Specifications Divisions 1 through 14

View the file

Other files

File Type Posted
BidAbstract.pdf PDF
ApparentLowBidder.doc DOC document
BidAmendment5.doc DOC document
revisedS2.2rev030508.pdf PDF
BidAmendmentNo4.pdf PDF
addedsection02227.pdf PDF
1_BidAmendmentNo3.pdf PDF
BidAmendmentNo3.pdf PDF
revisedspecsTOC.pdf PDF
revisedC1-4-rev022108.pdf PDF
addedChattoogaBoringReport.pdf PDF
addedC1-1A.pdf PDF
addedsection04720.pdf PDF
revisedC1-1-rev021808.pdf PDF
BidAmendmentNo2.pdf PDF
PreBidMeetingNotes.doc DOC document
PreBidAttendees.pdf PDF
LEEDbriefing.doc DOC document
revisedEsheets1.1-1.2-4.1.pdf PDF
BidAmendmentNo1.pdf PDF
specsdivisions15and16.pdf PDF
2_NoteonSpecificationsandDrawings.doc DOC document
ArchitecturalDrawings.pdf PDF
StructuralDrawings.pdf PDF
1_NoteonSpecificationsandDrawings.doc DOC document
Chattooga_River_Office_IFB.pdf PDF
Mech-Elec-PlumbingDrawings.pdf PDF
fs-2400-4_and_general_conditions.doc DOC document
NoteonSpecificationsandDrawings.doc DOC document
CivilDrawings.pdf PDF
OF-17 new.pdf PDF
Show all 31

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Chattooga River Ranger Office Project No. 0204.17

OWNER:

USDA Forest Service Southern Region 1720 Peachtree Road, N.W.

Atlanta, Georgia 30309

TEL: 404/347-4593 FAX: 404/347-2399

ARCHITECT:

MOMA Architecture, Inc.

123 Church Street, Suite 350 Marietta, Georgia 30060

TEL: 770/422-9040 FAX: 770/422-9050

CIVIL:

Engineering Management, Inc.

303 Swanson Dr.

Lawrenceville, Georgia 30043

TEL: 770/962-1387 FAX: 770/962-8010

STRUCTURAL:

Stability Engineering 431 West Ponce de Leon Ave., Suite 4 Decatur, Georgia 30030

TEL: 404/377-9316 FAX: 404/377-9317

MECHANICAL/ELECTRICAL:

HESM&A

1255 Collier Rd., Suite C Atlanta, Georgia 30318-2308

TEL: 404/881-5300 FAX: 404/881-0909

This Project Manual, as an Instrument of Service, is and shall remain the property of the Architect and shall not be reproduced, published or used in any way without the permission of the Architect.

© M O M A Architecture 2007

CHATTOOGA RIVER RANGER OFFICE TABLE OF CONTENTS

MOMA 0204.17 11/02/07 TOC-1

Issue Date

DIVISION 1 - GENERAL 01100 Summary 11/02/07 REQUIREMENTS 01200 Price and Payment Procedures 11/02/07 01300 Administrative Requirements 11/02/07 01354 Leed Credit Summary 11/02/07 01400 Quality Requirements 11/02/07 01500 Temporary Facilities and Controls 11/02/07 01575 Temporary Erosion and Sedimentation Control 11/02/07 01600 Product Requirements 11/02/07 01700 Execution Requirements 11/02/07 01732 Waste Management 11/02/07 01734 Indoor Air Quality 11/02/07 01780 Closeout Submittals 11/02/07

DIVISION 2 - SITE CONSTRUCTION 02200 Earthwork 11/02/07 02225 Earthwork for Utilities 11/02/07 02230 Site Clearing 11/02/07 02270 Temporary Erosion Control 11/02/07 02272 Rip Rap 11/02/07 02361 Termite Control 11/02/07 02601 Manholes 11/02/07 02660 Water Distribution Systems 11/02/07 02736 Sanitary Sewer 11/02/07 02751 Cement Concrete Pavement 11/02/07 02870 Site Furnishings 11/02/07 02931 Grassing 11/02/07

DIVISION 3 - CONCRETE 03130 Permanent Insulated Concrete Forming IICF) System 11/02/07 03300 Cast-In-Place Concrete 11/02/07

DIVISION 4 - MASONRY 04860 Stone Masonry 11/02/07

DIVISION 5 - METALS 05120 Structural Steel 11/02/07 05500 Metal Fabrications 11/02/07

DIVISION 6 - WOOD AND PLASTICS 06100 Rough Carpentry 11/02/07 06176 Metal-Plate-Connected Wood Trusses 11/02/07 06181 Glued Laminate Structural Units 11/02/07 06201 Exterior Finish Carpentry 11/02/07 06402 Interior Architectural Woodwork 11/02/07

DIVISION 7 -THERMAL AND 07115 Waterproofing Membrane MOISTURE 07210 Building Insulation 11/02/07 PROTECTION 07610 Sheet Metal Roofing 11/02/07 07920 Joint Sealants 11/02/07

DIVISION 8 - DOORS AND WINDOWS 08110 Steel Door Frames 11/02/07 08211 Flush Wood Doors 11/02/07 08411 Aluminum-Framed Entrances and Storefronts 11/02/07 08710 Door Hardware 11/02/07 08800 Glazing 11/02/07

DIVISION 9 - FINISHES 09250 Gypsum Board 11/02/07 09310 Ceramic Tile 11/02/07 09511 Acoustical Panel Ceilings 11/02/07 09651 Resilient Floor Tile 11/02/07 09653 Resilient Wall Base and Accessories 11/02/07 09681 Carpet Tile 11/02/07 09911 Painting 11/02/07

MOMA 0204.17 11/02/07 TOC-2

DIVISION 10 – SPECIALTIES 10155 Toilet Compartments 11/02/07 10270 Access Flooring 11/02/07 10431 Signage 11/02/07 10520 Fire-Protection Specialties 11/02/07 10801 Toilet and Bath Accessories 11/02/07

SECTION 11 – EQUIPMENT 11458 Disappearing Stairway 11/02/07

DIVISION 12 – FURNISHINGS 12485 Foot Grilles 11/02/07 12491 Horizontal Louver Blinds 11/02/07

SECTION 13 – SPECIAL Not used.

