AG0120S110032_CWCBunkhouseRFP_FNL.pdf

PDF 598 KB Posted

Attached to
Cordova Work Center (CWC) 12 Person Bunkhouse Accessibility Retrofit
Solicitation number
AG-0120-S-11-0032
Issued by

About this file

AG-0120-S-11-0032 Request for Proposal Solicitation Package

View the file

Other files

File Type Posted
AG0120S110032_Amend002_SF30.pdf PDF
AG0120S110032ConfCallAtndeList.pdf PDF
AG0120S110032ConfCall_AgendaMtgNotes.pdf PDF
WDOL_GnlDec_AK1_Mod33_19Aug2011.pdf PDF
AG0120S110032_CWCBunkhouse_SF1442.pdf PDF
AG0120S110032SiteAtndeList083111.pdf PDF
AG0120S110032_Amend001.pdf PDF
AG0120S110032_SiteVisitNotes.pdf PDF
laundry room with floor hatch.JPG JPG image
tv room.JPG JPG image
west end bathroom.JPG JPG image
kitchen 2.JPG JPG image
entry interior.JPG JPG image
exterior1.JPG JPG image
west end from entryway.JPG JPG image
hallway with fire door.JPG JPG image
kitchen 1.JPG JPG image
west end bedroom one of two.JPG JPG image
west end foyer.JPG JPG image
west end shower room.JPG JPG image
entry.JPG JPG image
pantry.JPG JPG image
errata_cwc12personbunkhouseaccessretrofit_081211.pdf PDF
CRDBunkhouse_final_drawings_061710.pdf PDF
CRDBunkhouse_final_specifications_081211.pdf PDF
AG0120S110032_CWCBunkhouse_ReturnPkg.pdf PDF
revised_M3.00_081211.pdf PDF
revised_E3.00_081211.pdf PDF
Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

OMB APPROVAL NO. 2700-0042

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

AG-0120-S-11-0032

2. TYPE OF SOLICITATION

SEALED BID (IFB)

NEGOTIATED (RFP)

3. DATE ISSUED

15 Aug 2011

PAGE OF PAGES

1 45

IMPORTANT - The “offer” section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

5. REQUISITION/PURCHASE REQUEST NO.

6. PROJECT NO.

7. ISSUED BY CODE 8. ADDRESS OFFER TO

US Forest Service Chugach National Forest 3301 C Street Suite 300 Anchorage AK 99503

US Forest Service Chugach National Forest 3301 C Street Suite 300 Anchorage AK 99503

9. FOR INFORMATION

CALL:

A. NAME

Denise Murphy

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

907-743-9531 – denisemurphy@fs.fed.us

SOLICITATION

NOTE: In sealed bid solicitations “offer” and “offeror” mean “bid” and “bidder.”

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date):

Chugach National Forest, Cordova Ranger District

Cordova Work Center (CWC) 12 Person Bunkhouse Accessibility Retrofit.

This acquisition is a total set-aside for small business concerns.

The estimated price range, in accordance with FAR 36.204, is between $250,000 and $500,000.

This is a best-value acquisition. A written technical proposal is required -- See L.11.

NOTE: This solicitation is being issued without the receipt and authorization of funding. Funding is anticipated but not guaranteed to be received prior to 09/09/2011. **If funding is received prior to this date an amendment will be issued establishing a response date for submission of proposals in anticipation of making an award by 09/28/2011. If funds are not received in sufficient time for processing an award this fiscal year, an amendment will be issued cancelling the solicitation. A telephone conference and site visit are planned prior to receipt of funds. See L.9 & L.10. All interested companies are encouraged to submit questions, in writing, to the Contracting Officer prior to these meetings.

11. The Contractor shall begin performance within 14 calendar days and complete it within 193 calendar days after receiving award, notice to proceed. This performance period is mandatory, negotiable. (See F.2 FAR 52.211-10.)

12A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If “YES,” indicate within how many calendar days after award in Item 12B.)

YES NO

12B. CALENDAR DAYS

Ten (10)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and two (2) copies to perform the work required are due at the place specified in Item 8 by **to be determined local time **to be determined. If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror’s name and address, the solicitation number, and the date and time offers are due.

B. An offer guarantee is, is not required.

C. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than 30 calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Computer Generated Prescribed by GSA FAR (48 CFR) 53.236-1(e)

OFFER (Must be fully completed by offeror)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)

15. TELEPHONE NO. (Include area code)

16. REMITTANCE ADDRESS (Include only if different than Item 14)

CODE FACILITY CODE

17. The offeror agrees to perform the work at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government within calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER

(Type or print)

20B. SIGNATURE

20C. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT

23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c)( ) 41 U.S.C. 253(c)( )

26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return ____ copies to issuing office.) Contractor agrees to furnish and deliver all items or perform all work, requisitions identified on this form and any continuation sheets for the consideration slated in this contract.

The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications or incorporated by reference in or attached to this contract.

