holding of poles once DE facilities have been removed and Joint User/Tenant facilities remain; this will be the responsibility of the Joint Users.
Page 3 of 3 PINELLAS COUNTY 07/20//2022
COUNTY PROJECT #: 004183 PROJECT TITLE: COUNTRYWIDE MAST ARM SIGNAL HARDENING AND
INTERSECTION IMPROVEMENT – TAMPA RD AND WEST LAKE RD INTERSECTION
UTILITY AGENCY/OWNER (UAO): DUKE DISTRIBUTION
SECTION C: UAO’s WORK ACTIVITIES
Action
Utility Facility (Type, Size, Material, Status)
From Station/ Offset
To Station / Offset
Utility Work Description Dependent Activity TCP Phase
Consecutive Days
Prior To During
1 POLE 60’ WD 51+20
OFF 39+8 L INSTALL 3 phase primary pole ROW staked per Section B During 5
2 Pedestal 51+43.9 OFF 46.5 R INSTALL pedestal ROW staked per Section B During 5
3 OH Primary Conductor, Existing
51+20
OFF 39+8 L
51+46.6 OFF 46.3 R INSTALL OH Single Phase primary span #1 During 5
4 OH Primary Conductor, Existing
51+55.8
OFF 39+8 L
51+46.6 OFF 46.3 R REMOVE OH Single Phase primary span #3 During 3
5 POLE 60’ WD 51+00
OFF 39+8 L REMOVE 3 phase primary pole #1 During 2
6 POLE 55’ WD 51+55.8
OFF 39+8 L REMOVE 3 phase primary pole #4 During 2
COUNTY PROJECT #: 004183F PROJECT TITLE: Countywide Mast Arm Hardening West Lake Rd at Tampa Rd Intersection Improvements
UTILITY AGENCY/OWNER (UAO): Frontier
A. Summary of Utility Work and Execution
NON-CONSTRUCTION ITEMS ESTIMATED *CALENDAR
DAYS
CONSTRUCTION ITEMS ESTIMATED *CALENDAR
DAYS
Total Preliminary 30 Prior to Pinellas County Project Construction 0 Total Material Procurement 0 During Pinellas County Project Construction 2 Total Right-of-Way Permitting 0 Total NON-Construction Time 30 * Calendar Days = UAO Work Days x 7/5 and takes into consideration simultaneous activities listed on Part “C” of this Schedule
This document has been developed as the method for a Utility Agency/Owner (UAO) to transmit to Pinellas County, the roadway contractor and other right-of-way users, the location, relocation, adjustment, installation and/or protection of their facilities on this Pinellas County project.
The following data is based on Pinellas County final design phase construction plans dated December 03, 2021. Any deviation by Pinellas County or its contractor from the plans, as provided, may require assessment and negotiation of a new work schedule. This UAO is not responsible for events beyond their control and that could not be reasonably anticipated and avoided with the exercise of due diligence. The UAO agrees to notify Pinellas County in writing prior to starting, stopping, resuming or completing work.
UAO Project Representative: Kyle Perkins Telephone Number: 727-313-6167 UAO Field Representative: Vernon Burrell Telephone Number: 813-486-4650
No changes to forms document.
Appendix “Changes to Forms Document” is attached. Number of Attachment Pages.
Authorized Utility Agent: Engineer of Record: Acceptance by Pinellas County:
(Signature) (Signature) (Signature)
Kyle Perkins Ben Rodgers, P.E. Tim Messina (Printed Name) (Printed Name) (Printed Name)
Frontier Engineer Engineer of Record Utility Coordinator (Title) (Title) (Title)
(Date) (Date) (Date)
(Signature)
8/12/2022
Scott Baird Digitally signed by Scott Baird Date: 2022.08.15 07:25:31
COUNTY PROJECT #: 004183F PROJECT TITLE: Countywide Mast Arm Hardening West Lake Rd at Tampa Rd Intersection Improvements
UTILITY AGENCY/OWNER (UAO): Frontier
B. Special Conditions / Constraints
Frontier and Frontier Contractor's normal business hours are from 8am to 5pm, Monday through Friday (excluding Holidays).
Any work outside of normal business hours to be scheduled a minimum of 72 hours in advance.
The road Contractor is to notify Frontier at 813-486-4650 48 hours prior to start of construction.