SECTION 14 – CONVEYING SYSTEMS 14210 Electric Traction Elevators 11/02/07

SECTION 15 - MECHANICAL 15010 Basic Mechanical Requirements 11/02/07 15011 Schedule of Submittal Data 11/02/07 15030 Excavating, Trenching, an Backfilling 11/02/07 15047 Identification of Pipe, Valves, and Equipment 11/02/07 15060 Pipe Hangers, Supports, and Anchors 11/02/07 15100 Valves (HVAC) 11/02/07 15170 Motors, Starters, and Disconnect Switches 11/02/07 15185 Pumps (HVAC) 11/02/07 15230 Mechanical Insulation 11/02/07 15241 Vibration Isolation 11/02/07 15410 Plumbing Fixtures and Trim 11/02/07 15421 Domestic Water Distribution 11/02/07 15431 Soil and Waste Piping Systems 11/02/07 15462 Light Duty Electric Storage Type Water Heaters 11/02/07 15510 HVAC Piping 11/02/07 15520 Piping Specialties 11/02/07 15545 Water Treatment System 11/02/07 15605 Geothermal Heat Pumps 11/02/07 15660 Fans 11/02/07 15680 Electric Heaters 11/02/07 15820 Ductwork Specialties 11/02/07 15860 Energy Recovery Units 11/02/07 15870 Grilles, Registers, and Diffusers 11/02/07 15891 Ductwork 11/02/07 15900 Construction IAQ Management Plan 11/02/07 15950 Building Systems Control 11/02/07 15990 Testing, Adjusting, and Balancing 11/02/07

MOMA 0204.17 11/02/07 TOC-3

SECTION 16 - ELECTRICAL 16010 Electrical General 11/02/07 16110 Raceway Systems 11/02/07 16120 Wires and Cables 11/02/07 16130 Boxes and Fittings 11/02/07 16140 Wiring Devices 11/02/07 16160 Panelboards 11/02/07 16165 Distribution Panelboards 11/02/07 16170 Motor and Feeder Disconnect Switches 11/02/07 16425 Service and Distribution 11/02/07 16450 Grounding 11/02/07 16505 Lighting 11/02/07 16560 Lighting Controls 11/02/07 16620 Surge Protection 11/02/07

END OF TOC

CHATTOOGA RIVER RANGER OFFICE SUMMARY

MOMA 0204.17 11/02/07 01100-1

SECTION 01100

SUMMARY

PART 1 GENERAL

1.1 PROJECT

A. Project Name: Chattooga River Ranger Office.

B. Owner's Name: U.S. Forest Service.

1.2 CONTRACT DESCRIPTION

A. Contract Type: A single prime contract based on a firm, fixed price as described in Section B of the Contract.

1.3 WORK BY OWNER

A. Items noted NIC (Not in Contract) will be supplied and installed by U.S. Forest Service before Substantial Completion. Some items include:

1. Movable cabinets.

2. Furnishings.

3. Small equipment.

1.4 OWNER OCCUPANCY

A. U.S. Forest Service intends to occupy the Project upon Substantial Completion.

B. Cooperate with U.S. Forest Service to minimize conflict and to facilitate U.S. Forest Service's operations.

C. Schedule the Work to accommodate U.S. Forest Service occupancy.

1.5 CONTRACTOR USE OF SITE AND PREMISES

A. Construction Operations: Limited to areas noted on Drawings.

B. Arrange use of site and premises to allow:

1. Work by Others.

2. Work by U.S. Forest Service.

C. Provide access to and from site as required by law and by U.S. Forest Service:

1. Emergency Building Exits During Construction: Keep all exits required by code open during construction period; provide temporary exit signs if exit routes are temporarily altered.

2. Do not obstruct roadways, sidewalks, or other public ways without permit.

D. Utility Outages and Shutdown:

1. Limit disruption of utility services to hours the building is unoccupied.

2. Prevent accidental disruption of utility services to other facilities.

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION - NOT USED

END OF SECTION

CHATTOOGA RIVER RANGER OFFICE PRICE AND PAYMENT PROCEDURES

MOMA 0204.17 11/02/07 01200-1

SECTION 01200

PRICE AND PAYMENT PROCEDURES

PART 1 GENERAL

1.1 SECTION INCLUDES

A. Procedures for preparation and submittal of applications for progress payments.

B. Documentation of changes in Contract Sum and Contract Time.

C. Change procedures.

D. Correlation of Contractor submittals based on changes.

E. Procedures for preparation and submittal of application for final payment.

1.2 SCHEDULE OF VALUES

A. Submit a printed schedule on AIA Form G703 - Application and Certificate for Payment Continuation Sheet. Contractor's standard form or electronic media printout will be considered.

B. Submit Schedule of Values in duplicate within 15 days after date of Owner-Contractor Agreement.

C. Format: Utilize the Table of Contents of this Project Manual. Identify each line item with number and title of the specification Section. Identify site mobilization.

1.3 APPLICATIONS FOR PROGRESS PAYMENTS

A. Payment Period: Submit at intervals stipulated in the Agreement.

B. Present required information on electronic media printout.

C. Form: Contractor's electronic media driven form including continuation sheets when required.

D. For each item, provide a column for listing each of the following:

1. Item Number.

2. Description of work.

3. Scheduled Values.

4. Previous Applications.

5. Work in Place and Stored Materials under this Application.

6. Authorized Change Orders.

7. Total Completed and Stored to Date of Application.

8. Percentage of Completion.

9. Balance to Finish.

E. Execute certification by signature of authorized officer.

F. Submit three copies of each Application for Payment to the COR.

G. Include the following with the application:

1. Transmittal letter as specified for Submittals in Section 01300.

2. Construction progress schedule, revised and current as specified in Section 01300.

3. Certified weekly payrolls.

H. When COR requires substantiating information, submit data justifying dollar amounts in question.

Provide one copy of data with cover letter for each copy of submittal. Show application number and date, and line item by number and description.

1.4 MODIFICATION PROCEDURES

A. COR will advise of minor changes in the Work not involving an adjustment to Contract Sum or Contract

CHATTOOGA RIVER RANGER OFFICE PRICE AND PAYMENT PROCEDURES

MOMA 0204.17 11/02/07 01200-2

Time as authorized by the Conditions of the Contract by issuing supplemental instructions on a Work Order.

B. Proposal Request: U.S. Forest Service's Contracting Officer may issue a document which includes a detailed description of a proposed change with supplementary or revised Drawings and specifications, a change in Contract Time for executing the change with a stipulation of any overtime work required and the period of time during which the requested price will be considered valid. Contractor shall prepare and submit a fixed price quotation within 14 days.

