Gallup Municipal Airport - Schedule I - Install AWOS III PT - NMDOT No. GUP-24-03
Solicitation number
ITB-2617
Issued by
Mckinley County, New Mexico

About this file

This document is a Construction Safety and Phasing Plan (CSPP) drawing for the City of Gallup's installation of a new FAA-certified Automated Weather Observing System (AWOS-III P/T) at Gallup Municipal Airport under NMDOT Project No. GUP-24-03. The project scope includes installing the new AWOS-III P/T system and removing the existing ASOS system within a 30-calendar-day Phase 1 construction schedule. The construction limits are defined by surveyed coordinates with site elevations ranging from 6,470 to 6,471 feet, and the project staging area is located north of the runway with a maximum obstruction height of 25 feet. The contractor must utilize a designated access gate for project ingress and egress, coordinate with the airport manager during the pre-construction meeting for gate access codes, and maintain closure and locking of the gate when not in use. All runway 6-24, taxiway systems (A, A1-A5), and terminal apron remain open throughout construction, and the contractor must monitor CTAF/UNICOM frequency 122.95 continuously and comply with all NOTAMs before entering the Airport Operations Area.

The drawing specifies detailed safety requirements including low-profile barricade installation with flashing red caution lights spaced no greater than 12 feet on center, reflectorized orange and white striping, and support structures capable of withstanding 100 mph wind forces. Runway safety dimensions are clearly marked with a Runway Safety Area of 7,915.66 feet by 150 feet, a Runway Object Free Area of 7,915.66 feet by 500 feet, and a Runway Obstacle Free Zone of 7,715.66 feet by 400 feet. The contractor must install survey lath at minimum at each corner of construction limits, route all vehicles off existing pavement edges during dry conditions, install temporary erosion control devices prior to soil-disturbing activities, and correct any rutting or pavement damage caused by contractor operations at no additional cost. All airport surfaces must be cleaned and all equipment, materials, and personnel removed from the work area upon completion, with coordination required between the contractor, airport manager, engineer, and Runway Protection Representative.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

X

X

X

X

X

X

X

X

X

X

X

X

X

X

XXXX

X X X

X X

X X X X X

X

X X

X

X

R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ

R -O

FZ

R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ

R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA

R -O

FA

R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA

RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA

RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA

R -O

FA

R -O

FZ

T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA

T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA

TS

A

TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA

TSA

TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA

X

X

X

X

X

X

X

X

X

X

X

X

X

X

XXXX

X X X

X X

X X X X X

X

X X

X

X

R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ

R -O

FZ

R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ

R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA

R -O

FA

R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA

RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA

RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA

R -O

FA

R -O

FZ

T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA

T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA T-OFA

TS

A

TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA

TSA

TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA TSA

EM

MENDOZA RD

APRON

PARALLEL TAXIWAY A

TAXIWAY A5

TAXIWAY A4 TAXIWAY A3 TAXIWAY A2

RUNWAY 6-24 (7,315' X 100')

TERMINAL

BUILDING

CONTRACTOR SHALL UTILIZE THE ACCESS

GATE AT THE LOCATION SHOWN FOR

PROJECT INGRESS/EGRESS. THE CONTRACTOR

SHALL COORDINATE WITH THE AIRPORT

MANAGER DURING THE PRE-CONSTRUCTION

MEETING FOR GATE CODE/KEY. GATE SHALL BE

CLOSED AND LOCKED WHEN NOT IN USE.

FUEL FARM

ELECTRICAL

VAULT

EXISTING

CHAINLINK FENCE

HANGAR

(TYP.)

ROTATING BEACON

GRAVEL ROAD

CONTRACTOR HAUL ROUTE

ALONG MENDOZA ROAD.

PROPOSED AWOS

CONTRACTOR'S

STAGING AREA

CONSTRUCTION LIMITS

TAXIWAY A1

U.S. RTE 66

LOW PROFILE BARRICADES

SEE CSPP DETAIL SHEETEXISTING ASOS

CONTRACTOR SHALL UTILIZE THE ACCESS

GATE AT THE LOCATION SHOWN FOR

ELECTRICAL VAULT INGRESS/EGRESS.

Scale in Feet

0 600300300

D ra w in g N am e:

C :\p w _w or ki ng \lo ch ne r-p w

-0 1\ d0

\2

T

O

- C

SP

P.

dw g Ja n

,2

- 1

1:

am

1.0

CONSTRUCTION SAFETY

AND PHASING PLAN

NOL

TA

LFC

12-12-2025

11-26-2025

12-03-2025

Pl ot

S ty le : a e.

ct b La st S av ed

B y:

n lo vo s

/0 1/

THIS DOCUMENT

IS PRELIMINARY

IN NATURE AND IS

NOT A FINAL

SIGNED AND

SEALED

DOCUMENT.

PROJECT NO.

