Addendum 2 - Q&A.pdf
PDF 206 KB Posted
- Attached to
- Law Enforcement Vehicle Upfitting
- Solicitation number
- ITB-14975
- Issued by
- Leon County, Florida
About this file
This Addendum 2 document provides Questions and Answers clarifications for the Florida Department of Financial Services, Criminal Investigations Division's Invitation to Bid (ITB) 2425-04 CI for law enforcement vehicle upfitting services. The Department estimates approximately 30 vehicles will require service per fiscal year, including new vehicles requiring full upfitting and used vehicles needing updates or retrofitting. The 20-business-day completion period for vehicle upfitting begins when the vehicle is dropped off and the Task Assignment Notification Form is signed, not when parts are ordered, accounting for typical manufacturer lead times of two to three months. The addendum confirms that parts markup or markdown percentages apply uniformly to all parts regardless of type or manufacturer for both initial and renewal contract terms.
The pricing evaluation methodology was modified in this addendum to allow respondents to submit negative percentages to indicate discounts off manufacturer's suggested retail price (MSRP), in addition to standard markup percentages. Bids are scored using a formula combining the Part Markup or Markdown percentage (averaged between initial and renewal terms) and the hourly Labor Cost rate, with the lowest combined score receiving the award. The updated Attachment 3 Price Response form requires respondents to submit Part Markup or Markdown percentages and hourly labor rates for both the initial and renewal contract terms, replacing the previous version entirely.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 01. ITB Doc Law Enforcement Vehicle Upfitting.pdf | ||
| 2425-04 ITB CI - Addendum 3.pdf | ||
| 03. Appendix B.xlsx | XLSX spreadsheet | |
| 03. Appendix B.xlsx | XLSX spreadsheet | |
| 04. Attachment 3.docx | DOCX document | |
| 06. Appendix C.docx | DOCX document | |
| 06. Appendix C.docx | DOCX document | |
| 04. Attachment 3.docx | DOCX document | |
| 05. Attachment 6.docx | DOCX document | |
| 06. Appendix C.docx | DOCX document | |
| 03. Appendix B.xlsx | XLSX spreadsheet | |
| 01. ITB Doc Law Enforcement Vehicle Upfitting.pdf | ||
| 04. Attachment 3.docx | DOCX document | |
| 2425-04 ITB CI Addendum 1 - Q&A.pdf | ||
| 05. Attachment 6.docx | DOCX document | |
| 2425-04 ITB CI Addendum 1 - Q&A.pdf | ||
| Updated Attachment 3 - Price Response.pdf | ||
| 01. ITB Doc Law Enforcement Vehicle Upfitting.pdf | ||
| 05. Attachment 6.docx | DOCX document |
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
QUESTIONS AND ANSWERS
2425-04 ITB CI
Law Enforcement Vehicle Upfitting
Addendum No. 2
Failure to file a protest within the time prescribed in section 120.57(3), Florida Statutes, or failure to post the bond or other security required by law within the time allowed for filing a bond shall constitute a waiver of proceedings under Chapter 120, Florida Statutes.
The Department has been made aware of additional questions that arrived before the deadline for submissions. This Addendum consists of the following sections:
A. Questions and Answers
B. Modifications to the ITB
-Remainder of This Page Intentionally Left Blank-
A. Questions and Answers
Below are the questions and answers related to this solicitation. In the table below, the Department of Financial Services (Department) has answered each of the questions submitted by potential respondents.
No.
Attachment
Identifier
Section
Number
Sub-Section
Reference
Item
Reference Page No. Question Department Response
1.
Invitation to
Bid Section 4 4.2
Part
Markup
If a respondent wants to bid a percentage off of MSRP, how should they indicate that? For instance, if they wish to bid 2% off MSRP, should they show that as -2% in the part markup section on Attachment 3?
Please see the modifications in Section
B of this Addendum 2.
Respondents may provide a negative number as their Part
Markup or Markdown response to indicate a percentage off MSRP if desired.
2.
2425-04 ITB
CI
Attachment 3
Price
Response
Form
For Attachment 3 of the 2025-04
ITB CI Price Response Form, is the parts markup percentage for the initial and renewal terms intended to be applied uniformly to all parts, irrespective of type or manufacturer?
Yes.
3. Attachment 2 Statement of Work 5.C 3 3
Given that most manufacturers have a two- to three-month lead time, does the 20-business-day completion period begin once all required products have been received?
The 20 business days start when the vehicle is dropped off and the
Task Assignment
Notification Form is signed, not when the parts are ordered.
4. Attachment 2 Statement of Work 1 Scope 1
What is the projected number of law enforcement vehicles the
Department will furnish that will require equipment installation, including new vehicles needing full upfitting and used vehicles requiring updates or retrofitting?
The Department estimates 30 vehicles will require service per fiscal year.
B. Modifications to the ITB: Insertions to the ITB are indicated by an underscore, deletions are indicated by a strikethrough. Please be advised that the following changes are also noted within the posted document titled 2425-04 ITB CI.
1. Section 4.2 of the ITB Document, Review of Price Response, is hereby modified as indicated below:
The Procurement Officer will evaluate the Price Response from responsible and responsive Respondents to determine the lowest bid based on the
Respondent’s Attachment 3, Price Response. Respondents’ bids will be scored as follows:
Part Markup or Markdown: Submitted as a percentage (%) above or below the manufacturer’s suggested retail price (MSRP), and averaged between initial and renewal terms.
Labor Cost: Submitted as an hourly rate, scoring percentage found with the formula:
Respondent’s Average Proposed Labor Rate (Initial and Renewal Term) _
Lowest Average Labor Rate Offered by Any Respondent
The two percentages will then be totaled and multiplied by 100 for a final score, with the lowest combined score being awarded.
2. Attachment 3, Price Response is hereby deleted in its entirety and replaced with the updated Attachment 3, Price Response. The update to the document is reflected below.
Initial Term Renewal Term
Part
Markup or
Markdown _____________% _____________%
Labor Cost $___________/hr. $___________/hr.
File details come from the government source that posted it. Updated .