AG-0343-S-16-0021 Amendment 0006 Building 26 Phase 3 Basement Renovation
View the file
Other files for this federal contract opportunity
Show all 36
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF
CONTRACT
1. CONTRACT ID CODE PAGE OF PAGES
1 3
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)
0006 06/29/2016
6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE
USDA, Forest Service
Western Montana Acquisition Zone
24 Fort Missoula Road
Missoula, MT 59804
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State, and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NO.
Potential Offerors
AG-0343-S-16-0021
9B. DATED (SEE ITEM 11)
05/18/2016
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended, is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing Items 8 and 15, and returning 01 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
(X) A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN
THE CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return * copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.
AG-0343-S-16-0021, Amendment 0006, Building 26, Phase 3 Basement Renovation
1. This amendment 0006 is to respond to questions that were submitted after Amendment 0005 was issued.
2. Amendment 0005 changed the response date for the RFP to June 30, 2016 at 4:00 p.m. local time.
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
N. JEAN WINDLE
Contracting Officer
15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
NSN 7540-01-152-8070
Previous edition unusable
30-105 STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
Building 26 – Phase3, Basement Renovation, Fort Missoula, Missoula, MT
Amendment No. 0006, dated 06/29/2016 Page 2 of 3
Building 26, Phase 3, Basement Renovation
Solicitation Number AG-0343-S-16-0021
Amendment 0006 – Questions and Answers
Q1.) Can you please look at the comments below and provide us with a clarification? This would be for
Alternate #3. The spec references recess rails in D-1 and then they refer to Surface Mounted Tracks in section 3.1. We need to know which style of tracks to include in the quote.
A1.) 105626 Mobile Storage Shelving, 2.4 Systems & Components, D. Tracks, 1. Mounting, REVISE to read: "1. Mounting: Mount track system to existing concrete floors and provide manufacturer's standard raised plywood carriage platform; recess rails in raised platform such that top of rails are flush with floor finish of raised carriage platform.
"2. Low Profile Entrance Ramp: Manufacturer's standard ABA/ADA compliant ramp, to allow access to all high density storage aisles."
Q2.) The dimensions of the system in the drawing are not specific enough to provide a quote. I have assumed that the carriages are to be 24” x 84” (they refer to 25” spacing but that makes me think that the
25” includes the space between carriages.
A2.) 105626 Mobile Storage Shelving, 2.4 Systems & Components, E. Carriages: REVISE to read:
"E. Carriages: Double-loaded (front and back ends of carriage allow for storage). Rigid frames consisting of C-shaped cold-formed steel beams and cross beams, designed to allow secure anchorage of shelving units. All carriages to be moveable. All final carriage dimensions and quantities to be field verified and based on existing conditions to allow for the clear floor space(s) indicated on Drawings within each room.
"1. Carriage Width: 24-1/4" (dimension on A6.5 of 25" includes the space between carriages).
"2. Carriage Length, for bidding purposes only, assume the following carriage lengths and quantities in each respective room:
"a. High Density Storage 012: Provide seven (7) count double-loaded carriages;
each double-loaded carriage to be 7'-8 1/2" long.
"b. High Density Storage 018: Provide (11) count double-loaded carriages, each double-loaded carriage to be 6'-9 1/2" long.
"c. High Density Storage 019: Provide ten (10) count double-loaded carriages, each double-loaded carriage to be 6'-9 1/2" long.
"d. High Density Storage 030: Provide seven (7) count double-loaded carriages;
each double-loaded carriage to be 7'-8 1/2" long.
"3. Carriage Height: Assume a standard carriage size of 5'-10"+/- tall, with a maximum height of 6'-0" above the finished floor.
"4. Carriage Aisle, between carriages in the fully open and locked position: 42" clear, minimum.
"5. Wheels: Manufacturer's standard number of bearing-mounted, steel wheels, precision ground to mate with tracks.
"6. Bumpers: Provide two rubber bumpers with minimum depth of 1/2 inch each side.
"7. Safety: Mechanical Metal Sweep Plate:
"a. Stops carriage movement by depressing metal sweep plate.
"b. Run continuous entire length of carriage in each aisle."
105626 Mobile Storage Shelving, 2.4 Systems & Components, F. Anti-Tip Brackets: ADD the following text: "Track and anti-tip protection to meet all local, state, and national seismic requirements."
-Continued on next page.-
Building 26 – Phase3, Basement Renovation, Fort Missoula, Missoula, MT
Amendment No. 0006, dated 06/29/2016 Page 3 of 3
Q3.) The shelving height appears to be determined by the maximum height allowed (6’ or 72”) this would require that the max shelving height be set at 64”.The number of shelves is in question; the sketch provided shows (5) openings yet the spec indicates (3) Adjustable Shelves and (1) fixed Shelf.
A3.) 105626 Mobile Storage Shelving, 2.6 Shelving, A. Shelving Units, 7. Shelf Styles, a.
Flat: CLARIFICATION - The bottom-most shelf is considered fixed, thus, in addition to the bottom-most fixed shelf, provide (3) three adjustable shelves and one (1) fixed shelf for a total of five (5) shelves. Refer to 16/A6.5 for typical shelf heights and arrangement.