DRAWN BY

CHECKED BY

REVISIONS

DATE

DATE

DATE

DESIGNED BY DATE

N M

D O

T

PR

O

JE

C T

N O

. G U

P-

-0

25683 - TO01

2201 BUENA VISTA DRIVE

SOUTHEAST STE 204

ALBUQUERQUE, NM 87106

P 505.508.2192

WWW.HWLOCHNER.COM

G

AL

LU

P

M U

N

IC

IP

AL

A

IR

PO

R

T (G

U P)

G

AL

LU

P, N

EW

M

EX

IC

O

LEGEND

CONTRACTOR HAUL ROUTE

CONTRACTOR STAGING AREA

CONSTRUCTION LIMITS

LOW PROFILE BARRICADES

(SYMBOL DOES NOT

DENOTE THE NUMBER OF

BARRICADES REQUIRED)

GENERAL PHASING NOTES:

1. CONSTRUCTION PERSONNEL AND EQUIPMENT WILL NOT BE ALLOWED

WITHIN AREAS OPEN TO AIRCRAFT OPERATIONS OR THE AIRPORT

OPERATIONS AREA (AOA) UNTIL THE AREA HAS BEEN CLOSED TO AIRCRAFT

AND NOTAMS HAVE BEEN ISSUED. CONTRACTOR MUST CONFIRM A NOTAM

IS IN PLACE PRIOR TO ENTERING AOA.

2. THE CONTRACTOR SHALL SUPPLY PORTABLE HAND-HELD RADIOS TO EACH

SUPERVISOR. THE CONTRACTOR SHALL MONITOR CTAF/UNICOM

FREQUENCY 122.95 AT ALL TIMES DURING CONSTRUCTION AND SHALL

RESPOND TO ANY INSTRUCTIONS FROM THE ENGINEER, AIRPORT

PERSONNEL AND/OR EMERGENCY PERSONNEL IMMEDIATELY.

3. CONTRACTOR SHALL ROUTE ALL VEHICLES OFF THE EDGES OF EXISTING

PAVEMENT DURING DRY CONDITIONS TO LIMIT WEAR OF EXISTING

PAVEMENTS.

4. TEMPORARY EROSION CONTROL DEVICES SHALL BE INSTALLED IN THE

AREA OF CONSTRUCTION PRIOR TO SOIL DISTURBING ACTIVITIES IN THAT

PHASE. TEMPORARY EROSION CONTROL DEVICES SHALL BE REMOVED AS

DIRECTED BY THE ENGINEER.

5. ANY RUTTING OR DAMAGE TO PAVEMENTS TO REMAIN CAUSED BY

CONTRACTOR'S VEHICLE OR EQUIPMENT OPERATIONS SHALL BE

CORRECTED BY THE END OF THE PROJECT BY THE CONTRACTOR AT THEIR

OWN EXPENSE.

6. CONTRACTOR SHALL INSTALL SURVEY LATH, AT A MINIMUM, AT EACH

CORNER OF THE CONSTRUCTION LIMITS. IF CONTRACTOR'S EMPLOYEES,

SUBCONTRACTORS, OR SUPPLIERS ARE NOTED TO CROSS INTO ACTIVE

PAVEMENT, ADDITIONAL LATH WILL BE REQUIRED TO BE INSTALLED.

RUNWAY 6-24 SAFETY DIMENSIONS

RUNWAY SAFETY AREA (RSA): 7,915.66' X 150'

RUNWAY OBJECT FREE AREA (R-OFA): 7,915.66' X 500'

RUNWAY OBSTACLE FREE ZONE (R-OFZ): 7,715.66' X 400'

TAXIWAY SAFETY DIMENSIONS

TAXIWAY SAFETY AREA (TSA): 79' WIDE

TAXIWAY OBJECT FREE AREA (T-OFA): 124' WIDE

PHASE 1 CONSTRUCTION LIMITS

POINT

NUMBER LATITUDE LONGITUDE SITE ELEVATION

(FT.)

OBSTRUCTION

HEIGHT (FT.)

OBSTRUCTION

ELEVATION (FT.) DESCRIPTION

1 N35°30' 31.78" W108°47' 36.52" 6470 40 6510 CONSTRUCTION LIMITS

2 N35°30' 31.80" W108°47' 34.10" 6471 40 6511 CONSTRUCTION LIMITS

3 N35°30' 29.32" W108°47' 34.07" 6471 40 6511 CONSTRUCTION LIMITS

4 N35°30' 29.31" W108°47' 36.49" 6471 40 6511 CONSTRUCTION LIMITS

5 N35°30' 30.60" W108°47' 34.09" 6470 25 6495 CONTRACTOR'S

STAGING AREA

6 N35°30' 30.60" W108°47' 29.49" 6470 25 6495 CONTRACTOR'S

STAGING AREA

7 N35°30' 28.49" W108°47' 29.48" 6470 25 6495 CONTRACTOR'S

STAGING AREA

8 N35°30' 28.47" W108°47' 34.10" 6470 25 6495 CONTRACTOR'S

STAGING AREA

NOTE: SITE ELEVATIONS FOR POINT 1 - 8 ARE FROM GOOGLE EARTH.

PHASE 1 CONSTRUCTION SCHEDULE (30 CALENDAR DAYS OR LESS)

1. THE GALLUP MUNICIPAL AIRPORT WILL BE OPEN FOR THE DURATION OF THE

PROJECT.