29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED

TO SIGN (Type or print)

31A. NAME OF CONTRACTING OFFICER (Type or print)

30B. SIGNATURE

30C. DATE

31B. UNITED STATES OF AMERICA

BY

31C. AWARD DATE

Computer Generated STANDARD FORM 1442 BACK (REV. 4-85)

ADDENDA SHEET

PROJECT NAME: CWC 12 Person

Bunkhouse Accessibility Retrofit

REFERENCE NO. OF DOCUMENT BEING CONTINUED

AG-0120-S-11-0032 Updated Thru FAC 2005-52

PAGE

OF

PART I—THE SCHEDULE

SECTION B--SUPPLIES OR SERVICES AND PRICES/COSTS

SCHEDULE OF ITEMS

ITEM NO. DESCRIPTION METOD OF

MEASUREMENT

UNIT ESTIMATED

QUANTITY

UNIT

PRICE

TOTAL

Base Items

001 Mobilization LSQ LS 1

002 Selective Structure

Demolition

LSQ LS 1

003 Interior Retrofit – includes purchase & installation of built in appliances (3 each)

LSQ LS 1

004 Ramp Construction LSQ LS 1

005 Roofing LSQ LS 1

Option Item

006 Replace linoleum in

Lounge & TV room

LSQ LS 1

Bunkhouse Accessibility Retrofit

REFERENCE NO. OF DOCUMENT BEING CONTINUED

AG-0120-S-11-0032 Updated Thru FAC 2005-52

PAGE

SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK

C.1 General Specifications

(a) Description: The scope of work includes, but is not limited to: an accessibility retrofit of an existing 12-

Person Bunkhouse at the Cordova Work Center in Cordova, Alaska. Work includes the renovation of the entrance, vestibule, shower room, toilet room, and bedrooms on the west end of the building, TV room, commons/dining area, kitchen, pantry, corridor, laundry room, and the laundry room access. Work also includes the installation of a new ramp on the west end of the building.

(b) The intent of this contract is to provide for the accessibility retrofit of the Cordova Work Center 12 person bunkhouse described in the contract. Unless otherwise provided, the Contractor shall furnish all labor, materials, equipment, tools, transportation, and supplies and perform all work required to complete the project in accordance with the drawings, specifications and provisions of the contract.

(c) Payment for work will only be made for and under those pay items included in the Schedule of Items. All other work and materials will be considered incidental to and included in the payment for pay items shown.

(d) The magnitude of the project is between $250,000 and $500,000.

(e) Location: This project is located on the Chugach National Forest, Cordova Ranger District, Cordova

Work Center, 908 LeFever Street, Cordova AK 99574

(f) Contractor use of basic utilities (electricity, water, heat) is permitted, within reasonable limits. There will be no charge to the contractor for use of the basic utilities listed.

(g) Contractor use of the bunkhouse, or any other Forest Service residence, for living quarters is not permitted.

C.2 AGAR 452.211-72 Statement of Work/Specifications (FEB 1988)

The Contractor shall furnish the necessary personnel, material, equipment, services and facilities (except as otherwise specified), to perform the Statement of Work/Specifications referenced in Section J.

C.3 AGAR 452.211-73 Attachments to Statement of Work/Specifications (FEB 1988)

The attachments to the Statement of Work/Specifications listed in Section J are hereby made part of this solicitation and any resultant contract.

Bunkhouse Accessibility Retrofit

REFERENCE NO. OF DOCUMENT BEING CONTINUED

AG-0120-S-11-0032 Updated Thru FAC 2005-52

PAGE

SECTION D--PACKAGING AND MARKING

D.1 Marking of Material Shipments All shipments of materials, equipment and/or supplies shall be addressed to the contractor and not to the

Government.

D.2 Project Labeling for Official Correspondence

The Government singularly identifies each project with a contract number at time of Award. The contract number is a unique identifier to purposely and permanently represent an awarded project. The Government issued contract number is to be referenced on all official communication starting upon notice of award.

SECTION E--INSPECTION AND ACCEPTANCE

E.1 FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):

www.acquisition.gov/far/ www.usda.gov/procurement/policy/agar.html

FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES

52.246-12 Inspection of Construction (AUG 1996)

E.2 Final Cleanup

Before final acceptance, all areas occupied by the Contractor in connection with the work shall be cleaned of all

Contractor's rubbish, excess materials, temporary structures, and equipment, and all parts of the work area shall be left in a neat and presentable condition.

SECTION F--DELIVERIES OR PERFORMANCE

F.1 FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):

52.242-14 Suspension of Work (APR 1984) http://www.acquisition.gov/far/ http://www.usda.gov/procurement/policy/agar.html

Bunkhouse Accessibility Retrofit

REFERENCE NO. OF DOCUMENT BEING CONTINUED

AG-0120-S-11-0032 Updated Thru FAC 2005-52

PAGE

F.2 FAR 52.211-10 Commencement, Prosecution, and Completion of Work (APR 1984) Alternate

I (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 14 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 01 April 2012 The time stated for completion shall include final cleanup of the premises.

The completion date is based on the assumption that the successful offeror will receive the notice to proceed by

21 September 2011. The completion date will be extended by the number of calendar days after the above date that the Contractor receives the notice to proceed, except to the extent that the delay in issuance of the notice to proceed results from the failure of the Contractor to execute the contract and give the required performance and payment bonds within the time specified in the offer.

F.3 AGAR 452.236-75 Maximum Workweek – Construction Schedule (NOV 1996)

At the post award (preconstruction) meeting, the Contractor must submit the following information in writing for approval:

(a) A schedule as required by FAR clause 52.236-15, Schedules for Construction Contracts, and

(b) The hours (including the daily starting and stopping times) and days of the week the Contractor proposed to carry out the work.

