Amendment 4

Solicitation: G-2B46-S-16-0011

Questions and Answer Document

Question:

Can the offer be e-mailed? If so, is scott.crist@wdc.usda.gov the correct e-mail address?

Response:

Yes, the bid can be e-mailed to the address noted above.

Amendment 03 indicates Page 1 of 9; however, only the SF 30 is posted on FEDBIZOPS. Please advise.

No additional pages applicable

Pre-Solicitation Notice indicates 334 calendar days to complete project. Solicitation Section F, Clause 52.211-10 indicates 396 calendar days. Please advise which is correct.

Response:

Period of performance has been changed from 334 to 396 as a result of the mandatory shut down times conveyed in during the site visit.

Are the mandatory shut-down days accounted for in the number of calendar days to complete project?

Yes the shut-down periods are already accounted for which is the reason for the switch from 334 to 396.

mailto:scott.crist@wdc.usda.gov

Will there be any power and water available at the project site for the contractor’s usage?

Response:

Per specification 08 Mobilization and Demobilization Item 4.A.3.g: Temporary Wiring and Connections: At the Contractors expense and in a manner satisfactory to the Contracting Officer, provide and maintain necessary temporary connections, distribution lines, and meter bases Contactor shall coordinate all temporary connections with the local utility authority. Include frequent inspection of all equipment and apparatus.

Is the De-Watering Plan due after award?

Response:

Contractor is responsible for developing a project dewatering plan, this plan shall be submitted to project engineer for review within ten (10) days of receiving the notice to proceed.

Can any debris removed from project area be placed in the areas designated for debris on the drawings?

Response:

If you notice sheet 15, the borrow area cross section shows a location for spoil and woody debris, these are separate piles and the contractor is responsible for separating and piling in accordance with that cross-section detail.

Borrow Area – what needs to be done when the project is complete? If backfilling is required, can the spoils placed in the areas designated on the drawings be used to backfill the borrow area?

Response:

Again please note the sheet 15 borrow area cross section detail, it as well as the construction specifications outline the requirements. The max depth and side slopes are shown on the construction detail. Please note that there is a typo on this detail and the side slopes shall be 5:1 or flatter upon closing the borrow area, not 3:1 as currently shown. This detail will be revised and included within this addenda.

What is the weight limit on the bridge?

It is unknown to NRCS. We can disclose that this is not a NCDOT maintained bridge it is private to the landowner.

Can the bid date for Outfall be extended?

Yes, the bid date is being changed to 9/9/16 at 2:00 p.m. EDT. Bid opening thereafter at 2:30 p.m..