Salmon Creek Reconstruction Notes.docx

DOCX document 23 KB Posted

Attached to
Salmon Creek Paving Federal contract opportunity
Solicitation number
AG-9A63-S-12-0102
Issued by
Department of Agriculture Forest Service R5-Pacific Southwest Region

About this file

Amendment 1 attachment - Reconstruction Notes

View the file

Other files for this federal contract opportunity

Other files attached to Salmon Creek Paving, newest first.
File Type Posted
Amendment 3 attachment.docx DOCX document
SF30.doc DOC document
7 Waterline Replacement Amended 8-14-12.pdf PDF
SF30 AMEND 001 Salmon Creek.doc DOC document
02221 trenching.doc DOC document
Spec List.xlsx XLSX spreadsheet
9 CLEARING LIMITS ASPHALT AND CULVERT DETAILS.PDF PDF
Forest Service Supplemental Specs- Salmon Creek.docx DOCX document
2 Site Plan.pdf PDF
02080_utility materials.doc DOC document
15251 waterlines appurten.doc DOC document
8 ASPHALT DITCH AND WATERLINE DETAILS.PDF PDF
3 Paving Culvert and Ditch Recon Section 1.pdf PDF
SOLICITATION Salmon Creek.doc DOC document
6 Paving Culvert and Ditch Recon Section 4.pdf PDF
5 Paving Culvert and Ditch Recon Section 3.pdf PDF
1 TITLE SHEET.PDF PDF
4 Paving Culvert and Ditch Recon Section 2.pdf PDF
7 Waterline Replacement.pdf PDF
15255 valves enclosrs.doc DOC document
Show all 20

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SALMON CREEK RECONSTRUCTION NOTES: ASPHALT NOTES

General Notes:

1. These notes are to be used in conjunction with all Specifications and the Drawings. The Specifications take precedence over these notes.

2. All new asphalt shall conform to the widths of the existing asphalt surface.

3. Asphalt patch all potholes that are over 2” in depth in the sections where existing asphalt is to be used as base.

4. Clean and Tack-coat all sections where new asphalt is placed on existing asphalt with SS1H Tack Coat or equivalent.

5. Sections recently paved in good condition: Use a 1.5” overlay on recent sections in good condition with no cracks as designated by the Engineer.

6. Sections where existing asphalt can be used as sub-base: Use 3”overlay over old roadbed where the old asphalt is good enough to use as the sub-base needing only to fill the potholes prior to paving.

7. Sections to be totally reconditioned: Use 3” overlay on top of totally reconditioned sub-base sections. Rip up existing roadbed. Pulverized asphalt may be used with ¾” crushed aggregate as compacted base material. Reconstructed sections shall be out- sloped at 2% to the west (creek side) of the road. Sections shall be approved in writing by the engineer prior to paving.

8. All prep work such as grinding and relaying, pothole patching etc. shall be completed and approved by the engineer in writing before new paving starts.

Asphalt Notes:

Main Campground Road (DRAWINGS: Paving, Culvert and Ditch Reconstruction Sections 2-4)

0+00New Asphalt- No overlay needed.
0+55Begin 1.5” overlay using existing asphalt as base - average width 18’
1+75Intersection Loop 1 (See Loop 1 notes below. STA 1+75 = STA 0+00 of Loop 1) Continue 1.5” overlay using existing asphalt as base -average width 18’

2+70 End 1.5” overlay. Begin 2” overlay using existing asphalt as base -average width 19’

3+50 Continue 2” overlay using existing asphalt as base, width 32’ in the middle of the intersection.

3+70 End 2”overlay. Begin 3” overlay using existing asphalt as base; fill potholes prior to paving.

4+00 End intersection. Continue 3” overlay using existing asphalt as base - average width 26’

5+00 Continue 3” overlay using existing asphalt as base - average width 19’

5+75 End 3” overlay. Begin 1.5” overlay using existing asphalt as base - average width 20’

6+90 End 1.5” overlay. Begin reconstruction. Reconstruct base, rip up old asphalt and aggregate. Old asphalt may be pulverized and used with ¾” crushed aggregate to become 4” of compacted base. Engineer shall approve base prior to paving. Place 3” new asphalt on reconstructed section. The new reconstructed area will be out-sloped at 2% to the west (creek side) of the road. Average width 18’.

8+85 End complete reconstruction. Begin 1.5” overlay using existing asphalt as base -average width 18’.

9+70 End 1.5” overlay. Begin reconstruction. Reconstruct base, rip up old asphalt and aggregate. Old asphalt may be pulverized and used with ¾” crushed aggregate to become 4” of compacted base. Place 3” new asphalt on reconstructed section. The new reconstructed area will be out-sloped at 2% to the west (creek side) of the road. Average width 18’.

15+20 End complete reconstruction. Begin 1.5” overlay using existing asphalt as base -average width 18’.

15+85 End 1.5” overlay. Begin 3” overlay using existing asphalt as base; fill potholes prior to paving. Average width 18’.

22+30 Intersection with end loop. Continue 3” overlay using existing asphalt as base. Average width 18’. Conform new asphalt width to existing asphalt on the ground. Conform to existing asphalt at the end of the loop.

22+50 Continue 3” overlay using existing asphalt as base.

22+60Continue 3” overlay using existing asphalt as base. Average width decreases
from 12’ to 11’.

23+00 Continue 3” overlay using existing asphalt as base. Average width 11’.

24+85 Continue 3” overlay using existing asphalt as base. Begin turnout. Width 42’ at widest part of turnout.

26+50 Continue 3” overlay using existing asphalt as base. Average width 12’.

28+50 Intersection with end loop. Continue 3” overlay using existing asphalt as base. Average width 24’.

