This document is a price submittal form for Phase 10 of the interior renovation project for One Griffin Center in Griffin, Georgia. The project is being solicited by the City of Griffin and will involve renovations to the water/wastewater and remaining hallway areas of the 4-floor facility. The renovation work will be completed in multiple phases to allow the building to remain operational during construction. Key items include demolition, installation of new ceilings, lighting, HVAC, flooring, walls, and doors, as well as various electrical, plumbing, and ADA accessibility upgrades. The project must be completed in the specified phased approach, with each phase finished before moving to the next.
The price submittal form provides a detailed line-item list of the required work, materials, and labor for Phase 10. Pricing is requested for items such as dumpster rentals, demolition, relocation of building systems, new construction, flooring, ceilings, painting, and ADA signage. Contractors will need to provide time and material estimates for electrical, carpentry, and plumbing work as well. The City has specified required materials, and contractors should include costs for any additional materials or equipment needed to complete the scope of work. Funding for the overall project is provided through the City of Griffin.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Copy of Addendum 10 forza group.xlsx | XLSX spreadsheet | |
| Addendum _2 _ One Griffin Center Remodel Cont.pdf | ||
| OGC Reno _ Ex B _ Price Spreadsheet.xlsx | XLSX spreadsheet | |
| 25_005 Addendum _7.pdf | ||
| 25_005 Addendum _10.xlsx | XLSX spreadsheet | |
| 25_005 Addendum _9.pdf | ||
| OGC Reno _ Ex A _ Phases_Description.docx | DOCX document | |
| Copy of 25_005 Addendum _11.xlsx | XLSX spreadsheet | |
| FINAL REVISED PERMIT SET.pdf | ||
| EXIBIT D _ ADA SIGNAGE.docx | DOCX document | |
| Pre_Bid Sign In sheet for Bid _ 25_005.pdf | ||
| Updated Pricing Sheet 11_14_24.xlsx | XLSX spreadsheet | |
| 25_005 Addendum _6.pdf | ||
| 25_005 Addendum _8.pdf | ||
| COMPLETE PERMIT SET.pdf | ||
| Addendum _ 4 _ Asbestos Summary and Lab Repor.pdf | ||
| Forza Group Answers to Questions 11_18_24.pdf | ||
| 25_005 _ OGC Renovation Bid M_E_ 10_28_24.docx | DOCX document | |
| 25_005 Addendum _3__ Pre_Bid Questions and A.pdf | ||
| 25_005 Addendum _5.pdf | ||
| 25_005 Addendum _1.pdf |
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PHASE 10
RFP# 25-005 PRICE SUBMITTAL FORM --- ONE GRIFFIN CENTER INTERIOR RENOVATIONS
PHASE 10 -- WATER / WASTE WATER & REMAINING HALLWAYS
| ITEM NUMER | ITEM DESCRIPTION | UNIT | QUANTITY | UNIT COST | TOTAL COST |
| 1 | CONSTRUCTION WASTE DISPOSAL - DUMPSTER 40 YARD | EA | 4 | ||
| 2 | DEMOLITION - REMOVAL OF EXHISTING ACOUSTICAL CEILING TILES AND FRAMES | SQFT | 6128 | ||
| 3 | DEMOLILTION - REMOVAL OF ALL FLOORING INCLUDING GLUE | SQFT | 6128 | ||
| 4 | RELOCATION - ELECTRICAL - SINGLE POLE LIGHT SWITCHES | EA | 5 | ||
| 5 | RELOCATING - ELECTRICAL - DOUBLE ELECTRICAL OUTLETS | EA | 15 | ||
| 6 | RELOCATING - ELECTRICAL - QUAD ELECTRICAL OUTLETS | EA | 2 | ||
| 7 | DEMOLITION - METAL STUD WALLS | FT | 100 | ||
| 8 | RELOCATING - HVAC - THERMOSTATS | EA | 6 | ||
| 9 | RELOCATING - IT DATA - CAT 6 MODULAR JACK | EA | 15 | ||
| 10 | DEMOLITION - REMOVAL OF INTERIOR DOORS AND FRAMES | EA | 3 | ||
| 11 | DEMOLITOIN - REMOVAL OF WALLPAPER | SQFT | 900 | ||
| 12 | REPLACING OF LIGHT FIXTURES WITH 2X4 LIGHT FIXTURES | EA | 72 | ||
| 13 | REPLACING OF EMERGENCY LIGHT FIXTURES TO 2X4 (QUANTITY INCLUDES 2X2 AND 2X4) | EA | 6 | ||
| 14 | REMOVAL OF UNUSED HVAC LINES & ELECTRICAL CONDUIT NOT IN USE FROM CEILING AREA | EA | 1 | ||
| 15 | INSTALLATION - FRAMING OF NEW WALL | FT | 100 | ||
| 16 | SHEETROCK HANGING AND FINISHING - INCLUDING FINISHING WHERE WALL PAPER WAS REMOVED | SQFT | 6128 | ||
| 17 | REMOVE AND INSTALL - FIRE SAFETY DEVICES - SMOKE DETECTORS IN NEW ENG TILE | EA | 10 | ||
| 18 | INSTALLATION OF NEW ACOUSTICAL CEILING - WHITE 2X2 GRID PATTERN | SQFT | 6128 | ||
| 19 | PAINTING - INCLUSIVE OF SHEETROCK PREP -- 2 COATS | SQFT | 6128 | ||
| 20 | INSTALLATION OF COMMERCIAL GRADE CARPET | SQFT | 6128 | ||
| 21 | INSTALLATION OF NEW ACOUSTICAL CEILING TILES | SQFT | 6128 | ||
| 22 | RELOCATING - FIRE SAFETY DEVICES - FIRE PULL HANDLE | EA | 2 | ||
| 23 | RELOCATING - HVAC VENTS WITH 2X2 GRILLS WITHIN SAME SPACIAL AREA AS ORIGINAL PLACEMENT | EA | 15 | ||
| 24 | INSTALLATION - HVAC MISC PARTS NEEDED FOR PHASE | EA | 1 | ||
