Text version

OMB Approval 2700‐0042

1. CONTRACT ID CODE PAGE OF PAGES

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1 2

2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)

07 03/18/2010

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE

U.S. Department of Agriculture, ARS FD, Facilities Contracts Branch, Darleen Masten 5601 Sunnyside Ave., Mail Stop 5124, RM. 4‐1252B Beltsville, MD 20705‐5124 Phone: 301‐504‐1183 E‐mail: darleen.masten@ars.usda.gov

Same as Block 7

8. NAME AND ADDRESS OF CONTRACTOR (No. Street, county, State and ZIP: Code) (�) 9A. AMENDMENT OF SOLICITATION NO.

AG‐3K15‐S‐09‐0019

X 9B. DATED (SEE ITEM 11)

01/29/2010

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing Items 8 and 15, and returning one (1) copy of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATA SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and data specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

(�) A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO

THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER Specify type of modification and authority)

E. IMPORTANT: Contractor is not, _ is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

The date for receipt of all proposals remains Friday, March 19, 2010. Proposals are due no later than 2pm, Eastern Time.

No more questions will be accepted at this time.

Except at provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED

(Signature of person authorized to sign)

BY _____________________________________________

(Signature of Contracting Officer)

NSN 7540‐01‐152‐8070 30‐105 STANDARD FORM 30 (REV. 10‐83)

PREVIOUS EDITION UNUSABLE Computer Generated Prescribed by GSA

FAR (48 CFR) 53.24

SOLICITATION NO. AG-3K15-S-09-0019

AMENDMENT No. 07

The following changes have been made to the solicitation.

01. Attached are some more questions and answers.

02. List of Attachments:

o Questions Received from Industry (Attachment A)

ATTACHMENT “A”

Questions Received from Industry

Please note that only answers provided via an amendment are the official answers to any questions.

163 “I would like to inquire on what drawings does it show restoration of stucco as described in Spec section 09225 “Stucco”. I cannot seem to find any areas other one small one that call out for this material.”

The new stucco work includes a stucco soffit indicated on Sheet A2.01, sequence number 40, Ground Floor Reflected Ceiling Plan – Area ‘A’, south of column line 8, between column lines “O” and “R”, and on Wall Section 3 on Sheet A8.02, sequence number 59, Wall Sections.

164 Questions 164 – 167 are regarding the leased trailers:

“In the floor plan layout of both building.

It shows that the building do not have support columns. But in this section it shows that beam span is less then 16 foot. This puts a support column every 16 feet through out the building. This is going to interfere with interior space. In the original spec the buildings were clear span and provided an open environment.”

The trailer floor plan is illustrative. The trailer manufacturer must add the necessary structural elements, and may tweak the interior trailer layouts, maintaining the minimum office sizes and workstation sizes and functionality.

165 “Is painted Dura temp siding acceptable in-lieu of the vinyl specified in 2.2 for the exterior walls.”

Substitutions will be reviewed and considered during shop drawing submittal.

166 “The interior doors in 2.7 call out for hollow core doors in-lieu of solid core with steel jambs.“

Minimum requirement is for hollow core doors. Substitutions will be reviewed and considered during shop drawing submittal.

167 “ Electrical calls out for 208 3 phase where trailers are manufactured to 220v single phase. Is the existing distribution panel able to support single phase power?”

Electrical service at 120/208 volts, 3 phase, 4 wire will work. Trailer manufacturer must supply necessary panels and breakers. Verify trailer loads are adequate for 600 Amp service.

Amend. No. 07 03/17/2010