28+66 End of Stationing at centerline. End paving once the intersection is reached and the end loop is complete.

OPTION: First Loop Overlay (DRAWINGS: OPTION: Paving, Culvert and Ditch Reconstruction Section 1)

0+00 Intersection Loop 1 (See Loop 1 notes below. STA 1+75 = STA 0+00 of Loop 1) No work required.

0+70 Begin 3” overlay using existing asphalt as base; fill potholes. Average width 10’.

12+50 End 3” overlay at intersection of Loop 1 with main road.

SALMON CREEK RECONSTRUCTION NOTES: DITCH AND WATERLINE RECONSTRUCTION NOTES

1. Ditch reconstruction is on the east side of the roadway and work to be completed is designated by the centerline stationing. Roadside ditch reconstruction shall be in conjunction with culvert installation.

2. These notes are to be used in conjunction with all Specifications and the Drawings. The Specifications take precedence over these notes.

Ditch and Waterline Reconstruction Notes:

Main Campground Road

5+00Begin roadside ditch reconstruction. Old 2 inch cast iron water pipe may be encountered in roadside ditch. Remove when possible or as needed to install new 2 inch HDPE waterline at a minimum of 1 foot below the bottom of reconstructed ditch. Remove all rocks, brush and trees within ditch.
5+25Install 24”X 48’ length C.M.P. Continue to clean, reconstruct ditch and install new water pipe to meet new culvert inlets. See Culvert Installation Reconstruction Notes for details.
11+50Continue roadside ditch reconstruction, cleaning and new water pipe installation. Heavy construction with rocks, brush, trees and water pipe in ditch.
12+22Install 35” X 24” Squash pipe, 30’ length. Continue to clean, reconstruct ditch and install new water pipe to meet new culvert inlets. See Culvert Installation Reconstruction Notes for details.
14+20Install (2) 42” X 29” squash pipe, each 30’ in length. Continue to clean, reconstruct ditch and install new water pipe to meet new culvert inlets. See Culvert Installation Reconstruction Notes for details. Major pipe inlet basin filled in with aggregates and needs to be reconstructed. Ditch entering from both sides. Continue roadside ditch reconstruction and new water pipe installation. Heavy construction with rocks, brush, trees and waterline in ditch.
15+10Install 24” X 40’ length CMP. Continue to clean, reconstruct ditch and install new water pipe to meet new culvert inlets. See Culvert Installation Reconstruction Notes for details. New water pipe shall cross under road alongside new culvert and connect to existing water line and water hydrant neat Campsite 22. New water pipe ends.
16+50Install 18” X 30’ length CMP under campground spur road. Continue to clean and reconstruct ditch to meet new culvert inlets. See Culvert Installation Reconstruction Notes for details.
17+60End roadside ditch reconstruction
18+08Begin roadside ditch reconstruction. Install 35” X 24” Squash pipe, 30’ length. Begin roadside ditch reconstruction. Continue to clean and reconstruct ditch to meet new culvert inlets. See Culvert Installation Reconstruction Notes for details.
18+75Install 18”X36’ CMP under campground spur road. Continue to clean and reconstruct ditch to meet new culvert inlets. See Culvert Installation Reconstruction Notes for details.
19+75Install 18”X 34’ CMP under campground spur road. Continue to clean and reconstruct ditch to meet new culvert inlets. See Culvert Installation Reconstruction Notes for details.
20+50End ditch reconstruction.
20+85Install 24” X 35” squash pipe, 30’ long. See Culvert Installation Reconstruction Notes for details.

Loop 1 Road Drainage is functioning. No work required.

SALMON CREEK RECONSTRUCTION NOTES: PIPE LOCATION AND SIZE RECONSTRUCTION NOTES

1. These notes are to be used in conjunction with all Specifications and the Drawings. Please refer to these items for proper installation. The Specifications take precedence over these notes.

2. All pipes shall be set at a minimum of 2%.

Pipe Location and Size Notes:

Main Campground Road

5+25Install 24”X 48’ length C.M.P. Replace existing pipe. Inlet moves south as approved by the Engineer. The outlet stays at current location. Reconstruct inlet at low spot, ditch from both sides.
12+22Install 35” X 24” Squash pipe, 30’ length. Replace existing pipe. Remove 3 trees. Existing waterline runs north/south within roadside ditch. New waterline to be installed. Reconstruct inlet and outlet to drain.
14+20Install (2) 42” X 29” squash pipes each in 30’ length. Major inlet excavation. Lower outlet by 2’ and reconstruct outlet ditch to daylight at 50’.
15+10Install 24” X 40’ length C.M.P. and waterline. Reconstruct inlet, deepen outlet ditch by 2’ to daylight at 50’. Turn ditch South away from Campsite 22. Waterline crosses road alongside the new C.M.P. and hooks up to existing water line near water station.
16+50Install 18” X 30’ length C.M.P. Pipe under spur to Campsite 23. Bury pipe deeper and match both the inlet and outlet to new roadside ditch.
18+08Install 35” X 24” squash pipe, 30’ length. Deepen inlet. Set pipe at 2% plus. Deepen outlet a minimum of 2’ and reconstruct ditch to drain and to daylight at 60’. Caution of existing waterline crossing outlet 65’ out.
18+75Install 18” X 36’ length C.M.P. Pipe under spur to Campsite 26. Bury pipe to match both the inlet and outlet to new roadside ditch.
19+75Install 18” X 34’ length C.M.P. Pipe under spur to Campsite 27. Bury pipe to match both the inlet and outlet to new roadside ditch.
20+85Install 35” X 24” squash culvert, 30’ length. Pipe is just after access to space 29. Use existing outlet ditch but lower 2’ to drain and daylight at 45’. Remove old rock and mortar at inlet.