Additional Tunnel Heating-M-1.pdf

PDF 292 KB Posted

Attached to
Steam Tunnel Ventilation Replacement Federal contract opportunity
Solicitation number
NB196000-26-00830
Issued by
Department of Commerce National Institute of Standards and Technology

About this file

This is a mechanical design and demolition plan document for Building 42 Tunnel Ventilation at the National Institute of Standards and Technology (NIST) facility located at 325 Broadway, Boulder, Colorado. The project involves the complete removal and replacement of existing ventilation and steam heating systems with new mechanical equipment.

Demolition work includes removal of two supply fans with power and controls, two steam heating coils with piping and controls, one steam condensate pump with piping and controls, and all associated HPS (High Pressure Steam) and CPD (Condensate) piping, insulation, and hangers. Field-verified capping of 2-inch HPS and 2-inch CPD pipes is required, along with temporary capping of curb openings. The new system installation requires a THYBAR prefab standard 14-inch tall insulated curb to support a Mark MAU-1 indoor mechanical unit (Model DGX-P124-H32-MF). Additional work includes removal and patching of spalled concrete at horizontal and vertical surfaces, application of SIKA-THOROSEAL-581 weather-resistant barrier coating, and installation of SIKA-FLEX-NP100 sealant beads. The tunnel stair enclosure plan specifies removal of three louver blank-offs, installation of insulated sheet metal plenum columns, and two automatic air dampers per enclosure balanced for 2,000 CFM of relief each. The design was prepared by NIST's Boulder Design and Construction Division with an approval date of March 10, 2026.

View the file

Other files for this federal contract opportunity

Other files attached to Steam Tunnel Ventilation Replacement, newest first.
File Type Posted
Specifications.zip ZIP file
Additional Tunnel Heating-M-4.pdf PDF
DRAFT SOW - Steam Tunnel Ventilation.docx DOCX document
001000 General Contractor Requirements and Site Standards.zip ZIP file
Additional Tunnel Heating-M-2.pdf PDF
01A NIST Boulder General Contractor Requirements.pdf PDF
Additional Tunnel Heating-M-0.pdf PDF
Additional Tunnel Heating-M-3.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

HPS

1 REMOVE SUPPLY FAN COMPLETELY INCLUDING POWER AND CONTROLS

TYPICAL OF 2 FANS. TEMPORARILY CAP CURB OPENINGS.

2 REMOVE STEAM HEATING COIL , PIPING AND CONTROLS, TYPICAL OF 2 COILS.

3 CUT AND WELD CAP TO 2" HPS, FIELD VERIFY SIZE AND LOCATION.

CP-001

2 HC-001

1 SF-001 SF-002

HC-002

VENTILATION AND STEAM SYSTEM DEMOLITION

14" H

PS

8" C

PD

4 CUT AND WELD CAP TO 2" CPD, FIELD VERIFY SIZE AND LOCATION.

5 REMOVE STEAM COND. PUMP INCLUDING PIPING, POWER AND CONTROLS.

6 CONCRETE CURB TO REMAIN, TEMPORARILY CAP & SECURE CURB OPENINGS.

7 REMOVE ALL HPS AND CPD PIPING, PIPE INSULATION AND PIPE HANGERS COMPLETELY.

DEMOLITION PLAN

4'-111 4"

MECHANICAL EQUIP. ON CONCRETE STRUCTURE

8' -3

3 4"

4'-83 4" 2'-91

2" 4'-83 4" 2'-4"

16'-91 2"

4' -8

3 4" 1'

-9 1 2"

2'-21 2"

1' -9

1 2"

REMOVE/DEMOLISH

EXISTING MECHANICAL

EQUIPMENT AT BOTH

CONCRETE OPENINGS

NEW MECANICAL UNIT

ON NEW INSULATED CURB.

