Addendum_3_08.19.26.pdf

PDF 6 MB Posted

Attached to
South Campus Building S202 Ceiling Tile Replacement & Corridors Re-Painting
Solicitation number
121-071426JVC-S202
Issued by
Cabarrus County, North Carolina

About this file

This Addendum #3 document, issued by Rowan-Cabarrus Community College in Concord, North Carolina, provides clarifications and revisions to Invitation for Bid (IFB) #121-071426JVC for the South Campus Building S202 Ceiling Tile Replacement and Corridors Re-Painting project. The scope encompasses partial demolition and replacement of ceiling tiles and grids across three levels of the building, corridor re-painting in "Relaxed Khaki" SW6149 eggshell finish, and installation of new 2'x2' acoustical ceiling grids and tiles in designated areas. The addendum clarifies that specialty installations including sprinkler heads, fire alarm devices, security cameras, and sensors shall be cut in and reinstalled by the College's contractors, with ceiling tiles left adjacent to devices for final installation. Two add-alternate line items are designated: Third Floor Classrooms (Rooms 305 and 307) requiring replacement of existing 2'x4' ceiling grids with new 2'x2' grids while retaining projector and screen alignments, and First Floor Corridor Ceiling Renovation with sprinklers to be re-aligned by College-designated contractors. Sealed bids must be submitted via email to collegeenvironment@rccc.edu by 2:00 p.m. local time on Thursday, August 27, 2026, with public bid opening and reading via Zoom immediately thereafter. The bid opening will be streamed live via the provided Zoom link.

The addendum addresses twelve questions from prospective bidders regarding bonding requirements, contractor responsibilities, material specifications, and scope clarifications. Bid bonds equal to 5% of the bid amount are required; upon award, contractors must provide 100% performance and payment bonds per North Carolina General Statute 44A-26 and State Purchasing Office contract requirements, with bond riders required if change orders increase contract value. Contractors are responsible for removing and replacing electrical outlet and light switch covers during painting, protecting in-place items, and coordinating all site work with the College's Project Manager. Baseboards remain in place and are to be taped off for repainting with additional coats of the same color; any discovered damage must be promptly reported. Building S202 was completed in 1998 with no asbestos concerns. The preferred new ceiling tile is USG ClimaPlus "Frost" #414 per the College's Facility Design Manual specifications. Contractors must wear company identification and high-visibility vests at all times, obtain classroom usage schedules from the College to coordinate work with classroom occupancy, and access classrooms and offices only when accompanied by the Project Manager to maintain campus security protocols.

View the file

Other files

File Type Posted
121-071426JVC.pdf PDF
Addendum_2_08.07.26.docx.pdf PDF
Addendum_1_07.27.26.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

IFB # 121-071426JVC

South Campus Building S202 Ceiling Tile Replacement & Corridors Re-Painting

ROWAN-CABARRUS COMMUNITY COLLEGE

1531 Trinity Church Rd.

Concord, NC

ADDENDUM # 3

DATE: August 19, 2026

NOTICE TO BIDDERS

This addendum is issued prior to receipt of bids, proposals, and its contents do hereby become a part of the documents for the above referenced project. All trade contractor bidders are responsible for assuring that their subcontractors and vendors are properly apprised of the contents of this Addendum. All information contained in this Addendum supersedes and takes precedence over any conflicting information in the documents.

This Addendum serves to clarify, revise and supersede information in the original Notice to Bid posted July 14, 2026.

All bidders must acknowledge receipt of this Addendum in the space provided on the Bid Form for their bid package.

GENERAL INFORMATION

1. Bids shall be submitted via email only to collegeenvironment@rccc.edu until, but no later than 2:00 pm, local prevailing time, Thursday, August 27, 2026, and then publicly opened and read immediately thereafter via ZOOM.

Bidders are encouraged to view the bid opening in real time via the ZOOM. The invite follows.

2. Refer to the North Carolina Electronic Vendor Portal (eVP), as listed in original Invitation to Bid posting, for any additional Addenda and documentation issued prior to the bid opening.

CLARIFICATIONS

1. Specialty installations, including sprinkler heads, fire alarm devices, security cameras, and sensors, shall be cut in and reinstalled by the College's contractors. Ceiling tiles shall be included in the Base Bid and left adjacent to devices for final installation.

2. Third Floor Classrooms (Rooms 305 and 307, indicated in magenta) are designated as Add Alternate Line Items. Retain existing projector and screen alignments. Replace the existing 2'x4' ceiling grid with a new 2'x2' ceiling grid and ceiling tiles only.

3. First Floor Corridor Ceiling Renovation (in “pink” shade) added by the College as “Add Alternate” for Scope of

Work. Sprinklers to be re-aligned (by College designated contractor) with existing lighting at center of corridors.

4. The School Calendar is available online at https://www.rccc.edu/ for exam, holiday, and special event considerations.

5. The awarded Contractor will be provided with the Classroom Usage Schedule to coordinate work activities with classroom occupancy and renovation constraints, including barricades, signage, overhead work, and after-hours work.

6. All classrooms and offices remain secured and locked when not in use or when required for campus security purposes. Common areas, including corridors, may be accessed during normal College operating hours for field verification and dimensional measurements. Contractors shall coordinate all site visits with the Project Manager to obtain any necessary access and to maintain campus security protocols. Personnel visiting the site shall wear company identification and company-logo apparel and/or high-visibility work vests at all times.

mailto:collegeenvironment@rccc.edu https://www.rccc.edu/

RESPONSES TO QUESTIONS (in RED):

1. We understand that a 5% bid bond is required with the bid. Please confirm whether the successful General Contractor will also be required to provide 100% Performance and Payment Bonds upon award. If required, please also confirm whether this requirement applies regardless of the final contract amount.

RESPONSE: Yes, a 5% bid bond is required. Per N.C.G.S. § 44A-26 and SCO contract requirements, performance and payment bonds must remain equal to 100% of the construction contract amount. Therefore, if a change order increases the contract value, the contractor should provide a bond rider increasing the performance and payment bonds to reflect the revised contract amount.

2. Is the GC or the owner responsible for moving furniture where necessary?

RESPONSE: Contractors shall not move furniture or computer equipment and will coordinate with Project Manager, especially in classrooms with ceiling work. All items left in place should be protected.

3. Will the existing baseboard in the receiving new paint remain or be replaced?

RESPONSE: Baseboards will remain in place as installed with re-painting taped off for additional coat(s) of same color (“Relaxed Khaki” SW6149 - “Eggshell” Finish) as already on walls. Any damage discovered within the work area shall be promptly reported to the Project Manager.

4. Will the existing light switch covers, electrical outlet covers, and other devices on walls receiving new paint be removed or remain to be painted around? If they are to be removed, will the GC or the owner be responsible for that?

RESPONSE: The contractor is responsible for any lighting switch or electrical receptacle covers removal prior to painting and replacement when walls have dried. Any signage should also be left in place, taped-off, and painted around including, wayfinding, room ID, schedule panels and all signage in Elevator Lobby areas.