| 25 | INSTALLATION - IT DATA - CAT 6 CABLE PURCHASE 1000' BOX | EA | 1 | ||
| 26 | INSTALLATION OF NEW 6" RUBBER COVE BASE | SQFT | 6128 | ||
| 27 | INSTALLATION OF INTERIOR DOORS AND FRAMES - REUSED FROM DEMO | EA | 2 | ||
| 28 | INSTALLATION OF STRIKE PLATES AT DOORS - INCLUDING POWER, LOOPS AND ALL HARDWARE | EA | 1 | ||
| 29 | ELECTRICAL - PURCHASE OF NEW WIRE 100' ROLLS | EA | 3 | ||
| 30 | ELECTRICAL - MISC SUPPLIES NEEDED FOR PHASE | CLF | 1 | ||
| 31 | ELECTRICAL - 3/4" CONDUIT EMT AND CONNECTORS | LF | 110 | ||
| 32 | LABOR - ELECTRICIAN | TOTAL TIME | |||
| 33 | LABOR - CARPENTER | TOTAL TIME | |||
| 34 | LABOR - ON STIE PROJECT MANAGER | TOTAL TIME | |||
| 35 | RAM BOARD 100' ROLLS INCLUDING TAPE FOR FLOOR PROTECTION - MUST BE MAINTAINED | EA | 4 | ||
| 36 | FURNITURE MOVING AND RELOCATING IN OFFICE AREAS | EA | 1 | ||
| 37 | HAGAR DOOR HANDLE SETS | EA | 2 | ||
| 38 | AIR SCRUBBER - IF NEEDED | EA | 2 | ||
| 39 | FLEXIBLE SELF LEVELING UNDERLAYMENT IF NEEDED FOR FLOORING | SQFT | 3516 | ||
| 40 | REPLACEMENT - HVAC -REPLACE LINEAR DIFFUSERS WITH 2X2 A/C VENT | EA | 40 | ||
| 41 | INSTALLATION OF ADA HANDICAP PUSH BUTTON DOOR OPENER (SET TO INCLUDE INT & EXT OF DOORWAY) | SET | 1 | ||
| 42 | REPLACE LIT EXIT LIGHTS | EA | 4 | ||
| 43 | TESTING OF FIRE ALARM SYSTEM FOR PROPER OPERATION | EA | 1 | ||
| 44 | REPLACE WATER FOUNTAIN WITH WATER FOUNTAIN BOTTLE FILLER COMBO | EA | 1 | ||
| 45 | ADA - UNISEX RESTROOM HANDICAP SIGN | EA | 2 | ||
| 46 | ADA - INCASE OF FIRE US STAIRS SIGN | EA | 2 | ||
| 47 | ADA - STAIRS SIGN (PLACEMENT OUTSIDE OF STAIRS) | EA | 3 | ||
| 48 | ADA - EXIT STAIRS SIGN (PLACEMENT INSIDE STAIRWELL) | EA | 1 | ||
| 49 | ADA - EXIT STAIRS SIGN (PLACEMENT INSIDE STAIRWELL ON LEVEL 2) | EA | 2 | ||
| 50 | ADA - EXIT STAIR DOWN SIGN ( PLACEMENT INSIDE STAIRWELL) | EA | 2 | ||
| 51 | ABATEMENT PROCESS | LUMP SUMP | |||
| 51 | LABOR - PLUMBER | TOTAL TIME | |||
| 52 | PVC SHUT OFF FOR SINK & WATER FOUNTAIN IN CHASE | EA | 4 | ||
| 53 | CLOSET VALVE FOR SINK | EA | 2 | ||
| 54 | SINGLE BOWL KITCHEN SINK | EA | 1 | ||
| 55 | KITCHEN FAUCET IN CHROME | EA | 1 | ||
| 56 | P TRAP FOR SINK | EA | 1 | ||
| 57 | 8' PVC DRAIN LINE | FT | 8 | ||
| 58 | COUPLER FOR DRAINLINE | EA | 2 | ||
| 59 | BLUE - PEX TUBE | FT | 14 | ||
| 60 | RED - PEX TUBE | FT | 10 | ||
| 61 | PEX COUPLERS | EA | 6 | ||
| 62 | VINYL TUBING FOR WATERFOUNTAIN | FT | 6 | ||
| 63 | FLEX LINE DRAIN TUBE FOR SINK | FT | 6 |
TOTAL
PHASE 9
RFP# 25-0005 PRICE SUBMITTAL FORM --- ONE GRIFFIN CENTER INTERIOR RENOVATIONS
PHASE 9 -- FINANCE & CONFERENCE ROOM
| ITEM NUMER | ITEM DESCRIPTION | UNIT | QUANTITY | UNIT COST | TOTAL COST |
| 1 | CONSTRUCTION WASTE DISPOSAL - DUMPSTER 40 YARD | EA | 4 | ||
| 2 | DEMOLITION - REMOVAL OF EXSHISTING ACOUSTICAL CEILING TILES AND GRID | SQFT | 4212 | ||
| 3 | DEMOLITION REMOVAL OF ALL FLOORING INCLUDING GLUE | SQFT | 4212 | ||
| 4 | RELOCATING - ELECTRICAL - SINGLE POLE LIGHT SWITCHES | EA | 18 | ||
| 5 | RELOCATING - ELECTRICAL - DOUBLE ELECTRICAL OUTLETS | EA | 40 | ||
| 6 | RELOCATING - ELECTRICAL - QUAD ELECTRICAL OUTLETS | EA | 3 | ||
| 7 | DEMOLITION - METAL STUD WALL | FT | 220 | ||
| 8 | RELOCATING - HVAC - THERMOSTATS | EA | 9 | ||
| 9 | RELOCATING - IT DATA - CAT 6 MODULAR JACK | EA | 14 | ||
| 10 | DEMOLITION - REMOVAL OF INTERIOR DOORS AND FRAMES | EA | 10 | ||
| 11 | DEMOLITION - REMOVAL OF WALLPAPER | SQFT | 4212 | ||
| 12 | REPLACING 6LIGHT FIXTURES WITH 2X4 LIGHT FIXTURES | EA | 66 | ||
| 13 | REPLACING OF EMERGENCY LIGHT FIXTURES TO 2X4 (QUANTITY INCLUDES 2X2 AND 2X4) | EA | 6 | ||
| 14 | REMOVAL OF UNUSED HVAC LINES & ELECTRICAL CONDUIT NOT IN USE FROM CEILING AREA | EA | 1 | ||
| 15 | INSTALLATION - FRAMING NEW WALLS | FT | 300 | ||
| 16 | SHEETROCK HANGING AND FINISHING - INCLUDING FINISHING WHERE WALL PAPER WAS REMOVED | SQFT | 4212 | ||
| 17 | REMOVE AND INSTALL - FIRE SAFETY DEVICES - SMOKE DETECTORS IN NEW CEILING TILE | EA | 15 | ||
| 18 | INSTALLATION OF NEW ACOUSTICAL CEILING GRID - WHITE 2X2 GRID PATTERN | SQFT | 4212 | ||
| 19 | PAINTING - INCLUSIVE OF SHEETROCK PREP -- 2 COATS | SQFT | 4212 | ||
| 20 | INSTALLATION OF COMMERCIAL GRADE CARPET | SQFT | 4212 | ||
| 21 | INSTALLATION OF NEW ACOUSTIC CEILING TILES | SQFT | 4212 | ||
| 22 | RELOCATING - FIRE SAFETY DEVICE - FIRE PULL HANDLE | EA | 2 | ||
| 23 | RELOCATING - HVAC VENTS WITH 2X2 GRILLS WITHIN SAME SPACIAL AREA AS ORIGINAL PLACEMENT | EA | 15 | ||