C. Contractor may propose a change by submitting a request for change to COR, describing the proposed change and its full effect on the Work, with a statement describing the reason for the change, and the effect on the Contract Sum and Contract Time with full documentation and a statement describing the effect on Work by separate or other contractors. Document any requested substitutions in accordance with Section 01600.

D. Computation of Change in Contract Amount:

1. Changes in Contract Price and Time will be negotiated between the Contractor and the U.S. Forest

Service's Contracting Officer.

E. Substantiation of Costs: Provide full information required for evaluation.

1. provide following data:

a. Quantities of products, labor, and equipment.

b. Taxes, insurance, and bonds.

c. Overhead and profit.

d. Justification for any change in Contract Time.

e. Credit for deletions from Contract, similarly documented.

F. Execution of Change Orders: The Contracting Officer will issue Change Orders for signatures of parties as provided in the Conditions of the Contract on SF-30.

1.5 APPLICATION FOR FINAL PAYMENT

A. Prepare Application for Final Payment as specified for progress payments, identifying total adjusted Contract Sum, previous payments, and sum remaining due.

CHATTOOGA RIVER RANGER OFFICE ADMINISTRATIVE REQUIREMENTS

MOMA 0204.17 11/02/07 01300-1

SECTION 01300

ADMINISTRATIVE REQUIREMENTS

A. Preconstruction meeting.

B. Progress meetings.

C. Construction progress schedule.

D. Submittals for review, information, and project closeout.

E. Number of copies of submittals.

F. Submittal procedures.

1.2 RELATED SECTIONS

A. Section 01100 - Summary: Stages of the Work, Work covered by each contract, occupancy,.

B. Section 01700 - Execution Requirements: Additional coordination requirements.

1.3 PROJECT COORDINATION

A. Cooperate with the COR in allocation of mobilization areas of site; for field offices and sheds, for vehicular access, traffic, and parking facilities.

B. During construction, coordinate use of site and facilities through the Project Coordinator.

C. Comply with COR's procedures for intra-project communications; submittals, reports and records, schedules, coordination drawings, and recommendations; and resolution of ambiguities and conflicts.

D. Comply with instructions of the COR for use of temporary utilities and construction facilities.

E. Coordinate field engineering and layout work under instructions of the COR.

F. Make the following types of submittals to the COR:

1. Requests for interpretation.

2. Requests for substitution.

3. Shop drawings, product data, and samples.

4. Test and inspection reports.

5. Manufacturer's instructions and field reports.

6. Applications for payment and change order requests.

7. Progress schedules.

8. Coordination drawings.

9. Closeout submittals.

PART 3 EXECUTION

3.1 PRECONSTRUCTION MEETING

A. U.S. Forest Service will schedule a meeting after Notice of Award.

B. Attendance Required:

1. U.S. Forest Service Contracting Officer.

MOMA 0204.17 11/02/07 01300-2

2. COR.

3. Contractor.

4. Project Superintendent.

C. Agenda:

1. Execution of the Notice to Proceed.

2. Submission of list of Subcontractors, list of Products, schedule of values, and progress schedule.

3. Designation of personnel representing the parties to Contract, Job Superintendant and COR.

4. Procedures and processing of field decisions, submittals, substitutions, applications for payments, proposal request, Change Orders, and Contract closeout procedures.

5. Scheduling.

D. Record minutes and distribute copies within 5 days after meeting to participants, with two copies to COR, U.S. Forest Service, participants, and those affected by decisions made.

3.2 PROGRESS MEETINGS

A. Schedule and administer meetings throughout progress of the Work at maximum monthly intervals.

B. COR will make arrangements for meetings, prepare agenda with copies for participants, preside at meetings.

C. Attendance Required: Job superintendent, major Subcontractors and suppliers, U.S. Forest Service, COR, as appropriate to agenda topics for each meeting.

D. Agenda:

1. Review minutes of previous meetings.

2. Review of Work progress.

3. Field observations, problems, and decisions.

4. Identification of problems which impede planned progress.

5. Review of submittals schedule and status of submittals.

6. Maintenance of progress schedule.

7. Corrective measures to regain projected schedules.

8. Planned progress during succeeding work period.

9. Maintenance of quality and work standards.

10. Effect of proposed changes on progress schedule and coordination.

11. Other business relating to Work.

E. Record minutes and distribute copies within two days after meeting to participants, with two copies to COR, U.S. Forest Service, participants, and those affected by decisions made.

3.3 CONSTRUCTION PROGRESS SCHEDULE

A. If preliminary schedule requires revision after review, submit revised schedule within 10 days.

B. Within 20 days after review of preliminary schedule, submit draft of proposed complete schedule for review.

1. Include written certification that major contractors have reviewed and accepted proposed schedule.

C. Within 10 days after joint review, submit complete schedule.

D. Submit updated schedule with each Application for Payment.

3.4 SUBMITTALS FOR REVIEW

A. When the following are specified in individual sections, submit them for review:

1. Product data.

2. Shop drawings.

3. Samples for selection.

4. Samples for verification.

B. Submit to COR for review for the limited purpose of checking for conformance with information given

MOMA 0204.17 11/02/07 01300-3

and the design concept expressed in the contract documents.

C. Samples will be reviewed only for aesthetic, color, or finish selection.

D. After review, provide copies and distribute in accordance with SUBMITTAL PROCEDURES article below.

3.5 SUBMITTALS FOR INFORMATION

A. When the following are specified in individual sections, submit them for information:

1. Design data.

2. Certificates.

3. Test reports.

4. Inspection reports.

5. Manufacturer's instructions.

6. Manufacturer's field reports.

7. Other types indicated.

B. Submit for COR's knowledge as contract administrator or for U.S. Forest Service.

3.6 SUBMITTALS FOR PROJECT CLOSEOUT

A. When the following are specified in individual sections, submit them at project closeout:

1. Project record documents.

2. Operation and maintenance data.

3. Warranties.

4. Bonds.

5. Other types as indicated.

B. Submit for U.S. Forest Service's benefit during and after project completion.

3.7 NUMBER OF COPIES OF SUBMITTALS

A. Documents for Review:

1. Small Size Sheets, Not Larger Than 8-1/2 x 11 inches: Submit the number of copies which the

Contractor requires, plus two copies which will be retained by the COR.

