This document is an Addendum #1 issued by the Huntsville, Alabama Finance Department's Procurement Services Division for Invitation for Bids #79-2025-55, specifically for Periodic Asphalt and Construction Projects 2025. The bid is scheduled to open on September 4, 2025, at 2:00:00 PM CDT, with key modifications to the original solicitation including updates to the Appendix C Supplement – Schedule of Bid Quantities. Specifically, the addendum removes language requiring 15% Rap in Open Graded Friction Courses (OGFCs), eliminates bid pricing for a specific line item, and modifies asphalt section language to allow regular coat application to all OGFCs at a rate of 0.20 to 0.25 gallons per square yard.

Proposers are required to acknowledge receipt of this addendum in the designated space on the proposal form (Appendix B), with a warning that failure to do so may result in the bid being deemed non-responsive. An Excel spreadsheet titled 'App C Supp – Revised and Published 08.21.2025' accompanies the addendum with the specific quantity and specification changes. The addendum emphasizes that all other requirements of the original Invitation for Bids remain unchanged, ensuring potential bidders understand the scope and nature of the modifications to the original solicitation.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Finance Department Procurement Services Division

PO Box 308 • Huntsville, Alabama 35804-0308 • Phone 256-427-5060 • FAX 256-427-5059 www.hsvcity.com

ADDENDUM #1 ISSUED: August 21, 2024

NAME OF BID: Periodic Asphalt and Construction Projects 2025

INVITATION FOR BIDS: #79-2025-55 OPENING DATE: September 4, 2025 @ 2:00:00 PM CDT

The above references solicitation is hereby amended as follows:

• Updates and Issues a Revised Appendix C Supplement – Schedule of Bid Quantities to correct the Bid Quantities.

o Line 3 – Removes language requiring 15% Rap in OGFCs o Line 34 – Removes quantity and unit of measure; a bid pricing is not required for this line item o Modified the language in the Asphalt section header to allow regular coat to be applied to all OGFCs at a rate of .20 to .25 gallons per square yard

• See Excel spreadsheet titled ‘App C Supp –– Revised and Published 08.21.2025’

PROPOSERS SHALL ACKNOWLEDGE RECEIPT OF ALL ADDENDA IN THE SPACE PROVIDED ON THE PROPOSAL FORM (APPENDIX B). FAILURE TO ACKNOWLEDGE RECEIPT OF ADDENDA SHALL NOT RELIEVE PROPOSER

OF FULL RESPONSIBILITY FOR ALL REQUIREMENTS CONTAINED IN ADDENDA AND MAY RESULT IN BID

BEING DEEMED NONRESPONSIVE.

REQUIREMENTS OF THE IFB NOT OTHERWISE ADDRESSED HEREIN REMAIN UNCHANGED.

ADDENDUM #1 ISSUED: August 21, 2024