The maximum workweek that will be approved is Monday – Saturday, 60 hours unless negotiated and approved in advance. On-site work shall not be conducted between 7 pm and 7 am.

SECTION G--CONTRACT ADMINISTRATION DATA

G.1 Contract Administration

(a) Contracting Officer means a person with the authority to enter into, administer and/or terminate contracts and make related determinations and findings. The Contracting Officer signs all contractual documents, approves and signs all modification to contracts, processes and approves payment requests, reviews and makes final decisions on contractual discrepancies, and administers the contract. The

Contracting Officer is the only authorized individual to make changes to a contract.

(b) Contracting Officer’s Technical Representative (COTR). The Contracting Officer will designate a representative, hereinafter referred to as the Contracting Officer’s Technical Representative (COTR), or alternatively, as the Engineer, who will provide on-the-ground administration for the Government.

The COTR will be designated in writing and a copy of the designation will be furnished to the

Contractor before or at the pre-work conference. The contractor is cautioned to read the COTR designation because certain authority under the contract is reserved solely for the Contracting Officer.

The term ―Contracting Officer‖ as used throughout the contract shall be interpreted to include the

Contracting Officer’s designated representative(s) acting within the limits of their delegation of authority.

(c) Contractor’s Representative. Any representative of the Contractor shall be designated in writing. The designation shall clearly indicate the name and limitations of the authority, if any, of the representative.

Bunkhouse Accessibility Retrofit

REFERENCE NO. OF DOCUMENT BEING CONTINUED

AG-0120-S-11-0032 Updated Thru FAC 2005-52

PAGE

Contact Inforamtion for the Contracting Officer

USDA Forest Service, Chugach National Forest

Attn: Denise Murphy

3301 C Street Suite 300

Anchorage AK 99503

All matters related to the performance of this contract shall be coordinated through the Contracting Officer.

G.2 AGAR 452.215-73 Post Award Conference (NOV 1996)

A post award (preconstruction) conference with the successful offeror is required. It will be scheduled within 20 days after contract award and prior to, or in conjunction with, the issuance of the Notice to

Proceed

G3. Reminder of Invoicing Requirements

(a) The Contractor is reminded that the elements of a proper invoice are listed in the clause at FAR 52.232-27 in

Section I.

(b) It is the sole responsibility of the Contractor to submit proper and timely invoices using its own invoice form or to request and complete the Microsoft Word format (Pay Estimate FS-6300-30 rev 02-05) received from the contracting office. Improper invoices (i.e. errors in extensions, quantities, or other base information) will be returned to the Contractor for correction and subsequent resubmission.

(c) In addition, when submitting the invoice the Contractor shall submit a copy (either electronically, hard copy, or via fax) to the Contracting Officer along with timely payrolls, if applicable and subcontractor payment information (see FAR 52.232-5 Payments Under Fixed Price Construction Contracts).

SECTION H--SPECIAL CONTRACT REQUIREMENTS

H.1 FAR 52.236-4 Physical Data (APR 1984) Data and information furnished or referred to below is for the Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor. (a) The indications of physical conditions on the drawings and in the specifications are the result of site investigations by visual investigation.

(b) Weather conditions:

CORDOVA NORTH, ALASKA (502173)

Period of Record Monthly Climate Summary

Period of Record : 6/12/1955 to 12/31/2010

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Annual

Average Max.

Temperature (F)

35.1 36.8 39.0 45.6 52.6 58.5 61.4 61.3 55.4 46.7 39.1 36.5 47.3

Average Min.

Temperature (F)

25.1 26.8 27.9 33.6 39.8 46.3 50.3 49.8 44.3 36.4 30.1 26.8 36.4

Average Total

Precipitation (in.)

12.91 11.39 10.38 10.19 11.23 6.75 9.33 13.47 20.94 20.83 14.68 16.30 158.39

Average Total

SnowFall (in.)

22.4 21.6 20.8 5.9 0.0 0.0 0.0 0.2 0.0 1.9 9.2 23.4 105.4

Bunkhouse Accessibility Retrofit

REFERENCE NO. OF DOCUMENT BEING CONTINUED

AG-0120-S-11-0032 Updated Thru FAC 2005-52

PAGE

Average Snow Depth

(in.)

10 11 13 6 0 0 0 0 0 0 2 6 4

Percent of possible observations for period of record.

Max. Temp.: 51.6% Min. Temp.: 51.8% Precipitation: 51.4% Snowfall: 49.6% Snow Depth: 49.3%

Check Station Metadata or Metadata graphics for more detail about data completeness.

Western Regional Climate Center, wrcc@dri.edu

(c) Transportation facilities access by road to Cordova is via the ferry system. Materials may also be barged or sent via air.

(d) There are local sources, in Cordova, for the following: concrete, disposal of demolition waste, and a lumber yard.

H.2 FAR 52.236-14 Availability and Use of Utility Services (APR 1984)

(a) The Government shall make all reasonably required amounts of utilities available to the Contractor from existing outlets and supplies, as specified in the contract. Unless otherwise provided in the contract, the amount of each utility service consumed shall be charged to or paid for by the Contractor at prevailing rates charged to the

Government or, where the utility is produced by the Government, at reasonable rates determined by the

Contracting Officer. The Contractor shall carefully conserve any utilities furnished without charge.