| 24 | INSTALLATION - HVAC - MISC PARTS NEEDED FOR PHASE | EA | 1 | ||
| 25 | INSTALLATION - IT DATA - CAT 6 CABLE PURCHASE 1000' BOX | EA | 1 | ||
| 26 | INSTALLATION OF NEW 6" VINYL COVE BASE | SQFT | 4212 | ||
| 27 | INSTALLATION OF INTERIOR DOORS AND FRAMES - REUSE FROM DEMO | EA | 10 | ||
| 28 | INSTALLATION OF STRIKE PLATES AT DOORS - INCLUDING POWER, LOOPS AND ALL HARDWARE | EA | 1 | ||
| 29 | ELECTRICAL - NEW WIRE 100' ROLLS | EA | 6 | ||
| 30 | ELECTRICAL - MISC SUPPLIES FOR PHASE | CLF | 30 | ||
| 31 | ELECTRICAL - 3/4" CONDUIT EMT AND CONNECTORS | LF | 110 | ||
| 32 | LABOR - ELECTRICIAN | TOTAL TIME | |||
| 33 | LABOR - CARPENTER | TOTAL TIME | |||
| 34 | LABOR - ON SITE PROJECT MANAGER | TOTAL TIME | |||
| 35 | RAM BOARD 100' ROLLS AND TAPE FOR FLOOR PROTECTION - MUST BE MAINTAINED | EA | 4 | ||
| 36 | FURNITURE MOVING AND RELOCATING IN OFFICE AREAS | EA | 1 | ||
| 37 | HAGAR DOOR HANDLE SETS | EA | 3 | ||
| 38 | AIR SCRUBBER - IF NEEDED | EA | 2 | ||
| 39 | FLEXIBLE SELF LEVELING UNDERLAYMENT IF NEEDED FOR FLOORING | SQFT | 3516 | ||
| 40 | REPLACEMENT - HVAC - LINEAR DIFFUSERS TO 2X2 A/C VENT | EA | 18 | ||
| 41 | PURCHASE OF NEW DOORS AND FRAMES NEEDED | EA | 2 | ||
| 42 | INSTALLATION OF ADA HANDICAP PUSH BUTTON DOOR OPENER (SET TO INCLUDE INT & EXT OF DOORWAY) | SET | 1 | ||
| 43 | GLASS WALL PURCHASE AND INSTALLATION - CONFERENCE ROOM AND OFFICE WALL | EA | 1 | ||
| 44 | LAMINATED COUNTER TOP FOR CONFERENCE ROOM - 2' WIDE | SQFT | 40 | ||
| 45 | 1X8 TOUNGE AND GROOVE ACCENT WALL INSTALLATION AND STAINING | EA | 1 | ||
| 46 | ELECTRICAL - ACCENT LIGHTING IN CONFERENCE ROOM | EA | 6 | ||
| 47 | ELECTRICAL - CAN LIGHTS IN CONFERENCE ROOM | EA | 10 | ||
| 48 | GLASS DOORS PURCHASE AND INSTALL - 1 SINGLE - 1 DOUBLE | EA | 3 | ||
| 49 | ABATEMENT PROCESS | LUMP SUM |
TOTAL
PHASE 8
RFP# 25-005 PRICE SUBMITTAL FORM --- ONE GRIFFIN CENTER INTERIOR RENOVATIONS
PHASE 8 -- CITY MANAGERS OFFICES
ITEM NUMER ITEM DESCRIPTION UNIT QUANTITY UNIT COST TOTAL COST
| 2 | CONSTRUCTION WASTE DISPOSAL - DUMPSTER 40 YARD | EA | 1 |
| 3 | DEMOLITION - REMOVAL OF ALL FLOORING INCLUDING GLUE | SQFT | 1800 |
| 4 | REPLACING OF LIGHT FIXTURES WITH 2X4 LIGHT FIXTURES | EA | 28 |
| 5 | REPLACING OF EMERGENCY LIGHT FIXTURES TO 2X4 (QUANTITY INCLUDES 2X2 AND 2X4) | EA | 3 |
| 6 | PAINTING - INCLUSIVE OF SHEETROCK PREP -- 2 COATS | EA | 2400 |
| 7 | INSTALLATION OF COMMERCIAL GRADE CARPET | SQFT | 1800 |
| 8 | INSTALLATION OF NEW 6" RUBBER COVE BASE | SQFT | 1800 |
| 9 | RAM BOARD 100' ROLLS AND TAPE FOR FLOOR PROTECTION - MUST BE MAINTAINED | EA | 4 |
| 10 | FURNITURE MOVING AND RELOCATING IN OFFICE AREAS | EA | 1 |
| 11 | FLEXIBLE SELF LEVELING UNDERLAYMENT IF NEEDED FOR FLOORING | SQFT | 3516 |
| 12 | REPLACEMENT - HVAC - LINEAR DIFFUSERS WITH 2X2 A/C VENT | EA | 20 |
| 13 | REPLACING - ELECTRICAL - CAN LIGHTING TO LED CAN LIGHTS | EA | 14 |
| 14 | LABOR - ELECTRICIAN | TOTAL TIME | |
| 15 | LABOR - CARPENTER | TOTAL TIME | |
| 16 | LABOR - ON SITE PROJECT MANAGER | TOTAL TIME | |
| 17 | ABATEMENT PROCESS | LUMP SUM |
TOTAL
PHASE 7
RFP# 25-005 PRICE SUBMITTAL FORM --- ONE GRIFFIN CENTER INTERIOR RENOVATIONS
PHASE 7 -- HUMAN RESOURCES
| ITEM NUMER | ITEM DESCRIPTION | UNIT | QUANTITY | UNIT COST | TOTAL COST |
| 1 | CONSTRUCTION WASTE DISPOSAL - DUMPSTER 40 YARD | EA | 3 | ||
| 2 | DEMOLITION - REMOVAL OF EXHISTING ACOUSTICAL CEILING TILES AND GRID | SQFT | 3274 | ||
| 3 | DEMOLITION - REMOVAL OF ALL FLOORING AND GLUE | SQFT | 3274 | ||
| 4 | RELOCATING - ELECTRICAL - SINGLE POLE LIGHT SWITCH | EA | 7 | ||
| 5 | RELOCATING - ELECTRICAL - DOUBLE ELECTRICAL OUTLET | EA | 8 | ||
| 6 | RELOCATING - ELECTRICAL - QUAD ELECTRICAL OUTLET | EA | 2 | ||
| 7 | DEMOLITION - METAL STUD WALL | FT | 60 | ||
| 8 | RELOCATING - HVAC THERMOSTAT | EA | 2 | ||
| 9 | RELOCATING - IT DATA - CAT 6 MODULAR JACK | EA | 6 | ||
| 10 | DEMOLITION - REMOVAL OF INTERIOR DOORS AND FRAMES | EA | 5 | ||
| 11 | DEMOLITION - REMOVAL OF WALLPAPER | SQFT | 800 | ||
| 12 | REPLACING OF LIGHT FIXTURES WITH 2X4 LIGHT FIXTURES | EA | 41 | ||
| 13 | REPLACING OF EMERGENCY LIGHT FIXTURES WITH 2X4 (QUANTITY INCLUDES 2X2 AND 2X4) | EA | 2 | ||
| 14 | REMOVAL OF UNUSED HVAC LINES & ELECTRICAL CONDUIT NOT IN USE FROM CEILING AREA | EA | 1 | ||
| 15 | INSTALLATION - FRAMING OF NEW WALL | FT | 100 | ||
| 16 | SHEETROCK HANGING AND FINISHING - INCLUDING FINISHING WHERE WALL PAPER WAS REMOVED | SQFT | 3274 | ||
