Section01781 ProjectRecordDocs.doc

DOC document 35 KB Posted

Attached to
RECOVERY - Repair/resurface Roofs: Main Bldg (North Wing); West Annex Bldg and Service Bldg, WRRC, Albany, CA
Solicitation number
AG-95CV-S-09-0020
Issued by

About this file

01781 - Project Record Documents

View the file

Other files

File Type Posted
ReportingReqmts.docx DOCX document
S090020A1.pdf PDF
Amend001.doc DOC document
GenDec9-4-09.doc DOC document
S090020a.pdf PDF
GenDec7-31-09.doc DOC document
S090020a.doc DOC document
S090020.pdf PDF
SupplementalInfo(ServiceBldgRoof).doc DOC document
SupplementalInfo(WAB(labs)Roof).doc DOC document
Section07620 ShtmtlFlashing Trim.doc DOC document
Section06105 Misc.Carpentry.doc DOC document
S090020.doc DOC document
Section07543 RoofRestoration.doc DOC document
Section01500 TempControls.doc DOC document
Section07540 TPAMembraneRoofing.doc DOC document
Section01740 Warranties.doc DOC document
Section01010 SummaryOfWork.doc DOC document
Section01631 Products Subs.doc DOC document
GenDec8-15-08.doc DOC document
SupplementalInfo(WAB(dir.wing)Roof).doc DOC document
Section01370 SchedOfValues.doc DOC document
Section01560 EnvProtection.doc DOC document
Section01600 Materials.doc DOC document
Section01016 SafetyDuringConst.doc DOC document
Section01105 SpecialConditions.doc DOC document
Section01040 ProjectCoord.doc DOC document
Section01732 SelectiveDemo.doc DOC document
BidDocumentsTableOfContents.doc DOC document
Section01700 ContractCloseout.doc DOC document
Section01736 SelectiveDemo.doc DOC document
Show all 31

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation No. AG-95CV-S-09-0020 Recovery – Replace or Repair/Resurface Roofs, Main Bldg

(N.Wing), WAB, & Service Bldg, WRRC, Albany, CA

SECTION 01781 – PROJECT RECORD DOCUMENTS

PART 1 GENERAL

1.1

SUMMARY

A.

This Section includes administrative and procedural requirements for Project Record Documents, including the following:

1.

Record drawings.

2.

Record product data.

1.2

SUBMITTALS

A.

Record Drawings: Submit three sets of marked-up Record Prints.

B.

Record Product Data: Submit three copies of each Product Data submittal. Where Record Product Data is required as part of maintenance manuals, submit marked-up Product Data as an insert in the manual instead of submittal as Record Product Data.

1.3

RECORD DRAWINGS

A.

Record Prints: Maintain one set of blue- or black-line white prints.

1.

Preparation: Mark Record Prints to show the actual installation where installation varies from that indicated in Contract Documents. Require individual or entity that obtained record data, whether individual or entity is Installer, subcontractor, or similar entity, to prepare the marked-up Record Prints.

a.

Give particular attention to information on concealed elements that would be difficult to identify or measure and record later.

b.

Accurately record information in an understandable drawing technique.

c.

Record data as soon as possible after obtaining it. Record and check the markup before enclosing concealed installations.

2.

Content: Types of items requiring marking include, but are not limited to, the following:

a.

Dimensional changes.

b.

Field Changes and changes made by Change Order.

c.

Changes made in response to Government directives.

d.

Field records for variable and concealed conditions.

e.

Record information on the Work that is addressed only schematically in the Contract Documents.

1) Mark the Contract Documents, completely and accurately.

2) Mark record sets with erasable, red-colored pencil. Use other colors to distinguish between changes for different categories of the Work at the same location.

3) Mark important additional information that was either shown schematically or omitted from the Contract Documents.

4) Note Change Order numbers and similar identification, where applicable.

B.

Format: Identify and date each Record Drawing; include the designation "Project Record Drawing" in a prominent location.

1.

Record Prints: Organize Record Prints and newly prepared Record Drawings into manageable sets. Bind each set with durable paper cover sheets. Include identification on cover sheets.

1.4

RECORD PRODUCT DATA

A.

Preparation: Mark Product Data to indicate the actual product installation where installation varies substantially from that indicated in Product Data submittal.

1.

Give particular attention to information on concealed products and installations that cannot be readily identified and recorded later.

2.

Include significant changes in the product delivered to Project site and changes in manufacturer's written instructions for installation.

3.

Note related Change Orders, Record Drawings, and Product Data where applicable.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

3.1

RECORDING AND MAINTENANCE

A.

Recording: Maintain one copy of each submittal during the construction period for Project Record Document purposes. Post changes and modifications to Project Record Documents as they occur; do not wait until the end of Project.

B.

Maintenance of Record Documents: Store Record Documents in the field apart from the Contract Documents used for construction. Do not use Project Record Documents for construction purposes. Maintain Record Documents in good order and in a clean, dry, legible condition, protected from deterioration and loss. Provide access to Project Record Documents for Government’s reference during normal working hours.

END OF SECTION 01781

PROJECT RECORD DOCUMENTS

01781 - 1