(b) The Contractor, at its expense and in a workmanlike manner satisfactory to the Contracting Officer, shall install and maintain all necessary temporary connections and distribution lines, and all meters required to measure the amount of each utility used for the purpose of determining charges. Before final acceptance of the work by the Government, the Contractor shall remove all the temporary connections, distribution lines, meters, and associated paraphernalia.

H.3 Product Substitution

Any modification of other items, designs, materials, products or equipment (including Government-furnished property), made necessary because of a substitution, will be the responsibility of the Contractor without adjustment in contract price or time. The Contracting Officer's approval of any substitute will not affect the

Contractor's responsibility for such modification. Any and all substitutions will be requested by the Contractor after award of the contract has been made. No approvals will be made prior to award.

H.4 Product Substitution Procedures

A. When submitted within 30 days after contract award, the Contracting Officer will consider formal requests for substitution of products, equipment and methods, in place of those specified. Requests submitted after 30 days will be considered only in case of product unavailability or other conditions beyond the control of

Contractor. Requests shall provide the information and be in the format as specified in paragraph B below.

B. Submit separate request for each substitution. Support each request with:

1. Complete data substantiating compliance of proposed substitution with requirements stated in contract documents:

a. Product identification, including manufacturer's name and address.

b. Manufacturer's literature; identify:

1) Product description

2) Reference standards

3) Performance and test data http://www.wrcc.dri.edu/cgi-bin/cliMeta.pl?ak2173 http://www.wrcc.dri.edu/cgi-bin/cliMeta2.pl?ak2173 mailto:wrcc@dri.edu

Bunkhouse Accessibility Retrofit

REFERENCE NO. OF DOCUMENT BEING CONTINUED

AG-0120-S-11-0032 Updated Thru FAC 2005-52

PAGE

c. Samples, as applicable

d. Name and address of similar projects on which product has been used, and date of each installation.

e. Comparative data of item to be deleted by proposed substitution. Include drawings to same (or larger) scale as pertinent portion of contract documents and marked to show how differences will be accommodated.

f. Show complete system/assembly as revised to accommodate proposed alternate for difference in performance, size, configuration, connections, service, accessibility, or any other significant characteristics.

g. Show complete layout of system except that which is identical to contract documents unless unchanged portion must be shown to indicate clearances, etc.

h. Include complete detail drawings of supports for all substitute equipment and complete load calculations for adequacy of support prepared and signed by a registered structural engineer.

1. Itemized comparison of the proposed substitution with product specified; list significant variations.

2. Data relating to changes in construction schedule.

3. Any effect of substitution on separate contracts.

4. List of changes required in other work or products.

5. Accurate cost data comparing proposed substitution with product specified.

6. Proposed amount of change to the contract.

7. Designation of required license fees or royalties.

8. Designation of availability of maintenance services, sources of replacement materials.

C. Substitutions will NOT be considered for acceptance when:

1. They are merely indicated or implied on shop drawings or product data submittals without a formal request from Contractor.

2. They are requested directly by a subcontractor or supplier.

3. Acceptance will require substantial revision of contract documents.

4. Substitution has not been requested in accordance with this and related clauses.

D. Substitute products shall not be ordered or installed without written acceptance of the Contracting Officer.

E. Contracting Officer will determine acceptability of proposed substitutions.

F. Number of Substitution Submittals: Only one proposed alternative will be considered for each item. Provide specified item if substitution proposal is rejected.

H.5 Contractor’s Representation and Responsibility

A. In making formal request for substitution the Contractor represents he/she:

1. Have investigated proposed product and determined that it is equal to or superior in all respects to that originally specified.

2. Will provide same warranties and bond for substitute as for originally specified product.

Bunkhouse Accessibility Retrofit

REFERENCE NO. OF DOCUMENT BEING CONTINUED

AG-0120-S-11-0032 Updated Thru FAC 2005-52

PAGE

3. Will coordinate installation of accepted substitution into the work, and will make such changes as may be required for the work to be complete in all respects.

4. Will waive claims for additional costs caused by substitution, which may subsequently become apparent.

5. Cost data is complete and includes related costs under the contract, but not:

a. Costs under separate contracts.

b. Contracting Officer costs for redesign or revision of contract documents.

B. The Contractor assumes full responsibility that the substitution and/or alternate items or procedures proposed will meet the job requirements.

C. The Contractor is solely responsible for the cost of redesign and modifications to this and other parts of the work caused by the substitutions or alternates furnished.

H.6 Public Officials not Personally Liable

There shall be no personal liability upon the Contracting Officer or officer in charge, their agents or employees, for any act performed in the discharge of any duty imposed or the exercise of any power or authority conferred upon them by, or within the scope of the contract, it being understood that in all such matters they act solely as agents and representatives of the Government.

H.7 Landscape Preservation

The Contractor shall give attention to the effect of contract operation upon the landscape, shall take care to maintain natural surroundings undamaged, and shall conduct the work at all times in compliance with the following requirements.

a. Prevention of the Landscape Defacement. The Contractor shall not remove, deface, injure, or destroy trees, shrubs, lawns, or other natural features or any other improvements in the work area unless specifically authorized by the Contracting Officer. Unless otherwise provided herein, the Contractor shall confine contract operations to within the areas designated in contract documents.

b. Protection of Streams, Lakes, and Reservoirs. The Contractor shall take sufficient precautions to prevent pollution of streams, lakes, small ponds, and reservoirs with fuels, oils, bitumens, calcium chloride, silt, or other harmful materials. Mechanical equipment shall not be operated in live streams without written approval of the

Contracting Officer.