| 17 | REMOVE AND INSTALL - FIRE SAFETY DEVICES - SMOKE DETECTORS IN NEW CEILING TILES | EA | 10 | ||
| 18 | INSTALLATION OF NEW ACOUSTICAL CEILING GRID - WHITE 2X2 GRID PATTERN | SQFT | 3274 | ||
| 19 | PAINTING - INCLUSIVE OF SHEETROCK PREP -- 2 COATS | SQFT | 3274 | ||
| 20 | INSTALLATION OF COMMERCIAL GRADE CARPET | SQFT | 3274 | ||
| 21 | INSTALLATION OF NEW CEILING TILES | SQFT | 3274 | ||
| 22 | RELOCATING - HVAC VENTS WITH 2X2 GRILLS WITHIN SAME SPACIAL AREA AS ORIGINALLY PLACED | EA | 6 | ||
| 23 | INSTALLATION - HVAC MISC PARTS NEEDED | EA | 1 | ||
| 24 | INSTALLATION - IT DATA - CAT 6 CABLE IF NEEDED FOR PHASE 1000' BOX | FT | 1 | ||
| 25 | INSTALATION OF NEW 6" RUBBER COVE BASE | SQFT | 3274 | ||
| 26 | INSTALLATION OF INTERIOR DOORS AND FRAMES - REUSE FROM DEMO | EA | 5 | ||
| 27 | ELECTRICAL - NEW WIRE IF NEEDED FOR PHASE | FT | 400 | ||
| 28 | ELECTRICAL - MISC SUPPLIES | CLF | 10 | ||
| 29 | ELECTRICAL - 3/4" CONDUIT EMT AND CONNECTORS | LF | 110 | ||
| 30 | LABOR - ELECTRICIAN | TOTAL TIME | |||
| 31 | LABOR - CARPENTER | TOTAL TIME | |||
| 32 | LABOR - ON SITE PROJECT MANAGER | TOTAL TIME | |||
| 33 | RAM BOARD 100' ROLLS AND TAPE FOR FLOORING PROTECTION - MUST BE MAINTAINED | EA | 4 | ||
| 34 | FURNITURE MOVING AND RELOCATING IN OFFICE AREAS | EA | 1 | ||
| 35 | HAGAR DOOR HANDLE SETS | EA | 2 | ||
| 36 | AIR SCRUBBER - IF NEEDED | EA | 2 | ||
| 37 | FLEXIBLE SELF LEVELING UNDERLAYMENT IF NEEDED FOR FLOORING | SQFT | 3516 | ||
| 38 | REPLACEMENT - HVAC - REPLACE LINEAR DIFFUSERS WITH 2X2 A/C VENT | EA | 18 | ||
| 39 | LAMINATED COUNTER TOP FOR KNEE WALLS | SQFT | 40 | ||
| 40 | INTERIOR SLIDING WINDOW WITH COUNTER TOP INSTALLED | EA | 1 | ||
| 41 | PURCHASE / INSTALLATION - DOUBLE GLASS DOORS | EA | 1 | ||
| 42 | INSTALLATION OF STRIKE PLATES AT DOORS - INCLUDING POWER, LOOPS AND ALL HARDWARE | EA | 1 | ||
| 43 | ELECTRICAL - 3-1/4" DEPTH, 4-11/16" SQUARE STEEL BOX | EA | 10 | ||
| 44 | ELECTRICAL - 20 AMP, 1 GANG, GFI DUPLES RECEPTACLE ASSEMBLY | EA | 10 | ||
| 45 | ABATEMENT PROCESS | LUMP SUM |
TOTAL
PHASE 6
RFP# 25-005 PRICE SUBMITTAL FORM --- ONE GRIFFIN CENTER INTERIOR RENOVATIONS
PHASE 6 -- CORRIDOR AND HALLWAY
| ITEM NUMER | ITEM DESCRIPTION | UNIT | QUANTITY | UNIT COST | TOTAL COST |
| 1 | CONSTRUCTION WASTE DISPOSAL - DUMPSTER 40 YARD | EA | 1 | ||
| 2 | DEMOLITION - REMOVAL OF ALL CEILING TILES | SQFT | 1076 | ||
| 3 | CEILING GRID PAINTED WHITE AND LEVELED | SQFT | 1076 | ||
| 4 | DEMOLITION - REMOVAL OF WALLPAPER | SQFT | 1076 | ||
| 5 | REPLACING OF LIGHT FIXTURES WITH 2X4 LIGHT FIXTURES | EA | 18 | ||
| 6 | REPLACING OF EMERGENCY LIGHT FIXTURES TO 2X4(QUANTITY INCLUDES 2X2 AND 2X4) | EA | 4 | ||
| 7 | REMOVE AND INSTALL - FIRE PROTECTION DEVICE - SMOKE DETECTOR IN NEW CEILING TILE | EA | 3 | ||
| 8 | PAINTING - INCLUSIVE OF SHEETROCK PREP -- 2 COATS | SQFT | 1076 | ||
| 9 | DEMOLITION - REMOVAL OF ALL FLOORING INCLUDING GLUE | SQFT | 1076 | ||
| 10 | INSTALLATION OF COMMERCIAL GRADE CARPET | SQFT | 1076 | ||
| 11 | INSTALLATION OF NEW ACOUSTICAL CEILING TILES | SQFT | 1076 | ||
| 12 | INSTALLATION OF NEW 6" RUBBER COVE BASE | SQFT | 1076 | ||
| 13 | LABOR - ELECTRICIAN | TOTAL TIME | |||
| 14 | LABOR - CARPENTER | TOTAL TIME | |||
| 15 | LABOR - ON SITE PROJECT MANAGER | TOTAL TIME | |||
| 16 | RAM BOARD 100 ' ROLLS AND TAPE FOR FLOOR PROTECTION - MUST BE MAINTAINED | EA | 4 | ||
| 17 | AIR SCRUBBER - IF NEEDED | EA | 2 | ||
| 18 | REPLACEMENT - HVAC - LINEAR DIFFUSERS WITH 2X2 A/C VENT | EA | 10 | ||
| 19 | REPLACEMENT OF LIT EXIT SIGNS | EA | 3 | ||
| 20 | ADA - HANDICAP MENS RESTROOM SIGN | EA | 1 | ||
| 21 | ADA - HANDICAP WOMENS RESTROOM SIGN | EA | 1 | ||
| 22 | ADA - INCASE OF FIRE USE STAIRS SIGN | EA | 1 | ||
| 23 | ADA - STAIRS SIGN (PLACEMENT OUTSIDE OF STAIRS) | EA | 2 | ||
| 24 | ADA - EXIT STAIR DOWN SIGN (PLACEMENT INSIDE OF STAIRWELL) | EA | 2 | ||
| 25 | ABATEMENT PROCESS | LUMP SUM |
TOTAL
PHASE 5
RFP# 25-005 PRICE SUBMITTAL FORM --- ONE GRIFFIN CENTER INTERIOR RENOVATIONS
PHASE 5 -- PLANNING & DEVELOPMENT - AND HALLWAY
| ITEM NUMER | ITEM DESCRIPTION | UNIT | QUANTITY | UNIT COST | TOTAL COST |
| 1 | CONSTRUCTION WASTE DISPOSAL - DUMPSTER 40 YARD | EA | 4 | ||
| 2 | DEMOLITION - REMOVAL OF EXHISTING ACOUSTICAL CEILING TILES | SQFT | 3620 | ||
| 3 | DEMOLITION - REMOVAL OF ALL FLOORING INCLUDING GLUE | SQFT | 3620 | ||
| 4 | RELOCATING - ELECTRICAL - SINGLE POLE LIGHT SWITCHES | EA | 5 | ||
| 5 | RELOCATING - ELECTRICAL - DOUBLE ELECTRICAL OUTLETS | EA | 8 | ||