CURB:

MAKE:THYBAR PREFAB

STANDARD 14-INCH TALL

INSULATED CURB

MECHANICAL UNIT:

MARK: MAU-1 indoor

MODEL: DGX-P124-H32-MF

REMOVE SPALLED CONCRETE

AT HORIZONTAL/ VERTICAL

SURFACES AND PATCH

SPALLED AREAS. INSTALL

SIKA-THOROSEAL-581 ON

HORIZONTAL AND VERTICAL

SURFACES, FROM EDGE OF

HORIZONTAL ROUGH OPENING

TO EXISTING TERMINATION

BAR ON VERTICAL FACE. (ALL

EXPOSED EXTERIOR

CONCRETE SURFACES).

ACCESS SIDE CONTROL CENTER

ACCESS SIDE BURNER

ACCESS SIDEACCESS SIDE

INTAKE V-BANK

FILTER

DIRECT GAS MIXEDFLOW BLOWER

2'-4"4'-83 4"2'-91

2"4'-83 4"2'-21

2"

12'-9" 2'-2"1'-101 2"

12'-9"1'-101 2"

1' -5

1 2" 5'

-4 3 4"

1' -5

1 2"

2'-2"

42-MAU-001-ELEVATION VIEW

42-MAU-001-PLAN VIEW

EQUIPMENT -DEMOLITION

SCALE: NOT TO SCALE

NEW MECANICAL UNIT CURB (THYBAR

PREFAB STANDARD 14-INCH TALL

INSULATED CURB).

TWO 1/4-INCH MIN. SEALANT BEADS

(SIKA-FLEX-NP100), SPACED 1-INCH MIN.

APART. SEALANT MUST BE 1-PART

DIRECTLY FROM SIKA; NO 2-PART

SEALANT PRODUCTS.

APPLY SIKA-THOROSEAL-581 PER

MANUFACTURER. REQUIREMENTS,

CONTINUOUS FROM EXISTING ROUGH

OPENINGS DOWN VERTICAL FACE OF

ONCRETE TO TERMINATION BARS.

REMOVE AND PATCH SPALLING CONC

-RETE PRIOR TO INSTALLING SIKA

-THOROSEAL-581.

NEW SIKA-FLEX

-NP100 SEALANT

FILLET BEAD AT

TOP OF TRIM BAR

OVER TOP OF

SIKA-THOROSEAL

-581 (CONTINUOUS).

EXISTING

TERMINATION

BAR AND

MEMBRANE.

EXISTING ROUGH OPENINGS.

WEATHER RESISTANT BARRIER COATING DETAIL

TUNNEL STAIR ENCLOSURE PLAN (TYP. OF 3 ENCLOSURES)

SCALE: NOT TO SCALE

37"X24" EXIST.

LOUVER, TYP. OF 3.

NOTES:

1. FIELD VERIFY ALL DIMENSIONS

INTERIOR COLUMN.

2. REMOVE LOUVER BLANK OFFS

INTERIOR COLUMN.

INSULATED SHEET METAL

PLENUM COLUMN TO

COLUMN, AT INTERIOR

LOUVER.

REMOVE LOUVERS BLANK OFFS

VERIFY LOCATIONS AND

QUANTITIES.

INTERIOR COLUMN.

AUTOMATIC AIR

DAMPER, REFER

TO SCHEDULE AND

CONTROL

SEQUENCE

3. BALANCE EACH AUTOMATIC DAMPER MAX OPEN POSITION FOR 2,000 CFM OF RELIEF EACH.

4. PROVIDE (2) AUTOMATIC DAMPERS PER ENCLOSURE.

SHEET NUMBER

PROJECT NAME of

325 BROADWAY BOULDER, COLORADO 80305-3328

NATIONAL INSTITUTE OF STANDARDS AND TECHNOLOGY

DATEDESIGN APPROVAL

BOULDER DESIGN AND CONSTRUCTION DIVISION

DATESUPV.BYDESCRIPTIONREVISION

3 DRAFTING

ADDITIONAL TUNNEL HEAT

COOK

BUILDING 42 TUNNEL VENTILATION

3/10/2026

M-1COOK

Sheets and Views
M-1