Construction Specification 61—Rock Riprap
1.
Scope
The work shall consist of the construction of rock riprap revetments and blankets, including filter or bedding where specified.
2.
Material
Rock riprap shall conform to the requirements of Material Specification 523, Rock for Riprap, or if so specified, shall be obtained from designated sources. It shall be free from dirt, clay, sand, rock fines, and other material not meeting the required gradation limits.
At least 30 days before rock is delivered from other than designated sources, the contractor shall designate in writing the source from which rock material will be obtained and provide information satisfactory to the contracting officer that the material meets contract requirements. The contractor shall provide the contracting officer's technical representative (COTR) free access to the source for the purpose of obtaining samples for testing. The size and grading of the rock shall be as specified in section 8.
Rock from approved sources shall be excavated, selected, and processed to meet the specified quality and grading requirements at the time the rock is installed.
Based on a specific gravity of 2.65 (typical of limestone and dolomite) and assuming the individual rock is shaped midway between a sphere and a cube, typical size/weight relationships are:
Sieve size Approx. weight Weight of of rock of rock test pile
16 inches 300 pounds 6,000 pounds
11 inches 100 pounds 2,000 pounds
6 inches 15 pounds 300 pounds
The results of the test shall be compared to the gradation required for the project. Test pile results that do not meet the construction specifications shall be cause for the rock to be rejected. The test pile that meets contract requirements shall be left on the job site as a sample for visual comparison. The test pile shall be used as part of the last rock riprap to be placed.
Filter or bedding aggregates when required shall conform to Material Specification 521, Aggregates for Drainfill and Filters, unless otherwise specified. Geotextiles shall conform to Material Specification 592, Geotextile.
3.
Subgrade preparation
The subgrade surface on which the rock riprap, filter, bedding, or geotextile is to be placed shall be cut or filled and graded to the lines and grades shown on the drawings. When fill to subgrade lines is required, it shall consist of approved material and shall conform to the requirements of the specified class of earthfill.
Rock riprap, filter, bedding, or geotextile shall not be placed until the foundation preparation is completed and the subgrade surface has been inspected and approved.
4.
Equipment-placed rock riprap
The rock riprap shall be placed by equipment on the surface and to the depth specified. It shall be installed to the full course thickness in one operation and in such a manner as to avoid serious displacement of the underlying material. The rock for riprap shall be delivered and placed in a manner that ensures the riprap in place is reasonably homogeneous with the larger rocks uniformly distributed and firmly in contact one to another with the smaller rocks and spalls filling the voids between the larger rocks. Some hand placing may be required to provide a neat and uniform surface.
Rock riprap shall be placed in a manner to prevent damage to structures. Hand placing is required as necessary to prevent damage to any new and existing structures.
5.
Hand placed rock riprap
The rock riprap shall be placed by hand on the surface and to the depth specified. It shall be securely bedded with the larger rocks firmly in contact one to another without bridging. Spaces between the larger rocks shall be filled with smaller rocks and spalls. Smaller rocks shall not be grouped as a substitute for larger rock. Flat slab rock shall be laid on its vertical edge except where it is laid like paving stone and the thickness of the rock equals the specified depth of the riprap course.
6.
Filter or bedding
When the contract specifies filter, bedding, or geotextile beneath the rock riprap, the designated material shall be placed on the prepared subgrade surface as specified. Compaction of filter or bedding aggregate is not required, but the surface of such material shall be finished reasonably smooth and free of mounds, dips, or windrows.
7.
Measurement and payment
Method 1—For items of work for which specific unit prices are established in the contract, the quantity of each type of rock riprap placed within the specified limits is computed to the nearest ton by actual weight. The volume of each type of filter or bedding aggregate is measured within the specified limits and computed to the nearest cubic yard by the method of average cross-sectional end areas. For each load of rock riprap placed as specified, the contractor shall furnish to the COTR a statement-of-delivery ticket showing the weight to the nearest 0.1 ton.
Payment is made at the contract unit price for each type of rock riprap, filter, or bedding. Such payment is considered full compensation for completion of the work.