| 6 | RELOCATING - ELECTRICAL - QUAD ELECTRICAL OUTLETS | EA | 2 | ||
| 7 | DEMOLITION - METAL STUD WALL | FT | 30 | ||
| 8 | RELOCATING - HVAC - THERMOSTATS | EA | 3 | ||
| 9 | RELOCATING - IT DATA - CAT 6 MODULAR JACK | EA | 4 | ||
| 10 | DEMOLITION - REMOVAL OF DOORS AND FRAMES | EA | 4 | ||
| 11 | REMOVAL OF WALLPAPER | SQFT | 1076 | ||
| 12 | REPLACING OF LIGHT FIXTURES WITH 2X4 LIGHT FIXTURES | EA | 55 | ||
| 13 | REPLACING OF EMERGENCY LIGHT FIXTURES WITH 2X4 (QUANTITY INCLUDEDS 2X2 AND 2X4) | EA | 4 | ||
| 14 | REMOVAL OF UNUSED HVAC LINES & ELECTRICAL CONDUIT NOT IN USE FROM CEILING AREA | EA | 1 | ||
| 15 | INSTALLATION - FRAMING OF NEW WALL | FT | 80 | ||
| 16 | SHEETROCK HANGING AND FINISHING - INCLUDING FINISHING WHERE WALL PAPER WAS REMOVED | SQFT | 200 | ||
| 17 | REMOVE AND INSTALL - FIRE SAFETY DEVICE - SMOKE DETECTOR IN NEW CEILING TILE | EA | 5 | ||
| 18 | ACOUSTICAL CEILING GRID PAINTED WHITE AND LEVELED | SQFT | 3620 | ||
| 19 | PAINTING - INCLUSIVE OF SHEETROCK PREP -- 2 COATS | SQFT | 3620 | ||
| 20 | INSTALLATION OF COMMERCIAL GRADE CARPET | SQFT | 3620 | ||
| 21 | INSTALLATION OF NEW ACOUSTICAL CEILING TILES | SQFT | 3620 | ||
| 22 | RELOCATING - HVAC VENTS WITH 2X2 GRILLS WITHIN SAME SPACIAL AREA AS ORIGINAL PLACEMENT | EA | 8 | ||
| 23 | INSTALLATION - HVAC - MISC PARTS | EA | 1 | ||
| 24 | INSTALLATION - IT DATA - CAT 6 CABLE PURCHASE 1000' BOX | EA | 1 | ||
| 25 | INSTALLATION OF NEW 6" RUBBER COVE BASE | SQFT | 3620 | ||
| 26 | INSTALLATION OF INTERIOR DOORS AND FRAMES - REUSE FROM DEMO | EA | 2 | ||
| 27 | ELECTRICAL - PURCHASE OF NEW WIRE 100' ROLLS | EA | 4 | ||
| 28 | ELECTRICAL - MISC SUPPLIES | CLF | 20 | ||
| 29 | ELECTRICAL - 3/4" CONDUIT EMT AND CONNECTORS | LF | 80 | ||
| 30 | LABOR - ELECTRICIAN | TOTAL TIME | |||
| 31 | LABOR - CARPENTER | TOTAL TIME | |||
| 32 | LABOR - ON SITE PROJECT MANAGER | TOTAL TIME | |||
| 33 | RAM BOARD 100' ROLLS AND TAPE FOR FLOOR PROTECTION - MUST BE MAINTIANED | EA | 4 | ||
| 34 | FURNITURE MOVING AND RELOCATING IN OFFICE AREAS | EA | 1 | ||
| 35 | HAGAR DOOR HANDLE SETS | EA | 2 | ||
| 36 | AIR SCRUBBER - IF NEEDED | EA | 2 | ||
| 37 | FLEXIBLE SELF LEVELING UNDERLAYMENT IF NEEDED FOR FLOORING | SQFT | 3620 | ||
| 38 | REPLACEMENT - HVAC - LINEAR DIFFUSERS WITH 2X2 A/C VENT | EA | 22 | ||
| 39 | INTERIOR GLASS DOORS AND FRAMES PURCHASED - SINGLE - 3'0x7'0 | EA | 1 | ||
| 40 | 1/2 GLASS WALL PURCHASE AND INSTALLATION - 6'HX10'L | EA | 1 | ||
| 41 | LAMINATED COUNTER TOP FOR KNEE WALL 3 FT WIDE - | SQFT | 54 | ||
| 42 | REPLACEMENT OF LIT EXIT SIGNS | EA | 5 | ||
| 43 | TESTING OF FIRE ALARM SYSTEM FOR PROPER OPERATION | EA | 1 | ||
| 44 | ELECTRICAL - 3-1/4" DEPTH, 4-11/16" SQUARE STEEL BOX | EA | 10 | ||
| 45 | ELECTRICAL - 20 AMP, 1 GANG, GFI DUPLEX RECEPTICAL ASSEMBLY | EA | 10 | ||
| 46 | ADA - HANDICAP MENS RESTROOM SIGN | EA | 1 | ||
| 47 | ADA - HANDICAP WOMENS RESTROOOM SIGN | EA | 1 | ||
| 48 | ADA - INCASE OF FIRE USE STAIRS SIGNS | EA | 1 | ||
| 49 | ADA - STAIRS SIGN ( PLACEMENT OUTSIDE STAIRWELL) | EA | 2 | ||
| 50 | ADA - EXIT STAIRS SIGN (PLACEMENT INSIDE STAIRWELL) | EA | 1 | ||
| 51 | ADA - EXIT STAIRS DOWN SIGN (PLACEMENT INSIDE STAIRWELL) | EA | 1 | ||
| 52 | ABATEMENT PROCESS | LUMP SUM |
TOTAL
PHASE 4
RFP# 25-005 PRICE SUBMITTAL FORM --- ONE GRIFFIN CENTER INTERIOR RENOVATIONS
PHASE FOUR -- IT DEPARTMENT & REMAINING HALLWAYS
| ITEM NUMER | ITEM DESCRIPTION | UNIT | QUANTITY | UNIT COST | TOTAL COST |
| 1 | CONSTRUCTION WASTE DISPOSAL - DUMPSTER 40 YARD | EA | 2 | ||
| 2 | DEMOLITION - REMOVAL OF EXHISTING ACOUSTICAL CEILING TILES AND GRID | SQFT | 4869 | ||
| 3 | DEMOLITION - REMOVAL OF ALL FLOORING INCLUDING GLUE | SQFT | 4869 | ||
| 4 | RELOCATING - ELECTRICAL - SINGLE POLE LIGHT SWITCHES | EA | 22 | ||
| 5 | RELOCATIN ELECTRICAL - DOUBLE ELECTRICAL OUTLETS | EA | 55 | ||
| 6 | RELOCATING - ELECTRICAL - QUAD ELECTRICAL OUTLETS | EA | 5 | ||
| 7 | DEMOLITION - METAL STUD WALL | SQFT | 3380 | ||
| 8 | RELOCATING- HVAC - THERMOSTATS | EA | 6 | ||
| 9 | RELOCATING- IT DATA - CAT 6 MODULAR JACK | EA | 40 | ||
| 10 | DEMOLITION - REMOVAL OF INTERIOR DOORS AND FRAMES | EA | 18 | ||
| 11 | REPLACING OF LIGHT FIXTURES WITH 2X4 LIGHT FIXTURES | EA | 75 | ||
| 12 | REPLACING OF EMERGENCY LIGHT FIXTURES TO 2X4 (QUANTITY INCLUDES 2X2 AND 2X4) | EA | 6 | ||
| 13 | REMOVAL OF UNUSED HVAC LINES & ELECTRICAL CONDUIT NOT IN USE FROM CEILING AREA | EA | 1 | ||
| 14 | INSTALLATION - FRAMING OF NEW WALL | SQFT | 3380 | ||
