A004_Atch1_FRTM_Schedule_B.pdf

PDF 30 KB Posted

Attached to
Forest Roads and Trail Maintenance and Construction Federal contract opportunity
Solicitation number
AG-0120-S-16-0003
Issued by
Department of Agriculture Forest Service R10-Alaska Region

About this file

AG0120S160003 A004 Attachment 1 Section B Replacement Schedule of Items

View the file

Other files for this federal contract opportunity

Other files attached to Forest Roads and Trail Maintenance and Construction, newest first.
File Type Posted
A005_0120S160003_PreProposalMtgNotes.pdf PDF
AG0120S160003_A005_SF30.pdf PDF
A004_Atch3_CRD-SampleTask.pdf PDF
A004_Atch3_SRD-GRD_SampleTask.pdf PDF
A004_Atch2_FRTM-IDIQSection_L.11(a)(3)2016_0715.pdf PDF
A004_Atch4_CWD_AK1_M10_15Jul2016.pdf PDF
AG0120S160003_A004_SF30.pdf PDF
A004_Atch1_FRTM-IDIQSectionB20160715.pdf PDF
AG0120S160003_A003.pdf PDF
AG0120S160003_A002_SF30.pdf PDF
0120S160003_A002_Atch1_Schedule_B.pdf PDF
0120S1600003_A002_PreProposalMeetingNotes.pdf PDF
AG0120S160003_A001.pdf PDF
Atch1_Schedule_B.pdf PDF
Atch5_ConstGnlDecAK1_Mod6_29Apr2016.pdf PDF
AG0120S160003_ForestRdTrailMaintConst.pdf PDF
Atch7_SCA_2005-2017_Rev21_29Dec2015.pdf PDF
Atch2_SampleTasksA-B.pdf PDF
Atch6_ConstGnlDecAK6_Mod0_08Jan2016pdf.pdf PDF
Atch4_BioPreferred_Product_Categories.pdf PDF
Atch2_SampleTasksA-B.pdf PDF
AG0120S160003_ForestRdTrailMaintConst.pdf PDF
Atch1_Schedule_B.pdf PDF
Atch6_ConstGnlDecAK6_Mod0_08Jan2016pdf.pdf PDF
Atch5_ConstGnlDecAK1_Mod6_29Apr2016.pdf PDF
Atch4_BioPreferred_Product_Categories.pdf PDF
Atch7_SCA_2005-2017_Rev21_29Dec2015.pdf PDF
Show all 27

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Schedule of Items (Amendment 4 Revision)

AG-0120-S-16-0003 Page 1 of 2

B.2 Schedule of Items Seward/Glacier Ranger District

Items 1-5 Subject to Service Contract Act

Item No.

Description (Items 1-5 Subject to Service

Contract Act) Unit Base Period

Unit Price Additional Assumptions

SG_1 81101B, Blading Roads with Compaction B MILE $__________

SG_2

81301A, Spot Surfacing, Contractor- Furnished Material, Gradation F, Compaction B

CU YD $__________

Assume 60 mile round trip haul, 100 cubic yard total volume, 3 inch compacted thickness

SG_3 83401, Clean and Recondition Culverts 24 inch Diameter and Under EACH $__________

SG_4 83404, Clean Ditches MILE $__________

SG_5 84201, Remove Roadway Vegetation MILE $__________

Items 6-14 Subject to Davis Bacon Act

Item No.

Description (Items 6-14 Subject to Davis Bacon

Act) Unit Base Period

Unit Price Additional Assumptions

SG_6 83301A-18, 18 Inch Culvert Pipe, Contractor Furnish & Install LN FT $__________

Assume all culvert replacements are on single-lane gravel roads, 60 feet in length, under 3 feet of fill, no flowing water present

SG_7 83301A-24, 24 Inch Culvert Pipe, Contractor Furnish & Install LN FT $__________ Assume same as 83301A above

SG_8 83302, Culvert Removal, 18” through 36” diameter pipe EACH $__________ Assume same as 83301A above

SG_9 80701, Wheel Loader HOUR $__________

SG_10 80702, Excavator HOUR $__________

SG_11 80703, Backhoe Loader HOUR $__________

SG_12 80704, Grader HOUR $__________

SG_13 80705, Dump Truck HOUR $__________

SG_14 80706, Brush Cutter HOUR $__________

Schedule of Items (Amendment 4 Revision)

AG-0120-S-16-0003 Page 2 of 2

B.3 Schedule of Items Cordova Ranger District

Items 1-5 Subject to Service Contract Act

Item No.

Description (Items 1-5 Subject to Service

Contract Act) Unit Base Period

Unit Price Additional Assumptions

C_1 81101B, Blading Roads with Compaction B MILE $__________

C_2 81301A, Spot Surfacing, Contractor- Furnished Material, Gradation F, Compaction B

CU YD $__________

Assume 60 mile round trip haul, 100 cubic yard total volume, 3 inch compacted thickness

C_3 83401, Clean and Recondition Culverts 24 inch Diameter and Under EACH $__________

C_4 83404, Clean Ditches MILE $__________

C_5 84201, Remove Roadway Vegetation MILE $__________

Items 6-14 Subject to Davis Bacon Act

Item No.

Description (Items 6-14 Subject to Davis Bacon

Act) Unit Base Period

Unit Price Additional Assumptions

C_6 83301A-18, 18 Inch Culvert Pipe, Contractor Furnish & Install LN FT $__________

Assume all culvert replacements are on single-lane gravel roads, 60 feet in length, under 3 feet of fill, no flowing water present

C_7 83301A-24, 24 Inch Culvert Pipe, Contractor Furnish & Install LN FT $__________ Assume same as 83301A above

C_8 83302, Culvert Removal, 18” through 36” diameter pipe EACH $__________ Assume same as 83301A above

C_9 80701, Wheel Loader HOUR $__________

C_10 80702, Excavator HOUR $__________

C_11 80703, Backhoe Loader HOUR $__________

C_12 80704, Grader HOUR $__________

C_13 80705, Dump Truck HOUR $__________

C_14 80706, Brush Cutter HOUR $__________

B.2 Schedule of Items Seward/Glacier Ranger District
B.3 Schedule of Items Cordova Ranger District

File details come from the government source that posted it. Updated .