This example goes with the example project. it is to be used to quote the example project.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Example_TASK_ORDER_FORM.xls | XLS spreadsheet | |
| Building GD ID120010 04-06-2012 ID10.pdf | ||
| Residential ID120004 01-06-2012 ID4.pdf | ||
| Residential ID120003 01-06-2012 ID3.pdf | ||
| AG-0261-S-12-0031.pdf | ||
| MASTER_TASK_ORDER_FORM.xls | XLS spreadsheet | |
| joc_proposal_orig.xls | XLS spreadsheet | |
| Example_idiq_project.pdf | ||
| StandardSpecs.docx | DOCX document | |
| Building GD ID120002 04-27-2012 ID2.pdf | ||
| SOW Boise NF Maint.pdf | ||
| bnf_map.pdf | ||
| Standard idiq_spec_dwgs.pdf |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
JOC PROPOSAL
| Title of Project | Elk Creek Bulilding #1109 Rehabilitation | JOB ORDER COST PROPOSAL FORM | ||
| Job Order Contract No: | Job Order Contract No. | Example | Modify and Attach a Copy of the Job Order Request Form |
If subcontracting a NON-PREPRICED item, attach 3 quotes for review.
| Job Order Number: | Enter Job Order Number | 1 | ||||||||||||
| Ranger District (Community): | Enter Ranger District or Community | Lowman Ranger District | ||||||||||||
| County: | Enter County | Valley County | ||||||||||||
| Site Superintendent: | Name of Site Superintendent | |||||||||||||
| Sub-Contractor: | Name of Sub-Contractor | |||||||||||||
| Sub-Contractor: | Name of Sub-Contractor | FLAT FEE ITEM | ||||||||||||
| Date Prepared: | Enter Date | Description | Quant. | Unit | Unit Cost | Total | ||||||||
| Prepared By: | Name of Preparer | Permits and Fees : | 0 | L.S. | Actual Cost | |||||||||
| Job Order Time: | Enter Days | 90 | Operation/Maintenance Manual: | 0 | L.S. | Actual Cost | ||||||||
| Job Order Perf. Period: | Enter Start Date | 1-Jul | ||||||||||||
| RSMEANS COSTS PRE-PRICED ITEMS | Bare Unit Costs | Total Costs | Adjusted Total Costs | |||||||||||
| Line # | Mean's Item | Description | Qty | Labor Hrs. | Unit | Mat. | Labor Rate | Equip. | Total Hrs. | Ttl mat'l/Eq | Ttl Labor | CCI by Div | Cost | |
| 1 | 22 41 23.30 3100 | Showers Fiberglass one piece, three walls 36" square | 1 | 2.909 | Ea | 555.00 | 143.00 | 0.00 | 2.91 | $ 555.00 | $ 415.99 | 86.9 | $ 843.79 | |
| 2 | 22 41 23.30 4200 | Showers Rough-in, supply, waste, and vent for shower | 1 | 2.05 | Ea | 590.00 | 385.00 | 0.00 | 2.05 | $ 590.00 | $ 789.25 | 86.9 | $ 1,198.57 | |
| 3 | 22 41 39.10 4240 | Faucets and fittings, shwer pressure balancing mixing valve, with shower head … Chrome | 1 | 1.303 | Ea | 222.00 | 71.00 | 0.00 | 1.30 | $ 222.00 | $ 92.51 | 86.9 | $ 273.31 | |
| 4 | 22 05 05.10 1340 | Selective Plumbing Demolition, Shower stall | 1 | 2.667 | Ea | 0.00 | 131.00 | 0.00 | 2.67 | $ - 0 | $ 349.38 | 91.9 | $ 321.08 | |