| 15 | SHEETROCK HANGING AND FINISHING - INCLUDING FINISHING WHERE ONLY WALL PAPER WAS REMOVED | SQFT | 4869 | ||
| 16 | REMOVE AND INSTALL - FIRE SAFETY DEVICES - SMOKE DETECTORS IN NEW CEILING TILES | EA | 10 | ||
| 17 | INSTALLATION OF NEW ACOUSTICAL CEILING GRID - WHITE 2X2 GRID PATTERN | SQFT | 4869 | ||
| 18 | PAINTING - INCLUSIVE OF SHEETROCK PREP -- 2 COATS | SQFT | 4869 | ||
| 19 | INSTALLATION OF COMMERCIAL GRADE CARPET | SQFT | 4869 | ||
| 20 | INSTALLATION OF NEW ACOUSTICAL CEILING TILES | SQFT | 4869 | ||
| 21 | RELOCATING - FIRE SAFETY DEVICES - FIRE PULL HANDLE | EA | 6 | ||
| 22 | RELOCATING - HVAC VENTS WITH 2X2 GRILLS WITHIN SAME SPACIAL AREA | EA | 15 | ||
| 23 | INSTALLATION - HVAC MISC PARTS NEEDED | EA | 1 | ||
| 24 | INSTALLATION - IT DATA - CAT 6 CABLE PURCHASE 1000' BOX | FT | 1 | ||
| 25 | INSTALLATION OF NEW 6" RUBBER COVE BASE | SQFT | 4869 | ||
| 26 | INSTALLATION OF INTERIOR DOORS AND FRAMES - REUSED FROM DEMO | EA | 18 | ||
| 27 | INSTALLATION - PURCHASE OF NEW DOORS AND FRAMES - LIKE KIND - FOR OFFICE SPACE | EA | 2 | ||
| 28 | INSTALLATION OF STRIKE PLATES AT DOORS - INCLUDING POWER, LOOPS AND ALL HARDWARE | EA | 1 | ||
| 29 | ELECTRICAL - NEW ELECTRICAL WIRE IF NEEDED FOR PHASE | FT | 1 | ||
| 30 | ELECTRICAL - MISC SUPPLIES NEEDED FOR PHASE | CLF | 14 | ||
| 31 | ELECTRICAL - 3/4" CONDUIT EMT AND CONNECTORS | FT | 113 | ||
| 32 | LABOR - ELECTRICIAN | TOTAL TIME | |||
| 33 | LABOR - CARPENTER | TOTAL TIME | |||
| 34 | LABOR - ON SITE PROJECT MANAGER | TOTAL TIME | |||
| 35 | RAM BOARD 100' ROLLS AND TAPE FOR FLOOR PROTECTION -- MUST BE MAINTAINED | EA | 6 | ||
| 36 | FURNITURE MOVING AND RELOCATING IN OFFICE AREAS | EA | 1 | ||
| 37 | HAGAR DOOR HANDLE SETS | EA | 2 | ||
| 38 | AIR SCRUBBER - IF NEEDED | EA | 2 | ||
| 39 | FLEXIBLE SELF LEVELING UNDERLAYMENT IF NEEDED FOR FLOORING | SQFT | 2268 | ||
| 40 | REPLACEMENT - HVAC - REPLACE LINEAR DIFFUSERS WITH 2X2 A/C VENTS | EA | 17 | ||
| 41 | REPLACING OF WATER FOUNTAIN TO WATER FOUNTAIN BOTTLE FILLER COMBO - STAINLESS | EA | 1 | ||
| 42 | LAMINATED COUNTER TOP - 2' WIDE | FT | 20 | ||
| 43 | REPLACEMENT - LIT EXIT LIGHTS ON FLOOR | EA | 4 | ||
| 44 | ADA - EXIT STAIR UP ( PLACEMENT INSIDE STAIRWELL) | EA | 2 | ||
| 45 | ELECTRICAL - 20 AMP, 1 GANG, GFI DUPLEX RECEPTACLE ASSEMBLY | EA | 12 | ||
| 46 | FIRE ALARM TESTING OF FLOOR FOR CORRECT OPERATION | EA | 1 | ||
| 47 | ELECTRICAL - 3-1/4" DEPTH, 4-11/16" SQUARE STEEL BOX | EA | 12 | ||
| 48 | ADA - UNISEX RESTROOM HANDICAP SIGN | EA | 2 | ||
| 49 | ADA - INSCASE OF FIRE USE STAIRS SIGN | EA | 2 | ||
| 50 | ADA - STAIRWELL SIGN (PLACEMENT OUTSIDE STAIRWELL) | EA | 2 | ||
| 51 | ABATEMENT PROCESS | LUMP SUM | |||
| 51 | BLUE - PEX TUBING | FT | 4 | ||
| 52 | PEX CONNECTORS | EA | 2 | ||
| 53 | VINYL TUBING FOR WATER FOUNTAIN | FT | 6 | ||
| 54 | FLEX DRAIN LINE | FT | 6 | ||
| 55 | PVC SHUT OFF | EA | 2 | ||
| 56 | LABOR - PLUMBER | TOTAL TIME |
TOTAL
PHASE 3
RFP# 25-005 PRICE SUBMITTAL FORM --- ONE GRIFFIN CENTER INTERIOR RENOVATIONS
PHASE THREE -- IT DATA CENTER & TELECOM OFFICES
| ITEM NUMER | ITEM DESCRIPTION | UNIT | QUANTITY | UNIT COST | TOTAL COST |
| 1 | CONSTRUCTION WASTE DISPOSAL - DUMPSTER 40 YARD | EA | 3 | ||
| 2 | DEMOLITION - REMOVAL OF EXHISTING ACOUSTICAL CEILING TILES AND GRID | SQFT | 1000 | ||
| 3 | DEMOLITION - REMOVAL OF ALL FLOORING INCLUDING GLUE | SQFT | 1630 | ||
| 4 | RELOCATING - ELECTRICAL - SINGLE POLE LIGHT SWITCH | EA | 2 | ||
| 5 | RELOCATING - ELECTRICAL - DOUBLE ELECTRICAL OUTLETS | EA | 2 | ||
| 6 | RELOCATING - ELECTRICAL - QUAD ELECTRICAL OUTLETS | EA | 2 | ||
| 7 | DEMOLITION - METAL STUD WALL | FT | 16 | ||
| 8 | RELOCATING - HVAC THERMOSTATS | EA | 1 | ||
| 9 | RELOCATING - IT DATA - CAT 6 MODULAR JACK | EA | 2 | ||
| 10 | DEMOLITION - REMOVAL OF INTERIOR DOORS AND FRAMES | EA | 1 | ||
| 11 | REPLACING LIGHT FIXTURES WITH 2X4 LIGHT FIXTURES | EA | 19 | ||
| 12 | INSTALLATION - FRAMING OF NEW WALL | FT | 24 | ||
| 13 | SHEETROCK HANGING AND FINISHING | FT | 24 | ||
| 14 | REMOVE AND REINSTALL - FIRE SAFETY DEVICE - SMOKE DETECTORS IN NEW CEILING TILES | EA | 4 | ||
| 15 | INSTALLATION OF NEW ACOUSTICAL CEILING GRID - WHITE 2X2 GRID PATTERN | SQFT | 1000 | ||
| 16 | PAINTING - INCLUSIVE OF SHEETROCK PREP -- 2 COATS | SQFT | 1680 | ||
| 17 | INSTALLATION OF COMMERCIAL GRADE CARPET IN OFFICE AREAS | SQFT | 1000 | ||
| 18 | INSTALLATION OF NEW ACOUSTICAL CEILING TILES | SQFT | 1000 | ||