2. Larger Sheets, Not Larger Than 24 x 36 inches: Submit the number of opaque reproductions which

Contractor requires, plus two copies which will be retained by COR.

B. Documents for Information: Submit two copies.

C. Documents for Project Closeout: Make one reproduction of submittal originally reviewed. Submit one extra of submittals for information.

D. Samples: Submit the number specified in individual specification sections; one of which will be retained by COR.

1. After review, produce duplicates.

2. Retained samples will not be returned to Contractor unless specifically so stated.

3.8 SUBMITTAL PROCEDURES

A. Transmit each submittal with approved form.

B. Sequentially number the transmittal form. Revise submittals with original number and a sequential alphabetic suffix.

C. Identify Project, Contractor, Subcontractor or supplier; pertinent drawing and detail number, and specification section number, as appropriate on each copy.

D. Apply Contractor's stamp, signed or initialed certifying that review, approval, verification of Products required, field dimensions, adjacent construction Work, and coordination of information is in accordance with the requirements of the Work and Contract Documents.

MOMA 0204.17 11/02/07 01300-4

E. Deliver submittals to COR at business address.

F. Schedule submittals to expedite the Project, and coordinate submission of related items.

G. For each submittal for review, allow 15 days excluding delivery time to and from the Contractor.

H. Identify variations from Contract Documents and Product or system limitations which may be detrimental to successful performance of the completed Work.

I. Provide space for Contractor and COR review stamps.

J. When revised for resubmission, identify all changes made since previous submission.

K. Distribute copies of reviewed submittals as appropriate. Instruct parties to promptly report any inability to comply with requirements.

L. Submittals not requested will not be recognized or processed.

CHATTOOGA RIVER RANGER OFFICE LEED CREDIT SUMMARY

MOMA 0204.17 11/02/07 01354-1

SECTION 01354

LEED CREDIT SUMMARY

1.01 DEFINITIONS

A. LEED Rating System: LEED-NC Version 2.2.

B. Required: Achievement of this credit is essential for certification of this project.

C Preferred: Achievement of this credit would be desirable but is not mandatory.

D. Not Required: Achievement of this credit is not expected or not possible for this project.

E. Owner's O&M Program: On-going procedures and information documented for purposes of achievement of initial certification and re-certification; prepared by Owner or Owner's consultant.

PART 2 CREDIT SUMMARY

2.01 CERTIFICATION TO BE ACHIEVED: LEED Certified, requiring minimum of 32 points.

2.02 SUSTAINABLE SITES (SS): 9 Points To Be Achieved.

A. SS Prerequisite 1 - Required - No points - Erosion and Sedimentation Control/Construction Activity Pollution Prevention.

1. Owner's O&M program addresses on-going maintenance.

2. During Construction:

a. Preventive measures and remediation are specified in Section 01575.

b. Preventive measures prescribed by State law will be followed.

3. Permanent erosion and sedimentation prevention features are to be provided:

a. Grading for sediment traps and retention ponds is specified in Section 02200.

b. Riprap is specified in Section 02272.

c. Turf (for lawns) is specified in Section 02931 (sodding).

d. Turf (for lawns) is specified in Section 02931 (seeding).

B. SS Credit 1 - Required - 1 point - Site Selection.

1. The project is not located on any of the inappropriate or environmentally sensitive lands defined for this credit.

C. SS Credit 4.2 - Required - 1 point - Alternative Transportation: Bicycle Storage & Changing Rooms.

1. Non-Residential Occupancy: Secure bicycle storage and shower and changing facilities are to be provided.

a. Showers are specified in Section 15410.

2. Bicycle racks are specified in Section 02871.

D. SS Credit 5.1 - Preferred - 1 point - Site Development: Protect or Restore Open Space.

1. The project site is undeveloped:

a. Limit disturbance of vegetation during site clearing

E. SS Credit 5.2 - Preferred - 1 point - Site Development: Maximize Open Space.

1. The building footprint and open space are designed to meet this requirement.

C. SS Credit 6.1 - Required - 1 point - Stormwater Management: Rate and Quantity Reduction.

1. The site design does not increase existing runoff rate and quantity.

2. The site design reduces runoff rate and quantity by at least 25 percent.

3. The site design mitigates at least 25 percent of annual stormwater falling on site.

4. Methods used are:

a. Using pervious surfacing:

MOMA 0204.17 11/02/07 01354-2

1) Grading is specified in Section 02200.

b. Modifying existing stormwater flows:

1) Grading is specified in Section 02200.

2) Turf is specified in Section 02931 (sodding).

G. SS Credit 6.2 - Required - 1 point - Stormwater Design: Quality Control.

1. Natural on-site stormwater treatment to remove sediment is provided:

a. Grading is specified in Section 02200.

b. Riprap is specified in Section 02272.

H. SS Credit 7.1 - Required - 1 point - Heat Island Reduction: Non-Roof.

1. The site design reduces thermal gradient differences by:

a. 1) Asphalt paving is not used.

2) Portland cement concrete paving, which typically has a reflectance of 0.3 to 0.4, is specified in Section 02751.

I. SS Credit 7.2 - Required - 1 point - Heat Island Reduction: Roof.

1. The roofing design reduces thermal gradient differences by:

a. Using high reflectance and high emissivity roofing for at least 75 percent of roof area.

1) Sheet metal roofing as specified in Section 07610.

J. SS Credit 8 - Required - 1 point - Light Pollution Reduction.

1. Appropriate exterior lighting fixtures are specified in Section 16520.

2. Appropriate interior lighting fixtures are specified in Section 16510.

2.03 WATER EFFICIENCY (WE): 5 Points To Be Achieved.

A. WE Credit 1.1 & 1.2 - Required - 1 point - Water Efficient Landscaping--Reduce Water Use (1 point for 50%, 2 points for 95%).

1. The landscaping does not require irrigation and no permanent irrigation system is provided.

a. The climate provides adequate rainfall for the landscaping intended without need for irrigation.

b. Plants that do not require irrigation are specified in Section 02930.

B. WE Credit 1.2 - Required - 1 point - Water Efficient Landscaping: No Potable Use or No Irrigation.

1. The landscaping does not require irrigation and no permanent irrigation system is provided.

a. The climate provides adequate rainfall for the landscaping intended without need for irrigation.

b. Plants that do not require any irrigation are specified in Section 02930.