| 5 | 08 05 05.10 0240 | Selective Demolition, Windows, Aluminum, to 25sf | 4 | 0.727 | Ea | 0.00 | 25.50 | 0.00 | 2.91 | $ - 0 | $ 74.15 | 89.9 | $ 66.66 | |
| 6 | 08 05 05.10 0200 | Selective Demolition, Doors, exterior | 1 | 0.5 | Ea | 0.00 | 17.55 | 0.00 | 0.50 | $ - 0 | $ 8.78 | 89.9 | $ 7.89 | |
| 7 | 07 05 05.10 5520 | Selective Demolition, Wood Shingles | 850 | 0.23 | SF | 0.00 | 0.80 | 0.00 | 195.50 | $ - 0 | $ 156.40 | 84.1 | $ 131.53 | |
| 8 | 08 14 33.20 0260 | Wood Door Residential, Exterior Door and Screen | 0.5 | 1.6 | Ea | 300.00 | 70.50 | 0.00 | 0.80 | $ 150.00 | $ 56.40 | 89.9 | $ 185.55 | |
| 9 | 08 52 10.70 9000 | **Plain Wood Window, Sliding, Labor/Equip Charge | 3 | 2.667 | Ea | 0.00 | 118.00 | 0.00 | 8.00 | $ - 0 | $ 944.12 | 89.9 | $ 848.76 | |
| 10 | 08 52 10.20 9000 | **Plain wood Window, Awning Labor/Equip Charge | 1 | 2 | Ea | 0.00 | 88.00 | 0.00 | 2.00 | $ - 0 | $ 176.00 | 89.9 | $ 158.22 | |
| 11 | 06 16 36.10 0302 | Sheathing, Plywood on roofs, CDX, 3/4" thick | 850 | 0.013 | SF | 0.70 | 0.59 | 0.00 | 11.05 | $ 595.00 | $ 6.52 | 81.2 | $ 488.43 | |
| 12 | 07 13 53.10 2200 | Sheet Waterproofing, Polyethelene and rubberixed asphalt | 850 | 0.29 | SF | 0.63 | 1.09 | 0.00 | 246.50 | $ 535.50 | $ 268.69 | 84.1 | $ 676.32 | |
| 13 | 07 31 29.13 0012 | Wood Shingles 16" No. 1 Red Cedar shingles, 5" exposure | 8.5 | 3.2 | SQ | 208.00 | 141.00 | 0.00 | 27.20 | $ 1,768.00 | $ 3,835.20 | 84.1 | $ 4,712.29 | |
| 14 | 07 31 29.13 2600 | Wood Shingles Steep Roofs over 7/12 pitch | 4.25 | 3.2 | SQ | 0.00 | 141.00 | 0.00 | 13.60 | $ - 0 | $ 1,917.60 | 84.1 | $ 1,612.70 | |
| 15 | 07 31 29.13 1000 | Wood ShinglesAdd to above for fire retardant shingles | 8.5 | 0 | SQ | 55.00 | 0.00 | 0.00 | 0.00 | $ 467.50 | $ - 0 | 84.1 | $ 393.17 | |
| 16 | 07 65 10.10 9100 | Sheet Metal Flashing and Counter Flashing Stainless, 26ga | 35 | 0.052 | SF | 7.25 | 1.93 | 0.00 | 1.82 | $ 253.75 | $ 3.51 | 84.1 | $ 216.36 | |
| 17 | 07 31 29 .13 1060 | Wood Shingles, Preformed ridge shingles | 25 | 0.02 | LF | 3.60 | 0.88 | 0.00 | 0.50 | $ 90.00 | $ 0.44 | 84.1 | $ 76.06 | |
| 18 | 02 41 19.19 0600 | Dumpster, weekly rental, 1 dump/ week 6cy capacity | 2 | 0 | Week | 460.00 | 0.00 | 0.00 | 0.00 | $ 920.00 | $ - 0 | 91.9 | $ 845.48 | |
| 19 | 06 05 23.10 0700 | Nails, material only, based on 50# box, common 3d to 60d, plain, Galvanized | 100 | 0 | LB | 1.56 | 0.00 | 0.00 | 0.00 | $ 156.00 | $ - 0 | 81.2 | $ 126.67 | |
| 20 | 06 22 13.50 5910 | Millwork Mouldings, window and Door, Window Trim sets | 4 | 0.615 | Ea | 34.50 | 27.00 | 0.00 | 2.46 | $ 138.00 | $ 66.42 | 81.2 | $ 165.99 | |