5. There are currently some electrical outlets in the ceiling onsite that might need to be removed for the new work, then reinstalled. Will that be the responsibility of the GC or the owner?

RESPONSE: Any specialty devices should be evaluated and re-worked by College contractors. This shall be coordinated with the ceiling grid and tiles work.

6. The 3/16"=1' scale given on the drawings seems to be incorrect and does not give accurate measurements. Can you please confirm or clarify.

RESPONSE: Marked drawings were for reference only with the Scope of Work identified by colorized areas.

“Grey or Black” notes and scale should be considered non-applicable. Refer to the attached marked-up original three (3) drawings for modifications and clarification of the indicated areas.

7. SOW specifies painting the walls in all corridors. We attended the pre bid, but so we can communicate clearly with subcontractors, can drawings be provided that highlight the areas that need to be painted? It is unclear if vestibules are going to be painted on AD201.

RESPONSE: See the original color-coded drawings, now designated as another Add Alternate for the First Floor Ceiling. Vestibule conditions are clarified by the colored areas shown on the attached drawings, and clouded notation: “No re-painting at [tall] Vestibules or Stair Towers (typical)”.

8. Quick clarification regarding the yellow areas: does the 2' x 2' ceiling grid scope require complete replacement of the existing grid system, including mains, cross tees, and wall angles, or is the intent to modify the existing 2' x 4' grid by adding cross tees?

RESPONSE: See Item #2 on Page 1 of this Addendum, Original Released drawings and attached mark-ups noting scope as “New 2x2 Grid and Tile”

9. Proof of no asbestos/when was the building built?

RESPONSE: Building S202 was completed in 1998.

10. Should any HVAC, electrical, or fire suppression work be necessary, will the owner be supplying these?

RESPONSE: See Clarifications #1 & 3 above re: Sprinklers and Specialty work by College.

11. Are the entrances being painted or just the corridors?

RESPONSE: Please refer to the drawings and scope of work, as well as Question Response #7 above.

12. Are the first-floor corridor ceiling tiles being added as an alternate?

RESPONSE: See Response #7 and refer to the drawings and scope of work.

ATTACHMENTS

1. Pre-Bid Sign-In Sheet

2. Price Sheet

3. Revised Drawings

3.1. AD201 – First Floor

3.2. AD202 – Second Floor

3.3. AD203 – Third Floor

BID OPENING ZOOM LINK

Join Zoom Meeting https://rccc-edu.zoom.us/j/93147817418

Meeting chat link https://rccc-edu.zoom.us/launch/jc/93147817418

Meeting ID: 931 4781 7418 One tap mobile +16465588656,,93147817418# US (New York)

+16469313860,,93147817418# US

Join instructions https://rcccedu.zoom.us/meetings/93147817418/invitations?signature=yLFGPa26hxbkrFX5umdPoyHVjMZ75TgGQ 3FCosP6giY

END OF ADDENDUM 3

https://rccc-edu.zoom.us/j/93147817418 https://rccc-edu.zoom.us/launch/jc/93147817418 https://rcccedu.zoom.us/meetings/93147817418/invitations?signature=yLFGPa26hxbkrFX5umdPoyHVjMZ75TgGQ3FCosP6giY https://rcccedu.zoom.us/meetings/93147817418/invitations?signature=yLFGPa26hxbkrFX5umdPoyHVjMZ75TgGQ3FCosP6giY

SCO-Proposal Form 7.07.2026 1 of 3

F O R M OF P R O P O S A L

Bldg.S202 Ceiling Tile Replacement & Corridor Re-Painting Contract:

Rowan-Cabarrus Community College Bidder:

Date: August 27, 2026

The undersigned, as bidder, hereby declares that the only person or persons interested in this proposal as principal or principals is or are named herein and that no other person than herein mentioned has any interest in this proposal or in the contract to be entered into; that this proposal is made without connection with any other person, company or parties making a bid or proposal;

and that it is in all respects fair and in good faith without collusion or fraud. The bidder further declares that he has examined the site of the work and the contract documents relative thereto and has read all special provisions furnished prior to the opening of bids; that he has satisfied himself relative to the work to be performed. The bidder further declares that he and his subcontractors have fully complied with NCGS 64, Article 2 in regards to E-Verification as required by Section 2.(c) of Session

Law 2013-418, codified as N.C. Gen. Stat. § 143-129(j).

The Bidder proposes and agrees if this proposal is accepted to contract with the

Rowan-Cabarrus Community College in the form of contract specified below, to furnish all necessary materials, equipment, machinery, tools, apparatus, means of transportation and labor necessary to complete the construction of

South Campus Building S202 Ceiling Tile Replacement and Corridors Re-Painting in full in complete accordance with the plans, specifications and contract documents, to the full and entire satisfaction of the Rowan-Cabarrus Community College; with a definite understanding that no money will be allowed for extra work except as set forth in the General Conditions and the contract documents, for the sum of:

SINGLE PRIME CONTRACT: (GENERAL CONTRACTOR)

Base Bid:

Dollars($)

General Contractor:

Lic

Ceiling Subcontractor:

Lic

Drywall Subcontractor:

Lic

Painting Subcontractor:

Lic

Other Subcontractor:

Lic

GS143-128(d) requires all single prime bidders to identify their subcontractors for the above subdivisions of work. A contractor whose bid is accepted shall not substitute any person as subcontractor in the place of the subcontractor listed in the original bid, except (i) if the listed subcontractor's bid is later determined by the contractor to be non-responsible or non-responsive or the listed subcontractor refuses to enter into a contract for the complete performance of the bid work, or (ii) with the approval of the awarding authority for good cause shown by the contractor.

SCO-Proposal Form 7.07.2026 2 of 3

ALTERNATES:

Should any of the alternates as described in the contract documents be accepted, the amount written below shall be the amount to be "added to" or "deducted from" the base bid. (Strike out "Add" or "Deduct" as appropriate.)

GENERAL CONTRACT:

Alternate No. 1 (Third Floor Classrooms 303 and 305 Ceiling 2x2 Grid and Tile Replacement)

(Add) Dollars($)

Alternate No. 2 (First Floor Corridors 2x2 Ceiling Grid Centering and Tile Replacement)

(Add) Dollars($)

UNIT PRICES

Unit prices quoted and accepted shall apply throughout the life of the contract, except as otherwise specifically noted. Unit prices shall be applied, as appropriate, to compute the total value of changes in the base bid quantity of the work all in accordance with the contract documents.

GENERAL CONTRACT: (Subcontracor Materials and Labor)

No. 1 Ceiling Grid and Acoustical Ceiling Tile (SqFt) Unit Price ($)

No. 2 Drywall Repairs, Patching, Prep for Paint (SqFt) Unit Price ($)

No. 3 Painting Corridor Walls and GWB Repairs (SqFt) Unit Price ($)

The bidder further proposes and agrees hereby to commence work under this contract on a date to be specified in a written order of the designer (Notice to Proceed) and shall fully complete all work thereunder within the time specified in the Supplementary General Conditions Article 23. Applicable liquidated damages amount is also stated in the Supplementary General Conditions Article 23.

