About this file
This document is Addendum #9 for the 25-005 One Griffin Center Interior Renovation project, issued by the City of Griffin in Georgia. The addendum provides responses to a question submitted by the Forza Group regarding the lack of plumbing items in the pricing spreadsheet to account for new plumbing items shown in the updated drawings. The overall project scope involves the interior renovation of all four floors within the One Griffin Center facility, with a phased approach due to the building remaining operational during construction.
The pricing spreadsheet does not currently include line items for the new plumbing work, and the addendum indicates that the contractor should capture these costs accordingly. The project is being competitively bid, and work must be completed in a workmanlike manner using the materials and labor as delineated in the contract documents.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Copy of Addendum 10 forza group.xlsx | XLSX spreadsheet | |
| Addendum _2 _ One Griffin Center Remodel Cont.pdf | ||
| Addendum _ 9 _ Updated Price Sheet.xlsx | XLSX spreadsheet | |
| OGC Reno _ Ex B _ Price Spreadsheet.xlsx | XLSX spreadsheet | |
| 25_005 Addendum _7.pdf | ||
| 25_005 Addendum _10.xlsx | XLSX spreadsheet | |
| OGC Reno _ Ex A _ Phases_Description.docx | DOCX document | |
| Copy of 25_005 Addendum _11.xlsx | XLSX spreadsheet | |
| FINAL REVISED PERMIT SET.pdf | ||
| EXIBIT D _ ADA SIGNAGE.docx | DOCX document | |
| Pre_Bid Sign In sheet for Bid _ 25_005.pdf | ||
| Updated Pricing Sheet 11_14_24.xlsx | XLSX spreadsheet | |
| 25_005 Addendum _6.pdf | ||
| 25_005 Addendum _8.pdf | ||
| COMPLETE PERMIT SET.pdf | ||
| Addendum _ 4 _ Asbestos Summary and Lab Repor.pdf | ||
| Forza Group Answers to Questions 11_18_24.pdf | ||
| 25_005 _ OGC Renovation Bid M_E_ 10_28_24.docx | DOCX document | |
| 25_005 Addendum _3__ Pre_Bid Questions and A.pdf | ||
| 25_005 Addendum _5.pdf | ||
| 25_005 Addendum _1.pdf |
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Date: Wednesday, November 18, 2024
Proposal ID Number: 25-005
ADDENDUM # 9 Answers to Forza Group Question submitted 11/18/24
25-005 One Griffin Center Interior Renvoations
ADDENDUM # 9
Question submitted from the Forza Group :
Plumbing added to updated pricing sheet
There are no plumbing items in the pricing spreadsheet to account for the new plumbing items shown in the new drawings. How are we supposed to capture this cost?
Stephen Gibson
Preconstruction Manager c: (678) 588-1190 o: (770) 632-0828 e: sgibson@forzagroup.us
665 Highway 74 South, Suite 100, Peachtree City, GA 30269