Amendment 1 attachment - Reconstruction Notes
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment 3 attachment.docx | DOCX document | |
| SF30.doc | DOC document | |
| 7 Waterline Replacement Amended 8-14-12.pdf | ||
| SF30 AMEND 001 Salmon Creek.doc | DOC document | |
| 02221 trenching.doc | DOC document | |
| Spec List.xlsx | XLSX spreadsheet | |
| 9 CLEARING LIMITS ASPHALT AND CULVERT DETAILS.PDF | ||
| Forest Service Supplemental Specs- Salmon Creek.docx | DOCX document | |
| 2 Site Plan.pdf | ||
| 02080_utility materials.doc | DOC document | |
| 15251 waterlines appurten.doc | DOC document | |
| 8 ASPHALT DITCH AND WATERLINE DETAILS.PDF | ||
| 3 Paving Culvert and Ditch Recon Section 1.pdf | ||
| SOLICITATION Salmon Creek.doc | DOC document | |
| 6 Paving Culvert and Ditch Recon Section 4.pdf | ||
| 5 Paving Culvert and Ditch Recon Section 3.pdf | ||
| 1 TITLE SHEET.PDF | ||
| 4 Paving Culvert and Ditch Recon Section 2.pdf | ||
| 7 Waterline Replacement.pdf | ||
| 15255 valves enclosrs.doc | DOC document |
Show all 20
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SALMON CREEK RECONSTRUCTION NOTES: ASPHALT NOTES
General Notes:
1. These notes are to be used in conjunction with all Specifications and the Drawings. The Specifications take precedence over these notes.
2. All new asphalt shall conform to the widths of the existing asphalt surface.
3. Asphalt patch all potholes that are over 2” in depth in the sections where existing asphalt is to be used as base.
4. Clean and Tack-coat all sections where new asphalt is placed on existing asphalt with SS1H Tack Coat or equivalent.
5. Sections recently paved in good condition: Use a 1.5” overlay on recent sections in good condition with no cracks as designated by the Engineer.
6. Sections where existing asphalt can be used as sub-base: Use 3”overlay over old roadbed where the old asphalt is good enough to use as the sub-base needing only to fill the potholes prior to paving.
7. Sections to be totally reconditioned: Use 3” overlay on top of totally reconditioned sub-base sections. Rip up existing roadbed. Pulverized asphalt may be used with ¾” crushed aggregate as compacted base material. Reconstructed sections shall be out- sloped at 2% to the west (creek side) of the road. Sections shall be approved in writing by the engineer prior to paving.
8. All prep work such as grinding and relaying, pothole patching etc. shall be completed and approved by the engineer in writing before new paving starts.
Asphalt Notes:
Main Campground Road (DRAWINGS: Paving, Culvert and Ditch Reconstruction Sections 2-4)
| 0+00 | New Asphalt- No overlay needed. | |
| 0+55 | Begin 1.5” overlay using existing asphalt as base - average width 18’ | |
| 1+75 | Intersection Loop 1 (See Loop 1 notes below. STA 1+75 = STA 0+00 of Loop 1) Continue 1.5” overlay using existing asphalt as base -average width 18’ |
2+70 End 1.5” overlay. Begin 2” overlay using existing asphalt as base -average width 19’
3+50 Continue 2” overlay using existing asphalt as base, width 32’ in the middle of the intersection.
3+70 End 2”overlay. Begin 3” overlay using existing asphalt as base; fill potholes prior to paving.
4+00 End intersection. Continue 3” overlay using existing asphalt as base - average width 26’
5+00 Continue 3” overlay using existing asphalt as base - average width 19’
5+75 End 3” overlay. Begin 1.5” overlay using existing asphalt as base - average width 20’
6+90 End 1.5” overlay. Begin reconstruction. Reconstruct base, rip up old asphalt and aggregate. Old asphalt may be pulverized and used with ¾” crushed aggregate to become 4” of compacted base. Engineer shall approve base prior to paving. Place 3” new asphalt on reconstructed section. The new reconstructed area will be out-sloped at 2% to the west (creek side) of the road. Average width 18’.
8+85 End complete reconstruction. Begin 1.5” overlay using existing asphalt as base -average width 18’.
9+70 End 1.5” overlay. Begin reconstruction. Reconstruct base, rip up old asphalt and aggregate. Old asphalt may be pulverized and used with ¾” crushed aggregate to become 4” of compacted base. Place 3” new asphalt on reconstructed section. The new reconstructed area will be out-sloped at 2% to the west (creek side) of the road. Average width 18’.
15+20 End complete reconstruction. Begin 1.5” overlay using existing asphalt as base -average width 18’.
15+85 End 1.5” overlay. Begin 3” overlay using existing asphalt as base; fill potholes prior to paving. Average width 18’.
22+30 Intersection with end loop. Continue 3” overlay using existing asphalt as base. Average width 18’. Conform new asphalt width to existing asphalt on the ground. Conform to existing asphalt at the end of the loop.
22+50 Continue 3” overlay using existing asphalt as base.
| 22+60 | Continue 3” overlay using existing asphalt as base. Average width decreases |
| from 12’ to 11’. |
23+00 Continue 3” overlay using existing asphalt as base. Average width 11’.
24+85 Continue 3” overlay using existing asphalt as base. Begin turnout. Width 42’ at widest part of turnout.
26+50 Continue 3” overlay using existing asphalt as base. Average width 12’.
28+50 Intersection with end loop. Continue 3” overlay using existing asphalt as base. Average width 24’.
28+66 End of Stationing at centerline. End paving once the intersection is reached and the end loop is complete.
OPTION: First Loop Overlay (DRAWINGS: OPTION: Paving, Culvert and Ditch Reconstruction Section 1)
0+00 Intersection Loop 1 (See Loop 1 notes below. STA 1+75 = STA 0+00 of Loop 1) No work required.