H.8 Safety Contractor shall provide a copy of their standard safety plan for renovation projects.

H.9 AGAR 452.228-71 Insurance Coverage. (NOV 1996)

Pursuant to FAR clause 52.228-5, Insurance-Work on a Government Installation, the Contractor will be required to present evidence to show, as a minimum, the amounts of insurance coverage indicated below:

(a) Workers Compensation and Employer's Liability. The Contractor is required to comply with applicable Federal and State workers' compensation and occupational disease statutes. If occupational diseases are not compensable under those statutes, they shall be covered under the employer's liability section of the insurance policy, except when contract operations are so commingled with a Contractor's commercial operations that it would not be practical to require this coverage. Employer's liability

Bunkhouse Accessibility Retrofit

REFERENCE NO. OF DOCUMENT BEING CONTINUED

AG-0120-S-11-0032 Updated Thru FAC 2005-52

PAGE

coverage of at least $100,000 shall be required, except in States with exclusive or monopolistic funds that do not permit worker's compensation to be written by private carriers.

(b) General Liability. The Contractor shall have bodily injury liability insurance coverage written on a comprehensive form of policy of at least $500,000 per occurrence

(c) Automobile Liability. The Contractor shall have automobile liability insurance written on a comprehensive form of policy. The policy shall provide for bodily injury and property damage liability covering the operation of all automobiles used in connection with performing the contract. Policies covering automobiles operated in the United States shall provide coverage of at least $200,000 per person and $500,000 per occurrence for bodily injury and $20,000 per occurrence for property damage or loss.

(d) Aircraft Public and Passenger Liability. When aircraft are used in connection with performing the contract, the Contractor shall have aircraft public and passenger liability insurance. Coverage shall be at least $200,000 per person and $500,000 per occurrence for bodily injury, other than passenger injury.

Coverage for passenger injury shall be at least $200,000 multiplied by the number of seats or passengers, whichever is greater.

H.10 Order of Precedence – Specifications and Plans

Resolve any inconsistences in the specifications of this solicitation and any resultant contract by giving precendence in the following order:

(a) Section H, Special Contract Requirements

(b) Construction Specifications Institute (CSI) Specifications

(c) Plans (the contract plans furnished by the Government showing the location, type, dimensions and details of the work). On the plans and drawings--

(1) Figured dimensions over scaled dimensions

(2) Large scale contract plans and drawings over small scale contract drawings

(3) Schedules on contract drawings over any conflicting notations on contract drawings

Bunkhouse Accessibility Retrofit

REFERENCE NO. OF DOCUMENT BEING CONTINUED

AG-0120-S-11-0032 Updated Thru FAC 2005-52

PAGE

PART II--CONTRACT CLAUSES

SECTION I--CONTRACT CLAUSES

I.1 FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):

52.202-1 Definitions (JUL 2004)

52.203-3 Gratuities (APR 1984)

52.203-5 Covenant Against Contingent Fees (APR 1984)

52.203-6 Restrictions on Subcontractor Sales to the Government (SEP 2006)

52.203-7 Anti-Kickback Procedures (OCT 2010)

52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity (JAN 1997)

52.203-10 Price or Fee Adjustment for Illegal or Improper Activity (JAN 1997)

52.203-12 Limitation on Payments to Influence Certain Federal Transactions (OCT 2010)

52.204-4 Printed or Copied Double- Sided on Recycled Paper (MAY 2011)

52.204-10 Reporting Executive Compensation & First Tier Subcontract Awards (JUL 2010)

52.209-2 Prohibition on Contracting with Inverted Domestic Corporations-Representation

52.209-6 Protecting the Government's Interest when Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (DEC 2010)

52.209-10 Prohibition on Contracting with Inverted Domestic Corporations

52.211-18 Variation in Estimated Quantity (APR 1984)

52.215-2 Audit and Records -- Negotiation (OCT 2010)

52.215-8 Order of Precedence – Uniform Contract Format (OCT 1997)

52.219-6 Notice of Total Small Business Set-Aside (JUN 2003)

52.219-8 Utilization of Small Business Concerns (Jan 2011)

52.219-14 Limitations on Subcontracting (DEC 1996)

52.222-3 Convict Labor (JUN 2003)

52.222-4 Contract Work Hours and Safety Standards Act -- Overtime Compensation (JUL 2005)

52.222-6 Davis-Bacon Act (JUL 2005)

52.222-7 Withholding of Funds (FEB 1988)

52.222-8 Payrolls and Basic Records (JUN 2010)

52.222-9 Apprentices and Trainees (JUL 2005)

52.222-10 Compliance with Copeland Act Requirements (FEB 1988)

52.222-11 Subcontracts (Labor Standards) (JUL 2005)

52.222-12 Contract Termination - Debarment (FEB 1988)

52.222-13 Compliance with Davis-Bacon and Related Act Regulations (FEB 1988)

52.222-14 Disputes Concerning Labor Standards (FEB 1988)