Addendum received and used in computing bid (Initials or N/A at each):

Addendum No. 1

Addendum No. 2

Addendum No. 3

SCO-Proposal Form 7.07.2026 3 of 3

Proposal Signature Page

The undersigned further agrees that in the case of failure on his part to execute the said contract and the bonds within ten (10) consecutive calendar days after being given written notice of the award of contract, the certified check, cash or bid bond accompanying this bid shall be paid into the funds of the owner's account set aside for the project, as liquidated damages for such failure; otherwise the certified check, cash or bid bond accompanying this proposal shall be returned to the undersigned.

Respectfully submitted this day of

(Name of firm or corporation making bid)

By:

Signature

Name:

Print or type

Title______________ (Owner/Partner/Pres./V.Pres)

Address

License No.

Email Address:

S

S

S S S S S

S S

S

OS

OS

OS OS

OS

OS

OS

OS

OS OS

OS

OS OS

F

F

F

F

F

F

F

F

F

F

S

F

S

S

S

S

S S

S

PLAN

N

TRUE

N

A A

B B

C C

D D

E E

CLASSROOM

CLASSROOM

OFFICE

104A

CLASSROOM

CLASSROOM

OFFICE

110B

CORRIDOR

101B

MECH./ELEC.

ELEV.

ELEVATOR

LOBBY

101A

JANITOR

ELEV.

MACH.

180B

STAIR #1

STAIR #2

WOMEN

MEN

STORAGE

BOILER

180A

WELDING

LAB

OFFICE

110A

CORRIDOR

101C

CORRIDOR

101D

CORRIDOR

101E

OFFICE

104B

OPEN

OFFICE

CORRIDOR

101F

OFFICE

CLASSROOM

C.1 C.1

C.1

C.1

C.1

C.3

C.0

EXISTING GWB HEADER TO

REMAIN

C.1

C.1

C.7 C.8

C.1

C.1C.1 C.1

C.2

C.2 C.2

C.2

C.2 C.2

C.2 C.2

R R

R

R

R

R R

R

R

R

C.1

C.1

R

R

REMOVE PORTION OF EXISTING CEILING

GRID TO INSTALL NEW GWB HEADER

NO CEILING WORK IN AREAS

SHOWN SHADED, TYPICAL

EXISTING WINDOW SHADES

TO REMAIN, UNLESS NOTED

OTHERWISE

EXISTING GWB HEADER TO

REMAIN

REMOVE EXISTING WINDOW SHADES

DURING DEMOLITION AND NEW WORK,

AND REINSTALL IN SAME LOCATION AT

END OF PROJECT

REMOVE EXISTING WINDOW SHADES

DURING DEMOLITION AND NEW WORK,

AND REINSTALL IN SAME LOCATION AT

END OF PROJECT

EXISTING WINDOW SHADES

TO REMAIN, UNLESS NOTED

OTHERWISE

C.0

C.0

C.0

C.0

C.0

C.0

C.0

C.0R

C.2 C.2

C.2

C.2

C.2

C.2

REMOVE EXISTING CEILING

TILE, 2x2 GRID TO REMAIN

OTS

OTS

CLASSROOM

C.3 C.3 C.3 C.3

C.3 C.3 C.3 C.3

C.3

REMOVE EXISTING CEILING GRID AND

TILE SHOWN DOTTED

REMOVE EXISTING ROLL DOWN PROJECTION

SCREEN, PROJECTOR AND SPEAKERS AND

RETURN TO OWNER

REMOVE EXISTING LIGHT FIXTURES

SHOWN DOTTED AND RE-USE IN

ELSEWHERE IN NEW WORK, SEE SHEET

A102 AND ELECTRICAL DRAWINGS

REMOVE EXISTING SPRINKLER HEADS AND

RE-INSTALL IN NEW CEILING, SEE SHEET A102

REMOVE EXISTING CEILING GRID AND

TILE SHOWN DOTTED, TYPICAL

REMOVE EXISTING LIGHT FIXTURES

SHOWN DOTTED AND RE-USE IN NEW

WORK, SEE SHEET A201 AND ELECTRICAL

DRAWINGS

REMOVE EXISTING SPRINKLER HEADS

IN CEILINGS TO BE REMOVED, TYPICAL

SEE FIRE PROTECTION DRAWINGS

REMOVE EXISTING HVAC DIFFUSERS

IN CEILINGS TO BE REMOVED, TYPICAL

SEE MECHANICAL DRAWINGS

REMOVE EXISTING FIRE ALARM

DEVICES, SMOKE DETECTORS,

OCCUPANCY SENSORS ETC, IN

CEILINGS TO BE REMOVED, TYPICAL

SEE ELECTRICAL DRAWINGS

REFLECTED CEILING PLAN KEYED NOTES

NO WORKC.0

REMOVE EXISTING CEILING TILES, EXISTING GRID TO REMAINC.1

REMOVE EXISTING LIGHT FIXTURE, SEE ELECTRICAL DRAWINGSC.2

REMOVE EXISTING LIGHT FIXTURE AND RE-USE IN NEW WORK, SEE ELECTRICAL DRAWINGSC.3

INFILL NEW CEILING GRID TEES TO MATCH EXISTING FOR 2X2 LAYOUT AND PROVIDE NEW CEILING TILE

NEW LIGHT FIXTURE, SEE ELECTRICAL DRAWINGS

EXISTING LIGHT FIXTURE RE-USED IN NEW LOCATION, SEE ELECTRICAL DRAWINGS

C.4

C.5

C.6

EXISTING CEILING MOUNTED PROJECTOR TO REMAIN, RELOCATE MOUNT SLIGHTLY AS

NECESSARY TO INSTALL NEW CEILING GRID TEES

C.7

EXISTING WALL MOUNTED ROLL DOWN SCREEN TO REMAINC.8

REMOVE EXISTING WALL MOUNTED ROLL DOWN SCREEN AND RE-USE IN NEW WORK.C.9

EXISTING WALL TO BE REMOVED

EXISTING WALL TO REMAIN

WALL LEGEND

NEW WALL

EXISTING 2 HR RATED WALL TO REMAIN

NOTE: WALL SYMBOLOGY FOR GRAPHICAL PURPOSES ONLY.

REFER TO PARTITION TYPES AND WALL SECTIONS FOR ACTUAL

WALL CONSTRUCTION.

EXISTING 1 HR RATED WALL TO REMAIN

NEW 1 HR RATED WALL

CEILING LEGEND

RECESSED LED DOWN LIGHT

2x4 RECESSED LED FIXTURE

2x2 RECESSED LED FIXTURE

SMOKE DETECTOR

OCCUPANCY SENSOROS

CEILING MOUNTED LIGHT

S

EXIT SIGN

DIRECTIONAL EXIT SIGN

UPRIGHT SPRINKLER HEAD

SPRINKLER HEAD MOUNTED IN CEILING

SUPPLY AIR DIFFUSER

RETURN AIR DIFFUSER /

EXHAUST GRILLE

LINEAR SUPPLY AIR DIFFUSER

INDICATES CEILING MOUNTED DEVICES, SPRINKLER HEADS, ETC. TO BE REMOVED

INDICATES CEILING MOUNTED DEVICES, SPRINKLER HEADS, ETC. TO BE RELOCATED

LOCATED IN CENTER OF NEW CEILING TILE, TYPICAL

R

SPEAKER WITH GRILLES

FIRE ALARM DEVICEF

CAMERA

101C 101D 101E 104A 104B 105 106 107 107A 111 112 117A 117B 117C 118A 118B 118C

REFLECTED CEILING BASE BID / ALTERNATE

WORK SHOWN IN THE FOLLOWING ROOMS IS BASE BID.