Extreme caution is to be used when excavating near or around Frontier facilities.
Frontier inspector is to be the point of contact during construction and to be notified when working within 2' of Frontier facilities.
Frontier is to have access throughout the duration of the project to monitor and maintain facilities for the ability to provide service.
COUNTY PROJECT #: 004183F PROJECT TITLE: Countywide Mast Arm Hardening West Lake Rd at Tampa Rd Intersection Improvements
UTILITY AGENCY/OWNER (UAO): Frontier
SECTION C: UAO’s WORK ACTIVITIES
Action
Utility Facility (Type, Size, Material, Status)
From Station/ Offset
To Station/ Offset
Utility Work Description Dependent Activity TCP Phase
Consecutive Days
Prior to During Const Const
All Frontier facilities within project limits are To Remain unless otherwise noted:
N/A N/A To Remain None N/A 0 0
1. 24-BFO, 200-BT,
1500-BT
50+76, 27’ RT
50+76, 28’ RT Monitor & Adjust as Needed Construction of Proposed
Signal Conduit Installation Phase I 0 2
Scott Baird Digitally signed by Scott Baird Date: 2022.08.15 07:26:18
8/10/2022
Date: 2022.08.19 07:58:58 -04'00'
Page 2 of 3 PINELLAS COUNTY 10/15//2019
COUNTY PROJECT #: 004183F PROJECT TITLE #: TAMPA RD / W LAKE RD
1: WOW! field inspector Dave Hamlin will be field point of contact for WOW! during construction duration of the project.
2: WOW! Working Days are during normal business hours, Monday – Friday, 7:30 am – 5:00 pm (excluding Holidays). WOW! will arrange any works after hour with an advance notice through WOW! field representative Dave Hamlin. Please call 48 hours prior to schedule any after hours work if needed. After hours emergency contact please call Richard LaGanga @ 727-422-8040 UAO project representative.
3: WOW! is to have access throughout the duration of the project to monitor and maintain WOW! facilities for the ability to provide service.
4: WOW! will need to coordinate with roadway construction for adjustment of OFOC for pole #2. Due to the high fiber count WOW may require to be onsite for mast arm construction to avoid fiber damage.
5: WOW! is dependant on Duke Energy placing poles within project limits and allowing enough time for joint users to attach prior to the installation of pole #1.
Page 3 of 3 PINELLAS COUNTY 10/15//2019
COUNTY PROJECT #: 004183F PROJECT TITLE #: TAMPA RD / W LAKE RD
Utility Facility (Type, Size, Material, Status)
From Station/ Offset
To Station/ Offset
Utility Work Description Dependent Activity TCP Phase
Consecutive Days
Prior To During
1 WOW! OFOC & OTV 49+51,
69’ LT
49+51, 62’ RT RAISE/LOWER ADJUST DURING CONST. CONSTRUCTION OF POLE #2
LOCATION DURING 0 4
2 WOW! OFOC & OTV 46+41,
42’ LT
50+99, 40’ LT RAISE/LOWER ADJUST DURING CONST. CONSTRUCTION OF POLE #2
LOCATION DURING 0 4
3 WOW! OTV 51+21,
40’ LT
51+47, 44’ RT OTV TO BE INSTALLED ADDITION OF DUKE POLE DURING 0 1
4 WOW! OTV 51+56,
39’ LT
51+47, 44’ RT REMOVE OTV REMOVAL OF DUKE POLES DURING 0 1
0 10
Page 1 of 4 PINELLAS COUNTY 11/19//2019
COUNTY PROJECT #: 004183M PROJECT TITLE: Signalization Plans – 113TH St and 54th Ave
UTILITY AGENCY/OWNER (UAO): Duke Energy Distribution
Total Preliminary 10 Prior to Pinellas County Project Construction 53 Total Material Procurement 45 During Pinellas County Project Construction 5 Total Right-of-Way Permitting 30 Total NON-Construction Time 85 * Calendar Days = UAO Work Days x 7/5 and takes into consideration simultaneous activities listed on Part “C” of this Schedule
This document has been developed as the method for a Utility Agency/Owner (UAO) to transmit to Pinellas County, the roadway contractor and other right-of-way users, the location, relocation, adjustment, installation and/or protection of their facilities on this Pinellas County project.
