Addendum One.pdf

PDF 753 KB Posted

Attached to
RFB-30-25 KCTCS Switchgear Replacement
Solicitation number
RFB 785 2500000019 5
Issued by
Cumberland County, Kentucky

About this file

This is Addendum No. 1 to an Invitation to Bid (RFB-30-25) issued by the Commonwealth of Kentucky Department for Facilities and Support Services Division of Engineering and Contract Administration for switchgear replacement at Owensboro Community & Technical College Downtown Campus in Owensboro, Kentucky. The addendum, dated July 22, 2024, modifies the original bid specifications and drawings for the electrical construction project. The primary scope includes installation of a new main distribution switchboard, emergency power generator, utility transformer pad, grounding electrode system, and associated electrical infrastructure. The work encompasses coordination with multiple trades, fire alarm system modifications through Innovative Fire & Security Solutions, utility work coordination with Owensboro Municipal Utilities (OMU), and comprehensive demolition and patching requirements. The project requires the electrical contractor to manage cutting, patching, and fire-rating compliance for all demolition and new construction work, obtain required permits and inspections, and facilitate utility power outages scheduled during after-business hours (8:00 PM to 6:00 AM weekdays; Friday 4:30 PM through Sunday 11:59 PM weekends) with owner approval.

The addendum establishes specific allowance costs that contractors must include in their bids: $5,000 for fire alarm system work performed by Innovative Fire & Security Solutions (exclusive of contractor overhead and profit) and $12,300 for work performed by OMU (exclusive of contractor overhead and profit). The electrical contractor must also assume all costs for overtime, utility disruptions, power outages, permits, inspections, and all labor and materials for installation of fire alarm cabling, conduit raceways, circuits, demolition of existing equipment, and grounding system installation. The addendum references revised Drawing E1.0 Rev 1 with updated lighting fixture schedules and acceptable manufacturers, including fixtures from Lithonia, Cooper Lighting Metalux, Columbia Lighting, Oracle Lighting, Dual-Lite, Sensorless Lighting, and Even-Lite. All materials, specifications, and technical requirements are subject to coordination with OMU, the using agency (KCTCS-Octc), and the architect prior to construction commencement.

View the file

Other files

File Type Posted
Final_RFB_785_2500000019_1_SO_FORM.PDF PDF
Addendum Three.pdf PDF
Final_RFB_785_2500000019_2_SO_FORM.PDF PDF
Final_RFB_785_2500000019_3_SO_FORM.PDF PDF
Final_RFB_785_2500000019_4_SO_FORM.PDF PDF
Final_RFB_785_2500000019_5_SO_FORM.PDF PDF
Addendum Two .pdf PDF
Addendum Four .pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

COMMONWEALTH OF KENTUCKY

DEPARTMENT FOR FACILITIES AND SUPPORT SERVICES

DIVISION OF ENGINEERING AND CONTRACT ADMINISTRATION

INVITATION TO BID NO: RFB-30-25

FOR: Switchgear Replacement Owensboro Community & Technical College Downtown Campus-KCTCS Owensboro, Kentucky

DATE: July 22, 2024

RFB-785-2500000019

ADDENDUM NO. One (1)

BIDDER SHALL CONFORM TO THE FOLLOWING CHANGES AS SAME SHALL BECOME BINDING

UPON THE CONTRACT TO BE ISSUED IN RESPONSE TO THIS INVITATION TO BID.

Item 1: Refer to addendum to be distributed by Lynn Imaging for all additions, deletions, and/or changes to specifications and/or drawings.

END OF ADDENDUM

Invitation to Bid No. RFB-30-25 For: Switchgear Replacement Owensboro Community & Technical College Downtown Campus-KCTCS

Susan Ward, Statewide Procurement Analyst II Division of Engineering and Contract Administration

July 22, 2024

Mr. Brian Cottongim Kentucky Finance and Administration Cabinet Department for Facilities & Support Services

Bush Building

403 Wapping Street Frankfort, Kentucky 40601

Re: Switchgear Replacement -Owensboro Community & Technical College – Downtown Campus -

KCTCS

Request for Bid: RFB-30-25

Account No.: 470-CB72-OC33-00 A/E Project no.: 2401-116

Dear Mr. Cottongim:

The following items need to be included in an addendum to the Switchgear Replacement - Owensboro Community & Technical College Downtown Campus – KCTCS Project.

Addendum Items:

1. Refer to attached Revised Drawing E1.0 Rev 1 Site Electrical Plan, Lighting Fixture Schedule.

a. Add acceptable manufacturers and fixture series as indicated on the revised drawing.