0+70 Begin 3” overlay using existing asphalt as base; fill potholes. Average width 10’.
12+50 End 3” overlay at intersection of Loop 1 with main road.
SALMON CREEK RECONSTRUCTION NOTES: DITCH AND WATERLINE RECONSTRUCTION NOTES
1. Ditch reconstruction is on the east side of the roadway and work to be completed is designated by the centerline stationing. Roadside ditch reconstruction shall be in conjunction with culvert installation.
2. These notes are to be used in conjunction with all Specifications and the Drawings. The Specifications take precedence over these notes.
Ditch and Waterline Reconstruction Notes:
Main Campground Road
| 5+00 | Begin roadside ditch reconstruction. Old 2 inch cast iron water pipe may be encountered in roadside ditch. Remove when possible or as needed to install new 2 inch HDPE waterline at a minimum of 1 foot below the bottom of reconstructed ditch. Remove all rocks, brush and trees within ditch. |
| 5+25 | Install 24”X 48’ length C.M.P. Continue to clean, reconstruct ditch and install new water pipe to meet new culvert inlets. See Culvert Installation Reconstruction Notes for details. |
| 11+50 | Continue roadside ditch reconstruction, cleaning and new water pipe installation. Heavy construction with rocks, brush, trees and water pipe in ditch. |
| 12+22 | Install 35” X 24” Squash pipe, 30’ length. Continue to clean, reconstruct ditch and install new water pipe to meet new culvert inlets. See Culvert Installation Reconstruction Notes for details. |
| 14+20 | Install (2) 42” X 29” squash pipe, each 30’ in length. Continue to clean, reconstruct ditch and install new water pipe to meet new culvert inlets. See Culvert Installation Reconstruction Notes for details. Major pipe inlet basin filled in with aggregates and needs to be reconstructed. Ditch entering from both sides. Continue roadside ditch reconstruction and new water pipe installation. Heavy construction with rocks, brush, trees and waterline in ditch. |
| 15+10 | Install 24” X 40’ length CMP. Continue to clean, reconstruct ditch and install new water pipe to meet new culvert inlets. See Culvert Installation Reconstruction Notes for details. New water pipe shall cross under road alongside new culvert and connect to existing water line and water hydrant neat Campsite 22. New water pipe ends. |
| 16+50 | Install 18” X 30’ length CMP under campground spur road. Continue to clean and reconstruct ditch to meet new culvert inlets. See Culvert Installation Reconstruction Notes for details. |
| 17+60 | End roadside ditch reconstruction |
| 18+08 | Begin roadside ditch reconstruction. Install 35” X 24” Squash pipe, 30’ length. Begin roadside ditch reconstruction. Continue to clean and reconstruct ditch to meet new culvert inlets. See Culvert Installation Reconstruction Notes for details. |
| 18+75 | Install 18”X36’ CMP under campground spur road. Continue to clean and reconstruct ditch to meet new culvert inlets. See Culvert Installation Reconstruction Notes for details. |
| 19+75 | Install 18”X 34’ CMP under campground spur road. Continue to clean and reconstruct ditch to meet new culvert inlets. See Culvert Installation Reconstruction Notes for details. |
| 20+50 | End ditch reconstruction. |
| 20+85 | Install 24” X 35” squash pipe, 30’ long. See Culvert Installation Reconstruction Notes for details. |
Loop 1 Road Drainage is functioning. No work required.
SALMON CREEK RECONSTRUCTION NOTES: PIPE LOCATION AND SIZE RECONSTRUCTION NOTES
1. These notes are to be used in conjunction with all Specifications and the Drawings. Please refer to these items for proper installation. The Specifications take precedence over these notes.
2. All pipes shall be set at a minimum of 2%.
Pipe Location and Size Notes:
Main Campground Road
| 5+25 | Install 24”X 48’ length C.M.P. Replace existing pipe. Inlet moves south as approved by the Engineer. The outlet stays at current location. Reconstruct inlet at low spot, ditch from both sides. |
| 12+22 | Install 35” X 24” Squash pipe, 30’ length. Replace existing pipe. Remove 3 trees. Existing waterline runs north/south within roadside ditch. New waterline to be installed. Reconstruct inlet and outlet to drain. |
| 14+20 | Install (2) 42” X 29” squash pipes each in 30’ length. Major inlet excavation. Lower outlet by 2’ and reconstruct outlet ditch to daylight at 50’. |
| 15+10 | Install 24” X 40’ length C.M.P. and waterline. Reconstruct inlet, deepen outlet ditch by 2’ to daylight at 50’. Turn ditch South away from Campsite 22. Waterline crosses road alongside the new C.M.P. and hooks up to existing water line near water station. |
| 16+50 | Install 18” X 30’ length C.M.P. Pipe under spur to Campsite 23. Bury pipe deeper and match both the inlet and outlet to new roadside ditch. |
| 18+08 | Install 35” X 24” squash pipe, 30’ length. Deepen inlet. Set pipe at 2% plus. Deepen outlet a minimum of 2’ and reconstruct ditch to drain and to daylight at 60’. Caution of existing waterline crossing outlet 65’ out. |
| 18+75 | Install 18” X 36’ length C.M.P. Pipe under spur to Campsite 26. Bury pipe to match both the inlet and outlet to new roadside ditch. |
| 19+75 | Install 18” X 34’ length C.M.P. Pipe under spur to Campsite 27. Bury pipe to match both the inlet and outlet to new roadside ditch. |
| 20+85 | Install 35” X 24” squash culvert, 30’ length. Pipe is just after access to space 29. Use existing outlet ditch but lower 2’ to drain and daylight at 45’. Remove old rock and mortar at inlet. |