The following data is based on Pinellas County final design phase construction plans dated 1/12/2022. Any deviation by Pinellas County or its contractor from the plans, as provided, may require assessment and negotiation of a new work schedule. This UAO is not responsible for events beyond their control and that could not be reasonably anticipated and avoided with the exercise of due diligence. The UAO agrees to notify Pinellas County in writing prior to starting, stopping, resuming or completing work.
UAO Project Representative: Kelly Berry Telephone Number: 727-418-8816 UAO Field Representative: Kelly Berry Telephone Number: 727-418-8816
Kelly Berry
Senior Engineer
05/19/2022
Kelly Berry Digitally signed by Kelly Berry Date: 2022.05.19 15:11:37 -04'00' Joshua Reichert Digitally signed by Joshua Reichert
Date: 2022.07.19 09:18:33 -04'00' Scott Baird Digitally signed by Scott Baird Date: 2022.07.21 13:31:45 -04'00'
Page 2 of 4 PINELLAS COUNTY 11/19//2019
1. Duke Energy and/or Duke Energy subcontractors normal work schedule is Monday through Friday from 7 a.m. to 5 p.m., excluding observed holiday's (New Years day, Good Friday, Memorial Day, July 4th, Labor day, Thanksgiving Day, the Friday after Thanksgiving, Christmas Eve Day and Christmas Day).
2. Duke Energy line crew availability may be affected or limited due to our required response to emergency conditions. This limitation will be dependent upon the severity of the emergency.
3. Emergency number for nights, weekends and Duke Energy Florida holidays is (800) 228-8485.
4. Bucket truck access must be maintained to all of this UAO’s facilities including: poles, pull boxes, transformers, and switchgear locations throughout the duration of the project construction for maintenance and outage restoration.
5. All NESC and OSHA required clearances from energized conductors and equipment should be maintained. Covering of conductors will not be provided by this UAO as this does not decrease the required code clearances.
6. Upon completion of any or all of relocations, as described in this approved Utility Work Schedule, any additional relocation of newly installed system that is required due to deviation by the County or its roadway contractor from the plans as provided to this UAO will be done at the expense of the County or its roadway contractor.
Upon notification of such change, UAO will proceed with the design and construction of the additional relocation within the standard work schedule of this UAO
7. De-energization of primary voltage (example: 12.47kV) power lines requires coordination with multiple internal groups. Notify this UAO via email at least 20 business days before any de-energization is required at each mast arm location. Due to the existing circuit loadings, distribution conductors may require de-energizing and grounding during non-peak hours (may require night work by County contractor if circuit loading during daytime is not feasible). And in some cases, de-energization may not be approved.
8. Temporary removal of streetlight wire or secondary voltage conductors (example: 120/240V) requires coordination with multiple internal groups. Notify this UAO via email at least 20 business days before any temporary removal of wire is required at each location.
9. Temporary removed services or de-energizing conductors will result in loss of power. This includes possible loss of power to the traffic signal cabinet and/or streetlight circuits and/or electric meters. This UAO is not responsible for generators needed during power outage.
10. Any bracing or holding of this UAO’s poles will require 20 business days advance written notice via email to this UAO.
11. All new electrical services requested by Pinellas County, or its contractor will be required to conform to “Requirements for Electric Service and Meter Installations” latest edition.
12. To establish a new service account the responsible party for the new service must call 866-372-4663.
13. A Contribution in Aid to Construction (CIAC) will be required for underground riser/pedestal installations and any additional required line construction work that does not meet the required revenue ratio as specified in this UAO’s approved rates and tariffs.
14. Duke Energy Distribution cannot remove old facilities until new facilities are energized and existing customers services have been relocated.
Page 3 of 4 PINELLAS COUNTY 11/19//2019
Utility Facility (Type, Size, Material, Status)
From Station/ Offset
To Station/ Offset
Utility Work Description Dependent Activity TCP Phase
Consecutive Days
Prior To During
Existing wood poles with 12.47KV overhead distribution conductors and equipment.
40+45 48’ Rt, 40+45
134’ Rt, 40+61
143’ Lt, To be removed and conductors and equipment transferred. After joint users have transferred from poles. N/A 5 0
Proposed taller wood poles with 12.47KV overhead distribution conductors and equipment to raise lines.