Sincerely, HAFER

Matt Brockman, P.E., LEED® AP

Attachments:

(1) Revised Drawing E1.0 Rev 1 Site Electrical Plan

G1. THE ELECTRICAL CONTRACTOR SHALL COORDINATE ALL DEMOLITION AND

NEW CONSTRUCTION REQUIREMENTS WITH THE WORK OF ALL OTHER TRADES

INVOLVED ON THIS PROJECT.

G2. CONTRACTOR SHALL BE RESPONSIBLE FOR ALL REQUIRED CUTTING AND

PATCHING TO PROVIDE DEMOLITION AND NEW CONSTRUCTION REQUIREMENTS.

ALL INSTALLATION AND PATCHING SHALL MEET THE FIRE RATINGS OF THE

EXISTING CEILING/WALL/FLOOR SYSTEMS.

G3. PERMITS & STATE INSPECTION COSTS. ALL COSTS ASSOCIATED WITH

OBTAINING THE REQUIRED PERMITS AND INSPECTIONS FOR THE NEW

CONSTRUCTION INSTALLATION SHALL BE INCLUDED IN THE ELECTRICAL

CONTRACTOR'S BID PRICE.

G4. FIRE ALARM SYSTEM MODIFICATIONS. THE CONTRACTOR SHALL PROVIDE

THE SERVICES OF INNOVATIVE FIRE & SECURITY SOLUTIONS, FOR ALL WORK

ASSOCIATED WITH MODIFICATIONS TO THE FIRE ALARM SYSTEM.

ROBERT HORTON

812-568-4977

RHORTON@IFSS-EVV.COM.

G5. ALLOWANCE FOR THE WORK PERFORMED BY INNOVATIVE FIRE &

SECURITY SOLUTIONS. THE CONTRACTOR SHALL INCLUDE IN THEIR BID PRICE A

TOTAL ALLOWANCE COST OF $5,000.00 FOR THE WORK PERFORMED BY

INNOVATIVE FIRE & SECURITY SOLUTIONS (IFSS). THE ALLOWANCE DOES NOT

INCLUDE ANY OVERHEAD AND PROFIT THE BIDDING CONTRACTOR NEEDS TO

ADD ON TOP OF THE ALLOWANCE. THE FOLLOWING IS A CLARIFICATION OF THE

SCOPE WHICH IS INCLUDED IN THE ALLOWANCE AMOUNT.

G5.1. IFSS SHALL FURNISH TO THE ELECTRICAL CONTRACTOR ALL

REQUIRED SMOKE DETECTORS, HEAT DETECTORS, ADDRESSABLE

RELAYS AND MONITOR MODULES AND AUDIO & VISUAL ALARM

INDICATING DEVICES REQUIRED TO MEET THE REQUIREMENTS OF

THE CONTRACT DRAWINGS AND SPECIFICATIONS.

G5.2. IFSS SHALL FURNISH ALL LABOR REQUIRED TO REMOVE DEMOED

FIRE ALARM EQUIPMENT FROM THE FIRE ALARM SYSTEM PANEL

PROGRAMMING.

G5.3. IFSS SHALL FURNISH ALL LABOR REQUIRED TO PROGRAM FIRE

ALARM DEVICES AFTER INSTALLATION OF THE DEVICES BY THE

ELECTRICAL CONTRACTOR HAS BEEN COMPLETED.

G5.4. IFSS WILL FURNISH LABOR TO BE PRESENT FOR AND ASSIST IN THE

TESTING OF THE FIRE ALARM SYSTEM AND NEW DEVICES. THIS

TESTING SHALL OCCUR AND BE COMPLETED DURING A MAXIMUM OF

TWO SITE VISITS.

G6. THE FOLLOWING WORK BY THE ELECTRICAL CONTRACTOR SHALL NOT BE

INCLUDED IN THE ALLOWANCE COST (IDENTIFIED IN PARAGRAPH G5. ABOVE) .

THE FOLLOWING COSTS SHALL BE INCLUDED IN THE CONTRACTOR'S BID PRICE.

G6.1. THE ELECTRICAL CONTRACTOR SHALL INSTALL ALL FIRE ALARM

SYSTEM DEVICES FURNISHED BY IFSS AS PART OF THE ALLOWANCE

COST.

G6.2. THE ELECTRICAL CONTRACTOR SHALL FURNISH AND INSTALL ALL

REQUIRED CABLING & CONDUIT RACEWAYS TO INSTALL THE FIRE

ALARM EQUIPMENT FURNISHED BY IFSS AS PART OF THE

ALLOWANCE COST.

G6.3. THE ELECTRICAL CONTRACTOR SHALL FURNISH AND INSTALL ALL

REQUIRED CIRCUITS BETWEEN THE FIRE ALARM SYSTEM AND

OTHER NON-FIRE ALARM SYSTEM EQUIPMENT REQUIRED FOR

CORRECT OPERATION.

G6.4. THE ELECTRICAL CONTRACTOR SHALL PROVIDE ALL LABOR AND

EQUIPMENT REQUIRED AND SHALL DEMO THE EXISTING FIRE ALARM

SYSTEM DEVICES AND ASSOCIATED CIRCUITS PER THE CONTRACT

DRAWINGS.

G6.5. THE ELECTRICAL CONTRACTOR SHALL FURNISH AND INSTALL ALL

REQUIRED CABLING AND CONDUIT RACEWAYS AND SHALL

REINSTALL THE FIRE ALARM EQUIPMENT REMOVED FOR

RELOCATION DURING DEMOLITION.

G6.6. THE ELECTRICAL CONTRACTOR SHALL BE PRESENT FOR ALL

TESTING OF THE FIRE ALARM SYSTEM AND ALL REQUIRED

INTERFACES OF OTHER NON-FIRE ALARM SYSTEM EQUIPMENT

AFTER ALL INSTALLATION HAS BEEN COMPLETED. SEE ALLOWANCE

PARAGRAPH ABOVE FOR ADDITIONAL REQUIREMENTS.

G7. ALLOWANCE FOR THE WORK PERFORMED BY OWENSBORO MUNICIPAL

UTILITIES (OMU). THE CONTRACTOR SHALL INCLUDE IN THEIR BID PRICE A TOTAL

ALLOWANCE COST OF $12,300.00 FOR THE WORK PERFORMED BY OMU. THE

ALLOWANCE DOES NOT INCLUDE ANY OVERHEAD AND PROFIT THE BIDDING

CONTRACTOR NEEDS TO ADD ON TOP OF THE ALLOWANCE. COORDINATE ALL

REQUIRED WORK WITH THE UTILITY COMPANY.

G8. UTILITY DISRUPTIONS AND POWER OUTAGES. ALL COSTS ASSOCIATED

WITH UTILITY DISRUPTIONS AND POWER OUTAGES SHALL BE INCLUDED IN THE

CONTRACTOR'S BID PRICE. COSTS FOR OVERTIME (TIME AND A HALF, DOUBLE

TIME, HOLIDAY PAY, ETC.) SHALL BE INCLUDED IN THE CONTRACTOR'S BID

PRICE. ALL UTILITY AND POWER OUTAGES SHALL BE COORDINATED WITH AND

APPROVED BY THE OWNER/USING AGENCY (I.E. KCTCS-OCTC) PRIOR TO THE

NEED FOR THE POWER DISRUPTIONS. POWER DISRUPTIONS SHALL ONLY

OCCUR DURING "AFTER NORMAL BUSINESS HOURS" AND "WEEKEND" TIME

PERIODS. FOR BIDDING PURPOSES, THE CONTRACTOR SHALL ASSUME THE

FOLLOWING TIMES FOR UTILITY AND POWER DISRUPTIONS:

G8.1. WEEK DAYS (MONDAY THRU THURSDAY): 8:00PM TO 6:00AM

G8.2. WEEKENDS (FRIDAY EVENING AFTER 4:30PM THRU

SUNDAY EVENING 11:59PM):

G9. EXISTING FEDERAL PACIFIC DISTRIBUTION EQUIPMENT. THE OWNER /

USING AGENCY (KCTCS-OCTC) WANTS THE OLD REMOVED FEDERAL PACIFIC

EQUIPMENT & OVER-CURRENT PROTECTION DEVICES AFTER DISCONNECTION

AND REMOVAL. THE CONTRACTOR SHALL DELIVER THE EQUIPMENT TO AN ON-

SITE STORAGE LOCATION AS DIRECTED BY KCTCS-OCTC.

GENERAL NOTES (THIS PROJECT):

W 15TH ST

F R

E D

E R

IC

A

S T

D A

V

IE

S S

S T

NEW UTILITY COMPANY PADMOUNT TRANSFORMER.

CONTRACTOR SHALL PROVIDE CONCRETE BASE

AND SHALL STUB PRIMARY SIDE CONDUITS OUT

PAST EDGE OF BASE. SEE UTILITY TRANSFORMER

PAD BASE DETAIL, THIS SHEET, FOR ADDITIONAL

REQUIREMENTS. COORDINATE ALL REQUIREMENTS

WITH UTILITY COMPANY.

EXISTING UTILITY COMPANY

POLE WITH PRIMARY FEED FROM

OVERHEAD TO BELOW GRADE

EXISTING UTILITY COMPANY UNDERGROUND

PRIMARY FEED TO PADMOUNT TRANSFORMER.

(NOTE: PRIMARY FEED REPLACED WITH NEW ~ 2017

[AROUND 7 YEARS OLD])

EXISTING UNDERGROUND FEED FROM

PADMOUNT TRANSFORMER TO EXISTING

MAIN DISTRIBUTION SWITCHBOARD.

NOTE 2.

EXISTING MAIN DISTRIBUTION

SWITCHBOARD

EXISTING UTILITY COMPANY

PADMOUNT TRANSFORMER,

500KVA, 480Y/277V, 3PH 4W.

Z=1.9% ("LIVE" FRONT PRIMARY)

NEW MAIN DISTRIBUTION SWITCHBOARD

NEW UNDERGROUND FEED FROM

PADMOUNT TRANSFORMER TO NEW

MAIN DISTRIBUTION SWITCHBOARD

TEMPORARY LOCATION OF

EXISTING AIR COMPRESSOR

NOTE: PER MTG WITH UTILITY COMPANY ON 3/12/2024,

NEED A 2-DAY (WEEKEND) POWER OUTAGE TO DISCONNECT PRIMARY FEEDER,

SET NEW PADMOUNT TRANSFORMER, REWORK PRIMARY FEEDER TO NEW

TRANSFORMER AND MAKE ALL PRIMARY AND SECONDARY CONNECTIONS.

NOTE: DURING THE 2-DAY (WEEKEND) POWER

OUTAGE (FOR UTILITY CO. WORK) ELEC

CONTRACTOR SHALL DISCONNECT THE UTILITY

FEED TO THE EXISTING MAIN SWITCHGEAR AND

PROVIDE NEW TEMPORARY FEED TO EXISTING

MAIN SWITCHGEAR FROM THE NEW MAIN

DISTRIBUTION SWITCHGEAR.

NOTE 3.

1. PROVIDE TRIAD GROUNDING ELECTRODE SYSTEM. SEE GROUNDING

SYSTEM DETAILS, SHEET E1.0, FOR ADDITIONAL REQUIREMENTS. COORDINATE

THE INSTALLATION LOCATION IN FIELD WITH ALL EXISTING UNDERGROUND

UTILITIES AND INSTALLATION.

2. THE EXISTING UNDERGROUND UTILITY FEED SHALL HAVE ALL

CONDUCTORS REMOVED. EXTERIOR CONDUIT ENDS SHALL BE CAPPED. THE

INTERIOR CONDUIT ENDS SHALL BE CUT FLUSH WITH FLOOR AND FILLED.

3. PRIOR TO BACK-FEEDING THE EXISTING MAIN DISTRIBUTION

SWITCHBOARD, THE CONTRACTOR SHALL DISCONNECT THE NEUTRAL /

GROUND BOND SO THAT THE ONLY PLACE WHERE THE NEUTRAL / GROUND

BOND OCCURS IS WITHIN THE NEW MAIN DISTRIBUTION SWITCHBOARD (I.E.

SERVICE DISCONNECT LOCATION). NOTE: THE NEW GROUNDING ELECTRODE

SYSTEM AND ALL REQUIRED GROUNDING/BONDING SHALL BE IN-PLACE PRIOR

TO BACK-FEEDING THE EXISTING DISTRIBUTION EQUIPMENT.

4. PROVIDE ALL SAW-CUTTING, REMOVALS, EXCAVATION, BACK-FILLING,

PATCHING AND REPAIR OF SITE AREAS & AREAS WITHIN THE BUILDING

REQUIRED TO PROVIDE NEW INSTALLATION.

5. PROVIDE ALL SAW-CUTTING, REMOVALS, EXCAVATION, BACK-FILLING,

PATCHING AND REPAIR OF SITE AREAS (CONCRETE, ASPHALT & PLANTED

AREAS) REQUIRED TO PROVIDE NEW INSTALLATION & LEAVE AS WAS (I.E.

ASPHALTED AREAS SHALL BE ASPHALTED, CONCRETE AREAS SHALL BE

CONCRETE, PLANTED AREAS SHALL BE PLANTED, ETC.) PRIOR TO START OF

DEMOLITION.

NOTES:

NOTE 1

NEW EMERGENCY POWER GENERATOR ON CONCRETE BASE

FINAL LOCATION OF EXISTING AIR

COMPRESSOR (OLD EMERGENCY

GENERATOR LOCATION)

NEW ELEC RM "1E"

NEW ELEC RM "14E"

NEW ELEC RM "19E" NEW ELEC RM "24E"

PROVIDE PROTECTION BOLLARD.

TYPICAL, OF 13. SEE CONCRETE FILLED

PROTECTION BOLLARD DETAIL, THIS

SHEET FOR ADDITIONAL REQUIREMENTS.

NOTE 4

NOTES 4 & 5

NOTE 5

SECTION VIEW

PLAN VIEW

GROUNDING ELECTRODE SYSTEM DETAIL

NO SCALE

20'-0"

60°

20'-0"

FINISHED GRADE

3'-0"

#4/0 INSULATED COPPER

GROUND CABLE TO BUILDING

MAIN GROUND BUS BAR,

LOCATED WITHIN THE MAIN

ELECTRICAL ROOM. ROUTE

CABLE WITHIN CONDUIT

WHERE CABLE IS ROUTED

THROUGH CONCRETE OR

MASONRY WALLS AND

FLOORS. SEE GROUNDING

SYSTEM RISER DIAGRAM,

SHEET E1.0, FOR ADDITIONAL

REQUIREMENTS.

3/4" x 10'-0" COPPER

GROUND ROD. TYPICAL.

EXOTHERMIC WELD OR

IRREVERSIBLE COMPRESSION

TYPE BOND. TYPICAL.

#4/0 INSULATED COPPER

GROUND ROD BONDING CABLES.

GROUNDING SYSTEM RISER DIAGRAM

NO SCALE

GENERAL GROUNDING NOTE:

ALL BONDS TO GROUND BUS BARS SHALL BE MADE USING 2-HOLE TYPE MECHANICAL LUGS.

BOND TRANSFORMER(S) SECONDARY

NEUTRAL "X0" TO GROUND BUS BAR.

SEE ONE-LINE DIAGRAM, SHEET E3.2,

FOR ADDITIONAL REQUIREMENTS

TRIAD BUILDING GROUNDING

ELECTRODE SYSTEM. SEE

GROUNDING ELECTRODE SYSTEM

DETAIL, THIS SHEET, FOR

ADDITIONAL REQUIREMENTS.

BUILDING MAIN GROUND BUS BAR.

PROVIDE 1/4"(T) x 4"(H) x 18"(L) COPPER BUS

BAR ON INSULATED STAND-OFF DEVICES.

[PROVIDE WITHIN THE MAIN ELEC ROOM]

1#4/0 INSULATED COPPER

CABLE IN CONDUIT RACEWAY.

BOND TO NEUTRAL BUS WITHIN THE MAIN

DISTRIBUTION SWITCHBOARD USING #4/0

INSULATED COPPER CABLE INSTALLED

WITHIN NON-FERROUS (AL) CONDUIT.

BOND TO NEAREST BUILDING

STRUCTURAL STEEL COLUMN USING #4/0

INSULATED COPPER CABLE INSTALLED

WITHIN NON-FERROUS (AL) CONDUIT.

BOND BUILDING METALLIC PIPING

SYSTEMS TO THE BUS BAR USING #3/0

INSULATED COPPER CABLE INSTALLED

WITHIN NON-FERROUS (AL) CONDUIT.

1#4/0 INSULATED

COPPER CABLE IN

CONDUIT RACEWAY.

GROUND BUS BAR. PROVIDE 1/4"(T) x 4"(H) x 12"(L)

COPPER BUS BAR ON INSULATED STAND-OFF

DEVICES. [PROVIDE WITHIN NEW ELEC ROOM 24E].

GROUND BUS BAR. PROVIDE 1/4"(T) x 4"(H) x 12"(L)

COPPER BUS BAR ON INSULATED STAND-OFF

DEVICES. [PROVIDE WITHIN NEW ELEC ROOM 19E].

GROUND BUS BAR. PROVIDE 1/4"(T) x 4"(H) x 12"(L)

COPPER BUS BAR ON INSULATED STAND-OFF

DEVICES. [PROVIDE WITHIN NEW ELEC ROOM 14E].

GROUND BUS BAR. PROVIDE 1/4"(T) x 4"(H) x 12"(L) COPPER BUS BAR ON

INSULATED STAND-OFF DEVICES. [PROVIDE WITHIN NEW ELEC ROOM 1E].

BOND TRANSFORMER(S) SECONDARY NEUTRAL "X0" TO

GROUND BUS BAR. SEE ONE-LINE DIAGRAM, SHEET E3.2,

FOR ADDITIONAL REQUIREMENTS

BOND TRANSFORMER(S) SECONDARY NEUTRAL "X0" TO GROUND BUS BAR.

SEE ONE-LINE DIAGRAM, SHEET E3.2, FOR ADDITIONAL REQUIREMENTS.

BOND TRANSFORMER(S) SECONDARY NEUTRAL "X0" TO GROUND BUS BAR.

SEE ONE-LINE DIAGRAM, SHEET E3.2, FOR ADDITIONAL REQUIREMENTS.

#4/0 INSULATED COPPER

GROUND CABLE TO EMERGENCY

POWER GENERATOR "X0". ROUTE

CABLE WITHIN CONDUIT WHERE

CABLE IS ROUTED BELOW

AND/OR THROUGH CONCRETE .

LIGHTING FIXTURE SCHEDULE

MANUFACTURERSYMBOL DESCRIPTION

TYPE

FIXTURE SERIES

LAMP

LENSWATTS REFLECTOR

MOUNTING

LIGHT CONTROL

REMARKS

FIXTURE

VOLTAGEQNTY PER

FIXTURE

LITHONIA

120/277

(MULTI-

VOLT)

COOPER LTG

METALUX

QNTY AS

REQUIRED

45W

(NOMINAL

FIXTURE

INPUT

WATTS)

RECESSED,

T-GRID ---

2'x4' LED EDGE-LIT FLAT PANEL, FULLY LUMINOUS

APPEARANCE ACROSS FACE OF THE LENS. PROVIDE

FIXTURE WITH DIMMING CAPABILITIES DOWN TO 1% OF FULL

RATED LUMEN OUTPUT.

(2.2" MAX FIXTURE DEPTH).

[FIXTURE LUMEN OUTPUT ~ 4998 LUMENS]

SATIN

WHITE

LEDS 3500K

(60,000 HRS WITH

97% LUMEN

MAINTENANCE)

L97/60

80+ CRI

EPANL-2x4-4800LM-80CRI-35K-1% DIMMING (0-to-10V)-MVOLT SERIES

24FP4735C-80CRI-35K-1% DIMMING

(0-to-10V)-UNV SERIES

F1D

F2

LITHONIA

120/277

(MULTI-

VOLT)

QNTY AS

REQUIRED

34W

(NOMINAL

FIXTURE

INPUT

WATTS)

SUSPENDED,

AIRCRAFT

CABLE

4' LENGTH LED STRIP LIGHTING FIXTURE WITH WHITE FINISH

AND SNAP-ON FLAT LENS.

[FIXTURE DIMENSIONS: 2-1/8"(H) x 2-3/16"(W) x 48"(L)].

[FIXTURE LUMEN OUTPUT ~ 4585 LUMENS]

SNAP-ON / OFF

FROSTED ,

DIFFUSE,

SYMMETRICAL

DISTRIBUTION

LEDS 4000K

(60,000 HRS WITH

70% LUMEN

MAINTENANCE)

L70/60

80 CRI

ZL1N-L48-SMR-5000LM-FST-

MVOLT-40K-80CRI-WH SERIES

1. COORDINATE THE REQUIRED INSTALLATION HEIGHT

(SUSPENSION ABOVE FINISHED FLOOR) WITH THE ARCHITECT

PRIOR TO START OF ROUGH-IN. PROVIDE ALL REQUIRED

SUPPLEMENTAL STEEL INSTALLATION AS REQUIRED TO INSTALL

FIXTURES IN THE GENERAL LOCATIONS AS INDICATED ON THE

CONTRACT DRAWINGS.

(END OF LIGHTING FIXTURE SCHEDULE)

COOPER LTG

METALUX

F3

LITHONIA

120/277

(MULTI-

VOLT)

QNTY AS

REQUIRED

31W

(NOMINAL

FIXTURE

INPUT

WATTS)

SUSPENDED,

AIRCRAFT

CABLE

2' LENGTH LED STRIP LIGHTING FIXTURE WITH WHITE FINISH

AND SNAP-ON FLAT LENS.

[FIXTURE DIMENSIONS: 2-1/8"(H) x 2-3/16"(W) x 24"(L)].

[FIXTURE LUMEN OUTPUT ~ 3666 LUMENS]

SNAP-ON / OFF

FROSTED ,

DIFFUSE,

SYMMETRICAL

DISTRIBUTION

LEDS 3500K

(60,000 HRS WITH

70% LUMEN

MAINTENANCE)

L70/60

80 CRI

ZL1N-L24-SMR-3500LM-FST-

MVOLT-35K-80CRI-WH SERIES

1. COORDINATE THE REQUIRED INSTALLATION HEIGHT

(SUSPENSION ABOVE FINISHED FLOOR) WITH THE ARCHITECT

PRIOR TO START OF ROUGH-IN. PROVIDE ALL REQUIRED

SUPPLEMENTAL STEEL INSTALLATION AS REQUIRED TO INSTALL

FIXTURES IN THE GENERAL LOCATIONS AS INDICATED ON THE

CONTRACT DRAWINGS.

COOPER LTG

METALUX

F4

EMB2

LED THERMOPLASTIC EMERGENCY LIGHTING UNIT WITH

TWO LED FIXTURE HEADS, INTEGRAL BATTERY BACK-UP

WITH HIGH OUTPUT WITH LITHIUM ION PHOSPHATE

BATTERIES CAPABLE OF 120 MINUTES OF OPERATION ON

LOSS OF NORMAL POWER SOURCE. PROVIDE WITH SELF-

DIAGNOSTICS.

ISOLITE BUG-6-WH-SD SERIES

120/277

(MULTI-

VOLT)

QNTY TWO

FIXTURE

HEADS

(QNTY 3 -

2W LEDS

PER HEAD)

6W PER

LAMP

HEAD

(12W

TOTAL)

SURFACE

WALLLED ---

1. COORDINATE THE REQUIRED INSTALLATION LOCATIONS AND

MOUNTING HEIGHT IN FIELD WITH ALL OTHER INSTALLATION

WITHIN THE INSTALLED ROOMS. AIM FIXTURE HEADS TO PROVIDE

THE MAXIMUM ILLUMINATION ON PATHWAYS AND EQUIPMENT

WHICH REQUIRES INSPECTION AND MAINTENANCE DURING A LOSS

OF NORMAL POWER CONDITION.

LITHONIA

120/277

(MULTI-

VOLT)

QNTY AS

REQUIRED

104W

(NOMINAL

FIXTURE

INPUT

WATTS)

SUSPENDED,

AIRCRAFT

CABLE

8' LENGTH LED STRIP LIGHTING FIXTURE WITH SYMMETRIC

REFLECTORS, WHITE FINISH AND SNAP-ON FLAT LENS.

[FIXTURE DIMENSIONS: 2-1/8"(H) x 2-3/16"(W) x 96"(L)].

[FIXTURE LUMEN OUTPUT ~ 12,933 LUMENS]

SNAP-ON / OFF

FROSTED ,

DIFFUSE,

SYMMETRICAL

DISTRIBUTION

LEDS 4000K

(60,000 HRS WITH

70% LUMEN

MAINTENANCE)

L70/60

80 CRI

TZL1N-L96-SMR-14000LM-FST-

MVOLT-40K-80CRI-WH SERIES

SYMMETRIC,

WHITE

FINISH

1. COORDINATE THE REQUIRED INSTALLATION HEIGHT

(SUSPENSION ABOVE FINISHED FLOOR) WITH THE ARCHITECT

PRIOR TO START OF ROUGH-IN. PROVIDE ALL REQUIRED

SUPPLEMENTAL STEEL INSTALLATION AS REQUIRED TO INSTALL

FIXTURES IN THE GENERAL LOCATIONS AS INDICATED ON THE

CONTRACT DRAWINGS.

COOPER LTG

METALUX

1. PROVIDE WITH QUANTITY OF DIMMER CONTROL SWITCHES AS

INDICATED ON THE CONTRACT DRAWINGS. DIMMER SWITCHES

SHALL BE FULLY COMPATIBLE WITH THE INSTALLED LIGHTING

FIXTURES.

COLUMBIA LTG

CBT24-A-LSCS-EDD-80CRI-35K-1%

DIMMING (0-to-10V) SERIES

ORACLE LTG

4-OC4-LED-5000L-1% DIMMING (0-

to-10V)-MVOLT-40K-85-WHITE SERIES

ORACLE LTG

2-OC4-LED-4000L-1% DIMMING (0-

to-10V)-MVOLT-35K-85-WHITE SERIES1

ORACLE LTG

8-OC4-LED-14000L-1% DIMMING (0-

to-10V)-MVOLT-40K-85-WHITE SERIES

DUAL-LITE EVHC12I-06L (WITH 120 MINUTE

BATTERY BACKUP) WHITE SERIES

4SNLED-LD5-48SL-SLW-UNV-L840-

CD1-U-WHITE SERIES

2SNLED-LD5-30HL-SLW-UNV-L835-

CD1-U-WHITE SERIES

8TSNLED-LD5-170HL-SLW-UNV-L840-

CD1-U-WHITE SERIES

EVEN-LITE TEBL6W-SD (WITH 120 MINUTE

BATTERY BACKUP) WHITE SERIES

DETAIL - GENSET CONCRETE BASE

NO SCALE

12" 12"

10"

28"

TOP OF PAD SHALL BE

SET AT AN ELEVATION

OF 4" ABOVE ADJACENT

FINISHED GRADE. SLOPE

FINISHED GRADE.1" CHAMFERED EDGE

NOTE: COORDINATE REQUIRED DIMENSIONS WITH GENERATOR SET TO ALLOW

PAD TO EXTEND 12" PAST THE OUTERMOST DIMENSIONS OF THE GENERATOR

AND BASE ON SIDES OF THE GENERATOR SET / ENCLOSURE WHICH DO NOT

REQUIRE ACCESS FOR MAINTENANCE. ON SIDES WHICH DO REQUIRE ACCESS FOR

MAINTENANCE AND INSPECTION, THE BASE SHALL EXTEND A MINIMUM OF 42" PAST

THE OUTER MOST EDGE OF THE GENERATOR SET / ENCLOSURE.

NOTE: IF A PLATFORM(S) ARE REQUIRED TO ACCESS OVERCURRENT PROTECTION

DEVICES, THEN THE BASE SHALL EXTEND A MINIMUM OF 6" PAST THE EDGE OF

THE PLATFORM.

#4's CONT. @ 12" O.C.

EA. WAY

PAD TO DRAIN

#4's @ 12" O.C.

EA. WAY

8" COMPACTED GRANULAR

FILL ON SUITABLE SUBGRADE

CAST IN-PLACE CONCRETE PAD.

4000 PSI W/ 6% ENTRAINED AIR.

PROVIDE LIGHT BROOM FINISH.

3 WIDE BY 3 DEEP DUCTBANK DETAIL

NO SCALE

MASONRY LEVELING

BLOCKS AT BASE

SPACERS AS NEEDED

BASE AND INTERMEDIATE

SPACERS 48" ON CENTER

SCHED 40 PVC CONDUIT

RACEWAY (TYPICAL)

4000 PSI

CONCRETE

#4 REBAR. TYPICAL.

#4 REBAR. TYPICAL.

18" ON CENTER

3" MINIMUM SEPARATION.

TYPICAL.

3" MINIMUM.

TYPICAL.

3" MINIMUM

SEPARATION.

TYPICAL.

1-1/2" MINIMUM

SEPARATION.

TYPICAL.

FINISHED GRADE

DUCTBANK

MARKING TAPE.

TYPICAL.EQUAL

EQUAL

M

IN

IM

U

M

#4 REBAR. TYPICAL.

1' - 6"

6" DIA. GALV. STANDARD

STEEL POST, FILL W/

CONCRETE (PAINT BRIGHT YELLOW)

SEALANT OVER 1/2"

EXPANSION JOINT IN

ASPHALT PAVEMENT

FIBER REINFORCED

CONCRETE FOUNDATION

COAT STEEL W/ BITUMINOUS

PAINT BELOW GRADE

COMPACTED #53 STONE BASE

COMPACTED SUBGRADE OR

BACKFILL, 96% MAX. DENSITY

CROWN CONCRETE FILL

REFLECTIVE BOLLARD TAPE

(2 BANDS) - TYPE 1, BY

REFLECTIVE INC.

CONCRETE WASH

NO SCALE

DETAIL - CONCRETE FILLED

PROTECTION BOLLARD

R E

NI

G

NEAN L

OI

S

E

S

F O R P

E

KENTU

C

K Y

FO

ET

A T S

D

ESNE

L I C

BROCKMAN

18703

J.

A T T

M

HE

W

REVISION HISTORY OF THIS DRAWING

DRAWING NO.

AS-BUILT DATE

DECA LOG #

DESCRIPTION OF REVISIONS DATE

DESCRIPTION OF REVISIONS DATE

DRAWING INFORMATION

A & E FILE NO.

DRAWN BY

CHECKED BY

PHASE

RTA DATE

COMMONWEALTH OF KENTUCKY

FINANCE AND ADMINISTRATION CABINET

DEPARTMENT FOR FACILITIES AND SUPPORT SERVICES

DIVISION OF ENGINEERING AND CONTRACT ADMINISTRATION

FRANKFORT, KENTUCKY

ACCOUNT NO.

DRAWING DATE

470-CB72-OC33-00

6/28/2024

06/28/2024

/1

/2

:1 :4

P

M

KCTCS - SWITCHGEAR REPLACEMENT - OWENSBORO COMMUNITY &

TECHNICAL COLLEGE - DOWNTOWN CAMPUS

MJB

6/28/2024

MJB

SITE ELECTRICAL PLAN

E1.0

2401-116

"C" - RTA

1" = 30'-0"

SITE ELECTRICAL PLAN

5'0' 15' 30'

1''=30'-0''

True North

Plan North

Approximate

NOTE: THIS PAD DETAIL WAS FURNISHED TO HAFER BY OMU AND IS INCLUDED ON THIS DRAWING FOR CONTRACTOR'S USE IN THE BIDDING PROCESS. ALL INSTALLATION SHALL BE IN ACCORDANCE WITH OMU. CONTRACTOR SHALL BE RESPONSIBLE FOR COORDINATING ALL REQUIREMENTS WITH OMU PRIOR TO START OF DEMOLITION AND NEW CONSTRUCTION.

ADDENDUM NO. 1 7/22/2024

Addendum One
Addendum No. 1 Verbage Letter wattached Revised Dwg E1.0 Rev 1
Addendum No. 1 Verbage Letter
E1.0 Rev 1 - SITE ELECTRICAL PLAN

File details come from the government source that posted it. Updated .