Adams County, Asotin County, Benton County, Chelan County, Clallam County, Clark County, Columbia County, Cowlitz County, Douglas County, Ferry County, Franklin County, Garfield County, Grant County, Grays Harbor County, Island County, Jefferson County, King County, Kitsap County, Kittitas County, Klickitat County, Lewis County, Lincoln County, Mason County, Okanogan County, Pacific County, Pend Oreille County, Pierce County, San Juan County, Skagit County, Skamania County, Snohomish County, Spokane County, Stevens County, Thurston County, Wahkiakum County, Walla Walla County, Whatcom County, Whitman County, Yakima County, Asotin City, Clarkston City, Clarkston Heights-Vineland CDP, West Clarkston-Highland CDP, Benton City, Chelan City, Chelan Falls CDP, Clallam Bay CDP, Lewisville CDP, Rock Island City, Pacific Beach CDP, Whidbey Island Station CDP, Mercer Island City, Pacific City, Bainbridge Island City, Kingston CDP, Kitsap Lake CDP, Kittitas City, Klickitat CDP, Okanogan City, Anderson Island CDP, Fort Lewis CDP, Fox Island CDP, Herron Island CDP, Ketron Island CDP, North Fort Lewis CDP, Raft Island CDP, Stevenson City, Hat Island CDP, Lake Stevens City, Snohomish City, Spokane City, Spokane Valley City, Puget Island CDP, Garfield Town, Yakima City, Washington

About this file

This document is an amendment to a solicitation (Competition No. 325-327) issued by the Washington State Parks and Recreation Commission (State Parks) for the fabrication and delivery of a replacement moorage float for the MV Thunderbird vessel at Deception Pass State Park. The amendment addresses questions received from potential bidders, including clarifying that Canadian Welding Bureau certification will be accepted for AWS welding certification, and that State Parks would consider a pontoon-style float design only if it meets the project's other criteria and requirements. The solicitation seeks a qualified fabricator/contractor to design, fabricate, and deliver the replacement float, with delivery to occur at the Deception Pass State Park, Cornet Bay Marine Crew Pier.

Regarding pricing and other terms, the amendment indicates that State Parks considers steel necessary for the structural support of the float due to permitting requirements, and that the decking must be grated, ruling out some alternative materials proposed by potential bidders. The solicitation covers multiple counties within the state of Washington, and the successful contractor will be required to construct the float using readily available equipment commonly used in the marine industry.

View the file

Other files

File Type Posted
Exhibit A-Sample Contract.pdf PDF
RFP 325-327 Prebid Presentation.pdf PDF
Attachment D-Area Map.pdf PDF
Exhibit C-Drawings-1.pdf PDF
Exhibit C-Drawings-2.pdf.crdownload CRDOWNLOAD file
RFP 325-327 Deception Pass-Float Fab.pdf PDF
325-327 PreBid Notes.pdf PDF
Exhibit B-Specifications.pdf PDF
Amendment 1.pdf PDF
Amendment 2.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Competition No. 325-327, Amendment #3 Page 1 of 2

-- SOLICITATION AMENDMENT 3 --

July 16, 2024

COMPETITION WEBS BID

RFP 325-327 Cornet Bay Float Fabrication Deception Pass State Park

PREVIOUS TERMS AND CONDITIONS IN EFFECT: All earlier terms, conditions, instructions, information, language, etc. not modified by this amendment remain in full force and effect.

NOTE: Bidders are invited to include this competition amendment with the Bidder’s bid response, but it is not mandatory.

ACTIONS: Answering questions State Parks received regarding this competition solicitation.

New Question

Question: Will CWB (Canadian Welding Bureau) certification be excepted for AWS welding certification for this project?

Answer: State Parks will accept Canadian Welding Bureau certification for AWS welding certification.

- -Previous Questions and Answers- -

Question: We manufacture marine grade aluminum framed floating docks with closed cell foam incapsulated in hand welded HDPE plastic and decked with Wolf PVC, would you consider us an approved equal?

Answer: State Parks and the engineer team consider steel is necessary for the structural support of the size and weight of the State Parks vessel the Thunderbird, due to permitting requirements the decking must be grated resulting in these substitutions not being considered acceptable for this project.

Question: Would you be open to an alternate design quote for a pontoon style float for your dock?

Competition No. 325-327, Amendment #3 Page 2 of 2

Answer: State Parks would consider a pontoon style float only if the design met the other criteria and requirements of the project such as but not limited to: float meets size specifications, steel framing to contain floats, decking is FRP grating with 60% light transmission, includes all pile loops, cleats, rub board/bumper and provide support for the gangway as detailed in the plans.