39+43 60’ Rt, 39+43 82’ Rt, 40+45 50’ Rt, 40+45
136’ Rt, 40+58’ 145’ Lt, 41+48 27’ Rt
To be installed and existing conductors and equipment attached. N/A 15 0
3 Install temporary inline switches
39+43 29’ Rt, 39+43 74’ Rt
To be installed temporarily to facilitate de-energizing of overhead section of line. N/A 1 0
4 Remove temporary inline switches
39+43 29’ Rt, 39+43 74’ Rt
To be removed once mast arm is installed N/A 0 1
5 Switching
39+43 29’ Rt, 39+43 74’ Rt
De-energize/Re-energize for drill shaft/mast arm installation Distribution Control Center approval N/A 0 2
6 Existing overhead 120V conductor for streetlight
39+0 20’ Rt
39+44 36’ Rt To be removed and re-installed for crane
Removed prior to drill shaft installation and re-installed after mast arm installation.
N/A 0 2
7 Existing down guys
41+34 27’ Rt, 40+61 143’ Lt
To be removed from existing pole. N/A 2 0
Page 4 of 4 PINELLAS COUNTY 11/19//2019
8 Proposed down guys
41+48 27’ Rt, 40+58’ 145’ Lt
To be installed on new pole. N/A 2 0
9 Pull boxes
38+90 29’ Rt, 38+90 34’ Rt
To be installed for new underground conductors N/A 4 0
10 Proposed buried 12.47KV conductors
38+90 29’ Rt, 38+90 34’ Rt, 38+90 29’ Rt, 38+90 34’ Rt
41+34 27’ Rt, 41+48 27’Rt, 39+43 60’ Rt, 39+43 82’ Rt, To be installed in 6” conduit crossing Duhme/113th St. N/A 14 0
11 Existing overhead 12.47KV conductors
39+47 23’ Rt
41+58 27’ Rt E/W span to be removed to raise N/S conductors N/A 4 0
12 Above ground pedestal 40+45 138’ Rt
To be installed at base of pole. N/A 1 0
13 Proposed wood poles
39+16, 52’ Rt 39+35 61’ Rt
Install new wood poles to re-route primary. N/A 2 0
14 Proposed overhead 7.2KV conductors
38+99 22’ Rt, 39+16 52’ Rt 39+35 61’ Rt
39+16 52’ Rt, 39+35 61’ Rt, 39+43 82’ Rt
Install new overhead conductors. N/A 3 0
COUNTY PROJECT #: 004183M PROJECT TITLE: Countywide Mast Arm Hardening 113th St (Duhme Rd) at 54th Ave Intersection Improvements
UTILITY AGENCY/OWNER (UAO): Frontier
A. Summary of Utility Work and Execution
NON-CONSTRUCTION ITEMS ESTIMATED *CALENDAR
DAYS
CONSTRUCTION ITEMS ESTIMATED *CALENDAR
DAYS
Total Preliminary 30 Prior to Pinellas County Project Construction 0 Total Material Procurement 0 During Pinellas County Project Construction 7 Total Right-of-Way Permitting 0 Total NON-Construction Time 30 * Calendar Days = UAO Work Days x 7/5 and takes into consideration simultaneous activities listed on Part “C” of this Schedule
This document has been developed as the method for a Utility Agency/Owner (UAO) to transmit to Pinellas County, the roadway contractor and other right-of-way users, the location, relocation, adjustment, installation and/or protection of their facilities on this Pinellas County project.
The following data is based on Pinellas County final design phase construction plans dated January 28, 2022. Any deviation by Pinellas County or its contractor from the plans, as provided, may require assessment and negotiation of a new work schedule. This UAO is not responsible for events beyond their control and that could not be reasonably anticipated and avoided with the exercise of due diligence. The UAO agrees to notify Pinellas County in writing prior to starting, stopping, resuming or completing work.
UAO Project Representative: Granville Stephens Telephone Number: 727-562-1190 UAO Field Representative: Vernon Burrell Telephone Number: 813-486-4650
No changes to forms document.
Appendix “Changes to Forms Document” is attached. Number of Attachment Pages.
