Construction Specification 806 - Seeding.doc

DOC document 51 KB Posted

Attached to
Emergency Watershed Protection Program (EWP) - Streambank Stabilization - Moran Site - Erie County, New York
Solicitation number
AG-2C31-S-09-0009
Issued by

About this file

Spec 806

View the file

Other files

File Type Posted
Abstract of Offers.pdf PDF
Amend 3.pdf PDF
Amend 2 - ERIE_Moran_EWP_spp_mks Sections2 —
Amend 2 - Bid Schedule_Modified_mks.pdf PDF
Amend 2 - cs023 modified_mks.pdf PDF
Amend 2 - ERIE_Moran_EWP_spp_mks Sections3 —
Amend 2 - ERIE_Moran_EWP_spp_mks Rock Chute Details —
Amend 2 - ERIE_Moran_EWP_spp_mks Sections —
Amend 2 - SF-300.pdf PDF
Amend 2 - ERIE_Moran_EWP_spp_mks Barb Details —
Amend 2 - ERIE_Moran_EWP_spp_mks Plan View —
cs005.doc DOC document
cs011.doc DOC document
2_ERIE_Moran_EWP_spp Plan View.pdf PDF
cs004.doc DOC document
8_ERIE_Moran_EWP_spp Rock Chute.pdf PDF
5_ERIE_Moran_EWP_spp Sections3.pdf PDF
7_ERIE_Moran_EWP_spp Barb Details.pdf PDF
cs023.doc DOC document
cs008.doc DOC document
3_ERIE_Moran_EWP_spp Sections.pdf PDF
Bio-Engineering.doc DOC document
6_ERIE_Moran_EWP_spp Erosion.pdf PDF
ms523.doc DOC document
cs021.doc DOC document
4_ERIE_Moran_EWP_spp Sections2.pdf PDF
8_ERIE_Moran_EWP_spp Tieback Details.pdf PDF
cs061.doc DOC document
1_ERIE_Moran_EWP_spp Cover Signed.pdf PDF
Davis Bacon Wage Rates - Erie County.pdf PDF
SF-1442 Bid Form.pdf PDF
Specifications.zip ZIP file
Solicitation Package.doc DOC document
ERIE_Moran_EWP_spp.zip ZIP file
Show all 34

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NATURAL RESOURCES CONSERVATION SERVICE

CONSTRUCTION SPECIFICATION

806 – SEEDING

1. SCOPE

This work shall consist of preparing a seedbed, furnishing and placing lime, fertilizer, seed and mulch on all disturbed areas and those areas shown on the drawings for the purpose of producing vegetative cover.

2. MATERIALS

Seed - All seed shall conform to the current rules and regulations of New York State and shall meet or exceed the standards for purity and germination or pure live seed as specified in Section 6.

No seed will be used with a date of test more than 9 months old. All seed shall be fully tagged or certified by a commercial supplier. Seed which has become wet, moldy or otherwise damaged in transit or storage shall not be used.

Fertilizer - The fertilizer shall be a commercial grade fertilizer and meet the standard for grade and quality specified by state law. Where fertilizer is furnished from bulk storage, the supplier shall furnish certification of analysis and weight.

Inoculants - The inoculant for treating legume seeds shall be a pure culture of nitrogen-fixing bacteria prepared specifically for the species. Inoculate legumes with the proper fresh culture no more than 8 hours prior to sowing unless pre-inoculated coated seed is used. If hydroseeding is used, inoculate immediately prior to hydroseeding. Use four times the recommended inoculant when hydroseeding. The inoculant shall be used no later than the date indicated on the container or as otherwise specified. Inoculant will be stored according to manufacturers recommendations until ready for use. A mixing medium, as recommended by the manufacturer, shall be used to bond the inoculant to the seed. When used with hydraulic seeding equipment with fertilizer in the mix, the inoculant shall be added last and it shall not remain in the seeder longer than 4 hours.

Lime - Lime shall consist of Standard Ground Agricultural Limestone, or approved equivalent. Standard Ground Agricultural Limestone is defined as ground limestone meeting current requirements of the State Department of Agriculture.

Mulch - Mulch shall be small grain, hay, or other approved mulch material. The mulch material shall be air dry and shall not be musty, moldy, caked, or otherwise of low quality. Mulch must be free of undesirable weed seeds. If mulch anchoring is specified in Section 6, use wood fiber hydromulch or other pre-approved materials and techniques.

3. SEEDBED PREPARATION AND TREATMENT

Areas to be treated shall be dressed to a smooth, firm surface.

On sites where equipment can safely operate, (generally slopes 3H:1V or flatter), the seedbed shall be adequately loosened to a depth of 4 to 6 inches and smoothed. Disking and dragging may be necessary.