ALL OTHER WORK SHOWN ON THE REFLECTED CEILING PLAN IS TO BE INCLUDED IN ALTERNATE #2

OWNERSHIP OF INSTRUMENTS OF SERVICE:

All reports, specifications, plans, computer files, field data, notes, and other documents and instruments of service shall remain the property of the Design Professional. The Design Professional shall retain all common law, statutory and other reserved rights, including the copyright thereto.

This drawing is the property of Yates - Chreitzberg - Hughes Architects and is not to be reproduced or copied in whole or any part. It is not to be used on any other project and is to be returned upon request.

© Copyright 2024

R C

C C

B ui dl in g S2

R en ov at io ns

T rin ity

C hu rc h

R d

C on co rd , N

C

CONSULTANT:

PROFESSIONAL SEALS:

CLIENT:

YCHA COM.#:

REVISIONS:

PHASE & DATE:

SHEET TITLE:

ARCHITECTURAL:

7035 NORTHWINDS DR NW

CONCORD, NC 28027

704.788.2000 www.ycharch.com

I T ZBERG - H UGH ES ARCH I TECTS

PA

O

DROCNC

, N. C.CAROL I NA

HTRON

O O

RE

GI

ST

ER

ED

ARCHI TECTURAL C

RP

RATION

CERT. NO.

YA

TE

S-

CH

RE

SCO #22-25351-02A

NCCCS #2692

S:

\R ev it

Lo ca l F ile s\

9.

R

C C

C B ui ld in g

S2

Re no va tio ns _b illh yc ha rc h.

co m

.rv t

4/

/2

6:

:1

PM

22219.00

FIRST LEVEL

REFLECTED CEILING

PLAN - DEMOLITION

AD201

CONSTRUCTION DOCUMENTS

04-08-24

AD201 3/16" = 1'-0"

1 FIRST LEVEL REFLECTED CEILING PLAN - DEMOLITION

disenhour Area Measurement

639.32 sf disenhour Typewritten Text Base Bid:

New ACT Grid and Tile In Yellow Areas (4) disenhour Area Measurement

72.3 sf disenhour Area Measurement

83.08 sf disenhour Area Measurement

83.84 sf john.cole Rectangle john.cole Rectangle john.cole Rectangle john.cole Rectangle john.cole Rectangle john.cole Rectangle john.cole Rectangle john.cole Rectangle john.cole Rectangle john.cole Rectangle john.cole Rectangle john.cole Rectangle john.cole Line john.cole Line john.cole Rectangle john.cole Rectangle john.cole Rectangle john.cole Rectangle john.cole Rectangle john.cole Rectangle john.cole Rectangle john.cole Rectangle john.cole Rectangle john.cole Line john.cole Rectangle john.cole Rectangle john.cole Rectangle john.cole Line john.cole Line john.cole Line john.cole Line john.cole Line john.cole Line john.cole Line john.cole Line john.cole Line john.cole Line john.cole Line john.cole Line john.cole Line john.cole Line john.cole Line john.cole Line john.cole Cloud john.cole Arrow john.cole Arrow john.cole Arrow john.cole Arrow john.cole Rectangle john.cole Rectangle john.cole Rectangle john.cole Rectangle john.cole Rectangle john.cole Typewritten Text Scope Edits and mark-ups by JV Cole / RCCC 8.12.26 john.cole Line john.cole Cloud john.cole Typewritten Text

* Add Alternate (Line Item)* :

New ACT Grid and Tile In "Pink" Corridor and Vestibule Areas; Specialty "cut-ins" by RCCC Subs (coordination):

Sprinkler (center in corridor);

Fire Alarm; IT; Security;

Mega-Dot Signs, etc.

john.cole Arrow john.cole Cloud john.cole Arrow john.cole Arrow john.cole Text Box

* Floor Plan for Reference Only...

Do not use former Reno Notes...

Ceiling Reno as marked in color areas only - ACT Grid to become 2x2 at 2x4 areas - Centered on Corridors, and Exist. Lighting.

john.cole Cloud john.cole Typewritten Text

* Preferred New Ceiling Tile = campus standard:

USG ClimaPlus "Frost" #414 per Facility Design Manual Spec's (typical all facilities / buildings).

john.cole Cloud john.cole Arrow john.cole Typewritten Text Re-paint and misc. Drywall Repairs at Existing Main Corridors - "Relaxed Khaki" SW6149 -remove plates at switches but retain wallbase and signage "as is" for re-paint "touch-ups" only -typical for all 3 floors...

john.cole Typewritten Text Exist. Lighting HVAC and Devices to remain (Typ.)

Tile cuts and tie-ups by Specialty Subs/Owner john.cole Cloud john.cole Cloud

SS S SS

SSS

S

OS

OS

OS

OS

OS

OS

OS

OS OS

OSOS

OS

OSOS

OS

OS

OS

OS

F

F

F F

F

F

F

F

F

FF

F

F

F

S

FOSOS

S S

S S

S

S

S

S S

S

SS

S S

S

S

S

S

S

S

S

S

S

S

S

S

S

S

PLAN

N

TRUE

N

A A

B B

C C

D D

E E

OFFICE

STORAGE

212C

STORAGE

212B

CLASSROOM

CLASSROOM

CLASSROOM

CLASSROOM

CLASSROOM

CLASSROOM

CLASSROOM

CLASSROOM

CLASSROOM

MEN

WOMEN

CORRIDOR

201A

CORRIDOR

201C

OFFICE

212A

STOR.

ENTRANCE

200 ENTRANCE

STOR.

214A

STOR.

214B

STOR.

STOR.

217A

STOR.

216A

CORRIDOR

ELEC.

JANITOR

223 OFFICE

OFFICE

OFFICE

OFFICE

OFFICE

ELEV.

ELEV.

