Am # 1 Dream Canyon Special Conditions.pdf
PDF 169 KB Posted
- Attached to
- PKAA, Dream Canyon Project
- Solicitation number
- DQ1 PKAA 2026000355 3
- Issued by
- Boulder County, Colorado
About this file
This document is an Amendment No. 1 to Special Conditions for the Dream Canyon Project, issued by the procuring jurisdiction on April 17, 2026, under contract reference DQ1 PKAA 2026*0355. The amendment clarifies procedures and modifies requirements outlined in the original bid documents, including the addition of a List of Equipment offered form to the project attachments. Bidders are advised that written inquiries regarding the project must be submitted via email to the designated Single Point of Contact by 4:00 p.m. Mountain Time on Wednesday, April 22, 2026. All terms and conditions of the original Documented Quote remain in effect except as modified by this amendment.
The amendment does not specify pricing terms, set-asides, contract duration, or renewal options. No information regarding funding sources, budget amounts, or incumbent contractors is provided in this document. This amendment functions primarily as a procedural clarification issued following a Pre-Bid Meeting, establishing the deadline for written inquiries and introducing an additional required form for the bidding process.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Special Conditions
Dream Canyon Project
Amendment No. 1 DQ1 PKAA 2026*0355
April 17, 2026
Thank you for your attendance at the Pre-Bid Meeting. The following clarifications and amendments should be noted and incorporated into the bid documents:
1. Written Inquiries
● Written inquiries may be submitted to the “Single Point of Contact” via email by 4:00 p.m. MT on Wednesday, April 22, 2026.
2. The List of Equipment offered form has been added to the attachments.
All terms and conditions of the Documented Quote other than as changed by this amendment remain the same.
Special Conditions
Dream Canyon Project
| Amendment No. 1 DQ1 PKAA 2026*0355 |
| April 17, 2026 |
File details come from the government source that posted it. Updated .