| 19 | INSTALLATION - HVAC MISC PARTS NEEDED | EA | 1 | ||
| 20 | INSTALLATION OF NEW 6: RUBBER COVE BASE | EA | 1680 | ||
| 21 | INSTALLATION OF INTERIOR DOORS AND FRAMES - REUSED FROM DEMO | EA | 1 | ||
| 22 | INSTALLATION OF STRIKE PLATES AT DOORS - INCLUDING POWER, LOOPS AND ALL HARDWARE | EA | 1 | ||
| 23 | ELECTRICAL - MISC SUPPLIES NEEDED FOR PHASE | CLF | 14 | ||
| 24 | ELECTRICAL - 3/4" CONDUIT EMT AND CONNECTORS | LF | 113 | ||
| 25 | LABOR - ELECTRICIAN | TOTAL TIME | |||
| 26 | LABOR - CARPENTER | TOTAL TIME | |||
| 27 | LABOR - ON SITE PROJECT MANAGER | TOTAL TIME | |||
| 28 | RAM BOARD ROLLS AND TAPE TO COVER FLOOR - MUST BE MAINTAINED | EA | 2 | ||
| 29 | FURNITURE MOVING AND RELOCATING IN OFFICE AREAS | EA | 1 | ||
| 30 | HAGAR DOOR HANDLE SETS | EA | 2 | ||
| 31 | AIR SCRUBBER - IF NEEDED | EA | 2 | ||
| 32 | REPLACEMENT - HVAC - REPLACE LINEAR DIFFUSERS WITH 2X2 A/C VENTS | EA | 17 | ||
| 33 | DUST BAGS TO ENCLOSE DATA EQUIPMENT | EA | 10 | ||
| 34 | TATE ACCESS FLOORING - CONCORE 1250 TILES | EA | 46 | ||
| 35 | TATE ACCESS FLOORING - CONCORE 1250 PERFORATED TILES | EA | 4 | ||
| 36 | STRINGERS, PEDESTALS, BORDER CAPS FOR TATE ACCESS FLOORING | EA | 55 | ||
| 37 | RELOCATION OF FM200 FIRE SUPPRESSION SYSTEM | FT | 15 | ||
| 38 | INSTALLATION - ELECTRICAL - NEW WIRE PURCHASE 100' ROLLS | EA | 3 | ||
| 39 | ELECTRICAL - 3-1/4" DEPTH, 4 -11/16" SQUARE BOX | EA | 12 | ||
| 40 | ELECTRICAL - 20 AMP, 1 GANG, GFI DUPLEX RECEPTACLE ASSEMBLY | EA | 12 | ||
| 41 | FLEXIBLE SELF LEVELING UNDERLAYMENT IF NEEDED FOR FLOORING | SQFT | 2268 | ||
| 42 | REPLACING OF EMERGENCY LIGHT FIXTURES TO 2X4 (QUANTITY INCLUDES 2X2 AND 2X4) | EA | 2 | ||
| 43 | ABATEMENT PROCESS | LUMP SUM |
PHASE 2
RFP# 25-005 PRICE SUBMITTAL FORM --- ONE GRIFFIN CENTER INTERIOR RENOVATIONS
PHASE TWO -- GIS STUDIO
| ITEM NUMER | ITEM DESCRIPTION | UNIT | QUANTITY | UNIT COST | TOTAL COST |
| 1 | CONSTRUCTION WASTE DISPOSAL - DUMPSTER 40 YARD | EA | 1 | ||
| 2 | DEMOLITION - REMOVAL OF EXHISTING ACOUSTICAL CEILING TILES AND GRID | SQFT | 1088 | ||
| 3 | DEMOLITION - REMOVAL OF ALL FLOORING INCLUDING GLUE | SQFT | 1088 | ||
| 4 | RELOCATING - ELECTRICAL - SINGLE POLE LIGHT SWITCH | EA | 2 | ||
| 5 | RELOCATING - ELECTRICAL - DOUBLE ELECTRICAL OUTLETS | EA | 10 | ||
| 6 | RELOCATING - ELECTRICAL - QUAD ELECTRICAL OUTLETS | EA | 11 | ||
| 7 | DEMOLITION - METAL STUD WALL | FT | 26 | ||
| 8 | RELOCATING - HVAC - THERMOSTATS | EA | 2 | ||
| 9 | RELOCATING - IT DATA - CAT 6 MODULAR JACK | EA | 7 | ||
| 10 | DEMOLITION - REMOVAL OF INTERIOR DOORS AND FRAMES | EA | 2 | ||
| 11 | DEMOLITION - REMOVAL OF PROJECTOR FILM FROM WALL | FT | 28 | ||
| 12 | REPLACING OF LIGHT FIXTURES WITH 2X4 LIGHT FIXTURES | EA | 18 | ||
| 13 | REPLACING OF EMERGENCY LIGHT FIXTURES TO 2X4 (QUANTITY INCLUDES 2X2 AND 2X4) | EA | 2 | ||
| 14 | REMOVAL OF UNUSED HVAC LINES & ELECTRICAL CONDUIT NOT IN USE FROM CEILING AREA | EA | 1 | ||
| 15 | INSTALLATION - FRAMING OF NEW 1/2 WALL | FT | 12 | ||
| 16 | SHEETROCK HANGING AND FINISHING - INCLUDING FINISHING WHERE PROJECTOR FILM WAS REMOVED | SQFT | 1088 | ||
| 17 | REMOVE AND INSTALL - FIRE SAFETY DEVICES - SMOKE DETECTORS IN NEW CEILING TILE | EA | 2 | ||
| 18 | INSTALLATION OF NEW ACOUSTICAL CEILING GRID - WHITE 2X2 GRID PATTERN | SQFT | 1088 | ||
| 19 | PAINTING - INCLUSIVE OF SHEETROCK PREP -- 2 COATS | SQFT | 1088 | ||
| 20 | INSTALLATION OF COMMERCIAL GRADE CARPET | SQFT | 1088 | ||
| 21 | INSTALLATION OF NEW ACOUSTICAL CEIING TILES | SQFT | 1088 | ||
| 22 | RELOCATION - FIRE SAFETY DEVICES - FIRE PULL HANDLE | EA | 1 | ||
| 23 | RELOCATING - HVAC VENTS WITH 2X2 GRILLS WITHIN SAME SPACIAL AREA AS ORIGINAL PLACEMENT | EA | 5 | ||
| 24 | INSTALLATION - HVAC MISC PARTS NEEDED | EA | 1 | ||
| 25 | INSTALLATION - IT DATA - CAT 6 CABLE PURCHASE 1000' BOX IF NEEDED FOR RENOVATION | FT | 1 | ||
| 26 | INSTALLATION OF NEW 6" RUBBER COVE BASE | SQFT | 1088 | ||
| 27 | INSTALLATION OF INTERIOR DOORS AND FRAMES - REUSED FROM DEMO | EA | 1 | ||
| 28 | ELECTRICAL - NEW ELECTRICAL WIRE 100' ROLLS IF NEEDED FOR RENOVATION | EA | 3 | ||
| 29 | ELECTRICAL - MISC SUPPLIES NEEDED FOR PHASE | CLF | 14 | ||
| 30 | ELECTRICAL - 3/4" CONDUIT EMT AND CONNECTORS | LF | 113 | ||
| 31 | LABOR - ELECTRICIAN | EA | 1 | ||
| 32 | LABOR - CARPENTER | EA | 1 | ||
| 33 | LABOR - ON SITE PROJECT MANAGER | EA | 1 | ||
| 34 | RAM BOARD 100' ROLLS & TAPE TO COVER FLOORING - MUST BE MAINTAINED | EA | 4 | ||
| 35 | FURNITURE MOVING AND RELOCATING IN OFFICE AREAS | EA | 1 | ||