C. WE Credit 2 - Required - 1 point - Innovative Wastewater Technologies.

1. Use of municipal water for sewage conveyance is reduced by at least 50 percent by:

a. Appropriate high efficiency and/or waterless fixtures are specified in Section 15410.

D. WE Credit 3.1 - Required - 1 point - Water Use Reduction.

1. No modifications to the facility are required.

2. Appropriate high efficiency and/or waterless fixtures are specified in Section 15410.

E. WE Credit 3.2 - Required -1 point - Water Use Reduction.

1. Same solutions as for WE Credit 3.1, but greater reduction.

2.04 ENERGY & ATMOSPHERE (EA): 8 Points To Be Achieved.

A. EA Prerequisite 1 - Required - No points - Existing Building Commissioning.

1. The Forest Service will serve as the commissioning authority. The COR will be the commissioning agent's on the ground representative. Coordinate with the COR to obtain the commissioning plan and provide all needed actions indicated in it as required to accomplish the prerequisite including assurance testing, measurements, adjustments, calibrations, and training as indicated in the plan.

MOMA 0204.17 11/02/07 01354-3

B. EA Prerequisite 2 - Required - No points - Minimum Energy Performance.

1. The building envelope, HVAC, lighting, etc., have been designed to meet ASHRAE 90.1-

2004.

C. EA Prerequisite 3 - Required - No points - Fundamental Refrigerant Management.

1. New equipment: No CFC-based refrigerants are used in any equipment. Non-CFC refrigerants are specified in the following sections which section:

D. EA Credit 1 -Required - 7 points - Optimize Energy Performance.

2. Whole building energy simulation (Option 1) shows that the design reduces energy cost compared to the specified standard 31.5 percent – 10 points.

E. EA Credit 4 - 1 point - Enhanced Refrigerant Management.

1. No Halon is used in any equipment or extinguishing system.

2. HVAC:

a. Combined Contribution to Ozone Depletion and Global Warming Potential:

2.05 MATERIALS & RESOURCES: 3 Points To Be Achieved.

A. MR Prerequisite 1 - Required - No points - Storage & Collection of Recyclables.

1. Dedicated room not needed due to size of building and due to the existent of the recycle center directly across the road. Recyclables will be transported across the road to the recycle center as needed by staff.

B. MR Credit 2.1 - Required - 1 point - Construction Waste Management, Divert 50% from Disposal.

1. Construction procedures and measurement of diverted waste are specified in Section

01732. This section requires the Contractor to perform the measurement and computation.

2. Waste prevention and disposal procedures specific to certain types of work are specified in many sections.

C. MR Credit 2.2 - Required - 1 point - Construction Waste Management, Divert 75% from Disposal.

1. Same as for MR Credit 2.1, but increased quantity.

F. MR Credit 5.1 - 1 point - Regional Materials: 10% Extracted, Processed & Manufactured Regionally.

1. For the purposes of the contract documents, the term "regionally-sourced" is used instead of "regional materials" and is defined in Section 01600 in the same way as for this credit.

2. Products that must be regionally-sourced are specified in the appropriate section(s).

2.06 INDOOR ENVIRONMENTAL QUALITY: 12 Points To Be Achieved.

A. EQ Prerequisite 1 - Required - No points - Minimum IAQ Performance.

1. The building ventilation has been designed to meet the minimum requirements of ASHRAE

62.1-2004.

B. EQ Prerequisite 2 - Required - No points - Environmental Tobacco Smoke (ETS) Control.

1. Owner intends to prohibit smoking in the building.

C. EQ Credit 3 - Required - 1 point - Construction IAQ Management Plan, During Construction.

1. Good construction procedures intended to prevent future problems are specified in Section

01734.

2. Contractor is required to perform either a full building flush-out or air quality testing prior to occupancy, both of which are specified in Section 01734

D. EQ Credit 3.1 Required- 1 point - Construction IAQ management Plan (During Construction)

1. Contractor to provide IAQ based on section 15900 (During Construction)

E. EQ Credit 3.2 - Required - 1 point - Construction IAQ Management Plan, Before Occupancy

MOMA 0204.17 11/02/07 01354-4

1. Contractor to provide IAQ plan (Before Occupancy)

2. Contractor is required to perform either a full building flush-out or air quality testing prior to occupancy, both of which are specified in Section 01734.

F. EQ Credit 4, Low-Emitting Materials, consists of 4 parts;

G. EQ Credit 4.1 - Required - 1 point - Low-Emitting Materials, Adhesives & Sealants.

1. Architectural joint sealants with maximum VOC content meeting the credit criteria are specified in Section 07900.

2. Duct sealers and sealants are specified in Section 15810.

H. EQ Credit 4.2 - Required - 1 point - Low-Emitting Materials, Paints & Coatings.

1. Paints and stains are specified in Section 09900.

a. Water-based paints or solvent-based paints with VOC content meeting the credit criteria are used for all interior opaque applications.

b. Other coatings, such as stains and clear finishes, are specified to meet the most stringent of Federal EPA, State, or local criteria.

2. High performance coatings specified in Section 09960 are specified to meet the most stringent of Federal EPA, State, or local criteria.

I. EQ Credit 4.3 - Required - 1 point - Low-Emitting Materials, Carpet Systems.

1. Carpet tile that complies with requirements of CRI Green Label Plus program is specified in

Section 09685.

2. Adhesives used in connection with carpet systems comply with requirements of EQ Credit

4.1.

J. EQ Credit 4.4 - Required - 1 point - Low-Emitting Materials, Composite Wood & Agrifiber Products.

1. The products covered by this credit include particleboard, plywood, medium density fiberboard (MDF), wheatboard, strawboard, panel substrates, door cores, and laminating adhesives used on-site or in the shop.

2. A project-wide prohibition on use of these products if they contain added urea-formaldehyde is specified in various Sections.

K. EQ Credit 5 - Required - 1 point - Indoor Chemical & Pollutant Source Control.

1. At High Volume Entryways: Permanent grilles or grates to capture dirt, etc., are provided.

a. Floor mats and recessed frames are specified in Section 12486.

2. Air Filtration Media: Outside air and return air are to be provided with filtration media meeting the criteria.

a. Air filters are specified in Section 15860.

L. EQ Credit 6.1 - Required - 1 point - Controllability of Systems: Lighting.

1. Lighting controls meeting the criteria are to be provided.

a. Manual switching devices are specified in Section 16140.

b. Automatic switching devices are specified in Section 16414.