Method 2—For items of work for which specific unit prices are established in the contract, the quantity of each type of rock riprap placed within the specified limits is computed to the nearest 0.1 ton by actual weight. The quantity of each type of filter or bedding aggregate delivered and placed within the specified limits is computed to the nearest 0.1 ton. For each load of rock riprap placed as specified, the contractor shall furnish to the engineer a statement-of-delivery ticket showing the weight to the nearest 0.1 ton. For each load of filter or bedding aggregate, the contractor shall furnish to the COTR a statement-of-delivery ticket showing the weight to the nearest 0.1 ton.
Payment is made at the contract unit price for each type of rock riprap, filter, or bedding. Such payment is considered full compensation for completion of the work.
Method 3—For items of work for which specific unit prices are established by the contract, the volume of each type of rock riprap and filter or bedding aggregate is measured within the specified limits and computed to the nearest cubic yard by the method of average cross-sectional end areas.
Payment is made at the contract unit price for each type of rock riprap, filter, or bedding. Such payment is considered full compensation for completion of the work.
Method 4—For items of work for which specific unit prices are established by the contract, the volume of each type of rock riprap, including filter and bedding aggregate, is measured within the specified limits and computed to the nearest cubic yard by the method of average cross-sectional end areas.
Payment is made at the contract unit price for each type of rock riprap, including filter and bedding. Such payment is considered full compensation for completion of the work.
Method 5—For items of work for which specific unit prices are established by the contract, the quantity of each type of rock riprap placed within the specified limits is computed to the nearest ton by actual weight. For each load of rock for riprap placed as specified, the contractor shall furnish to the COTR a statement-of-delivery ticket showing the weight to the nearest 0.1 ton.
Payment is made at the contract unit price for each type of rock riprap, including geotextile used for filter or bedding. Such payment is considered full compensation for completion of the work.
Method 6—For items of work for which specific unit prices are established by the contract, the volume of each type of rock riprap is measured within the specified limits and computed to the nearest cubic yard by the method of average cross-sectional end areas.
Payment is made at the contract unit price for each type of rock riprap, including geotextile used for filter or bedding. Such payment is considered full compensation for completion of the work.
All methods—The following provision applies to all methods of measurement and payment. Compensation for any item of work described in the contract, but not listed in the bid schedule, is included in the payment for the item of work to which it is made subsidiary. Such items and the items to which they are made subsidiary are identified in section 8.
No separate payment is made for testing the gradation of the test pile. Compensation for testing is included in the appropriate bid item for riprap.
8.
ITEMS OF WORK AND CONSTRUCTION DETAILS
The items of work to be performed in conformance with this specification and the construction details are:
A. Bid Item 6, Rock Riprap
1. This item shall consist of the work necessary to place all of the rock riprap including the keys, toe and slope rock, tieback, rock chute, and stream barbs as shown on the drawings.
2. All rock used shall conform to Material Specification 523.
3. The following specification will apply to the toe and slope rock, rock chute, tieback, and upstream and downstream key:
i. 5 % (by weight) shall be equal to or less than 150 lbs.
ii. 95 % shall be between 300 and 2,000 lbs. and well-graded.
iii. Maximum weight of 3,000 lbs.
4. The following gradation will apply to all rock used for the stream barbs:
i. 5 % (by weight) shall be equal to or less than 150 lbs.
ii. 95 % shall be between 300 and 2,800 lbs. and well-graded
iii. Maximum weight of 5,500 lbs.
5. The rock shall be placed such that all rocks are in contact with the neighboring rocks at as many edges as possible with voids no larger than 6 inches in any two directions. NRCS personnel on site will check all voids.
6. Hand chinking will be required for all the rock being placed. Chinking rock should be reasonably well-graded rock, 3 inches to 10 inches in size and is to be from the same source as the slope rock. Chinking shall fill the entire void area.
7. In Section 7, Measurement and Payment, shall be by linear foot of rock placed.
B. Subsidiary Item, Bedding:
1. This item shall consist of the hauling and placing of the gravel bedding placed on the banks beneath the rock.
2. The gradation of the bedding material will be as follows:
iv. Well graded
v. Less than 5% by weight of material passing the #200 sieve
vi. Maximum stone size of 3 inches
3. The contractor shall be responsible for assuring the proper gradation of the bedding material and placement as shown on drawings.
4. Section 7, Measurement and Payment, no separate payment will be made for this item. Full compensation will be included in Bid Item 5, Rock Riprap
NY-MORAN
NRCS-NEH-20 61-3