| 36 | HAGAR DOOR HANDLE SETS | EA | 1 | ||
| 37 | AIR SCRUBBER - IF NEEDED | EA | 2 | ||
| 38 | FLEXIBLE SELF LEVELING UNDERLAYMENT IF NEEDED FOR FLOORING | SQFT | 2268 | ||
| 39 | REPLACEMENT - HVAC - LINEAR DIFFUSERS WITH 2X2 A/C VENTS | EA | 17 | ||
| 40 | DEMOLITION - ELECTRICAL - LIGHT SWITCH REMOVAL | EA | 4 | ||
| 41 | LAMINATED COUNTER TOP FOR KNEE WALLS - 2' WIDE | FT | 12 | ||
| 42 | ELECTRICAL - 3-1/4" DEPTH 4-11/16" QUARE STEEL BOX | EA | 12 | ||
| 43 | ELECTRICAL - 20 AMP, 1 GANG, GFI DUPLES RECEPTACLE ASSEMBLY | EA | 12 | ||
| 44 | ABATEMENT PROCESS | LUMP SUM |
EA
TOTAL
PHASE 1
RFP# 25-005 PRICE SUBMITTAL FORM --- ONE GRIFFIN CENTER INTERIOR RENOVATIONS
PHASE ONE -- EOC & PUBLIC WORKS
| ITEM NUMER | ITEM DESCRIPTION | UNIT | QUANTITY | UNIT COST | TOTAL COST |
| 1 | CONSTRUCTION WASTE DISPOSAL - DUMPSTER 40 YARD | EA | 2 | ||
| 2 | DEMOLITION - REMOVAL OF EXHISTING ACOUSTICAL CEILING TILES AND GRID | SQFT | 806 | ||
| 3 | DEMOLITION - REMOVAL OF ALL FLOORING INCLUDING GLUE | SQFT | 1975 | ||
| 4 | RELOCATING - ELECTRICAL -SINGLE POLE LIGHT SWITCHES | EA | 3 | ||
| 5 | RELOCATING - ELECTRICAL - DOUBLE ELECTRICAL OUTLETS | EA | 3 | ||
| 6 | RELOCATING - ELECTRICAL - QUAD ELECTRICAL OUTLETS | EA | 3 | ||
| 7 | DEMOLITION - BLOCK WALLL REMOVAL | FT | 26 | ||
| 8 | DEMOLITION - METAL STUD WALLS | FT | 52 | ||
| 9 | RELOCATING - HVAC - THERMOSTATS | EA | 2 | ||
| 10 | RELOCATING - IT DATA- CAT 6 MODULAR JACK | EA | 12 | ||
| 11 | DEMOLITION -REMOVAL OF INTERIOR DOORS AND FRAMES | EA | 6 | ||
| 12 | DEMOLITION - REMOVAL OF WALLPAPER | SQFT | 300 | ||
| 13 | REPLACING OF LIGHT FIXTURES WITH 2X4 LIGHT FIXTURES | EA | 20 | ||
| 14 | REPLACING OF EMERGENCY LIGHT FIXTURES TO 2X4 (QUANTITY INCLUDES 2X2 AND 2X4) | EA | 3 | ||
| 15 | REMOVAL OF UNUSED HVAC LINES & ELECTRICAL CONDUIT NOT IN USE FROM CEILING AREA | EA | 1 | ||
| 16 | INSTALLATION - FRAMING OF NEW WALL | FT | 12 | ||
| 17 | SHEETROCK HANGING AND FINISHING - INCLUDING FINISHING WHERE WALLPAPER REMOVED | SQFT | 806 | ||
| 18 | REMOVE & INSTALL - FIRE SAFETY DEVICES - SMOKE DETECTORS IN NEW CEILING TILE | EA | 9 | ||
| 19 | INSTALLATION OF NEW ACOUSTICAL CEILING GRID - WHITE 2X2 GRID PATTERN | SQFT | 806 | ||
| 20 | PAINTING - INCLUSIVE OF SHEETROCK PREP -- 2 COATS | SQFT | 806 | ||
| 21 | INSTALLATION OF COMMERCIAL GRADE CARPET | SQFT | 1975 | ||
| 22 | INSTALLATION OF NEW ACOUSTICAL CEILING TILES | SQFT | 806 | ||
| 23 | RELOCATING - FIRE SAFETY DEVICES - FIRE PULL HANDLE | EA | 1 | ||
| 24 | RELOCATING -- HVAC VENTS WITH 2X2 GRILLS WITHIN SAME SPACIAL AREA AS ORIGINAL PLACEMENT | EA | 1 | ||
| 25 | INSTALLATION -- HVAC MISC PARTS NEEDED | EA | 1 | ||
| 26 | INSTALLATION - IT DATA - CAT 6 CABLE PURCHASE 1000' BOX | EA | 1 | ||
| 27 | INSTALLATION OF NEW 6" RUBBER COVE BASE | SQFT | 806 | ||
| 28 | INSTALLATION OF INTERIOR DOORS AND FRAMES - REUSED FROM DEMO | EA | 1 | ||
| 29 | INSTALLATION OF STRIKE PLATES AT DOORS - INCLUDING POWER, LOOPS AND ALL HARDWARE | EA | 1 | ||
| 30 | MATERIALS - RAISED PLATFORM - 12"Hx10'Dx18'L - 2X8 JOIST- 16" OC -1/2" PLYWOOD FLOOR - TRIM OUT PLATFORM | EA | 1 | ||
| 31 | CONSTRUCTION AND INSTALLATION PRICE OF RAISED PLATFORM | EA | 1 | ||
| 32 | SHEETROCK HANGING AND FINISHING - INCLUDING FINISHING WHERE WALLPAPER REMOVED | EA | 1 | ||
| 33 | ELECTRICAL - MISC SUPPLIES NEEDED FOR PHASE | CLF | 14 | ||
| 34 | ELECTRICAL - 3/4" CONDUIT EMT AND CONNECTORS | LF | 113 | ||
| 35 | LABOR - ELECTRICIAN | EA | 1 | ||
| 36 | LABOR - CARPENTER | EA | 1 | ||
| 37 | LABOR - ON SITE PROJECT MANAGER | EA | 1 | ||
| 38 | RAM BOARD 100' ROLLS AND TAPE TO COVER FLOORING - MUST BE MAINTAINED | EA | 4 | ||
| 39 | FURNITURE MOVING AND RELOCATING IN OFFICE AREAS | EA | 1 | ||
| 40 | HAGAR DOOR HANDLE SETS | EA | 2 | ||
| 41 | AIR SCRUBBER - IF NEEDED | EA | 2 | ||
| 42 | FLEXIBLE SELF LEVELING UNDERLAYMENT IF NEEDED FOR FLOORING | SQFT | 2268 | ||
| 43 | REPLACEMENT - HVAC -REPLACE LINEAR DIFFUSERS WITH 2X2 A/C VENTS | EA | 17 | ||
| 44 | INSTALLATION OF ADA HANDICAP PUSH BUTTON DOOR OPENER (SET TO INCLUDE INT & EXT OF DOORWAY) | SET | 2 | ||
| 45 | DEMOLITION - ELECTRICAL - LIGHT SWITCH REMOVAL | EA | 5 | ||
| 46 | INSTALLALTION - ELECTRICAL - NEW ELECTRICAL WIRE 100 ' ROLLS NEEDED FOR PHASE | EA | 2 | ||
| 47 | ELECTRICAL -- 3-1/4" DEPTH 4-11/16" SQUARE BOX | EA | 12 | ||
| 48 | ELECTRICAL - 20 AMP, 1 GANG, GFI DUPLEX RECEPTACLE ASSEMBLY | EA | 12 | ||
| 49 | ABATEMENT PROCESS | LUMP SUM |