| 21 | 09 91 13.70 0140 | Exterior Painting,Doors and Windows, Primer and 2 Coats, exterior latex | 100 | 0.03 | LF | 0.19 | 1.15 | 0.00 | 3.00 | $ 19.00 | $ 3.45 | 83 | $ 18.63 | |
| 22 | 02 83 19.23 0270 | Lead Based Paint Encapsulation Exterior, Brushwork, | 200 | 0.027 | Lf | 1.98 | 1.02 | 0.00 | 5.40 | $ 396.00 | $ 5.51 | 91.9 | $ 368.99 | |
| 23 | ||||||||||||||
| 24 | ||||||||||||||
| 25 | ||||||||||||||
| 26 | Total Adjusted Costs: | $ 13,736.46 | ||||||||||||
| 27 | Contractor's Coefficient : | 1.00 | $0.00 | |||||||||||
| 28 | ** Cost for installation only. Materials costs in Non-Prepriced list for custom window materials | TOTAL PREPRICED ITEMS Costs: | $ 13,736.46 | |||||||||||
| 29 | ||||||||||||||
| 30 | ||||||||||||||
| 31 | The provided list of items is for reference and may or may not be all inclusive. If you determine additional or alternate Mean's Items are required to complete the work, please include them in the list with the appropriate RSMEANS information and quantities. | |||||||||||||
| 32 | ||||||||||||||
| 33 | ||||||||||||||
| 34 | ||||||||||||||
| 35 | ||||||||||||||
| NON-PREPRICED MATERIALS OR NON-SUBCONTRACTED ONLY | ||||||||||||||
| Line # | Non-Prepriced | Materials Description | Qty | Unit | *Unit Price | Cost | ||||||||
| 1 | Non-Prepriced | Cedar Breather, Materials Costs, 200 SF rolls | 5.00 | Roll | $ - 0 | |||||||||
| 2 | Non-Prepriced | Windows, Materials Costs | 5.00 | EA | $ - 0 | |||||||||
| 3 | Non-Prepriced | Log Repairs, Including all touch up work | 1.00 | LS | $ - 0 | |||||||||
| 4 | Non-Prepriced | Foundation Settling Repairs - See note 5 on sheet 5 of the project specific drawings | 1.00 | LS | $ - 0 | |||||||||
| 5 | Non-Prepriced | $ - 0 | ||||||||||||
| 6 | Non-Prepriced | $ - 0 | ||||||||||||
| 7 | Non-Prepriced | $ - 0 | ||||||||||||
| 8 | Non-Prepriced | $ - 0 | ||||||||||||
| 9 | Non-Prepriced | * Please Provide Unit Prices for Items | $ - 0 | |||||||||||
| Total Adjusted Costs: | $ - 0 | |||||||||||||
| Contractor's Coefficient : | 1.00 | $0.00 | ||||||||||||
| TOTAL NON-PREPRICED ITEMS Costs: | $ - 0 | |||||||||||||
| NON-PREPRICED SUBCONTRACTED ITEMS ONLY | ||||||||||||||
| Line # | Mean's Item | Description | Qty | Unit | *Unit Price | SUB COEFF | Cost | |||||||
| 1 | Non-Prepriced | 1.25 | $ - 0 | |||||||||||
| 2 | Non-Prepriced | 1.25 | $ - 0 | |||||||||||
| 3 | Non-Prepriced | 1.25 | $ - 0 | |||||||||||
| 4 | Non-Prepriced | 1.25 | $ - 0 | |||||||||||
| 5 | Non-Prepriced | 1.25 | $ - 0 | |||||||||||
| Total NON-PREPRICED SUBCONTRACTED Costs: | $ - 0 | |||||||||||||
| * Please Provide Unit Prices for Items | ||||||||||||||
| Job Order Total Cost: | $13,736.46 |