Authorized Utility Agent: Engineer of Record: Acceptance by Pinellas County:
(Signature) (Signature)
Granville Stephens
(Signature)
P.E. Tim Messina (Printed Name) (Printed Name) (Printed Name)
Senior Network Engineer Engineer of Record Utility Coordinator (Title) (Title) (Title)
(Date) (Date) (Date)
(Signature)
5/23/2022
Joshua Reichert Digitally signed by Joshua Reichert Date: 2022.07.19 10:33:04 -04'00'
Scott Baird Digitally signed by Scott Baird Date: 2022.07.26 07:56:32
COUNTY PROJECT #: 004183M PROJECT TITLE: Countywide Mast Arm Hardening 113th St (Duhme Rd) at 54th Ave Intersection Improvements
UTILITY AGENCY/OWNER (UAO): Frontier
B. Special Conditions / Constraints
Frontier and Frontier Contractor's normal business hours are from 8am to 5pm, Monday through Friday (excluding Holidays).
Any work outside of normal business hours to be scheduled a minimum of 72 hours in advance.
The road Contractor is to notify Frontier at 813-486-4650 48 hours prior to start of construction.
Extreme caution is to be used when excavating near or around Frontier facilities.
Frontier inspector is to be the point of contact during construction and to be notified when working within 2' of Frontier facilities.
Frontier is to have access throughout the duration of the project to monitor and maintain facilities for the ability to provide service.
COUNTY PROJECT #: 004183M PROJECT TITLE: Countywide Mast Arm Hardening 113th St (Duhme Rd) at 54th Ave Intersection Improvements
UTILITY AGENCY/OWNER (UAO): Frontier
SECTION C: UAO’s WORK ACTIVITIES
Action
Utility Facility (Type, Size, Material, Status)
From Station/ Offset
To Station/ Offset
Utility Work Description Dependent Activity TCP Phase
Consecutive Days
Prior to During Const Const
All Frontier facilities within project limits are To Remain unless otherwise noted:
N/A N/A To Remain None N/A 0 0
1. 200-BT 54+50,
51’ LT.
54+71, 53’ LT. Monitor & Adjust as Needed Construction of Proposed
Ped Pole Foundations Phase I 0 2
2. 50-OHT 54+51,
49’ RT Adjust to new Duke Power Pole Proposed Construction within SE corner Phase I 0 1
3. 6PR-BFOT 54+54,
53’ RT.
54+75, 78’ RT. Monitor & Adjust as Needed Construction of Proposed
Ped Pole Foundations Phase I 0 2
4. 200-BT 55+44,
55’ LT. Monitor & Adjust as Needed Construction of Proposed
Ped Pole Foundation Phase I 0 2
Page 1 of 3 PINELLAS COUNTY 11/19//2019
COUNTY PROJECT #: 004183M PROJECT TITLE: 113TH AND 54TH
UTILITY AGENCY/OWNER (UAO): Spectrum Sunshine State LLC.
A. Summary of Utility Work and Execution
NON-CONSTRUCTION ITEMS ESTIMATED *CALENDAR
DAYS
CONSTRUCTION ITEMS ESTIMATED *CALENDAR
DAYS
Total Preliminary 10 Prior to Pinellas County Project Construction 14 Total Material Procurement 45 During Pinellas County Project Construction 0 Total Right-of-Way Permitting 0 Total NON-Construction Time 0 * Calendar Days = UAO Work Days x 7/5 and takes into consideration simultaneous activities listed on Part “C” of this Schedule
This document has been developed as the method for a Utility Agency/Owner (UAO) to transmit to Pinellas County, the roadway contractor and other right-of-way users, the location, relocation, adjustment, installation and/or protection of their facilities on this Pinellas County project.
The following data is based on Pinellas County final design phase construction plans dated 01/12/22. Any deviation by Pinellas County or its contractor from the plans, as provided, may require assessment and negotiation of a new work schedule. This UAO is not responsible for events beyond their control and that could not be reasonably anticipated and avoided with the exercise of due diligence. The UAO agrees to notify Pinellas County in writing prior to starting, stopping, resuming or completing work.
UAO Project Representative: Art Dubinas Telephone Number: 727-290-1509 UAO Field Representative: Art Dubinas Telephone Number: 727-290-1509
No changes to forms document.
Appendix “Changes to Forms Document” is attached. Number of Attachment Pages.