52.222-15 Certification of Eligibility (FEB 1988)

52.222-21 Prohibition of Segregated Facilities (FEB 1999)

52.222-26 Equal Opportunity (MAR 2007)

52.222-27 Affirmative Action Compliance Requirements for Construction (FEB 1999)

52.222-35 Equal Opportunity for Special Disabled Veterans, Veterans of the Vietnam Era, and other

Eligible Veterans (SEP 2010)

Bunkhouse Accessibility Retrofit

REFERENCE NO. OF DOCUMENT BEING CONTINUED

AG-0120-S-11-0032 Updated Thru FAC 2005-52

PAGE

52.222-36 Affirmative Action for Workers with Disabilities (OCT 2010)

52.222-37 Employment Reports on Special Disabled Veterans, Veterans of the Vietnam Era, and other Eligible Veterans (SEP 2010)

52.222-40 Notification of Employee Rights Under the National Labor Relations Act (Dec 2010)

52.222-50 Combating Trafficking in Persons (FEB 2009)

52.222-54 Employment Eligibility Verification (JAN 2009)

52.223-2 Affirmative Procurement of Biobased Products under Service and Construction Contracts

(DEC 2007)

52.223-3 Hazardous Material and Material Safety Data (JAN 1997)

52.223-6 Drug-Free Workplace (MAY 2001)

52.223-15 Energy Efficiency in Energy-Consuming Products (DEC 2007)

52.223-17 Affirmative Procurement of EPA-designated Items in Service and Construction Contracts

(May 2008)

52.223-18 Contractor Policy to Ban Text Messaging While Driving (Sep 2010)

52.223-19 Compliance with Environmental Management Systems (MAY 2011)

52.225-13 Restrictions on Certain Foreign Purchases (JUN 2008)

52.227-1 Authorization and Consent (DEC 2007)

52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement (DEC 2007)

52.227-4 Patent Indemnity -- Construction Contracts (DEC 2007)

52.228-2 Additional Bond Security (OCT 1997)

52.228-5 Insurance – Work on a Government Installation (Jan 1997)

52.228-11 Pledges of Assets (SEP 2009)

52.228-12 Prospective Subcontractor Requests for Bonds (OCT 1995)

52.228-14 Irrevocable Letter of Credit (DEC 1999)

52.228-15 Performance and Payment Bonds – Construction (OCT 2010)

52.229-3 Federal, State, and Local Taxes (APR 2003)

52.232-5 Payments Under Fixed-Price Construction Contracts (SEP 2002)

52.232-17 Interest (OCT 2010)

52.232-18 Availability of Funds (APR 1984)

52.232-23 Assignment of Claims (JAN 1986)

52.232-27 Prompt Payment for Construction Contracts (OCT 2008)

52.232-33 Payment by Electronic Funds Transfer – Central Contractor Registration (OCT 2003)

52.233-1 Disputes (JULY 2002)

52.233-3 Protest After Award (AUG 1996)

52.233-4 Applicable Law for Breach of Contract Claim (OCT 2004)

52.236-2 Differing Site Conditions (APR 1984)

52.236-3 Site Investigation and Conditions Affecting the Work (APR 1984)

52.236-5 Material and Workmanship (APR 1984)

52.236-6 Superintendence by the Contractor (APR 1984)

52.236-7 Permits and Responsibilities (NOV 1991)

52.236-8 Other Contracts (APR 1984)

52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements

(APR 1984)

52.236-10 Operations and Storage Areas (APR 1984)

52.236-11 Use and Possession Prior to Completion (APR 1984)

52.236-12 Cleaning Up (APR 1984)

52.236-13 Accident Prevention (NOV 1991)

52.236-15 Schedules for Construction Contracts (APR 1984)

52.236-17 Layout of Work (APR 1984)

52.236-21 Specifications and Drawings for Construction (FEB 1997)

Bunkhouse Accessibility Retrofit

REFERENCE NO. OF DOCUMENT BEING CONTINUED

AG-0120-S-11-0032 Updated Thru FAC 2005-52

PAGE

Alternate II (APR 1984) Fill in text: Two sets each hard and electronic copies

52.236-26 Preconstruction Conference (FEB 1995)

52.242-13 Bankruptcy (JUL 1995)

52.243-4 Changes (JUN 2007)

52.244-6 Subcontracts for Commercial Items (DEC 2010)

52.246-21 Warranty of Construction (MAR 1994)

52.248-3 Value Engineering – Construction (OCT 2010)

52.249-2 Termination for Convenience of the Government (Fixed-Price) (MAY 2004)--Alternate I

(SEP 1996)

52.249-10 Default (Fixed-Price Construction) (APR 1984)

52.253-1 Computer Generated Forms (JAN 1991)

AGRICULTURE ACQUISITION REGULATION (48 CFR CHAPTER 4) CLAUSES

452.232-70 Reimbursement for Bond Premiums – Fixed-Price Construction Contracts (NOV 1996)

452.236-71 Prohibition Against the Use of Lead-Paint (NOV 1996)

452.236-72 Use of Premises (NOV 1996)

452.236-74 Control of Erosion, Sedimentation and Pollution (NOV 1996)

452.236-76 Samples and Certificates (FEB 1988)

452.236-77 Emergency Response (NOV 1996)

I.2 FAR 52.204-7 CENTRAL CONTRACTOR REGISTRATION (APR 2008)

(a) Definitions. As used in this clause—

―Central Contractor Registration (CCR) database‖ means the primary Government repository for Contractor information required for the conduct of business with the Government.

―Data Universal Numbering System (DUNS) number‖ means the 9-digit number assigned by Dun and

Bradstreet, Inc. (D&B) to identify unique business entities.

―Data Universal Numbering System +4 (DUNS+4) number‖ means the DUNS number assigned by D&B plus a 4-character suffix that may be assigned by a business concern. (D&B has no affiliation with this 4-character suffix.) This 4-character suffix may be assigned at the discretion of the business concern to establish additional

CCR records for identifying alternative Electronic Funds Transfer (EFT) accounts (see the FAR at Subpart 32.11) for the same concern.

―Registered in the CCR database‖ means that—

(1) The Contractor has entered all mandatory information, including the DUNS number or the DUNS+4 number, into the CCR database; and

(2) The Government has validated all mandatory data fields, to include validation of the Taxpayer

Identification Number (TIN) with the Internal Revenue Service (IRS), and has marked the record ―Active‖. The

Contractor will be required to provide consent for TIN validation to the Government as a part of the CCR registration process.

(b)(1) By submission of an offer, the offeror acknowledges the requirement that a prospective awardee shall be registered in the CCR database prior to award, during performance, and through final payment of any contract, basic agreement, basic ordering agreement, or blanket purchasing agreement resulting from this solicitation.

(2) The offeror shall enter, in the block with its name and address on the cover page of its offer, the annotation ―DUNS‖ or ―DUNS +4‖ followed by the DUNS or DUNS +4 number that identifies the offeror’s name and address exactly as stated in the offer. The DUNS number will be used by the Contracting Officer to verify that the offeror is registered in the CCR database.

http://acquisition.gov/comp/far/current/html/Subpart%2032_11.html#wp1043964

Bunkhouse Accessibility Retrofit

REFERENCE NO. OF DOCUMENT BEING CONTINUED

AG-0120-S-11-0032 Updated Thru FAC 2005-52

PAGE

(c) If the offeror does not have a DUNS number, it should contact Dun and Bradstreet directly to obtain one.

(1) An offeror may obtain a DUNS number—

(i) Via the Internet at http://fedgov.dnb.com/webform or if the offeror does not have internet access, it may call Dun and Bradstreet at 1-866-705-5711 if located within the United States; or

(ii) If located outside the United States, by contacting the local Dun and Bradstreet office. The offeror should indicate that it is an offeror for a U.S. Government contract when contacting the local Dun and Bradstreet office.

(2) The offeror should be prepared to provide the following information:

(i) Company legal business.

(ii) Tradestyle, doing business, or other name by which your entity is commonly recognized.

(iii) Company Physical Street Address, City, State, and ZIP Code.

(iv) Company Mailing Address, City, State and ZIP Code (if separate from physical).

(v) Company Telephone Number.

(vi) Date the company was started.

(vii) Number of employees at your location.

(viii) Chief executive officer/key manager.

(ix) Line of business (industry).

(x) Company Headquarters name and address (reporting relationship within your entity).

(d) If the Offeror does not become registered in the CCR database in the time prescribed by the Contracting

Officer, the Contracting Officer will proceed to award to the next otherwise successful registered Offeror.

(e) Processing time, which normally takes 48 hours, should be taken into consideration when registering.

Offerors who are not registered should consider applying for registration immediately upon receipt of this solicitation.

(f) The Contractor is responsible for the accuracy and completeness of the data within the CCR database, and for any liability resulting from the Government’s reliance on inaccurate or incomplete data. To remain registered in the CCR database after the initial registration, the Contractor is required to review and update on an annual basis from the date of initial registration or subsequent updates its information in the CCR database to ensure it is current, accurate and complete. Updating information in the CCR does not alter the terms and conditions of this contract and is not a substitute for a properly executed contractual document.

(g)(1)(i) If a Contractor has legally changed its business name, “doing business as” name, or division name

(whichever is shown on the contract), or has transferred the assets used in performing the contract, but has not completed the necessary requirements regarding novation and change-of-name agreements in Subpart 42.12, the

Contractor shall provide the responsible Contracting Officer a minimum of one business day’s written notification of its intention to (A) change the name in the CCR database; (B) comply with the requirements of Subpart 42.12 of the FAR; and (C) agree in writing to the timeline and procedures specified by the responsible Contracting Officer.

The Contractor must provide with the notification sufficient documentation to support the legally changed name.

(ii) If the Contractor fails to comply with the requirements of paragraph (g)(1)(i) of this clause, or fails to perform the agreement at paragraph (g)(1)(i)(C) of this clause, and, in the absence of a properly executed novation or change-of-name agreement, the CCR information that shows the Contractor to be other than the Contractor indicated in the contract will be considered to be incorrect information within the meaning of the ―Suspension of

Payment‖ paragraph of the electronic funds transfer (EFT) clause of this contract.

(2) The Contractor shall not change the name or address for EFT payments or manual payments, as appropriate, in the CCR record to reflect an assignee for the purpose of assignment of claims (see

FAR Subpart 32.8, Assignment of Claims). Assignees shall be separately registered in the CCR database.

Information provided to the Contractor’s CCR record that indicates payments, including those made by EFT, to http://fedgov.dnb.com/webform http://acquisition.gov/comp/far/current/html/Subpart%2042_12.html#wp1084217 http://acquisition.gov/comp/far/current/html/Subpart%2042_12.html#wp1084217 http://acquisition.gov/comp/far/current/html/Subpart%2032_8.html#wp1029202

Bunkhouse Accessibility Retrofit

REFERENCE NO. OF DOCUMENT BEING CONTINUED

AG-0120-S-11-0032 Updated Thru FAC 2005-52

PAGE

an ultimate recipient other than that Contractor will be considered to be incorrect information within the meaning of the ―Suspension of payment‖ paragraph of the EFT clause of this contract.

(h) Offerors and Contractors may obtain information on registration and annual confirmation requirements via the internet at http://www.ccr.gov or by calling 1-888-227-2423, or 269-961-5757.

I.3 52.217-9 -- Option to Extend the Term of the Contract. (Mar 2000)

(a) The Government may extend the term of this contract by written notice to the Contractor within 30;

provided that the Government gives the Contractor a preliminary written notice of its intent to extend at least 60 days before the contract expires. The preliminary notice does not commit the Government to an extension.

(b) If the Government exercises this option, the extended contract shall be considered to include this option clause.

(c) The total duration of this contract, including the exercise of any options under this clause, shall not exceed nine (9) months.

I.4 52.225-9 -- Buy American Act–Construction Materials. (Sep 2010)

(a) Definitions. As used in this clause--

―Commercially available off-the-shelf (COTS) item‖—

(1) Means any item of supply (including construction material) that is—

(i) A commercial item (as defined in paragraph (1) of the definition at FAR 2.101);

(ii) Sold in substantial quantities in the commercial marketplace; and

(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and

(2) Does not include bulk cargo, as defined in section 3 of the Shipping Act of 1984 (46 U.S.C.

App. 1702), such as agricultural products and petroleum products.

―Component‖ means an article, material, or supply incorporated directly into a construction material.

―Construction material‖ means an article, material, or supply brought to the construction site by the

Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.

―Cost of components‖ means--

(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or

(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.

―Domestic construction material‖ means— http://www.ccr.gov/

Bunkhouse Accessibility Retrofit

REFERENCE NO. OF DOCUMENT BEING CONTINUED

AG-0120-S-11-0032 Updated Thru FAC 2005-52

PAGE

(1) An unmanufactured construction material mined or produced in the United States;

(2) A construction material manufactured in the United States, if—

(i) The cost of its components mined, produced, or manufactured in the United States exceeds 50 percent of the cost of all its components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic; or

(ii) The construction material is a COTS item.

―Foreign construction material‖ means a construction material other than a domestic construction material.

―United States‖ means the 50 States, the District of Columbia, and outlying areas.

(b) Domestic preference.

(1) This clause implements the Buy American Act (41 U.S.C. 10a-10d) by providing a preference for domestic construction material. In accordance with 41 U.S.C. 431, the component test of the Buy American Act is waived for construction material that is a COTS item. (See FAR

12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.

(2) This requirement does not apply to information technology that is a commercial item or to the construction materials or components listed by the Government as follows: None.

(3) The Contracting Officer may add other foreign construction material to the list in paragraph

(b)(2) of this clause if the Government determines that

(i) The cost of domestic construction material would be unreasonable. The cost of a particular domestic construction material subject to the requirements of the Buy

American Act is unreasonable when the cost of such material exceeds the cost of foreign material by more than 6 percent;

(ii) The application of the restriction of the Buy American Act to a particular construction material would be impracticable or inconsistent with the public interest; or

(iii) The construction material is not mined, produced, or manufactured in the United

States in sufficient and reasonably available commercial quantities of a satisfactory quality.

(c) Request for determination of inapplicability of the Buy American Act.

(1)

(i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including--

(A) A description of the foreign and domestic construction materials;

(B) Unit of measure;

(C) Quantity;

(D) Price;

(E) Time of delivery or availability;

(F) Location of the construction project;

(G) Name and address of the proposed supplier; and

(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.

(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.

(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).

(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor

Bunkhouse Accessibility Retrofit

REFERENCE NO. OF DOCUMENT BEING CONTINUED

AG-0120-S-11-0032 Updated Thru FAC 2005-52

PAGE

does not submit a satisfactory explanation, the Contracting Officer need not make a determination.

(2) If the Government determines after contract award that an exception to the Buy American

Act applies and the Contracting Officer and the Contractor negotiate adequate consideration, the

Contracting Officer will modify the contract to allow use of the foreign construction material.

However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.

(3) Unless the Government determines that an exception to the Buy American Act applies, use of foreign construction material is noncompliant with the Buy American Act.

(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:

Foreign and Domestic Construction Materials Price Comparison

Construction material description Unit of measure Quantity Price (dollars) *

Item 1

Foreign construction material

Domestic construction material

Item 2

Foreign construction material

Domestic construction material

List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.

Include other applicable supporting information.

*Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued).

I.5 FAR 52.228-1 Bid Guarantee (SEP 1996)

(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.

(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United

States. The Contracting Officer will return bid guarantees, other than bid bonds –

(1) To unsuccessful…

This is the start of the file's text. The full file is on GovTribe.