LOBBY

VESTIBULE

201E

CORRIDOR

201B

CORRIDOR

201D

CLASSROOM

R R R R R R RRR R R

R R

R

RR

R

R

R

R

RR

R

EXISTING WINDOW SHADES

TO REMAIN, TYPICAL

EXISTING GWB HEADER TO

REMAIN

REMOVE EXISTING CEILING MOUNTED

PROJECTORS AND SPEAKERS, RE-USE

IN NEW WORK, SEE SHEET A203

REMOVE EXISTING CEILING MOUNTED

PROJECTORS AND SPEAKERS, RE-USE

IN NEW WORK, SEE SHEET A203 AND

ELECTRICAL DRAWINGS

REMOVE EXISTING CEILING GRID AND

TILE SHOWN DOTTEDREMOVE WALL MOUNTED ROLL DOWN

PROJECTION SCREENS AND RE-USE IN NEW

WORK, SEE SHEET A203

REMOVE EXISTING CEILING GRID AND

TILE SHOWN DOTTED

EXISTING GWB HEADER TO

REMAIN

EXISTING GWB HEADER TO REMAIN

EXISTING WINDOW SHADES

TO REMAIN, TYPICAL

REMOVE EXISTING CEILING

TILE, 2x2 GRID TO REMAIN

REMOVE EXISTING CEILING MOUNTED

PROJECTOR, CAMERA AND SPEAKERS,

AND RETURN TO OWNER

C.1

C.1

C.1

C.0

C.0 C.1

C.1

C.1 C.1

C.1 C.1

C.0 C.0 C.0 C.0

C.0

C.7 C.7

RRRRRR

R

R RRRRRR RRRRRRR RR

R

C.8C.8

R

R

C.1 C.1

C.1

C.1 C.1

C.1 C.1

C.1

R

R

R

R R R R R

R R R

R

R

R R

R R R

R R R

R R

R

R

OPEN TO ABOVE OPEN TO ABOVE

REMOVE EXISTING LIGHT FIXTURES

SHOWN DOTTED AND RE-USE IN NEW

WORK, SEE SHEET A202 AND ELECTRICAL

DRAWINGS

NO CEILING WORK IN AREAS

SHOWN SHADED, TYPICAL

C.0

C.0

C.0

C.0

C.1

C.1

C.2

C.2

R

C.1 C.2 C.2

C.2 C.2

R

C.0

C.0

REMOVE EXISTING WALL MOUNTED

ROLL DOWN PROJECTION SCREEN

AND RETURN TO OWNER

EXISTING CUBICLE CURTAIN

AND TRACK TO REMAIN

REFLECTED CEILING PLAN KEYED NOTES

NO WORKC.0

REMOVE EXISTING CEILING TILES, EXISTING GRID TO REMAINC.1

REMOVE EXISTING LIGHT FIXTURE, SEE ELECTRICAL DRAWINGSC.2

REMOVE EXISTING LIGHT FIXTURE AND RE-USE IN NEW WORK, SEE ELECTRICAL DRAWINGSC.3

INFILL NEW CEILING GRID TEES TO MATCH EXISTING FOR 2X2 LAYOUT AND PROVIDE NEW CEILING TILE

NEW LIGHT FIXTURE, SEE ELECTRICAL DRAWINGS

EXISTING LIGHT FIXTURE RE-USED IN NEW LOCATION, SEE ELECTRICAL DRAWINGS

C.4

C.5

C.6

EXISTING CEILING MOUNTED PROJECTOR TO REMAIN, RELOCATE MOUNT SLIGHTLY AS

NECESSARY TO INSTALL NEW CEILING GRID TEES

C.7

EXISTING WALL MOUNTED ROLL DOWN SCREEN TO REMAINC.8

REMOVE EXISTING WALL MOUNTED ROLL DOWN SCREEN AND RE-USE IN NEW WORK.C.9

EXISTING WALL TO BE REMOVED

EXISTING WALL TO REMAIN

WALL LEGEND

NEW WALL

EXISTING 2 HR RATED WALL TO REMAIN

NOTE: WALL SYMBOLOGY FOR GRAPHICAL PURPOSES ONLY.

REFER TO PARTITION TYPES AND WALL SECTIONS FOR ACTUAL

WALL CONSTRUCTION.

EXISTING 1 HR RATED WALL TO REMAIN

NEW 1 HR RATED WALL

CEILING LEGEND

RECESSED LED DOWN LIGHT

2x4 RECESSED LED FIXTURE

2x2 RECESSED LED FIXTURE

SMOKE DETECTOR

OCCUPANCY SENSOROS

CEILING MOUNTED LIGHT

S

EXIT SIGN

DIRECTIONAL EXIT SIGN

UPRIGHT SPRINKLER HEAD

SPRINKLER HEAD MOUNTED IN CEILING

SUPPLY AIR DIFFUSER

RETURN AIR DIFFUSER /

EXHAUST GRILLE

LINEAR SUPPLY AIR DIFFUSER

INDICATES CEILING MOUNTED DEVICES, SPRINKLER HEADS, ETC. TO BE REMOVED

INDICATES CEILING MOUNTED DEVICES, SPRINKLER HEADS, ETC. TO BE RELOCATED

LOCATED IN CENTER OF NEW CEILING TILE, TYPICAL

R

SPEAKER WITH GRILLES

FIRE ALARM DEVICEF

CAMERA

REFLECTED CEILING BASE BID / ALTERNATE

WORK SHOWN IN THE FOLLOWING ROOMS IS BASE BID.

204 205 207 210 218 219 220 221 222

ALL OTHER WORK SHOWN ON THE REFLECTED CEILING PLAN IS TO BE INCLUDED IN ALTERNATE #2

OWNERSHIP OF INSTRUMENTS OF SERVICE:

All reports, specifications, plans, computer files, field data, notes, and other documents and instruments of service shall remain the property of the Design Professional. The Design Professional shall retain all common law, statutory and other reserved rights, including the copyright thereto.

This drawing is the property of Yates - Chreitzberg - Hughes Architects and is not to be reproduced or copied in whole or any part. It is not to be used on any other project and is to be returned upon request.

© Copyright 2024

R C

C C

B ui dl in g S2

R en ov at io ns

T rin ity

C hu rc h

R d

C on co rd , N

C

CONSULTANT:

PROFESSIONAL SEALS:

CLIENT:

YCHA COM.#:

REVISIONS:

PHASE & DATE:

SHEET TITLE:

ARCHITECTURAL:

7035 NORTHWINDS DR NW

CONCORD, NC 28027

704.788.2000 www.ycharch.com

I T ZBERG - H UGH ES ARCH I TECTS

PA

O

DROCNC

, N. C.CAROL I NA

HTRON

O O

RE

GI

ST

ER

ED

ARCHI TECTURAL C

RP

RATION

CERT. NO.

YA

TE

S-

CH

RE

SCO #22-25351-02A

NCCCS #2692

S:

\R ev it

Lo ca l F ile s\

9.