2. RUNWAY 6-24, TAXIWAY A, TAXIWAY A1, TAXIWAY A2, TAXIWAY A3, TAXIWAY A4,

TAXIWAY A5, AND TERMINAL APRON WILL REMAIN OPEN FOR THE DURATION OF

THIS PHASE.

3. THE FOLLOWING WORK SHALL BE COMPLETED WITHIN THE CONSTRUCTION LIMITS:

3.1. INSTALL NEW AWOS-III P/T SYSTEM.

3.2. REMOVE EXISTING ASOS SYSTEM.

4. AT THE COMPLETION OF THE ITEMS ABOVE, COORDINATE WITH AIRPORT MANAGER,

ENGINEER AND RPR TO OPEN THE WORK AREAS AS DESCRIBED IN THE STEPS

BELOW:

4.1. CLEAN ALL AIRPORT SURFACES.

4.2. REMOVE ALL EQUIPMENT, MATERIALS, AND PERSONNEL FROM THE WORK

AREA.

D ra w in g N am e:

C :\p w _w or ki ng \lo ch ne r-p w

-0 1\ d0

\2

T

O

- C

SP

P D

TL

S.

dw g

Ja n

,2

- 1 1:

am

1.1

CONSTRUCTION SAFETY

AND PHASING PLAN

DETAILS

NOL

TA

LFC

12-12-2025

11-26-2025

12-03-2025

Pl ot

S ty le : a e.

ct b La st S av ed

B y:

n lo vo s

/0 1/

THIS DOCUMENT

IS PRELIMINARY

IN NATURE AND IS

NOT A FINAL

SIGNED AND

SEALED

DOCUMENT.

PROJECT NO.

DRAWN BY

CHECKED BY

REVISIONS

DATE

DATE

DATE

DESIGNED BY DATE

N M

D O

T

PR

O

JE

C T

N O

. G U

P-

-0

25683 - TO01

2201 BUENA VISTA DRIVE

SOUTHEAST STE 204

ALBUQUERQUE, NM 87106

P 505.508.2192

WWW.HWLOCHNER.COM

G

AL

LU

P

M U

N

IC

IP

AL

A

IR

PO

R

T (G

U P)

G

AL

LU

P, N

EW

M

EX

IC

O

4'

NOTES:

1. BARRIER SHALL BE SHERWIN INDUSTRIES, 10" X 96" LOW PROFILE AIRPORT BARRIER,

AS SHOWN, OR APPROVED EQUAL.

2. THE ENTIRE AREA OF ORANGE AND WHITE STRIPES SHALL BE REFLECTORIZED WITH

SMOOTH SURFACE TYPE REFLECTIVE SHEETING.

3. LIGHTS MUST BE MOUNTED ON BARRIERS AND SPACED AT NO MORE THAN 10 FT.

4. BARRICADES SHALL BE SPACED NO GREATER THAN 12' ON CENTER OR 4' END TO END

5. THE BARRIERS SHALL BE WEIGHTED AGAINST PROPWASH AND CAPABLE OF

WITHSTANDING UP TO 100 M.P.H. WIND FORCES.

6. FLASHING RED CAUTION LIGHTS SHALL BE BATTERY OPERATED AND SHALL MAINTAIN

SUCH INTENSITY SO AS TO BE READILY IDENTIFIED FROM DISTANCES OF AT LEAST 200

FEET DURING DARKNESS.

7. THE CONTRACTOR SHALL CHECK ALL BARRIERS AND LIGHTS EACH DAY BEFORE

LEAVING THE AIRPORT TO ENSURE LIGHTS ARE WORKING PROPERLY AND MAY NOT

LEAVE WITHOUT ALL BARRIERS AND LIGHTS BEING IN PROPER WORKING ORDER.

8. NO ADDITIONAL PAYMENT SHALL BE MADE FOR THIS ITEM. IT SHALL BE CONSIDERED

SUBSIDIARY TO OTHER BID ITEMS.

8'

" M

AX

BATTEN TO KEEP

FLAG EXTENDED

20" MIN. X 20" MIN. FLAGS

ALTERNATING ORANGE AND WHITE,

ONE FLAG PER BARRIER. SUPPORTS

SHALL BE VERTICAL AND FRANGIBLE.

FLASHING RED

CAUTION

LIGHTS

REFLECTIVE ORANGE

(BOTH SIDES)REFLECTIVE WHITE

(BOTH SIDES)

LOW PROFILE BARRICADE DETAIL

NO SCALE

NOTES:

1. FLAG MUST HAVE A CHECKERED PATTERN OF

INTERNATIONAL ORANGE AND WHITE SQUARES.

COLORS SHALL BE IN ACCORDANCE WITH THE

CURRENT VERSION OF AC 150/5210-5.

2. FLAG AND FLASHING BEACON REQUIRED PER

CONSTRUCTION SAFETY AND PHASING PLAN (CSPP).

36"

12" 12" 12"

FLAG DETAIL

NO SCALE

Blank Page
Blank Page

File details come from the government source that posted it. Updated .