M. EQ Credit 6.2 - 1 point - Controllability of Systems: Temperature & Ventilation.

1. HVAC Controls: Individual controls are to be provided for at least 50 percent of occupants in regularly occupied areas.

a. Obtained by use of individually controlled registers in each work space.

N. EQ Credit 7.1 - Undecided - 1 point - Thermal Comfort: Compliance.

1. No modifications to the facility are required.

2. Thermal comfort meeting the credit criteria is to be provided to meet ASHRAE Standard

55-2004

4. The overall design solution is implemented in the drawings and many sections of the specifications.

O. EQ Credit 8.1 - Undecided - 1 point - Daylight & Views: Daylight. 75% of spaces.

1. Daylighting to meet the credit criteria is to be provided.

MOMA 0204.17 11/02/07 01354-5

2. The overall design solution is implemented in the drawings with light-admitting materials specified in many sections of the specifications, including:

a. Glazed aluminum storefront specified in Section 08410.

P. EQ Credit 8.2 - Required - 1 point - Daylight & Views: Views. 90% of spaces.

1. Views meeting the credit criteria are to be provided.

2. The overall design solution is implemented in the drawings with vision glazing specified in many sections of the specifications, including:

a. Glazed aluminum storefront specified in Section 08410.

2.07 INNOVATION IN UPGRADES, OPERATIONS AND MAINTENANCE (IUOM): 1- Points To Be Achieved.

A. To be managed by Owner.

CHATTOOGA RIVER RANGER OFFICE QUALITY REQUIREMENTS

MOMA 0204.17 11/02/07 01400-1

SECTION 01400

QUALITY REQUIREMENTS

A. References and standards.

B. Control of installation.

C. Tolerances.

D. Testing and inspection services.

E. Manufacturers' field services.

1.2 RELATED SECTIONS

A. Section 01300 - Administrative Requirements: Submittal procedures.

B. Section 01600 - Product Requirements: Requirements for material and product quality.

1.3 REFERENCES

A. ASTM C 1021 - Standard Practice for Laboratories Engaged in Testing of Building Sealants; 2001.

B. ASTM C 1077 - Standard Practice for Laboratories Testing Concrete and Concrete Aggregates for Use in Construction and Criteria for Laboratory Evaluation; 2003a.

C. ASTM C 1093 - Standard Practice for Accreditation of Testing Agencies for Unit Masonry; 1995 (Reapproved 2001).

D. ASTM D 3740 - Standard Practice for Minimum Requirements for Agencies Engaged in the Testing and/or Inspection of Soil and Rock as Used in Engineering Design and Construction; 2001.

E. ASTM E 329 - Standard Specification for Agencies Engaged in the Testing and/or Inspection of Materials Used in Construction; 2003.

F. ASTM E 543 - Standard Practice for Agencies Performing Nondestructive Testing; 2002.

1.4 SUBMITTALS

A. Testing Agency Qualifications:

1. Prior to start of Work, submit agency name, address, and telephone number, and names of full time registered Engineer and responsible officer.

2. Submit copy of report of laboratory facilities inspection made by NIST Construction Materials

Reference Laboratory during most recent inspection, with memorandum of remedies of any deficiencies reported by the inspection.

B. Design Data: Submit for COR's knowledge as contract administrator or for the U.S. Forest Service, for information for the limited purpose of assessing conformance with information given and the design concept expressed in the contract documents.

C. Test Reports: After each test/inspection, promptly submit two copies of report to COR and to Contractor.

1. Include:

a. Date issued.

b. Project title and number.

c. Name of inspector.

d. Date and time of sampling or inspection.

e. Identification of product and specifications section.

f. Location in the Project.

MOMA 0204.17 11/02/07 01400-2

g. Type of test/inspection.

h. Date of test/inspection.

i. Results of test/inspection.

j. Conformance with Contract Documents.

k. When requested by COR, provide interpretation of results.

2. Test reports are submitted for COR's knowledge as contract administrator or for the U.S. Forest Service, for information for the limited purpose of assessing conformance with information given and the design concept expressed in the contract documents.

D. Certificates: When specified in individual specification sections, submit certification by the manufacturer and Contractor or installation/application subcontractor to COR, in quantities specified for Product Data.

1. Indicate material or product conforms to or exceeds specified requirements. Submit supporting reference data, affidavits, and certifications as appropriate.

2. Certificates may be recent or previous test results on material or product, but must be acceptable to

COR.

E. Manufacturer's Instructions: When specified in individual specification sections, submit printed instructions for delivery, storage, assembly, installation, start-up, adjusting, and finishing, for the U.S.

Forest Service's information. Indicate special procedures, perimeter conditions requiring special attention, and special environmental criteria required for application or installation.

F. Erection Drawings: Submit drawings for COR's benefit as contract administrator or for U.S. Forest Service.

1. Submit for information for the limited purpose of assessing conformance with information given and the design concept expressed in the contract documents.

1.5 REFERENCES AND STANDARDS

A. For products and workmanship specified by reference to a document or documents not included in the Project Manual, also referred to as reference standards, comply with requirements of the standard, except when more rigid requirements are specified or are required by applicable codes.

B. Conform to reference standard of date of issue current on date of Contract Documents, except where a specific date is established by applicable code.

C. Obtain copies of standards where required by product specification sections.

D. Should specified reference standards conflict with Contract Documents, request clarification from COR before proceeding.

E. Neither the contractual relationships, duties, or responsibilities of the parties in Contract nor those of COR shall be altered from the Contract Documents by mention or inference otherwise in any reference document.

1.6 TESTING AND INSPECTION AGENCIES

A. Contractor shall employ and pay for services of an independent testing agency to perform specified testing and inspection.

B. Employment of agency in no way relieves Contractor of obligation to perform Work in accordance with requirements of Contract Documents.

C. Contractor Employed Agency:

1. Testing agency: Comply with requirements of ASTM E 329, ASTM E 543, ASTM C 1021, ASTM

C 1077, and ASTM C 1093.

2. Inspection agency: Comply with requirements of ASTM D3740 and ASTM E329.

3. Laboratory: Authorized to operate in Georgia.

4. Laboratory Staff: Maintain a full time registered Engineer on staff to review services.

5. Testing Equipment: Calibrated at reasonable intervals either by NIST or using an NIST established

Measurement Assurance Program, under a laboratory measurement quality assurance program.