R

C C

C B ui ld in g

S2

Re no va tio ns _b illh yc ha rc h.

co m

.rv t

4/

/2

6:

:2

PM

22219.00

SECOND LEVEL

REFLECTED CEILING

PLAN - DEMOLITION

AD202

CONSTRUCTION DOCUMENTS

04-08-24

AD202 3/16" = 1'-0"

1 SECOND LEVEL REFLECTED CEILING PLAN - DEMOLITION

disenhour Area Measurement 1,696.92 sf disenhour Area Measurement

90.03 sf disenhour Area Measurement

90.22 sf disenhour Typewritten Text New ACT Grid and Tile In Yellow Area - Re-Center ALL 2x2 Fixtures and align with Lighting disenhour Area Measurement

82.87 sf john.cole Rectangle john.cole Rectangle john.cole Rectangle john.cole Rectangle john.cole Rectangle john.cole Rectangle john.cole Line john.cole Line john.cole Line john.cole Line john.cole Line john.cole Line john.cole Line john.cole Line john.cole Line john.cole Line john.cole Line john.cole Line john.cole Line john.cole Line john.cole Rectangle john.cole Rectangle john.cole Rectangle john.cole Line john.cole Line john.cole Line john.cole Line john.cole Line john.cole Line john.cole Line john.cole Line john.cole Rectangle john.cole Rectangle john.cole Line john.cole Rectangle john.cole Line john.cole Rectangle john.cole Rectangle john.cole Rectangle john.cole Arrow john.cole Arrow john.cole Arrow john.cole Arrow john.cole Cloud john.cole Rectangle john.cole Rectangle john.cole Rectangle john.cole Cloud john.cole Typewritten Text

* Preferred New Ceiling Tile = campus standard:

USG ClimaPlus "Frost" #414 per Facility Design Manual Spec's (typical all facilities / buildings).

john.cole Cloud john.cole Typewritten Text Scope Edits and mark-ups by JV Cole / RCCC 8.12.26 john.cole Text Box

* Floor Plan for Reference Only...

Do not use former Reno Notes...

Ceiling Reno as marked in color areas only - ACT Grid to become 2x2 at 2x4 areas - Centered on Corridors, and Exist. Lighting.

john.cole Cloud john.cole Typewritten Text Exist. Lighting HVAC and Devices to remain (Typ.)

Tile cuts and tie-ups by Specialty Subs/Owner john.cole Cloud john.cole Arrow john.cole Typewritten Text Re-paint and misc. Drywall Repairs at Existing Main Corridors - "Relaxed Khaki" SW6149 -remove plates at switches but retain wallbase and signage "as is" for re-paint "touch-ups" only -typical for all 3 floors...

OS

F

OS

F

OS

F

OS

F

OS

F

OSOS

OSOSOS

S

OS

OS

F

OS

F

OS

OS F

F

OS

OSF

OS

F

S S

S

SSSS

S

S

S

S

SS S

S

S

S

S

SS

S

S

S

S

S S

PLAN

N

TRUE

N

A A

B B

C C

D D

E E

EXISTING WINDOW SHADES

TO REMAIN, TYPICAL

EXISTING GWB HEADER TO

REMAIN

NO CEILING WORK IN AREAS

SHOWN SHADED, TYPICAL

R RR R RR R RRR

R

RRRRRRRRR RR

R

R R R

R

RR

R

R R R

RRR

R

RRRR

R R R

D

R

R

R R

R R

R

R

C.3

C.0

C.0

C.1

C.3

REMOVE EXISTING CEILING MOUNTED

PROJECTORS, SPEAKERS AND CAMERAS,

RE-USE IN NEW WORK, SEE SHEET A203

AND ELECTRICAL DRAWINGS

C.3 C.3

C.3 C.3

C.3C.3C.3

C.1

C.3 C.3

C.3C.3

C.3C.3C.3

C.3

D

C.3C.3

C.3C.3

C.3

RRR

C.7 C.7

C.7

C.7 C.7

C.1

R

C.1

CLASSROOM

CLASSROOM

CLASSROOM

CLASSROOM

CLASSROOM

CLASSROOM

CLASSROOM

MEN

WOMEN

CORRIDOR

301A

CORRIDOR

301C

IDF

381A

IDF

CORRIDOR

ELEC.

OFFICE

314A

OFFICE

314B

OFFICE

314C

OFFICE

314D

OFFICE

314E

OFFICE

ELEV.

STOR.

OFFICE

308A

OFFICE

309A

STOR.

308B

ELEVATOR

LOBBY

ENTRANCE

202ENTRANCE

VESTIBULE

301E

CORRIDOR

301B

CORRIDOR

301D

C.1 C.1

C.0

C.1

C.1

C.0

C.1

C.0

EXISTING GWB ON SHAFT AT

ROOF LADDER TO REMAIN

C.0

C.1

C.1

C.1

R

C.1 C.1 C.1

C.7 C.7 C.8

C.1

C.8

C.1

C.1

C.1

C.1

REMOVE WALL MOUNTED ROLL DOWN

PROJECTION SCREENS AND RE-USE IN NEW

WORK, SEE SHEET A203

REMOVE EXISTING CEILING GRID AND TILE

SHOWN DOTTED

C.3

C.1

C.1

C.1 C.1

C.8

C.1

C.2 C.2

C.2 C.2

C.2 C.2

C.2 C.2 C.2

C.2C.2C.2

EXISTING GWB HEADER TO

REMAIN

C.1

C.1

C.2C.2

C.2C.2

C.2C.2

C.2C.2C.2

C.2 C.2 C.2

EXISTING GWB HEADER TO

REMAIN

EXISTING WINDOW SHADES

TO REMAIN, TYPICAL

REMOVE EXISTING CEILING

TILE, 2x2 GRID TO REMAIN

REMOVE EXISTING CEILING

TILE, 2x2 GRID TO REMAIN

REMOVE EXISTING CEILING MOUNTED

PROJECTORS, SPEAKERS AND CAMERAS,

RE-USE IN NEW WORK, SEE SHEET A203

REMOVE EXISTING CEILING GRID AND

TILE SHOWN DOTTED

REMOVE EXISTING LIGHT FIXTURES

SHOWN DOTTED AND RE-USE IN NEW

WORK, SEE SHEET A202 AND ELECTRICAL

DRAWINGS

C.0

C.2

C.2

C.2

C.2

C.2 C.2

C.2 C.2

C.2C.2

C.2 C.2

C.2

C.2

REMOVE ALL EXISTING DOWNLIGHTS

IN EXTERIOR GWB SOFFIT

REMOVE ALL EXISTING DOWNLIGHTS

IN EXTERIOR GWB SOFFIT

R

R R R

R RR R

CLASSROOM

CLASSROOM

CLASSROOM

WORK IN THIS AREA TO BE ALTERNATE #1

REMOVE EXISTING CEILING SPEAKERS AND

CAMERAS, RE-USE IN NEW WORK, SEE ELEC.