Authorized Utility Agent: Engineer of Record: Acceptance by Pinellas County:
(Signature) (Signature) (Signature)
Art Dubinas Joshua Reichert Tim Messina (Printed Name) (Printed Name) (Printed Name)
Construction Coordinator Engineer of Record Utility Coordinator (Title) (Title) (Title)
06/02/2022 7/19/2022 (Date) (Date) (Date)
Joshua Reichert Digitally signed by Joshua Reichert Date: 2022.07.19 11:34:41 -04'00'
Scott Baird Digitally signed by Scott Baird Date: 2022.07.21 12:07:16
Page 2 of 3 PINELLAS COUNTY 11/19//2019
COUNTY PROJECT #: 004183M PROJECT TITLE: 113TH AND 54TH
UTILITY AGENCY/OWNER (UAO): Spectrum Sunshine State LLC.
1. Spectrum relocation activities will not commence until a signed UWS and approved permit are received.
2. Spectrums normal business hours are from 8am to 5pm, Monday through Friday (excluding Holidays).
3. Any work outside of normal business hours are to be scheduled a minimum of 72 hours in advance.
4. Spectrum is to have access throughout the duration of the project to monitor and maintain Spectrum facilities for the ability to provide service.
5. UAO Field Rep listed on page 1 will be point of contact for Spectrum during the entire duration of the construction project unless otherwise notified.
6. Extreme caution is to be used when excavating near or around Spectrum facilities.
7. Spectrums relocation work is contingent on securing an approved joint use agreement (JUA) with Duke-Energy to attach to their existing and proposed power-poles.
Page 3 of 3 PINELLAS COUNTY 11/19//2019
COUNTY PROJECT #: 004183M PROJECT TITLE: 113TH AND 54TH
Utility Facility (Type, Size, Material, Status)
From Station/ Offset
To Station/ Offset
Utility Work Description Dependent Activity TCP Phase
Consecutive Days
Prior To During
1 New Duke poles
40+45 136’Rt 40+45 50’Rt 40+58 145’Lt 41+48 27’Lt
Elevating and attaching spectrum facilities New Duke poles installed N/A 14 0
2 Existing Duke poles 40+45 134’Rt 40+45 48’Rt 40+61 143’Lt
Removing Spectrum attachments and facilities New Duke poles installed N/A 14 0
3 Aerial spans with Spectrum utilities
Throughout project limits
Throughout project limits Elevating aerial spans with utilities to accommodate clearance New Duke poles installed N/A 14 0
COUNTY PROJECT #: 004183AM PROJECT TITLE: 113TH ST / DUHME ROAD AT 54TH AVENUE
UTILITY AGENCY/OWNER (UAO): TECO PEOPLES GAS
A. Summary of Utility Work and Execution
NON-CONSTRUCTION ITEMS ESTIMATED *CALENDAR
DAYS
CONSTRUCTION ITEMS ESTIMATED *CALENDAR
DAYS
Total Preliminary 0 Prior to Pinellas County Project Construction 0 Total Material Procurement 0 During Pinellas County Project Construction 0 Total Right-of-Way Permitting 0 Total NON-Construction Time 0 * Calendar Days = UAO Work Days x 7/5 and takes into consideration simultaneous activities listed on Part “C” of this Schedule
This document has been developed as the method for a Utility Agency/Owner (UAO) to transmit to Pinellas County, the roadway contractor and other right-of-way users, the location, relocation, adjustment, installation and/or protection of their facilities on this Pinellas County project.
The following data is based on Pinellas County final design phase construction plans dated 01/12/2022 . Any deviation by Pinellas County or its contractor from the plans, as provided, may require assessment and negotiation of a new work schedule. This UAO is not responsible for events beyond their control and that could not be reasonably anticipated and avoided with the exercise of due diligence. The UAO agrees to notify Pinellas County in writing prior to starting, stopping, resuming or completing work.
UAO Project Representative: Bolivar A. Feliz Nunez Telephone Number: 813-275-3712 UAO Field Representative: Raymond Zwissler Telephone Number: 727-423-7124
No changes to forms document.
Appendix “Changes to Forms Document” is attached. 2 Number of Attachment Pages.
Authorized Utility Agent: Engineer of Record: Acceptance by Pinellas County:
(Signature) (Signature) (Signature)
Bolivar A. Feliz Nunez (Printed Name) (Printed Name) (Printed Name)
Gas Design Tech I Project Coordinator (Title) (Title) (Title)
08/03/2022 (Date)…