MOMA 0204.17 11/02/07 01400-3

6. Agency shall be acceptable to the U.S. Forest Service.

3.1 CONTROL OF INSTALLATION

A. Monitor quality control over suppliers, manufacturers, products, services, site conditions, and workmanship, to produce Work of specified quality.

B. Comply with manufacturers' instructions, including each step in sequence.

C. Should manufacturers' instructions conflict with Contract Documents, request clarification from COR before proceeding.

D. Comply with specified standards as minimum quality for the Work except where more stringent tolerances, codes, or specified requirements indicate higher standards or more precise workmanship.

E. Have Work performed by persons qualified to produce required and specified quality.

F. Verify that field measurements are as indicated on shop drawings or as instructed by the manufacturer.

G. Secure products in place with positive anchorage devices designed and sized to withstand stresses, vibration, physical distortion, and disfigurement.

3.2 TOLERANCES

A. Monitor fabrication and installation tolerance control of products to produce acceptable Work. Do not permit tolerances to accumulate.

B. Comply with manufacturers' tolerances. Should manufacturers' tolerances conflict with Contract Documents, request clarification from COR before proceeding.

C. Adjust products to appropriate dimensions; position before securing products in place.

3.3 TESTING AND INSPECTION

A. Testing Agency Duties:

1. Provide qualified personnel at site. Cooperate with COR and Contractor in performance of services.

2. Perform specified sampling and testing of products in accordance with specified standards.

3. Ascertain compliance of materials and mixes with requirements of Contract Documents.

4. Promptly notify COR and Contractor of observed irregularities or non-conformance of Work or products.

5. Perform additional tests and inspections required by COR.

6. Submit reports of all tests/inspections specified.

B. Limits on Testing/Inspection Agency Authority:

1. Agency may not release, revoke, alter, or enlarge on requirements of Contract Documents.

2. Agency may not approve or accept any portion of the Work.

3. Agency may not assume any duties of Contractor.

4. Agency has no authority to stop the Work.

C. Contractor Responsibilities:

1. Deliver to agency at designated location, adequate samples of materials proposed to be used which require testing, along with proposed mix designs.

2. Cooperate with laboratory personnel, and provide access to the Work.

3. Provide incidental labor and facilities:

a. To provide access to Work to be tested/inspected.

MOMA 0204.17 11/02/07 01400-4

b. To obtain and handle samples at the site or at source of Products to be tested/inspected.

c. To facilitate tests/inspections.

d. To provide storage and curing of test samples.

4. Notify COR and laboratory 24 hours prior to expected time for operations requiring testing/inspection services.

5. Employ services of an independent qualified testing laboratory and pay for additional samples, tests, and inspections required by Contractor beyond specified requirements.

6. Arrange with U.S. Forest Service's agency and pay for additional samples, tests, and inspections required by Contractor beyond specified requirements.

D. Re-testing required because of non-conformance to specified requirements shall be performed by the same agency at no charge to the U.S. Forest Service.

3.4 MANUFACTURERS' FIELD SERVICES

A. When specified in individual specification sections, require material or product suppliers or manufacturers to provide qualified staff personnel to observe site conditions, conditions of surfaces and installation, quality of workmanship, start-up of equipment, test, adjust and balance of equipment as applicable, and to initiate instructions when necessary.

B. Submit qualifications of observer to the Contracting Officer 30 days in advance of required observations.

1. Observer subject to approval of COR.

C. Report observations and site decisions or instructions given to applicators or installers that are supplemental or contrary to manufacturers' written instructions.

3.5 DEFECT ASSESSMENT

A. Replace Work or portions of the Work not conforming to specified requirements.

B. If, in the opinion of COR, it is not practical to remove and replace the Work, COR will direct an appropriate remedy or adjust payment.

CHATTOOGA RIVER RANGER OFFICE TEMPORARY FACILITIES AND CONTROLS

MOMA 0204.17 11/02/07 01500-1

SECTION 01500

TEMPORARY FACILITIES AND CONTROLS

A. Temporary utilities.

B. Temporary telephone service.

C. Temporary sanitary facilities.

D. Temporary Controls: Barriers, enclosures, and fencing.

E. Security requirements.

F. Vehicular access and parking.

G. Waste removal facilities and services.

H. Project identification sign.

I. Field offices.

1.2 TEMPORARY UTILITIES

A. New permanent facilities may not be used.

B. Use trigger-operated nozzles for water hoses, to avoid waste of water.

1.3 TELEPHONE SERVICE

A. Provide, maintain, and pay for telephone service to field office at time of project mobilization.

1.4 TEMPORARY SANITARY FACILITIES

A. Provide and maintain required facilities and enclosures. Provide at time of project mobilization.

B. Maintain daily in clean and sanitary condition.

1.5 BARRIERS

A. Provide barriers to prevent unauthorized entry to construction areas, to allow for owner's use of site and to protect existing facilities and adjacent properties from damage from construction operations and demolition.

B. Protect non-owned vehicular traffic, stored materials, site, and structures from damage.

1.6 FENCING

A. Construction: Contractor's option.

1.7 SECURITY

A. Provide security and facilities to protect Work, existing facilities, and U.S. Forest Service's operations from unauthorized entry, vandalism, or theft.

1.8 VEHICULAR ACCESS AND PARKING

A. Coordinate access and haul routes with governing authorities and U.S. Forest Service.

B. Provide means of removing mud from vehicle wheels before entering streets.

C. Provide temporary parking areas to accommodate construction personnel. When site space is not adequate, provide additional off-site parking.

CHATTOOGA RIVER RANGER OFFICE TEMPORARY FACILITIES AND CONTROLS

MOMA 0204.17 11/02/07 01500-2

1.9 WASTE REMOVAL

A. See Sections 01354 - LEED Credit Summary, and 01732 - Waste Management, for additional requirements.

B. Provide waste removal facilities and services as required to maintain the site in clean and orderly condition.

C. Provide containers with lids. Remove trash from site periodically.

D. If materials to be recycled or re-used on the project must be stored on-site, provide suitable non-combustible containers; locate containers holding flammable material outside the structure unless otherwise approved by the authorities having jurisdiction.

E. Open free-fall chutes are not permitted. Terminate closed chutes into appropriate containers with lids.

1.10 PROJECT IDENTIFICATION

A. Erect on site at location established by COR.

B. No other signs are allowed without U.S. Forest Service permission except those required by law.

CHATTOOGA RIVER RANGER OFFICE TEMPORARY EROSION AND SEDIMENTATION CONTROL

MOMA 0204.17 11/02/07 01575-1

SECTION 01575

TEMPORARY EROSION AND SEDIMENTATION CONTROL

A. Prevention of erosion due to construction activities.

B. Prevention of sedimentation of waterways, open drainage ways, and storm and sanitary sewers due to construction activities.