DWGS., TYPICAL

C

BASE BID FOR EXISTING CLASSROOMS 202, 204 AND 206:

REMOVE EXISTING CEILING TILES, EXISTING GRID TO REMAIN

C

REFLECTED CEILING PLAN KEYED NOTES

NO WORKC.0

REMOVE EXISTING CEILING TILES, EXISTING GRID TO REMAINC.1

REMOVE EXISTING LIGHT FIXTURE, SEE ELECTRICAL DRAWINGSC.2

REMOVE EXISTING LIGHT FIXTURE AND RE-USE IN NEW WORK, SEE ELECTRICAL DRAWINGSC.3

INFILL NEW CEILING GRID TEES TO MATCH EXISTING FOR 2X2 LAYOUT AND PROVIDE NEW CEILING TILE

NEW LIGHT FIXTURE, SEE ELECTRICAL DRAWINGS

EXISTING LIGHT FIXTURE RE-USED IN NEW LOCATION, SEE ELECTRICAL DRAWINGS

C.4

C.5

C.6

EXISTING CEILING MOUNTED PROJECTOR TO REMAIN, RELOCATE MOUNT SLIGHTLY AS

NECESSARY TO INSTALL NEW CEILING GRID TEES

C.7

EXISTING WALL MOUNTED ROLL DOWN SCREEN TO REMAINC.8

REMOVE EXISTING WALL MOUNTED ROLL DOWN SCREEN AND RE-USE IN NEW WORK.C.9

EXISTING WALL TO BE REMOVED

EXISTING WALL TO REMAIN

WALL LEGEND

NEW WALL

EXISTING 2 HR RATED WALL TO REMAIN

NOTE: WALL SYMBOLOGY FOR GRAPHICAL PURPOSES ONLY.

REFER TO PARTITION TYPES AND WALL SECTIONS FOR ACTUAL

WALL CONSTRUCTION.

EXISTING 1 HR RATED WALL TO REMAIN

NEW 1 HR RATED WALL

CEILING LEGEND

RECESSED LED DOWN LIGHT

2x4 RECESSED LED FIXTURE

2x2 RECESSED LED FIXTURE

SMOKE DETECTOR

OCCUPANCY SENSOROS

CEILING MOUNTED LIGHT

S

EXIT SIGN

DIRECTIONAL EXIT SIGN

UPRIGHT SPRINKLER HEAD

SPRINKLER HEAD MOUNTED IN CEILING

SUPPLY AIR DIFFUSER

RETURN AIR DIFFUSER /

EXHAUST GRILLE

LINEAR SUPPLY AIR DIFFUSER

INDICATES CEILING MOUNTED DEVICES, SPRINKLER HEADS, ETC. TO BE REMOVED

INDICATES CEILING MOUNTED DEVICES, SPRINKLER HEADS, ETC. TO BE RELOCATED

LOCATED IN CENTER OF NEW CEILING TILE, TYPICAL

R

SPEAKER WITH GRILLES

FIRE ALARM DEVICEF

CAMERAREFLECTED CEILING BASE BID / ALTERNATES

WORK SHOWN IN THE FOLLOWING ROOMS IS BASE BID: 307 308A 309A 314 314A 314B 314C 314D 314E

ALL OTHER WORK SHOWN ON THE REFLECTED CEILING PLAN IS TO BE ALTERNATE #2

ALTERNATE #1 - REMOVE ALL CEILING GRID, TILE, LIGHTS, DIFFUSERS, ETC. IN ROOMS 302 304 306

BASE BID FOR EXISTING CLASSROOMS: 302 304 306

REMOVE EXISTING CEILING TILES, EXISTING GRID, LIGHTS, DIFFUSERS, ETC. TO REMAIN

OWNERSHIP OF INSTRUMENTS OF SERVICE:

All reports, specifications, plans, computer files, field data, notes, and other documents and instruments of service shall remain the property of the Design Professional. The Design Professional shall retain all common law, statutory and other reserved rights, including the copyright thereto.

This drawing is the property of Yates - Chreitzberg - Hughes Architects and is not to be reproduced or copied in whole or any part. It is not to be used on any other project and is to be returned upon request.

© Copyright 2024

R C

C C

B ui dl in g S2

R en ov at io ns

T rin ity

C hu rc h

R d

C on co rd , N

C

CONSULTANT:

PROFESSIONAL SEALS:

CLIENT:

YCHA COM.#:

REVISIONS:

PHASE & DATE:

SHEET TITLE:

ARCHITECTURAL:

7035 NORTHWINDS DR NW

CONCORD, NC 28027

704.788.2000 www.ycharch.com

I T ZBERG - H UGH ES ARCH I TECTS

PA

O

DROCNC

, N. C.CAROL I NA

HTRON

O O

RE

GI

ST

ER

ED

ARCHI TECTURAL C

RP

RATION

CERT. NO.

YA

TE

S-

CH

RE

SCO #22-25351-02A

NCCCS #2692

S:

\R ev it

Lo ca l F ile s\

9.

R

C C

C B ui ld in g

S2

Re no va tio ns _b illh yc ha rc h.

co m

.rv t

4/

/2

6:

:3

PM

22219.00

THIRD LEVEL

REFLECTED CEILING

PLAN - DEMOLITION

AD203

CONSTRUCTION DOCUMENTS

04-08-24

AD203 3/16" = 1'-0"

1 THIRD LEVEL REFLECTED CEILING PLAN - DEMOLITION

disenhour Area Measurement 2,399.63 sf disenhour Area Measurement

207.42 sf disenhour Area Measurement

884.93 sf disenhour Area Measurement

874.93 sf disenhour Area Measurement 1,008.76 sf disenhour Area Measurement

885.03 sf disenhour Area Measurement 1,032.15 sf disenhour Area Measurement 1,853.87 sf disenhour Typewritten Text New ACT Tile Only In Teal Area disenhour Typewritten Text New 2x2 ACT Grid and Tile In Yellow Areas disenhour Area Measurement

81.73 sf disenhour Area Measurement

583.59 sf disenhour Area Measurement

602.39 sf disenhour Typewritten Text Price Magenta Rooms as an Add Alternate - New 2x2 ACT Grid and Tile john.cole Typewritten Text Exist. Lighting HVAC and Devices to remain (Typ.)

Tile cuts and tie-ups by Specialty Subs/Owner john.cole Line john.cole Line john.cole Line john.cole Line john.cole Line john.cole Line john.cole Text Box

* Floor Plan for Reference Only...

Do not use former Reno Notes...

Ceiling Reno as marked in color areas only - ACT Grid to become 2x2 at 2x4 areas - Centered on Corridors, and Exist. Lighting.

john.cole Line john.cole Line john.cole Line john.cole Line john.cole Line john.cole Line john.cole Typewritten Text No work in Exist.

