Affidavit_of_Wages_Paid.pdf
PDF 111 KB Posted
- Solicitation number
- ITB-2617
- Issued by
- Mckinley County, New Mexico
About this file
This is an Affidavit of Wages Paid form required by the City of Gallup, New Mexico for the Gallup Municipal Airport AWOS III PT installation project (NMDOT No. GUP-24-03). The form must be completed after construction is finished and submitted to the contracting agency. It captures general contractor information, subcontractor details across multiple tiers, project identification including the State Wage Decision Number, and project physical address and completion date. The form requires signatures from all contractors and certifies that all workers employed on the public works project were paid no less than the Prevailing Wage Rate as determined by the Department of Workforce Solutions, Labor Relations Division.
Contractors executing this form certify compliance with New Mexico's Prevailing Wage Laws and acknowledge that violations—including incorrect job classification, improper payment of prevailing wages, and overtime violations—subject them to debarment procedures and requirements to pay back wages to workers. The affidavit references compliance with the Labor Relations Division Public Works Minimum Wage Act Policy Manual (11.1.2 NMAC) and the Public Works Minimum Wage Act (13-4-11 through 13-4-18, NMSA 78). Separate signed forms are required for each contractor tier, with specific instructions provided for general contractors, subcontractors, and second or higher tier subcontractors to ensure complete documentation of wage compliance across all project participants.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AFFIDAVIT OF WAGES PAID
To Be Completed After Construction Is Complete
All FIELDS ARE REQUIRED
FORM MUST BE SENT TO THE CONTRACTING AGENCY
General Contractor Information Company Name:
Address:
City: State: Zip:
Phone: Fax: E-Mail:
Estimated Completion Date: State Wage Decision Number:
Project Title:
Project Physical Address:
Print Name:
General Contractor Signature:
Sub Contractor Information
Date you completed work on this project:
Company Name:
Address:
City: State: Zip:
Phone: Fax: E-Mail:
Sub Contractor Signature:
2nd, 3rd, etc. Tier Sub Contractor Information
Date you completed work on this project:
Company Name:
Address:
City: State: Zip:
Phone: Fax: E-Mail:
Tier Signature:
I hereby certify that the above information is correct and that all workers I employ on this public works project were paid no less than the Prevailing Wage Rate(s) as determined by the Department of Workforce Solutions, Labor Relations Division for this project as identified by the State Wage Decision Number. I understand that contractors who violate Prevailing Wage Laws (i.e., incorrect job classification, improper payment of prevailing wages, and/or overtime, etc.), are subject to debarment procedures and shall be required to pay any back wages due to workers. (Ref. Labor Relations Division Public Works Minimum Wage Act Policy Manual (11.1.2 NMAC) & Public Works Minimum Wage Act (13-4-11 through 13-4-18, NMSA 78)).
Contractor’s Signature Date
(Revised 08/23/13)
INSTRUCTIONS FOR COMPLETING AFFIDAVIT OF WAGES PAID
GENERAL CONTRACTOR
1. Enter general contractor information and provide signature.
2. Enter State Wage Decision Number as listed in bid documents. (Example: BE 13-0123 B)
3. Enter project title - listed in bid documents.
4. Enter project physical address - exact location of project (job site).
5. Enter completion date of project.
6. All Affidavits’ must be sent to the Contracting Agency.
SUB CONTRACTOR
1. Enter general contractor information, but general contractor signature is not needed.
2. Enter sub contractor information as indicated and provide signature.
3. Enter sub contractor completion date.
NOTE: A separate signed form is needed for each contractor.
2ND, 3rd, etc TIER SUB CONTRACTOR
1. Enter sub contractor information, subcontractor signature is not needed.
2. Enter 2nd tier sub contractor information and provide signature.
3. Enter 2nd tier contract completion date.
(Revised 8/23/13)
File details come from the government source that posted it. Updated .