C. Restoration of areas eroded due to insufficient preventive measures.

D. Compensation of U.S. Forest Service for fines levied by authorities having jurisdiction due to non-compliance by Contractor.

1.2 RELATED SECTIONS

A. Section 01354 - LEED Credit Summary: Overall project goals relating to environment and energy.

1.3 REFERENCES

A. ASTM D 4355 - Standard Test Method for Deterioration of Geotextiles by Exposure to Light, Moisture, and Heat in a Xenon Arc Type Apparatus; 2002.

B. ASTM D 4491 - Standard Test Methods for Water Permeability of Geotextiles by Permittivity; 1999a.

C. ASTM D 4533 - Standard Test Method for Trapezoid Tearing Strength of Geotextiles; 1991 (Reapproved 1996).

D. ASTM D 4632 - Standard Test Method for Grab Breaking Load and Elongation of Geotextiles; 1991 (Reapproved 2003).

E. ASTM D 4751 - Standard Test Method for Determining Apparent Opening Size of a Geotextile; 1999a.

F. ASTM D 4873 - Standard Guide for Identification, Storage, and Handling of Geosynthetic Rolls and Samples; 2002.

G. EPA 832-R-92-005 - Storm Water Management for Construction Activities; U.S. Environmental Protection Agency; 1992.

1.4 PERFORMANCE REQUIREMENTS

A. Comply with all requirements of U.S. Environmental Protection Agency and State of Georgia for erosion and sedimentation control.

B. Develop and follow an Erosion and Sedimentation Prevention Plan and submit periodic inspection reports.

C. Do not begin clearing, grading, or other work involving disturbance of ground surface cover until applicable permits have been obtained; furnish all documentation required to obtain applicable permits.

D. Timing: Put preventive measures in place as soon as possible after disturbance of surface cover and before precipitation occurs.

E. Erosion On Site: Minimize wind, water, and vehicular erosion of soil on project site due to construction activities for this project.

1. Control movement of sediment and soil from temporary stockpiles of soil.

2. Prevent development of ruts due to equipment and vehicular traffic.

3. If erosion occurs due to non-compliance with these requirements, restore eroded areas at no cost to

U.S. Forest Service.

MOMA 0204.17 11/02/07 01575-2

U.S. Forest Service.

F. Erosion Off Site: Prevent erosion of soil and deposition of sediment on other properties caused by water leaving the project site due to construction activities for this project.

1. Prevent windblown soil from leaving the project site.

2. Prevent tracking of mud onto public roads outside site.

3. Prevent mud and sediment from flowing onto sidewalks and pavements.

4. If erosion occurs due to non-compliance with these requirements, restore eroded areas at no cost to

U.S. Forest Service.

G. Sedimentation of Waterways Off Site: Prevent sedimentation of waterways off the project site, including rivers, streams, lakes, ponds, open drainage ways, storm sewers, and sanitary sewers.

1. If sedimentation occurs, install or correct preventive measures immediately at no cost to U.S. Forest

Service; remove deposited sediments; comply with requirements of authorities having jurisdiction.

H. Open Water: Prevent standing water that could become stagnant.

I. Maintenance: Maintain temporary preventive measures until permanent measures have been established.

1.5 SUBMITTALS

A. See Section 01300 - Administrative Requirements, for submittal procedures.

B. Erosion and Sedimentation Control Plan:

1. Include:

a. Site plan identifying soils and vegetation, existing erosion problems, and areas vulnerable to erosion due to topography, soils, vegetation, or drainage.

b. Site plan showing grading; new improvements; temporary roads, traffic accesses, and other temporary construction; and proposed preventive measures.

2. Obtain the approval of the Plan by U.S. Forest Service.

C. Certificate: Mill certificate for silt fence fabric attesting that fabric and factory seams comply with specified requirements, signed by legally authorized official of manufacturer; indicate actual minimum average roll values; identify fabric by roll identification numbers.

D. Inspection Reports: Submit report of each inspection; identify each preventive measure, indicate condition, and specify maintenance or repair required and accomplished.

PART 2 PRODUCTS

2.1 MATERIALS

A. Grass Seed For Temporary Cover: Select a species appropriate to climate, planting season, and intended purpose. If same area will later be planted with permanent vegetation, do not use species known to be excessively competitive or prone to volunteer in subsequent seasons.

B. Silt Fence Fabric: Polypropylene geotextile resistant to common soil chemicals, mildew, and insects;

non-biodegradable; in longest lengths possible; fabric including seams with the following minimum average roll lengths:

1. Average Opening Size: 30 U.S. Std. Sieve, maximum, when tested in accordance with ASTM D

4751.

2. Permittivity: 0.05 sec^-1, minimum, when tested in accordance with ASTM D 4491.

3. Ultraviolet Resistance: Retaining at least 70 percent of tensile strength, when tested in accordance with ASTM D 4355 after 500 hours exposure.

4. Tensile Strength: 100 lb-f, minimum, in cross-machine direction; 124 lb-f, minimum, in machine direction; when tested in accordance with ASTM D 4632.

5. Elongation: 15 to 30 percent, when tested in accordance with ASTM D 4632.

6. Tear Strength: 55 lb-f, minimum, when tested in accordance with ASTM D 4533.

7. Color: Manufacturer's standard, with embedment and fastener lines preprinted.

MOMA 0204.17 11/02/07 01575-3

C. Silt Fence Posts: One of the following, minimum 5 feet long:

1. Steel U- or T-section, with minimum mass of 1.33 lb per linear foot.

2. Softwood, 4 by 4 inches in cross section.

3. Hardwood, 2 by 2 inches in cross section.

3.1 EXAMINATION

A. Examine site and identify existing features that contribute to erosion resistance; maintain such existing features to greatest extent possible.

3.2 PREPARATION

A. Schedule work so that soil surfaces are left exposed for the minimum amount of time.

3.3 SCOPE OF PREVENTIVE MEASURES

A. In all cases, if permanent erosion resistant measures have been installed temporary preventive measures are not required.

B. Linear Sediment Barriers: Made of silt fences.

1. Provide linear sediment barriers:

a. Along downhill perimeter edge…