Hard Ceiling Areas -just color areas for 2x4 grid to upgrade to 2x2 (Typ.)

john.cole Arrow john.cole Line john.cole Line john.cole Line john.cole Line john.cole Line john.cole Line john.cole Line john.cole Line john.cole Line john.cole Line john.cole Line john.cole Line john.cole Line john.cole Line john.cole Line john.cole Line john.cole Line john.cole Line john.cole Line john.cole Line john.cole Line john.cole Line john.cole Line john.cole Line john.cole Line john.cole Line john.cole Line john.cole Line john.cole Line john.cole Line john.cole Line john.cole Line john.cole Arrow john.cole Cloud john.cole Cloud john.cole Cloud john.cole Typewritten Text Re-paint and misc. Drywall Repairs at Existing Main Corridors - "Relaxed Khaki" SW6149 -remove plates at switches but retain wallbase and signage "as is" for re-paint "touch-ups" only -typical for all 3 floors...

john.cole Arrow john.cole Arrow john.cole Typewritten Text No re-painting at Vestibules or Stair towers (typical) john.cole Cloud john.cole Arrow john.cole Arrow john.cole Typewritten Text Scope Edits and mark-ups by JV Cole / RCCC 8.12.26 john.cole Cloud john.cole Rectangle john.cole Rectangle john.cole Rectangle john.cole Rectangle john.cole Rectangle john.cole Typewritten Text

* Preferred New Ceiling Tile = campus standard:

USG ClimaPlus "Frost" #414 per Facility Design Manual Spec's (typical all facilities / buildings).

john.cole Cloud john.cole Rectangle john.cole Rectangle john.cole Rectangle john.cole Rectangle john.cole Rectangle john.cole Rectangle john.cole Rectangle john.cole Rectangle john.cole Rectangle john.cole Rectangle john.cole Rectangle john.cole Rectangle john.cole Rectangle

Facility Design Manual

Issue: November 15, 2020 College Standards Page 3-21 Revised: February 1, 2024

Level 3 This gypsum board finish is typically specified in appearance areas that will receive heavy or medium texture finishes before final painting or in areas where heavy-duty commercial-grade wallcoverings will be applied as the final decoration. Level 3 is not recommended for smooth wall designs or applications where light textures; non-continuous textures or lightweight wallcoverings will be applied. After wiping joints with a joint knife, leaving a thin layer of compound over all joints and interior angles, add a separate coat of joint compound over all joints and interior angles.

Cover fastener heads and accessories with two layers of joint compound.

Make sure the surface is smooth and free of tool marks.

Level 4 Finish Level 4 is typically specified in appearance areas where smooth wall designs are going to be decorated with flat paints, light textures or non-continuous textures or where wallcoverings will be applied. This level of finish is not recommended in spaces where non-flat or dark/deep-tone paints are going to be applied. As in previous levels, all joints and interior angles have tape embedded in the joint compound. After wiping joints with a joint knife, leaving a thin layer of compound over all joints, add two coats of joint compound over all flat joints. After wiping interior angles with a joint knife, leaving a thin layer of compound, add one separate coat of joint compound over interior angles. Cover fastener heads and accessories with three layers of joint compound. Make sure the surface is smooth and free of tool marks. If finishing glass mat or fiber-reinforced gypsum panels, check with the manufacturer for finishing recommendations.

Level 5 Gypsum board finishing Level 5 is typically specified in appearance areas where smooth wall designs are decorated with non-flat paints, glossy or decorative finishes, or dark/deep-tone paints or where critical lighting conditions occur. Level 5 provides a uniform surface and minimizes the possibility of joint photographing and/or fasteners showing through the final decoration. In Level 5, all joints and interior angles have tape embedded in the joint compound. All joints are then wiped with a joint knife, leaving a thin layer of compound over all joints and interior angles. Add two coats of joint compound over all flat joints. Add one coat of joint compound over interior angles. Cover fastener heads and accessories with three coats of joint compound. Apply a skim coat of joint compound or material manufactured for this purpose to the entire surface. Make sure the surface is smooth and free of tool marks.

3.9.2. Acoustical Tile Ceilings

Acoustical tile ceilings shall be exposed grid, lay-in system. Acoustical tiles shall be two feet square (2’x2’) lay-in tiles composed of non-combustible materials.

3.9.2.1. The standard Acoustical ceiling tile suspension systems shall be wide faces, double web, steel which are hot-dip galvanized with prefinished 15/16” flanges. They shall be rated for intermediate duty. Color: White. Acceptable manufacturers are Armstrong, USG, and Chicago Metallic Corporation.

3.9.2.2. The standard acoustical ceiling tiles shall be ¾” thick, white, mineral based, treated with mold/mildew inhibitor. They shall have a reflectance of no less than LR 0.83, with a Noise Reduction Coefficient (NRC) of 0.70, and a Ceiling Attenuation Class on not less than 40 Armstrong Tundra, medium texture with tegular edge shall be the basis of design. Acceptable john.cole Highlight

3.9.2. Acoustical Tile Ceilings

john.cole Highlight The standard acoustical ceiling tiles shall be ¾” thick, white, mineral based, treated with mold/mildew inhibitor. They shall have a reflectance of no less than LR 0.83, with a Noise Reduction Coefficient (NRC) of 0.70, and a Ceiling Attenuation Class on not less than 40

Facility Design Manual

Issue: November 15, 2020 College Standards Page 3-22 Revised: February 1, 2024 manufacturers are Armstrong, USG, and CertainTeed. 3.9.2.1. USG Frost™ ClimaPlus™ #414, 2'x2'x3/4", Shadowline Edge with Bevel – Flat White 050.

3.9.2.3. Open Office and Collaboration spaces will have ceilings with high NRC and CAC characteristics.

3.9.2.4. Class A “Fire-Rated” materials shall be specified to complete a UL fire-rated ceiling system for fire protection of structural components, where fire-rated assembly is required by Code.

3.9.3. Flooring

The following materials are preferred at the locations indicated:

3.9.3.1. Terrazzo or non-slip porcelain tile – high traffic areas such as lobbies and corridors.

At ornamental stairs, treads and risers shall match the adjacent materials with non-slip nosings.

3.9.3.2. Luxury Vinyl Tile (LVT) – low traffic lobbies and corridors, general purpose rooms, labs, classrooms where appropriate.

3.9.3.3. Carpet Tile – offices, conference rooms, auditorium aisles (with permanent seating), lounges, classrooms as appropriate, music or language listening rooms.

3.9.3.4. Porcelain Tile – restroom, bathrooms and showers.

3.9.3.5. Quarry Tile or Anti-bacterial Cement – food service areas.

3.9.3.6. Sealed Concrete – mechanical rooms, storage rooms, custodial rooms.

3.9.3.7. Raised, Removable Panels supported on interconnecting grids and pedestals, providing an under-floor plenum for air distribution and utilities may be utilized in Server Rooms, and other appropriate spaces.

3.9.3.8. Steel Trowel Finish Concrete – treads and risers with non-slip nosings for service and egress stairs.

3.9.3.9. Walk- off Carpet Tiles - building entrances.

3.9.4. Tile Carpeting

All carpet shall be selected from the North Carolina Qualified Products List (QPL) established by the State Purchasing Department.

Light colors (such as white, yellow, or gold) and solid colors which immediately show all traffic patterns and any stain must be avoided.

All carpet to be 24” x 24” tiles to facilitate replacement of damaged carpet and storage of attic stock.

Use of broadloom carpet must be approved by the College.

All newly carpeted areas shall be appropriately covered with plastic or brown paper to protect the carpet from construction debris. Carpet shall be in clean, like new condition when turned over to the College.

Tile carpeting with a hard composition backing, but not containing PVC, is preferred for public spaces where floor access is desirable and for ease of repair. A mixed pattern with high soil and stain hiding capabilities is preferred.

3.9.4.1. Carpet Specification Requirements

john.cole Highlight USG Frost™ ClimaPlus™ #414, 2'x2'x3/4", Shadowline Edge with Bevel – Flat White 050.

File details come from the government source that posted it. Updated .