Bid Schedule 8-6-10.pdf
PDF 18 KB Posted
- Attached to
- RECOVER - OXBOWS FLOODPLAIN RESTORATION
- Solicitation number
- AG-1535-S-10-0018
About this file
New Bid Schedule
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sampling Locations.pdf | ||
| RFI Question.docx | DOCX document | |
| Exceedances Summary.pdf | ||
| Oxbows Full Set 8-6-10_2.pdf | ||
| NAE-2010-1107 IP.PDF | ||
| Construction Specs COMPLETE_final 8-6-10.pdf | ||
| Amend6.pdf | ||
| Oxbows Permit.pdf | ||
| SumCo RFI.doc | DOC document | |
| Amend5.pdf | ||
| Amend4.pdf | ||
| Bid Schedule 6-1-10.docx | DOCX document | |
| Amend3.pdf | ||
| RI1_dvb.htm | HTM file | |
| Request for Informatio1.docx | DOCX document | |
| Amend1.pdf | ||
| Amend2.pdf | ||
| SF1442.pdf | ||
| Bid Schedule and Clauses.docx | DOCX document | |
| Attachment 2 Oxbows Construction Specs 6-1-10.docx | DOCX document | |
| Oxbows Construction Drawings 6-1-10.pdf | ||
| ATTACH 1 General Decision Number.docx | DOCX document |
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Bid Schedule - Oxbows Floodplain Restoration Project
Bid Item
Sub Level 1 Description
NRCS
Spec.
No.
Supp'l Spec.
No. Units QTY
Unit Price
Total Price
1 Temporary Facilities and Controls - - - -
Temporary Construction Entrance and Access Roads 5 - LS 1
2 Staging and Stockpile Area 5 - LS 1 Erosion and Sediment Control
Installation of Silt Fence and Hay Bales 5 - LS 1
4 Removal of Silt Fence and Hay Bales - - LS 1
Removal of Temporary Facilities and Controls - - LS 1
2 Cofferdam and Dewatering - - - - Installation and Removal of Cofferdam - - - - 1 Phase I - Dike Removal 11 - LS 1
Phase II - Oxbow 2 Connection Channel 11 - LS 1
Phase III - Oxbow 3 Connection Channel 11 - LS 1
Phase V -Oxbow 1 Connection Channel 11 - LS 1
Execution of Dewatering Requirements - - - - 5 Phase I - Dike Removal 11 - LS 1
Phase II - Oxbow 2 Connection Channel 11 - LS 1
Phase III - Oxbow 3 Connection Channel 11 - LS 1
Phase V -Oxbow 1 Connection Channel 11 - LS 1
3 Site Work - - - - 1 Clearing and Grubbing 2,4 - LS 1
Clearing Oxbow 2 and 3 Connection Culvert 1 - LS 1
3 Soil/Sediment Excavation 21 - CY 650 4 Grading/Fill 23 - CY 100 5 Furnish and Place Riprap 61 - CY 15 6 Top Soil 26 - CY 1400 7 Coconut Fiber Matting - 401 SY 1400
Geo-Grid Material/Installation (Tensar
TX5) - 402 SY 265
9 Log Crib - 405 LF 340 10 Log Check Dam - 403 LS 1 11 Foot Bridge - 404 LS 1 12 Stone Crossing 25 - LS 1 13 Seeding/ Vegetation 6 - LS 1 14 Concrete Removal 3 - LS 1 4 Mobilization/Demobilization 8 - LS 1
TOTAL: