Addendum - No. 1.pdf

PDF 538 KB Posted

Attached to
Outside Elevator Maintenance & Repairs Contract Open-End PCC
Solicitation number
ARFQ 0608 DCR2200000118 2
Issued by
Summers County, West Virginia

About this file

This is an addendum to a Request for Quotes (RFQ) issued by the West Virginia Department of Culture and Resources (WVDCR) for Outside Elevator Maintenance & Repairs services (Solicitation Number: ARFQ - DCR2200000118). Addendum No. 1, revised on October 22, 2020, modifies three key aspects of the original solicitation: the bid closing date has been extended to April 1, 2022 at 4:00 PM EST, with bids opening on April 4, 2022 at 10:00 AM EST. The addendum attaches vendor questions and agency responses regarding contract requirements, as well as mandatory pre-bid sign-in sheets. The contract requires maintenance and repair services for three lifts or platforms, including bi-annual inspections and bi-annual preventive maintenance activities.

The addendum clarifies that vendors must cover all costs associated with third-party inspections as warranted and obtain prior agency approval before engaging any inspectors. Vendors are prohibited from subcontracting services without agency approval. Within 30 days of contract award, the selected vendor must submit a proposed preventive maintenance schedule for agency approval, detailing all inspections, lubrications, adjustments, tests, cleaning, and routine repairs. All provisions of the original solicitation remain in effect except as modified by this addendum. Vendors must acknowledge receipt of all addenda by completing the Addendum Acknowledgment Form and submitting it with their bid, as failure to do so may result in bid disqualification.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Revised 6/8/2012

SOLICITATION NUMBER: [Insert RFQ, RFP No.] Addendum Number: [Insert Number]

The purpose of this addendum is to modify the solicitation identified as [insert RFQ, RFP No.] (“Solicitation”) to reflect the change(s) identified and described below.

Applicable Addendum Category:

[ ] Modify bid opening date and time

[ ] Modify specifications of product or service being sought

[ ] Attachment of vendor questions and responses

[ ] Attachment of pre-bid sign-in sheet

[ ] Correction of error

[ ] Other

Description of Modification to Solicitation:

Additional Documentation: Documentation related to this Addendum (if any) has been included herewith as Attachment A and is specifically incorporated herein by reference.

Terms and Conditions:

1. All provisions of the Solicitation and other addenda not modified herein shall remain in full force and effect.

2. Vendor should acknowledge receipt of all addenda issued for this Solicitation by completing an Addendum Acknowledgment, a copy of which is included herewith.

Failure to acknowledge addenda may result in bid disqualification. The addendum acknowledgement should be submitted with the bid to expedite document processing.

ATIACHMBNT A

Addendum - #1

ARFQ DCR2200000118

Outside Elevator Maintenance & Repairs - PCC Question and Answer

Q1) Please confirm the cost of the third-party inspection is to be covered by the vendor under this contract?

A1) YES, if warranted any third party inspections shall be covered under this contract at Vendor's Expense; Vendor must also obtain prior approval from the Agency for any such inspections; See specifications section 4.1.1.10

- Vendor shall not subcontract any services performed under this contract without approval by Agency.

Q2) Per section 4.1.2.1, please confirm bi-annual inspections are required under this contract?

A2) YES, Vendor shall perform Bi-Annual inspections on all three lifts/ platforms.

Q3) Per section 4.1.3.2, please confirm bi-annual preventive maintenance is to be performed under this contract?

A3) YES, Agency confirms Vendor shall perform preventative maintenance on a Bi-Annual basis NOT QUARTERLY, Vendor shall submit a proposed schedule of all preventative maintenance within 30 days of Vendor being awarded a contract, for approval by Agency. The proposed schedule must include inspections, lubrications, adjustments, tests, cleaning, routine repairs, and all other known preventative maintenance activities.

Revised 10/22/2020 - WVDCR

ADDENDUM ACKNOWLEDGEMENT FORM

SOLICITATION NO.: ARFQ - DCR2200000118

Instructions: Please acknowledge receipt of all addenda issued with this solicitation by completing this addendum acknowledgment form. Check the box next to each addendum received and sign below. Failure to acknowledge addenda may result in bid disqualification. Acknowledgment: I hereby acknowledge receipt of the following addenda and have made the necessary revisions to my proposal, plans and/or specification, etc.

Addendum Numbers Received:

(Check the box next to each addendum received)

Addendum No. 1 Addendum No. 6 Addendum No. 2 Addendum No. 3 Addendum No. 4

Addendum No. 7 Addendum No. 8 Addendum No. 9

Addendum No. 5 Addendum No. 10

I understand that failure to confirm the receipt of addenda may be cause for rejection of this bid. I further understand that any verbal representation made or assumed to be made during any oral discussion held between Vendor’s representatives and any state personnel is not binding. Only the information issued in writing and added to the specifications by an official addendum is binding.

Company

Authorized Signature

Date

NOTE: This addendum acknowledgement should be submitted with the bid to expedite document processing.

Text1: ARFQ - DCR2200000118
Text2: 01
Check Box4: Yes
Check Box5: Off
Check Box6: Yes
Check Box7: Yes
Check Box8: Off
Check Box9: Off
Text3: Addendum 01 is issued to reflect three (3) changes:

1) MODIFY THE BID CLOSING & OPENING DATES;

New Bid Closing Date - APRIL 1, 2022 (04/01/2022) @ 4:00pm EST New Bid Opening Date - APRIL 4, 2022 (04/04/2022) @10:00am EST

2) ATTACH VENDOR QUESTIONS & AGENCY RESPONSES

3) ATTACH MANADATORY PRE-BID SIGN IN SHEETS

Addendum No 1: Off
Addendum No 2: Off
Addendum No 3: Off
Addendum No 4: Off
Addendum No 5: Off
Addendum No 6: Off
Addendum No 7: Off
Addendum No 8: Off
Addendum No 9: Off
Addendum No 10: Off
Company_2:
Authorized_2:
Signature_2:
Date_2:

File details come from the government source that posted it. Updated .