On sites where equipment cannot operate, the seedbed shall be prepared by hand or other means such that the surface is scarified and roughened so that seed will stay in place.

If seeding is to be done immediately following construction, seedbed preparation may not be required except on compacted, polished, or freshly cut areas.

Rocks 4 inches and larger in diameter, trash, weeds, and other debris that will interfere with seeding or future operation and maintenance shall be removed.

Seedbed preparation shall be discontinued when soil moisture conditions are not suitable for the preparation of a satisfactory seedbed.

4. SEEDING, LIMING, FERTILIZING, AND MULCHING

Seeding will be done only when soil moisture conditions and surface roughness are suitable for equipment to operate on the site and seed to germinate.

Seed, fertilizer, and lime materials and application rates shall be as specified in Section 6. Substitutions shall be approved by the approving official or designated representative.

Fertilizer and lime shall be uniformly applied as specified in Section 6. When specified, the fertilizer and lime shall be thoroughly incorporated into the soil immediately after being applied. Incorporation shall be by disking, harrowing, or other methods which mix the materials into the soil.

All operations shall be performed in such a manner that the seed is applied in the specified quantities and uniformly on the designated areas. The method and rate of seed application shall be as specified in Section 6.

After seeding, firm the seedbed to obtain good soil to seed contact.

The rate, amount, and type of mulching material shall be as specified in Section 6. Mulch shall be applied uniformly to the seeded areas immediately after seeding. Hay and mulch materials shall be stabilized. For small areas, when saturation is specified, the entire mulch shall be saturated with water applied uniformly at a rate that will avoid runoff. When tracking is specified, the tracks will be run up and down the slope, (producing dozer track impressions across the slope) offsetting each pass to cover the entire area with tracks.

Livestock will be excluded from seeded areas for 1 full growing season.

The seeding, liming, fertilizing, and mulching operations must produce a good vegetative cover over the entire area to be seeded. Necessary steps shall be taken to keep the seeding materials in place until germination otherwise, areas shall be re-seeded where original seeding failed.

5. MEASUREMENT AND PAYMENT

Method 1

For items of work for which specific unit prices are established in the contract, the seeded area will be measured to the nearest 0.1 acre of surface area. Payment for the seeding will be made at the contract unit price. Such payment shall constitute full compensation for all labor, materials, equipment, tools, and other appurtenances necessary and incidental to the completion of the work.

Method 2

For items of work for which specific lump sum prices are established in the contract, the quantity of seeding will not be measured. Payment for this item will be made at the contract lump sum price. Such payment shall constitute full compensation for all labor, materials, equipment, tools, and other appurtenances necessary and incidental to the completion of the work.

All Methods

Compensation for any item of work described in the contract but not listed in the bid schedule will be included in the payment for the item of work to which it is made subsidiary. Such items and the items to which they are made subsidiary are identified in Section 6.

6. ITEMS OF WORK AND ADDITIONAL CONDITIONS

A. Subsidiary Item, Seeding

This item shall consist of work and materials necessary to create a smooth firm seedbed, and to seed, fertilize, lime and mulch ALL disturbed areas. The seeding area shall include all areas disturbed by construction activities including the embankment side slopes.

Fertilizer shall be applied at a rate of 150 lb./ac of 10-20-20, or equivalent. Lime, if needed, shall be applied at a rate of 3 ton/ac, 100% ENV.

The seeding mixture shall consist of:

Certified Seed

Cultivar

P.L.S. lbs./ac. (cool season)

KY-31 Tall Fescue

Redtop

Pennfine Perennial Ryegrass

Empire Birdsfoot Trefoil

If the seeding is to be completed after September 15, add 5 lbs./ac. Annual rye.

Seeding method shall be:

Drill _____

Broadcast __ X___

Hydroseeder _____

Cultipacker Seeder ____

Impregnated Mat _____

Other _____

Straw or hay mulch shall be applied at a rate of 2 ton/ac.

Mulch anchoring shall not be used.

B. SPECIAL REQUIREMENTS:

1. Minimum seed germination rate shall be 85%, and a minimum seed purity shall be 95%. Similar growth habit varieties may be substituted. Fescue shall have low levels of endophyte.

2. Inoculate trefoil with the proper fresh culture a maximum of 24 hours prior to sowing. Use four times the recommended inoculant when hydroseeding.

3. In Section 5 MEASUREMENT AND PAYMENT, There will be no separate payment for seeding. Compensation for Seeding shall be included in the payment of Bid Item 1, Mobilization and Demobilization.

NRCS-NY-CTA

806-4

FEBRUARY 2001